SynC · SynC Standards

Aggregate Base Course

Written and maintained by SynC.

Rev6
IssuedNov 16, 2026
LicenseCC BY 4.0
Contents

Revision history

Build a datasheet from this standard Start a project with this standard already attached — one click, no setup.
Use in a project

1 Scope

NOTE This standard governs the material, source qualification, placement, compaction, tolerance, testing, and acceptance of dense-graded aggregate base and subbase courses, from the accepted subgrade to the accepted base surface on which a pavement, a slab, or a pad is built. (1.1)
NOTE A base course does three things for the surface above it. It spreads a wheel or slab load over an area of subgrade large enough that the soil is not overstressed; it gives the paving or concrete crew a firm, trimmed platform to build a uniform thickness on; and it keeps the surface course off a soil that softens when wet. All three depend on the aggregate being dense, well graded, low in plastic fines, and compacted through its full depth, and none of them can be inspected once the surface course is on. (1.2)
NOTE The course thicknesses, the material designation, and the compaction targets belong to the pavement design, which is recorded on the civil drawings and in the geotechnical report. This standard carries those values in datasheet fields that defer to those documents, and states a fallback only where they are silent. (1.3)
NOTE A dense-graded base is a structural layer, not a drainage layer. Its fines fill the voids the water would have to move through, so a section that depends on draining the base is designed with an open-graded layer or an edge drain under the standards that govern those, and the dense base above or beside it is built under this one. (1.4)
NOTE This standard owns one decision about a product it does not specify: whether a separation geotextile is placed between the subgrade and the base. The fabric's product properties, class, overlap, and the cover it needs before traffic are governed by GeosyntheticsGeosynthetics and GeotextilesResolves to the current adopted revision.sync/geosynthetics. (1.5)
NOTE Beneath a building slab on ground, Slab On GradeSlab-on-GradeResolves to the current adopted revision.sync/slab-on-grade selects the subbase type, its thickness, and the tolerance of its surface, and beneath an equipment pad Concrete PadsConcrete Equipment PadsResolves to the current adopted revision.sync/concrete-pads states the base thickness. Where either calls for a dense-graded aggregate base, this standard governs its material, lifts, and compaction. (1.6)
NOTE Where a utility trench or a pavement patch cuts through an existing pavement, the base replaced in the cut is built under this standard. The trench backfill beneath it is governed by EarthworkEarthworkResolves to the current adopted revision.sync/earthwork, and the surface courses above it by Asphalt PavingAsphalt PavingResolves to the current adopted revision.sync/asphalt-paving or Concrete PavingConcrete Paving, Curbs, and SidewalksResolves to the current adopted revision.sync/concrete-paving. (1.7)
NOTE The following are outside this standard: (1.8)
  • The subgrade, its proof rolling, its stabilization where proof rolling fails, and its acceptance, under EarthworkEarthworkResolves to the current adopted revision.sync/earthwork, and its fine grading under Site Rough GradingSite Grading and Subgrade PreparationResolves to the current adopted revision.sync/site-rough-grading
  • Chemically treated subgrade, subbase, and base under Soil StabilizationSoil Stabilization and ModificationResolves to the current adopted revision.sync/soil-stabilization
  • Asphalt base courses, full-depth reclaimed base, and prime coat under Asphalt PavingAsphalt PavingResolves to the current adopted revision.sync/asphalt-paving
  • Open-graded reservoir and choker courses under Permeable PavingPermeable PavingResolves to the current adopted revision.sync/permeable-paving, and open-graded drainage layers and edge drains under SubdrainageSubdrainageResolves to the current adopted revision.sync/subdrainage
  • Pipe bedding and embedment within the pipe zone, under the standard for the utility installed
  • Geotextile and geogrid products and their installation under GeosyntheticsGeosynthetics and GeotextilesResolves to the current adopted revision.sync/geosynthetics, including a geogrid selected to reinforce the base
  • Aggregate surfacing left without a bound surface, railroad ballast, and landscape stone
1.9 Base and subbase courses shall conform to the pavement design and the recommendations of the geotechnical investigation report prepared for the Project.
1.10 Where this standard and the pavement design conflict, the pavement design shall govern for the section, the course thicknesses, the material designation, and the compaction targets, and this standard shall govern for procedure, testing, and acceptance, unless the Engineer of Record directs otherwise in writing.
1.11 The Contractor shall not reduce the thickness of a base or subbase course, substitute one course for another, or change the aggregate source after acceptance, without the written approval of the Engineer of Record.
1.12 The Contractor shall coordinate work under this standard with EarthworkEarthworkResolves to the current adopted revision.sync/earthwork and Site Rough GradingSite Grading and Subgrade PreparationResolves to the current adopted revision.sync/site-rough-grading for acceptance and protection of the subgrade; with Soil StabilizationSoil Stabilization and ModificationResolves to the current adopted revision.sync/soil-stabilization for the cure and acceptance of a treated layer that receives base; with GeosyntheticsGeosynthetics and GeotextilesResolves to the current adopted revision.sync/geosynthetics for a geosynthetic placed beneath the base; with Storm DrainageStorm DrainageResolves to the current adopted revision.sync/storm-drainage, Sanitary Sewer SystemsSanitary Sewer Systems (Site)Resolves to the current adopted revision.sync/sanitary-sewer-systems, Site UtilitiesSite UtilitiesResolves to the current adopted revision.sync/site-utilities, and SubdrainageSubdrainageResolves to the current adopted revision.sync/subdrainage for completion and testing of every buried line beneath the base before it is placed; and with Asphalt PavingAsphalt PavingResolves to the current adopted revision.sync/asphalt-paving, Concrete PavingConcrete Paving, Curbs, and SidewalksResolves to the current adopted revision.sync/concrete-paving, Slab On GradeSlab-on-GradeResolves to the current adopted revision.sync/slab-on-grade, and Concrete PadsConcrete Equipment PadsResolves to the current adopted revision.sync/concrete-pads for the surface this standard delivers to them.

2 Referenced Standards

2.1 Materials, testing, and execution shall comply with the latest adopted edition of each of the following unless a specific edition is cited.
2.2 Where referenced standards conflict, the more stringent requirement shall govern unless the Engineer of Record directs otherwise in writing.
Standard Title
ASTM D2940/D2940M Graded Aggregate Material for Bases or Subbases for Highways or Airports
AASHTO M 147 Materials for Aggregate and Soil-Aggregate Subbase, Base, and Surface Courses
ASTM D75/D75M Sampling Aggregates
ASTM C702/C702M Reducing Samples of Aggregate to Testing Size
ASTM C136/C136M Sieve Analysis of Fine and Coarse Aggregates
ASTM C117 Materials Finer than 75-µm (No. 200) Sieve in Mineral Aggregates by Washing
ASTM D4318 Liquid Limit, Plastic Limit, and Plasticity Index of Soils
ASTM D2419 Sand Equivalent Value of Soils and Fine Aggregate
ASTM C131/C131M Resistance to Degradation of Small-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine
ASTM C535 Resistance to Degradation of Large-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine
ASTM C88/C88M Soundness of Aggregates by Use of Sodium Sulfate or Magnesium Sulfate
ASTM D5821 Determining the Percentage of Fractured Particles in Coarse Aggregate
ASTM D4792/D4792M Potential Expansion of Aggregates from Hydration Reactions
ASTM D1883 California Bearing Ratio (CBR) of Laboratory-Compacted Soils
ASTM D698 Laboratory Compaction Characteristics of Soil Using Standard Effort
ASTM D1557 Laboratory Compaction Characteristics of Soil Using Modified Effort
ASTM D4718/D4718M Correction of Unit Weight and Water Content for Soils Containing Oversize Particles
ASTM D6938 In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)
ASTM D1556/D1556M Density and Unit Weight of Soil in Place by Sand-Cone Method
ASTM D2216 Laboratory Determination of Water (Moisture) Content of Soil and Rock by Mass
ASTM D3740 Minimum Requirements for Agencies Engaged in Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction
AASHTO T 99 Moisture-Density Relations of Soils Using a 2.5-kg Rammer and a 305-mm Drop
AASHTO T 180 Moisture-Density Relations of Soils Using a 4.54-kg Rammer and a 457-mm Drop

3 Submittals

3.1 Action Submittals

3.1.1 The Contractor shall submit the following for review by the Engineer of Record before aggregate is delivered from the source it describes:
  • Aggregate source report for each source and each material: the producer and pit or quarry, the material designation under the governing specification, gradation per ASTM C136/C136M and ASTM C117 plotted against the specified limits, liquid limit and plasticity index per ASTM D4318, and each quality test the datasheet requires, all on samples taken within the preceding 12 months
  • State DOT approved-source listing or producer certification for the designated material, where the datasheet accepts it as source qualification
  • Laboratory compaction curve for each source and material by the reference method in the datasheet, with the oversize correction applied where this standard requires it
  • Recycled material report for recycled concrete aggregate or a blend containing reclaimed asphalt pavement: the processor, the origin of the feedstock, the proportion of each constituent, and the content of brick, wood, gypsum, metal, and other foreign material
  • Slag report for slag aggregate: the furnace type, the age and curing history of the stockpile, and, for steel slag, expansion per ASTM D4792/D4792M
  • Laboratory California Bearing Ratio per ASTM D1883, where the datasheet requires it
  • Test strip plan, where a test strip is required: location, lift thickness, roller type and weight, and the pass counts to be tried
  • Base placement plan: haul routes over the accepted subgrade, stockpile locations, the spreading and compaction equipment, and the sequence by area
Action Submittals Requiredcheckbox
☑ Aggregate source report for each source and material
☐ State DOT approved-source listing or producer certification
☑ Laboratory compaction curve for each source and material
☐ Recycled material report
☐ Slag report
☐ Laboratory California Bearing Ratio
☐ Test strip plan
☐ Base placement plan
3.1.2 Aggregate shall not be delivered from a source until the submittals for that source have been reviewed and the source accepted.
3.1.3 Review of a submittal does not relieve the Contractor of responsibility for compliance with the Contract Documents.

3.2 Closeout Submittals

3.2.1 The Contractor shall deliver the following for each area before the base in that area is covered, and shall deliver the compiled set before substantial completion:
  • Field density test reports for every test taken, passing and failing, with the location, lift, material, reference curve, dry density, moisture content, percent compaction, and disposition of each
  • Production gradation and plasticity test reports for the aggregate delivered
  • Thickness measurements for each course, with the location and the measured and required thickness of each
  • Survey of the finished base surface against the design elevations
  • Proof-rolling record for each area of completed base proof-rolled, with the date, the vehicle and its loaded weight, the areas rejected, and the correction applied
  • Written acceptance of the completed base by the geotechnical engineer of record for each area
  • Summary of aggregate delivered, by source, material, and tonnage, from the delivery tickets
Closeout Submittals Requiredcheckbox
☑ Field density test reports, passing and failing
☑ Production gradation and plasticity test reports
☑ Course thickness measurements
☑ Finished base surface survey
☑ Proof-rolling record for the completed base
☑ Written acceptance of the completed base
☐ Delivery summary by source, material, and tonnage

4 Quality Assurance

4.1 Geotechnical Engineer of Record and Base Acceptance

4.1.1 The geotechnical engineer of record retained by the Owner shall accept or reject each aggregate source on the basis of the source submittals and the requirements of this standard.
4.1.2 The geotechnical engineer of record shall observe proof rolling of the completed base where the datasheet requires it, and shall accept the completed base in each area in writing before it is covered.
4.1.3 The geotechnical engineer of record may stop base placement that does not conform to the pavement design or to this standard, and the Contractor shall comply with that direction.
4.1.4 The Contractor shall give the geotechnical engineer of record and the testing agency not less than 24 hours notice before base placement begins in each area and before each area of completed base is ready for proof rolling or acceptance.
NOTE Written acceptance is the hand-off the following trade relies on: the standards for the asphalt, the concrete pavement, the slab, and the pad each make an accepted base a condition of starting, and the acceptance is the one record that the density tests, the thickness, the surface, and the proof roll were all looked at together for that area. (4.1.5)

4.2 Base Course Testing Agency

4.2.1 Field density testing, production material testing, and thickness measurement shall be performed by the testing agency retained as indicated in the datasheet.
Base Course Testing Agency Retained Byradio
● Owner
○ Contractor, with results reported directly to the Owner
NOTE Owner retention keeps the agency independent of the party whose work it accepts. Contractor retention with direct reporting to the Owner is used on design-build work and on small projects where the Owner holds no separate testing contract, and it depends on the reporting path being enforced. (4.2.2)
4.2.3 The testing agency shall meet ASTM D3740 for the tests it performs, and the technician taking nuclear gauge readings shall hold the certification and the radiation safety training the gauge license requires.
4.2.4 The testing agency shall standardize each nuclear gauge at the start and end of every testing day in accordance with ASTM D6938 and shall record the standard counts.

4.3 Aggregate Source Qualification

4.3.1 Each aggregate source shall be qualified by one of the forms of evidence indicated in the datasheet before material is delivered from it.
Acceptable Source Qualification Evidencecheckbox
Any of:
☑ Current state DOT approved-source listing for the designated material
☑ Source report by an independent laboratory on samples the laboratory took
☐ Source report from the producer's quality control laboratory
NOTE A DOT approved-source listing is evidence that the material has been sampled and accepted repeatedly, in volume, by an agency with no stake in the sale, and it costs the Project nothing; it exists only for the materials the DOT designates and only in states that keep such a list. An independent laboratory report is the equivalent for a source or a material that has no listing, and adds the sampling trip and the test time to the schedule. The producer's own report is the fastest and rests on the laboratory of the party selling the stone. (4.3.2)
4.3.3 Samples for source qualification and for production testing shall be taken per ASTM D75/D75M and reduced per ASTM C702/C702M.
4.3.4 The Contractor shall notify the Engineer of Record in writing before changing a source, a pit face or ledge within a source, or the proportions of a blended material, and the changed material shall be qualified as a new source before it is delivered.
4.3.5 A new laboratory compaction curve shall be developed whenever the source changes and whenever production gradation moves from the gradation on which the current curve was run by enough that the geotechnical engineer of record judges the curve no longer represents the material.

4.4 Pre-Placement Conference

4.4.1 Before base placement begins, the Contractor shall convene a conference attended by the Contractor's superintendent for the base work, the aggregate supplier's representative, the testing agency, the geotechnical engineer of record, the Engineer of Record, and the superintendent of the trade that will cover the base.
4.4.2 The conference shall review the accepted sources and their compaction curves, the subgrade acceptance record and how the accepted subgrade is protected, the lift thickness and equipment, the moisture window, the compaction targets and reference method, the testing frequency and reporting path, the thickness and surface tolerances the covering trade needs, the proof-rolling procedure, and the handling of a failing test.

4.5 Test Strip

4.5.1 A test strip shall be built where the datasheet requires one, and wherever the compacted lift thickness in the datasheet exceeds 8 in.
Test Stripradio
○ Required
● Not required
NOTE A test strip settles, before production starts, how many passes of a particular roller bring a particular aggregate to the target through the full lift, and what the surface looks like when it gets there. On ordinary site work with a 6 in. lift and a familiar local material the first day's density tests answer the same question. The strip earns its cost where the lift is thick, where the material is a recycled or blended aggregate the crew has not placed before, where the area is large enough that a wrong rolling pattern would be repeated over acres, and where the nuclear gauge needs a moisture correction established before its readings are relied on. (4.5.2)
4.5.3 The test strip shall be not less than 100 ft long and one spreader width wide, shall be built within the Work on accepted subgrade, and shall use the material, lift thickness, moisture, and equipment proposed for production.
4.5.4 The testing agency shall measure density after each pass until additional passes produce no further increase, and shall test the full depth of the lift at not fewer than three locations at the end of rolling.
4.5.5 The rolling pattern that meets the compaction target in the test strip shall be recorded and used for production, and a change in material, lift thickness, or roller shall require a new strip.
4.5.6 A test strip that meets every requirement of this standard may remain as part of the Work.

5 Aggregate Material

5.1 Governing Material Specification

NOTE Dense-graded aggregate base in the United States is produced overwhelmingly to state department of transportation designations, and the quarries in a region stock those materials and hold the test history for them. A project that names the DOT designation gets a stockpiled product with a known record; a project that names a national specification gets limits written without regard to what the local pits produce, which is the choice where the site is far from DOT work, where the Owner builds in many states to one specification, or where the DOT material is known locally to be marginal for the use. ASTM D2940/D2940M is a single dense grading for base and a second for subbase, with tight fines and plasticity limits; AASHTO M 147 is a family of six gradings that runs from a coarse crushed base to a sand-clay-gravel mixture and admits more fines. (5.1.1)
5.1.2 Base and subbase aggregate shall conform to the specification indicated in the datasheet.
Governing Specification for Base and Subbase Aggregateradio
● State DOT standard specifications
○ ASTM D2940/D2940M
○ AASHTO M 147
5.1.3 Where the state DOT standard specifications govern, the gradation, fines, plasticity, and aggregate quality limits of that specification for the designated material shall apply in place of the fines, plasticity, abrasion, soundness, and fractured-particle limits in the datasheet.
5.1.4 The acceptable source materials, the placement, compaction, tolerance, testing, and acceptance provisions, and the warranty of this standard shall apply whichever specification governs the aggregate.
5.1.5 Where ASTM D2940/D2940M or AASHTO M 147 governs, the aggregate shall meet that specification and the limits in the datasheet, and the more stringent limit shall govern.

5.2 State DOT Material Designation

5.2.1 Requirements in this article apply where the state DOT standard specifications govern the aggregate.
5.2.2 The base course aggregate shall be the state DOT material designation indicated in the datasheet.
State DOT Aggregate Base Designationtext
Enter value...
Per drawings — the pavement section details and paving notes on the civil drawings (deferred by default)
5.2.3 Where the pavement section includes a subbase course, the subbase aggregate shall be the state DOT material designation indicated in the datasheet.
State DOT Aggregate Subbase Designationtext
Enter value...
Per drawings — the pavement section details and paving notes on the civil drawings (deferred by default)
5.2.4 The designation shall be read with the edition of the state DOT standard specifications current at the date of the Contract Documents, including its supplemental specifications for the material.
5.2.5 Measurement, payment, lot, and pay-factor provisions of the state DOT standard specifications shall not apply.

5.3 ASTM D2940 Base and Subbase Gradings

5.3.1 Requirements in this article apply where ASTM D2940/D2940M governs the aggregate.
5.3.2 The base course shall meet the grading ASTM D2940/D2940M states for bases, and a subbase course shall meet the grading it states for subbases.
5.3.3 The job-mix tolerances of ASTM D2940/D2940M shall apply to production gradation about the gradation reported in the accepted source report.

5.4 AASHTO M 147 Grading

5.4.1 Requirements in this article apply where AASHTO M 147 governs the aggregate.
5.4.2 The base course shall meet the AASHTO M 147 grading indicated in the datasheet.
AASHTO M 147 Grading, Base Courseselect
Grading A
Grading B
Grading C
Grading D
Grading E
Grading F
5.4.3 Where the pavement section includes a subbase course, the subbase shall meet the AASHTO M 147 grading indicated in the datasheet.
AASHTO M 147 Grading, Subbase Courseselect
Grading A
Grading B
Grading C
Grading D
Grading E
Grading F
NOTE The six gradings run from coarse to fine. A and B are the coarsest and suit a thick course placed in full lifts; A is the leanest in fines and behaves most like a crushed base, and B admits considerably more. C and D have a smaller top size, trim to a closer surface, and suit a thin course or the top lift beneath a slab or a thin pavement. E and F are sandy soil-aggregate mixtures with the most fines of the six; they are subbase and light-duty materials where a natural sand-gravel is the local resource, and they hold water and lose strength in a wet or freezing section more readily than the coarser gradings. (5.4.4)

5.5 Acceptable Source Materials

5.5.1 Base and subbase aggregate shall be produced from one or more of the source materials indicated in the datasheet, and a material the governing specification permits but the datasheet does not list shall not be furnished.
Acceptable Aggregate Source Materialscheckbox
Any of:
☑ Crushed stone
☑ Crushed gravel
☐ Air-cooled blast-furnace slag
☐ Steel slag
☐ Recycled concrete aggregate
☐ Blend containing reclaimed asphalt pavement
NOTE Crushed quarry stone is fractured on every face and is the reference material the rest are measured against. Crushed gravel performs the same where enough of its rounded particles are broken, which is why it alone carries a fractured-particle requirement. Air-cooled blast-furnace slag is angular, light, and stable. Steel slag is dense and very strong and contains free lime and magnesia that hydrate and swell for months unless the stockpile has been aged and wetted, which makes it a risk beneath anything rigid and confined. Recycled concrete aggregate compacts to a stiff, partly self-cementing layer, weighs less, absorbs more water, and releases a high-pH leachate that precipitates in drains and filter fabrics. Reclaimed asphalt pavement in a blend reduces the cost and the haul, lowers the maximum density, and creeps under sustained load as its share rises. (5.5.2)
5.5.3 Aggregate from every source material shall consist of hard, durable particles free of organic matter, clay lumps, soil, and other deleterious material.
5.5.4 Steel slag shall have been stockpiled, wetted, and aged before delivery, shall show expansion of not more than 0.50 percent at 7 days per ASTM D4792/D4792M, and shall not be placed beneath a building slab, an equipment pad, or a concrete pavement, or against a structure, unless the Engineer of Record accepts it for that location in writing.
5.5.5 Recycled concrete aggregate shall be free of reinforcing steel, wood, gypsum, plaster, and soil, and shall contain not more than 5 percent by mass of brick, asphalt, and other foreign material combined.
5.5.6 Recycled concrete aggregate shall not be placed where it drains to an underdrain, an edge drain, or a drainage geotextile, and shall not be placed within 24 in. of aluminum or galvanized steel that remains in service, unless the Engineer of Record accepts it for that location in writing.
5.5.7 Where a blend containing reclaimed asphalt pavement is acceptable, the reclaimed asphalt pavement shall not exceed the percentage of the blend indicated in the datasheet, and the blend shall be proportioned and mixed at the processor's plant and not on grade.
Reclaimed Asphalt Pavement Content of a Blended Baserange
Not more than
% by mass
10152025304050
5.5.8 The source material actually furnished shall meet every limit of the governing specification as a finished product, and acceptance of a source material in the datasheet shall not waive a limit.

5.6 Fines and Plasticity

NOTE The fraction passing the No. 200 sieve is what makes a graded aggregate dense and what makes it fail. A few percent of non-plastic rock dust fills the voids, raises the density, and holds the surface together under a grader; more than that, or the same amount of clay, fills the voids with a material that holds water, softens, pumps to the surface under traffic, and heaves when it freezes. The limits below are therefore the ones that separate a base from a fill, and they tighten where the section is wet, where it freezes, and where the surface course is thin. (5.6.1)
5.6.2 The base course aggregate shall contain not more than the percentage passing the No. 200 sieve indicated in the datasheet, determined by washing per ASTM C117.
Fines Passing the No. 200 Sieve, Base Courserange
Not more than
%
5678101215
5.6.3 The fraction of the aggregate passing the No. 40 sieve shall have a plasticity index not greater than that indicated in the datasheet and a liquid limit not greater than 25, per ASTM D4318.
Plasticity Index of the Fraction Passing the No. 40 Sieverange
Not more than
246810
NOTE A fines limit of 8 percent is the ASTM D2940/D2940M limit for base; 5 to 7 percent is set where the base lies within the frost depth over a frost-susceptible subgrade with water available, and 10 to 15 percent admits a finer soil-aggregate grading in a dry, unfrozen section. A plasticity index of 6 is the AASHTO M 147 limit and the common DOT one; 4 is the ASTM D2940/D2940M limit; zero requires non-plastic fines, the position for a base beneath a thin pavement in a wet freezing climate; values above 6 admit a clay binder that holds an unsurfaced course together in an arid climate and softens a covered one wherever water reaches it. (5.6.4)
5.6.5 Where the governing specification permits a sand equivalent value in place of the plasticity limits, the sand equivalent shall be determined per ASTM D2419 and reported with the plasticity index.

5.7 Abrasion, Soundness, and Fractured Particles

5.7.1 The coarse aggregate shall have a Los Angeles abrasion loss not greater than that indicated in the datasheet, per ASTM C131/C131M, or per ASTM C535 for a grading coarser than ASTM C131/C131M covers.
Los Angeles Abrasion Lossrange
Not more than
%
30354045505560
NOTE A soft aggregate breaks down under the roller and under traffic, so the material in the ground is finer than the material that was tested and accepted. A 50 percent loss is the most common limit for base and admits most limestones and dolomites; 40 to 45 percent is set beneath heavy truck pavements and where the aggregate will be worked repeatedly; values above 50 admit the softer local stone of regions that have nothing harder, at the cost of fines generated in place. (5.7.2)
5.7.3 Sulfate soundness of the aggregate shall be tested per ASTM C88/C88M with the solution indicated in the datasheet, through five cycles.
Sulfate Soundness Testradio
○ Sodium sulfate
○ Magnesium sulfate
○ Not required
5.7.4 Where the datasheet requires a soundness test, the weighted loss shall not exceed that indicated in the datasheet.
Sulfate Soundness Loss, Five Cyclesrange
Not more than
%
8101215182025
5.7.5 Where the datasheet requires a soundness test and states no loss limit, the limit shall be 12 percent with sodium sulfate and 18 percent with magnesium sulfate.
NOTE The soundness test grows salt crystals in the pores of the particles to imitate the pressure of freezing water, and it screens out stone that splits and slakes over winters in a wet base. Magnesium sulfate is the more severe solution and produces a higher loss on the same stone, which is why the two limits differ and why a limit is meaningless without the solution named. The test is omitted where the base never freezes wet, and where the source carries a DOT listing or a service record that already answers the question. (5.7.6)
5.7.7 Sulfate soundness limits shall not apply to recycled concrete aggregate, whose cement paste the test solution attacks chemically.
5.7.8 Where crushed gravel is furnished, not less than the percentage indicated in the datasheet of the particles retained on the 3/8 in. sieve, by count, shall have two or more fractured faces per ASTM D5821.
Fractured Particles in Crushed Gravelrange
Not less than
% by count
5060758590100
NOTE A rounded particle rolls under load where a fractured one locks against its neighbors, so the stability of a crushed gravel base follows the share of its coarse particles that were actually broken. Seventy-five percent is the ASTM D2940/D2940M requirement; a higher share is set beneath heavy wheel loads, and a lower one admits a gravel source whose feed is too small to fracture fully, for a subbase or a lightly loaded pavement. (5.7.9)

5.8 Laboratory Bearing Ratio

5.8.1 A laboratory California Bearing Ratio requirement shall apply to the base aggregate where the datasheet requires one.
Laboratory California Bearing Ratio Requirementradio
○ Required
● Not required
5.8.2 Where a bearing ratio is required, the aggregate shall have a laboratory California Bearing Ratio per ASTM D1883, soaked, at the compaction target and reference method of the datasheet, of not less than the value indicated in the datasheet.
Soaked California Bearing Ratio of the Base Aggregaterange
Not less than
50607080100
Per drawings — the pavement design in the geotechnical report (deferred by default)
NOTE A bearing ratio requirement ties the material to the layer strength the pavement designer assumed, and it is set where the design method takes the base strength as an input and the material is not one with a published record: a recycled or blended aggregate, a marginal local stone, a soil-aggregate grading. For a DOT-designated crushed base the gradation and quality limits already imply a bearing ratio well above what a site pavement design assumes, and the test adds a week and no information. (5.8.3)
5.8.4 A bearing ratio that meets the datasheet shall not excuse a failure of gradation, fines, plasticity, or any other limit of this standard.

6 Base Section and Separation Layer

6.1 Course Thickness and Limits

6.1.1 The compacted thickness of the base course beneath pavements, curbs, and walks shall be as indicated in the datasheet.
Base Course Compacted Thicknessrange
in
324
Per drawings — the pavement section details on the civil drawings (deferred by default)
6.1.2 Where the pavement section includes a subbase course, its compacted thickness shall be as indicated in the datasheet.
Subbase Course Compacted Thicknessrange
in
436
Per drawings — the pavement section details on the civil drawings (deferred by default)
NOTE Thickness is the output of the pavement design and usually differs between the light-duty and heavy-duty sections of one site, so the field records the section details as its source and the tolerance on the built thickness is stated with the other tolerances of this standard. (6.1.3)
6.1.4 Where the subgrade is high, the Contractor shall trim the subgrade to grade and shall not thin the base or subbase to meet the finished elevation.
6.1.5 The base course shall extend beyond the edge of the pavement and beyond the back of the curb by the distance indicated in the datasheet.
Base Extension Beyond Pavement Edge and Back of Curbrange
Not less than
in
612182436
Per drawings — the pavement edge and curb details on the civil drawings (deferred by default)
6.1.6 Where the drawings do not show an extension, the base shall extend a distance equal to its own thickness and not less than 6 in.
NOTE A wheel at the pavement edge spreads its load outward through the base as well as inward, and a base that stops at the edge of the asphalt or the back of the curb leaves the edge carried on half the support the interior has. The extension also gives the roller a place to run so the base under the edge itself is compacted. Zero extension is the condition against a building, a wall, or a property line, where the edge is confined by something else. (6.1.7)

6.2 Separation Geotextile Beneath the Base

6.2.1 A separation geotextile shall be placed between the subgrade and the base or subbase to the extent indicated in the datasheet.
Separation Geotextile Beneath the Baseradio
○ Over the entire subgrade that receives base
○ Where the geotechnical engineer of record directs at subgrade acceptance
○ Not provided
Per drawings — the pavement recommendations of the geotechnical report (deferred by default)
NOTE Under repeated wheel loads a wet silt or clay subgrade works up into the voids of the aggregate above it while the stone punches down, and the bottom few inches of the base become a soil-aggregate mixture with the strength of the soil. A separation geotextile stops that exchange for a small fraction of the cost of the stone it protects. Full coverage is the position where the subgrade is fine-grained and wet across the site or the pavement carries heavy trucks; coverage directed at subgrade acceptance places fabric only on the areas that prove soft or wet when the subgrade is proof-rolled, which costs less and depends on the observer and on a price being in the Contract for the areas found; none is the position on a granular or chemically treated subgrade, where there are no fines to migrate, and beneath a building slab that carries no repeated wheel load. (6.2.2)
6.2.3 Where a separation geotextile is provided, the geotextile, its overlap, and the cover required over it before construction traffic shall conform to the geosynthetics requirements of the Contract Documents, stated for this Project in GeosyntheticsGeosynthetics and GeotextilesResolves to the current adopted revision.sync/geosynthetics.
6.2.4 Where the geotechnical engineer of record directs a separation geotextile in an area the Contract Documents did not identify, the geotextile shall be paid at the unit price the Contract Documents state for it, or as a change where they state none.
6.2.5 A separation geotextile shall not be used to bridge a subgrade that failed proof rolling; a rejected subgrade shall be stabilized and accepted under the subgrade acceptance requirements of the Contract Documents before base is placed.

7 Subgrade Condition at Base Placement

7.1 Base shall not be placed in any area until the subgrade in that area has been proof-rolled and accepted in writing under the subgrade acceptance requirements of the Contract Documents, stated for this Project in EarthworkEarthworkResolves to the current adopted revision.sync/earthwork.
7.2 Base shall not be placed on a chemically treated layer until that layer has cured and been accepted under the requirements of the Contract Documents for the treatment, stated for this Project in Soil StabilizationSoil Stabilization and ModificationResolves to the current adopted revision.sync/soil-stabilization.
7.3 Base shall not be placed over a storm, sanitary, water, electrical, or drainage line until the line has been tested and its trench backfill accepted.
7.4 The Contractor shall verify, on the day base is placed, that the accepted subgrade is at the elevation and cross slope shown, is free of ruts, loose material, standing water, mud, ice, snow, and frost, and has not been softened by rain or disturbed by traffic since acceptance.
7.5 A subgrade that has rutted, softened, frozen, or dried and cracked since acceptance shall be reworked and accepted again before base is placed on it, at the Contractor's expense where the Contractor's traffic or failure to protect it is the cause.
7.6 The Contractor shall confine haul trucks on the accepted subgrade to the routes in the base placement plan, and shall spread base ahead of the trucks wherever the subgrade ruts under them.
NOTE The accepted subgrade is at its best on the day it is accepted. A week of rain, a freeze, or the base contractor's own loaded trucks turn it into something nobody tested, and the base is then compacted against a surface that yields, which shows up as density tests that will not pass no matter how many passes are made. (7.7)

8 Delivery, Stockpiling, and Handling

8.1 Each load of aggregate shall be delivered with a ticket stating the source, the material designation, the date, and the net weight, and the Contractor shall keep the tickets for the delivery summary.
8.2 Aggregate shall be loaded, hauled, and dumped so that the coarse and fine fractions do not separate, and a load that arrives visibly segregated shall be remixed before it is spread or shall be rejected.
8.3 Where aggregate is stockpiled on the site, the stockpile shall be built in horizontal layers on a prepared, drained surface, and shall not be built as a cone by dumping from one point.
8.4 Aggregate shall be recovered from a stockpile by working the full face, and the bottom 6 in. of a stockpile built on soil shall not be used.
8.5 Aggregate that has frozen in the stockpile or in the truck, or that contains frozen lumps, shall not be placed.
NOTE A dense-graded aggregate segregates every time it rolls down a slope: the coarse particles run to the bottom and the fines stay where they landed. A coned stockpile and an end-dumped pile both produce pockets of clean stone that cannot be compacted to density beside pockets of fines that hold water, from a material that met its gradation at the plant. (8.6)

9 Placement and Spreading

9.1 Lift Thickness

9.1.1 Base and subbase shall be placed in lifts whose compacted thickness does not exceed that indicated in the datasheet.
Compacted Lift Thicknessrange
Not more than
in
34681012
NOTE A roller densifies from the top down, and the density at the bottom of a lift falls off as the lift thickens. Six inches is the depth a vibratory roller of ordinary size reaches reliably in a dense-graded aggregate and the depth a nuclear gauge probe is commonly set to; 8 in. and thicker lifts save a pass of the spreader on a thick section and depend on a heavy roller and on a test strip that proves the bottom of the lift; 3 to 4 in. is the lift for plate compactors and small rollers in confined work. (9.1.2)
9.1.3 No lift shall have a compacted thickness less than 3 in. or less than twice the nominal maximum particle size of the aggregate, whichever is greater.
9.1.4 Where a course is thicker than the lift thickness in the datasheet, it shall be placed in lifts of approximately equal thickness, and each lift shall be compacted, tested, and found passing before the next is placed.
9.1.5 The surface of a lift that has dried, crusted, or been contaminated before the next lift is placed shall be cleaned, moistened, and lightly scarified so the lifts bond.

9.2 Spreading

9.2.1 Aggregate shall be spread to a uniform loose depth by a mechanical spreader, a spreader box, a paver, or a motor grader working from windrows or from loads dumped at measured intervals.
9.2.2 Aggregate shall not be spread by pushing a single dumped pile across the grade with a dozer, except in an area too small for other equipment.
9.2.3 Spreading shall proceed so that haul trucks travel on spread base and not on the uncovered subgrade wherever the subgrade ruts under them, and over a geosynthetic in every case.
9.2.4 The first lift over a geosynthetic shall be placed and spread under the cover placement requirements for geosynthetics of the Contract Documents, stated for this Project in GeosyntheticsGeosynthetics and GeotextilesResolves to the current adopted revision.sync/geosynthetics, and shall then be compacted and tested as any other lift under this standard.
9.2.5 Areas of coarse, open-textured aggregate or of excess fines visible in the spread lift shall be removed or remixed with a grader before compaction.
9.2.6 The Contractor shall not place more base in a day than can be compacted and tested that day.

10 Moisture Conditioning and Compaction

10.1 Moisture at Compaction

10.1.1 At the time of compaction, the moisture content of the aggregate through the full depth of the lift shall be not drier than optimum by more than the amount indicated in the datasheet, with optimum taken from the reference compaction curve for the material.
Moisture Window, Dry of Optimumrange
Not more than
percentage points
1234
10.1.2 At the time of compaction, the moisture content of the aggregate through the full depth of the lift shall be not wetter than optimum by more than the amount indicated in the datasheet.
Moisture Window, Wet of Optimumrange
Not more than
percentage points
123
NOTE A dense-graded aggregate has a narrow moisture window because its fines are few and non-plastic: too dry, and the particles lock before they have moved into their densest arrangement; too wet, and the water carries the load, the surface weaves under the roller, and the fines pump to the top. Two points either side of optimum is the common window; the wet side is narrowed to one point or to zero for a material with fines near the limit or a subgrade that softens when water drains into it, and the dry side is widened in an arid climate where the lift loses water faster than a water truck can replace it. (10.1.3)
10.1.4 The moisture shall be brought into the window by one of the methods indicated in the datasheet.
Acceptable Moisture Conditioning Methodscheckbox
Any of:
☑ Mixed with water in a pugmill at the source
☑ Water added and mixed through the lift on grade
10.1.5 Water added on grade shall be mixed through the full depth of the lift with a grader or a mixer before compaction, and sprinkling the surface of a spread lift shall not be accepted as moisture conditioning.
10.1.6 Aggregate wetter than the window shall be aerated by blading until it is within the window, or shall be removed.
10.1.7 The Contractor shall not compact aggregate outside the moisture window on the expectation that the density test will pass.

10.2 Compaction Reference and Targets

10.2.1 The laboratory compaction curve against which field density is compared shall be developed for each source and material by the reference method indicated in the datasheet, which shall be the method on which the pavement design states its compaction requirement for the base.
Laboratory Compaction Reference Methodradio
○ ASTM D698 standard effort
○ ASTM D1557 modified effort
Derived — the compaction test method on which the pavement design in the geotechnical report states its base compaction requirement (by default)
NOTE Modified effort puts about four and a half times the energy of standard effort into the specimen and returns a higher maximum density at a lower optimum moisture, so a percentage of one is not the same density as that percentage of the other. Aggregate base is specified against modified effort by most pavement designers and by the AASHTO T 180 states, and against standard effort, usually at 100 percent or more, by the AASHTO T 99 states. The method follows the pavement design because the design assumed one of them. (10.2.2)
10.2.3 Where the pavement design does not state a reference method for the base, ASTM D1557 shall be used.
10.2.4 Where more than 5 percent of the aggregate by mass is retained on the sieve that bounds the specimen in the compaction method used, the maximum dry density and optimum moisture shall be corrected for the oversize fraction per ASTM D4718/D4718M.
10.2.5 The base course shall be compacted through the full depth of each lift to not less than the percentage of maximum dry density indicated in the datasheet.
Compaction Target, Base Courserange
Not less than
% of maximum dry density
929598100102105
Per drawings — the pavement design recommendations of the geotechnical report (deferred by default)
10.2.6 A subbase course shall be compacted through the full depth of each lift to not less than the percentage of maximum dry density indicated in the datasheet.
Compaction Target, Subbase Courserange
Not less than
% of maximum dry density
90929598100102
Per drawings — the pavement design recommendations of the geotechnical report (deferred by default)
10.2.7 Where the pavement design does not state a compaction target, the target for base and for subbase shall be 95 percent where the reference method is ASTM D1557 and 100 percent where it is ASTM D698.
NOTE A higher target buys stiffness and less rutting in the base under the first years of traffic, at the cost of more passes, a narrower workable moisture range, and more failing tests. Against modified effort, 95 percent is the common target for site pavements and slabs, and 98 to 100 percent is set beneath heavy truck lanes, loading docks, and container or crane areas. Against standard effort the same densities read as 100 to 105 percent. A subbase is commonly set at or a step below the base, because the stress it sees is lower. (10.2.8)
10.2.9 Base within a confined area, at an edge, or against a structure shall meet the same compaction target as base in the open.

10.3 Compaction Equipment and Rolling

10.3.1 Base in open areas shall be compacted with a smooth-drum vibratory roller, or with a pneumatic-tired roller, of a size that reaches the compaction target through the full lift thickness placed.
10.3.2 Rolling shall begin at the low edge of a sloped surface and at the outer edges of a crowned one, and shall progress toward the high side with each pass overlapping the last.
10.3.3 Vibration shall be turned off when the roller stops or reverses, and on the final passes where continued vibration loosens the surface or breaks down the aggregate.
10.3.4 Rolling shall continue until the lift meets the compaction target, shows no movement under the roller, and has a tight surface with no loose or segregated stone.
10.3.5 A lift that weaves, pumps, or ruts under the roller shall not be accepted on a passing density test, and the Contractor shall determine whether the lift is too wet or the subgrade beneath it has softened and shall correct the cause.

10.4 Compaction Beside Structures

10.4.1 Heavy vibratory rollers shall not operate within the setback indicated in the datasheet from a foundation, wall, curb, catch basin, manhole, light pole base, or other structure, or directly over a pipe or duct bank with less cover than the standard for that utility requires for construction loading.
Heavy Vibratory Roller Setback From Structuresrange
Not less than
ft
23456810
10.4.2 Base within the setback shall be compacted with plate compactors, rammers, or small walk-behind rollers in lifts not exceeding the hand-compacted lift thickness indicated in the datasheet.
Hand-Compacted Lift Thicknessrange
Not more than
in
346
NOTE A large vibratory drum beside a wall loads the wall sideways and shakes whatever is cast or buried next to it, and a curb or a shallow pipe is cracked this way more often than by anything that drives over it later. A 3 ft setback clears curbs, inlets, and pole bases; 5 ft and more is set beside tall or freshly cast walls and waterproofed surfaces; the hand-compacted lift is thinned to match what a plate actually reaches, and the strip along a curb or around a manhole is where pavements settle first because it is where this lift is most often placed full depth and rolled once. (10.4.3)

11 Base Beneath Building Slabs and Pads

11.1 Requirements in this article apply where a dense-graded aggregate base is the subbase beneath a building slab on ground or the base beneath an equipment pad.
11.2 The thickness of the base and the tolerance of its surface shall be those stated by the slab-on-ground and equipment pad requirements of the Contract Documents, stated for this Project in Slab On GradeSlab-on-GradeResolves to the current adopted revision.sync/slab-on-grade and Concrete PadsConcrete Equipment PadsResolves to the current adopted revision.sync/concrete-pads, and the thickness, extension, and surface tolerance fields of this standard shall not apply.
11.3 The base shall be placed after the under-slab plumbing, electrical, and drainage lines have been installed, tested, and backfilled, and the backfill of each trench shall be accepted before base is placed over it.
11.4 Base placed within the foundation walls shall be compacted with equipment that respects the roller setback of this standard from the walls, the column footings, and the pipe risers, and with hand-operated equipment within that setback.
11.5 Where a loaded truck cannot reach the base inside the building, the geotechnical engineer of record shall accept the completed base on the density tests and on observation of the surface under the compaction equipment, and proof rolling of the completed base shall not be required there.
11.6 The base beneath a slab shall be compacted, tested, and accepted before the vapor retarder, the reinforcement, or the edge forms are placed on it.
NOTE Inside a building the base is cut up by footings, risers, and trenches into areas a full-size roller cannot work, and it is built by the building contractor's crew rather than a paving crew. The failures follow from that: a trench across the slab backfilled after the base was accepted, a strip along the wall placed full depth and never compacted, and a surface regraded by hand after testing. The article exists to keep the same lift, moisture, and density rules in force where the equipment is smaller. (11.7)

12 Base in Trench Restorations and Pavement Patches

12.1 Requirements in this article apply where base is replaced in a utility trench cut through an existing pavement, in a full-depth pavement patch, and over a new trench that crosses an area already brought to base grade.
12.2 The trench backfill or the patch subgrade shall be compacted and accepted under the trench backfill and subgrade requirements of the Contract Documents, stated for this Project in EarthworkEarthworkResolves to the current adopted revision.sync/earthwork, before base is placed on it.
12.3 The replacement base shall be the base aggregate of this standard, at a compacted thickness not less than the adjoining existing base and not less than the thickness shown on the trench restoration and pavement patch details on the civil drawings.
12.4 The existing pavement and base shall be cut back beyond each trench wall by the distance indicated in the datasheet, so that the replacement base bears on undisturbed material at its edges.
Base Cutback Beyond Each Trench Wallrange
Not less than
in
6121824
NOTE The soil at the lip of a trench loosens and ravels while the trench is open, and a patch built only as wide as the trench sits with its edges on that loosened strip; the pavement then cracks along both sides of the patch. A 12 in. cutback, the T-shaped patch of most municipal details, carries the edge of the new base onto ground the trench never disturbed. A wider cutback is set where the trench was deep or stood open long, and zero is the condition where the trench was cut and shored with vertical walls and the authority that owns the pavement asks for the narrowest patch. (12.5)
12.6 Replacement base shall be placed in lifts not exceeding the hand-compacted lift thickness in the datasheet wherever the width of the cut does not admit a roller, and each lift shall be compacted to the base compaction target.
12.7 Not less than one field density test shall be taken on each lift of replacement base in each trench crossing or patch, and not less than one per lift for each 100 linear ft of trench.
12.8 The surface courses over the replacement base shall be built under the standard for the pavement being restored.

13 Thickness and Surface Tolerances

13.1 The finished surface of the base beneath a pavement, curb, or walk shall be within the elevation tolerance indicated in the datasheet of the design elevation.
Finished Base Surface Elevation Tolerancerange
Not more than
in
0.250.3750.50.751
13.2 The finished surface of the base beneath a pavement shall not deviate from a 10 ft straightedge, laid in any direction, by more than the amount indicated in the datasheet.
Finished Base Surface Deviation Under a 10 ft Straightedgerange
Not more than
in
0.250.3750.50.75
13.3 The compacted thickness of each course at any point shall not be less than the required thickness by more than the amount indicated in the datasheet, and the average of the thickness measurements in any area shall not be less than the required thickness.
Course Thickness Deficiency at Any Pointrange
Not more than
in
0.250.3750.50.751
NOTE The base surface is the form the surface course is cast against. A high spot comes straight out of the asphalt or concrete thickness above it, and a low spot is filled with the more expensive material; an asphalt paver follows the base and reproduces its waves, while a concrete paver strikes off a plane and turns them into thickness variation. Half an inch on elevation and three-eighths in 10 ft suit an asphalt section of ordinary thickness and a concrete pavement; the tighter values are set beneath a thin asphalt section, where a half-inch high spot is a large share of the lift, and the looser ones beneath a subbase or a thick section where a following course absorbs the variation. (13.4)
13.5 The tolerances of this article shall apply to a full-depth reclaimed or chemically treated base only to the extent the standard for that base adopts them.
13.6 A high area shall be corrected by trimming to grade and rerolling, and the trimmed material shall be removed and not spread as a thin layer elsewhere.
13.7 A low area shall be corrected by scarifying to a depth of not less than 3 in., adding aggregate, mixing, and recompacting, and shall not be filled with a thin layer on the compacted surface.
13.8 An area deficient in thickness shall be corrected by scarifying, adding aggregate, and recompacting to the required thickness and elevation, and the surface course shall not be thickened to make up the deficiency unless the Engineer of Record accepts it in writing.
13.9 The finished base shall drain at the cross slope and grade of the pavement above it, and shall hold no ponded water.

14 Proof Rolling of the Completed Base

14.1 The completed base beneath pavements shall be proof-rolled to the extent indicated in the datasheet, in the presence of the geotechnical engineer of record, before it is accepted.
Proof Rolling of the Completed Baseradio
● Entire base surface beneath pavements
○ Areas the geotechnical engineer of record designates
○ Not required
NOTE A density test proves the top lift at one spot; a loaded truck proves the whole section, base and subgrade together, across the whole area, and it finds the subgrade that softened after it was accepted and the trench that was backfilled late. Rolling the entire surface is the check the paving standards assume before the first course. Rolling designated areas is used on a large site where the engineer has watched placement and wants the truck only over trenches, transitions, and areas that tested marginally. Omitting it is the position where the base is thin and the subgrade proof roll was recent and the base was placed immediately over it, and wherever a loaded truck would damage what lies beneath. (14.2)
14.3 Proof rolling shall be performed with a loaded rubber-tired dump truck or a pneumatic-tired roller of gross weight not less than that indicated in the datasheet, in overlapping passes at a speed not exceeding 3 mph.
Base Proof-Rolling Vehicle Gross Weightrange
Not less than
tons
101520253040
14.4 An area of base that ruts or deflects under the proof-rolling vehicle by more than the limit indicated in the datasheet, or that pumps, weaves, or cracks, shall be rejected.
Base Proof-Rolling Rut and Deflection Limitrange
Not more than
in
0.250.50.751
NOTE A compacted base is stiffer than the subgrade it sits on, so the limit under the truck is tighter than the one the subgrade was held to: movement of half an inch in a finished base means something beneath it is yielding. A quarter inch is set beneath heavy truck pavements; the looser limits are set over a subgrade the geotechnical report describes as resilient but stable, where the base deflects and recovers without rutting. (14.5)
14.6 Where an area is rejected, the Contractor shall remove the base to the depth needed to find the cause, shall correct a base cause under this standard and a subgrade cause under the subgrade requirements of the Contract Documents, and shall rebuild, retest, and re-proof-roll the area.
14.7 Correction of a rejected area shall be at the Contractor's expense, except where the cause is a subgrade condition that was accepted and that the Contractor's traffic, delay, or failure to protect did not cause.
14.8 Proof rolling shall not be performed on a base that is frozen or that has standing water on it.

15 Field Testing and Acceptance

15.1 Field Density Testing

15.1.1 Field density and moisture shall be measured by the method indicated in the datasheet.
Field Density Test Methodradio
● Nuclear gauge, ASTM D6938
○ Sand cone, ASTM D1556/D1556M
NOTE The nuclear gauge tests a spot in minutes without disturbing it, which lets a failed spot be retested after more passes and lets one technician keep pace with a spreader. The sand cone is the reference the gauge is checked against and the method where a gauge cannot be licensed or carried; it takes most of an hour per test and its hole is hard to dig cleanly in a coarse base. (15.1.2)
15.1.3 Nuclear gauge tests shall be taken in direct transmission with the source rod set to the depth of the lift, and not in backscatter.
15.1.4 The testing agency shall check the nuclear gauge against the sand-cone method on each source and material at the start of production and at not less than one check per 20 nuclear tests thereafter.
15.1.5 On recycled concrete aggregate and on a blend containing reclaimed asphalt pavement, the testing agency shall establish a moisture correction for the nuclear gauge from oven-dried samples per ASTM D2216 before the gauge moisture readings are used, and shall apply it per ASTM D6938.
NOTE The gauge infers water from hydrogen, and it counts the hydrogen bound in cement paste and in asphalt as water. Uncorrected, it reports a recycled base as wetter and therefore less dense, dry, than it is, and a crew chasing that false reading over-rolls and breaks down the material. (15.1.6)
15.1.7 Field density tests on each lift of base and subbase shall be taken at not less than one test for each area of lift surface indicated in the datasheet, and not less than one test per lift in each separately placed area on each day of placement.
Base Area Per Density Testrange
Not more than
sq ft per test per lift
500100015002000250030005000
15.1.8 Test locations shall be selected by the testing agency and not by the Contractor, and shall include the strips beside curbs and structures and the areas over trenches in proportion to their share of the area.
15.1.9 Each field density test shall meet the compaction target, and each moisture measurement shall be reported against the moisture window.

15.2 Production Material Testing

15.2.1 The testing agency shall sample the aggregate as delivered, from the spread lift before compaction, and shall test gradation per ASTM C136/C136M and ASTM C117 at not less than one test for each quantity indicated in the datasheet, and not less than one test for each source.
Aggregate Quantity Per Production Gradation Testrange
Not more than
tons per test
2505001000200025005000
15.2.2 Liquid limit and plasticity index shall be tested on one of every three production gradation samples, and on every sample whose fines content is within 1 percentage point of its limit.
NOTE A closer interval catches a quarry that has moved into a dirtier ledge before a week of its stone is under pavement; 1,000 tons is roughly a day of placement for one crew on site work. The interval is closed to 250 or 500 tons for a recycled or blended material, whose feedstock changes from load to load, and opened where the source carries a DOT listing and is tested daily by the producer under that program. (15.2.3)
15.2.4 Aggregate that fails a production test shall not be placed, and aggregate from the same production already placed shall be resampled in place and removed where it fails.

15.3 Thickness Measurement

15.3.1 The testing agency shall measure the compacted thickness of each course at not less than one location for each area per density test in the datasheet, by a test hole through the course or by the difference between surveyed elevations of the accepted subgrade and the finished course at the same point.
15.3.2 Test holes shall be backfilled with base aggregate compacted in lifts.

15.4 Failing Tests and Retesting

15.4.1 Where a field density test fails, the Contractor shall scarify the lift, bring its moisture within the window, recompact it, and request a retest at the same location before the next lift or the surface course is placed.
15.4.2 Where a retest also fails, the Contractor shall remove the lift, or shall rework it with the moisture, the equipment, or the lift thickness changed as the geotechnical engineer of record directs, and shall retest.
15.4.3 The cost of rework and of every retest after a failing test shall be borne by the Contractor.
15.4.4 Where tests in an area fail repeatedly, the geotechnical engineer of record shall determine whether the material, the moisture, the equipment, the lift thickness, or the subgrade is the cause, and shall direct the correction in writing.
15.4.5 Base or pavement placed over a lift before its failing test has been retested and passed shall be removed at the Contractor's expense.

15.5 Test Records and Reporting

15.5.1 Each field density test shall be recorded with the Project, date, test number, location by coordinates or by station and offset, course and lift, source and material, reference curve, wet density, moisture content, dry density, percent of maximum dry density, the target, and the pass or fail result.
15.5.2 The testing agency shall report each failing test to the Contractor's superintendent and to the geotechnical engineer of record on the day the test is taken.
15.5.3 The testing agency shall deliver the written report of each day's tests to the Owner, the Engineer of Record, the geotechnical engineer of record, and the Contractor within 24 hours of the tests.
15.5.4 Failing tests shall appear in the written reports with their retests, and a report that omits a failing test shall be corrected and reissued.

16 Weather Limits and Protection of the Completed Base

16.1 Base shall not be placed on a frozen subgrade or on a frozen lift, and shall not be placed when the aggregate cannot be compacted and tested before it freezes.
16.2 A lift that freezes before it is tested shall be thawed, brought within the moisture window, and recompacted before it is tested or covered.
16.3 Base placement shall stop when rain raises the moisture of the spread aggregate or of the receiving surface above the wet limit of the moisture window, and shall resume when both are within it.
NOTE A frozen base tests dense and thaws loose. The ice holds the particles apart at a volume the dry material would not keep, the gauge reads the ice as density, and the settlement appears in the spring under whatever was paved over it in the fall. (16.4)
16.5 The Contractor shall maintain the accepted base at grade, at density, and free of contamination until it is covered, and shall keep it damp enough that the surface does not ravel under traffic.
16.6 Construction traffic on the accepted base shall be limited to the vehicles needed to place the surface course, and mud tracked onto the base shall be removed with the contaminated aggregate beneath it.
16.7 An accepted base that has been rutted, loosened, contaminated, saturated, or frozen before it is covered shall be reworked, retested, and accepted again, at the Contractor's expense.
16.8 An accepted base beneath pavements that remains uncovered through a period of freezing weather, or for more than 30 days, shall be retested for density and proof-rolled again before it is covered.
NOTE An unbound base left open is a road, and it wears like one: the fines wash or blow off the surface, the stone loosens, and every truck that crosses a wet section works subgrade soil up into it. The acceptance on record describes the base on the day it was tested, and the last four requirements exist so that the base the surface course goes on is still that base. (16.9)

17 Warranty

17.1 The Contractor shall warrant the base and subbase courses against settlement, rutting, pumping, and loss of grade attributable to nonconforming aggregate, thickness, moisture, or compaction for the period indicated in the datasheet, beginning at substantial completion.
Base Course Warranty Periodrange
Not less than
years
1235
NOTE One year matches the correction period of most construction contracts and carries the base through one wet season and one winter, which is when a base with excess fines or low density shows itself. A longer period is set to match a longer pavement warranty, so the Owner is not left with a warranted surface on an unwarranted base. (17.2)
17.3 Warranty correction shall include removal and replacement of the nonconforming base, restoration of the pavement, slab, curb, or pad above it, and repair of damage to adjacent work caused by the defect or by the correction, at the Contractor's expense.
17.4 Where the parties disagree whether a defect in the surface is attributable to the base, to the subgrade beneath it, or to the surface course, the geotechnical engineer of record shall make the initial determination.
17.5 The warranty does not limit the Owner's remedies for a latent defect in the base discovered after the warranty period.

SynC Standards are reference material provided for informational purposes only and as a guide. They are not engineering, architectural, or legal advice and are not a substitute for the judgment of a licensed design professional. It is the responsibility of the user to determine the applicability of any standard to a specific project and to verify all requirements against the governing codes, manufacturer data, and project conditions. SynC does not render professional services and forms no professional relationship by publishing this content. Provided "as is," without warranty of any kind, including fitness for a particular purpose. See our Terms of Use for the complete terms. Moderation log.

This standard is written and maintained by SynC and licensed under Creative Commons Attribution 4.0. You may share and adapt it, including commercially, provided you credit SynC Standards, link to the license, and indicate any changes. Each standard is drafted from cited sources under published authoring rules, reviewed before adoption, and corrected in the open. Keep the attribution and notice below with any copy; it carries the warranty notice the license asks you to retain.

Attribution and reuse notice. Keep this with any copy:
"Aggregate Base Course," SynC Standards, revision 6. Licensed under CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Source: https://synergyinconstruction.com/standards/general/aggregate-base-course. Reference material only; not professional engineering advice and provided without warranty. Verify against governing codes and have a licensed professional review before use.