SynC · SynC Standards

Air Barriers

Rev4
IssuedAug 26, 2026

Revision history

Build a datasheet from this standard Start a project with this standard already attached — one click, no setup.
Use in a project

1 Scope

NOTE This standard covers the materials, accessories, substrate preparation, installation, transitions, and field verification of the continuous air barrier system for the above-grade exterior wall enclosure. (1.1)
NOTE An air barrier is the assembled system of materials, accessories, and connections that controls air movement across the building enclosure. It is distinct from, though frequently combined with, the water-resistive barrier, which controls liquid water, and the vapor retarder, which controls diffusion. A single product can perform all three functions, but the three requirements are evaluated separately and can be selected independently. (1.2)
NOTE Air leakage is the dominant moisture transport mechanism across an enclosure. Bulk air driven through gaps, laps, and unsealed transitions by wind, stack effect, and mechanical pressurization carries orders of magnitude more water vapor than diffusion through an intact membrane, and it carries that vapor to whatever surface inside the assembly is below the dew point. The consequences are energy loss, drafts and comfort complaints, entry of exterior pollutants and noise, and condensation that feeds mold growth, corrosion, and decay inside the wall. (1.3)
NOTE The defining property of an air barrier is continuity, not the material. The failures that matter are almost never a defective membrane in the field of the wall; they are discontinuities at the places where the plane changes material, changes direction, crosses a building system, or passes from one trade's scope to another's. This standard therefore treats transitions, sequencing, and verification as the substance of the work, and the selection of the field membrane as a comparatively minor decision. (1.4)
NOTE The boundary of work under this standard is the air barrier plane of the above-grade wall: from its tie-in to the below-grade waterproofing at or near grade, up the wall field, across every wall penetration and opening, to its tie-in to the roof air barrier at the parapet or eave. The following are outside that boundary: (1.5)
  • The roofing membrane and the roof air barrier plane, covered by Membrane RoofingMembrane RoofingResolves to the current edition.sync/membrane-roofing
  • Below-grade waterproofing and dampproofing, covered by Below Grade WaterproofingBelow-Grade WaterproofingResolves to the current edition.sync/below-grade-waterproofing
  • Windows, doors, and curtain walls as manufactured units, covered by GlazingGlass and GlazingResolves to the current edition.sync/glazing and Glazed Curtain WallsGlazed Curtain WallsResolves to the current edition.sync/glazed-curtain-walls
  • Joint sealants and their backing at opening perimeters and movement joints, covered by Joint SealantsJoint SealantsResolves to the current edition.sync/joint-sealants
  • Interior vapor retarders that serve no air barrier function, and through-penetration firestopping
NOTE The connection of the wall air barrier to each of the systems listed above is within this standard, even where the adjoining system is not. (1.6)
1.7 The air barrier system shall comply with the air leakage provisions of the adopted energy code, the weather protection provisions of the adopted building code, and the air barrier manufacturer's published installation instructions.

2 Referenced Standards

2.1 Materials, accessories, and installation shall comply with the latest adopted edition of each of the following unless a specific edition is cited.
2.2 Where the contract documents, the adopted codes, the manufacturer's installation instructions, or a referenced standard conflict, the more stringent requirement shall govern unless the Engineer of Record directs otherwise in writing.
Standard Title
IECC International Energy Conservation Code (commercial air leakage provisions)
IBC International Building Code (exterior wall weather protection and flame propagation provisions)
ASTM E2178 Standard Test Method for Determining Air Leakage Rate and Calculation of Air Permeance of Building Materials
ASTM E2357 Standard Test Method for Determining Air Leakage Rate of Air Barrier Assemblies
ASTM E1677 Standard Specification for Air Barrier (AB) Material or Assemblies for Low-Rise Framed Building Walls
ASTM E283 Standard Test Method for Determining Rate of Air Leakage Through Exterior Windows, Curtain Walls, and Doors Under Specified Pressure Differences Across the Specimen
ASTM E3158 Standard Test Method for Measuring the Air Leakage Rate of a Large or Multizone Building
ASTM E779 Standard Test Method for Determining Air Leakage Rate by Fan Pressurization
ASTM E1827 Standard Test Methods for Determining Airtightness of Buildings Using an Orifice Blower Door
ASTM E1186 Standard Practices for Air Leakage Site Detection in Building Envelopes and Air Barrier Systems
ASTM E96 Standard Test Methods for Gravimetric Determination of Water Vapor Transmission Rate of Materials
ASTM E84 Standard Test Method for Surface Burning Characteristics of Building Materials
ASTM E1354 Standard Test Method for Heat and Visible Smoke Release Rates for Materials and Products Using an Oxygen Consumption Calorimeter
ASTM E331 Standard Test Method for Water Penetration of Exterior Windows, Skylights, Doors, and Curtain Walls by Uniform Static Air Pressure Difference
ASTM D4541 Standard Test Method for Pull-Off Strength of Coatings Using Portable Adhesion Testers
ASTM D7234 Standard Test Method for Pull-Off Adhesion Strength of Coatings on Concrete Using Portable Pull-Off Adhesion Testers
ASTM D3330 Standard Test Method for Peel Adhesion of Pressure-Sensitive Tape
ASTM D779 Standard Test Method for Water Resistance of Paper, Paperboard, and Other Sheet Materials by the Dry Indicator Method
AATCC 127 Water Resistance: Hydrostatic Pressure Test
AAMA 711 Voluntary Specification for Self-Adhering Flashing Used for Installation of Exterior Wall Fenestration Products
AAMA 714 Voluntary Specification for Liquid-Applied Flashing Used to Create a Water-Resistive Seal Around Exterior Wall Openings
NFPA 285 Standard Fire Test Method for Evaluation of Fire Propagation Characteristics of Exterior Non-Load-Bearing Wall Assemblies Containing Combustible Components
ABAA QAP Air Barrier Association of America Site Quality Assurance Program (contractor accreditation, installer certification, and independent site audits)

3 Submittals

3.1 Action Submittals

NOTE The air barrier, its accessories, and the adjoining water- and vapor-control products are reviewed as one coordinated system rather than as a set of individual products, because the interfaces between products that were never verified compatible are where the plane most often opens. (3.1.1)
3.1.2 The Contractor shall submit the following for the Engineer of Record's review and return before procurement and installation:
  • Product data for the primary air barrier material, reporting material air permeance per ASTM E2178, assembly air leakage per ASTM E2357 where an assembly test is the qualification basis, water vapor permeance per ASTM E96 with the resulting vapor retarder class, surface burning characteristics per ASTM E84, and the published maximum exposure period before cover-up
  • Product data for every accessory material, including transition membranes, self-adhered and liquid-applied flashings, primers, termination mastics, seam tapes, sealants, and fasteners with their reinforcing plates or washers
  • Product data for self-adhered flashing showing conformance to AAMA 711 and for liquid-applied flashing showing conformance to AAMA 714, for flashings used at fenestration openings
  • A schedule of every substrate the air barrier will be applied to, with the primer and surface preparation required for each
  • Shop drawings on which the air barrier plane is drawn as a single unbroken line on every wall section, with a keyed transition detail at the roof or parapet, the grade line, each opening type, each attachment through the plane, each movement joint, and each typical penetration
  • Written compatibility documentation from the primary air barrier manufacturer covering the accessories, the adjoining waterproofing and roofing membranes, the joint sealants, the fenestration perimeter seals, and any adhesives used to attach insulation or cladding components through or against the plane
  • Evidence of compliance with the vertical and lateral flame propagation provisions of the adopted building code for the exterior wall assembly incorporating the air barrier
Action Submittals Requiredcheckbox
Primary air barrier product data
Accessory product data
Fenestration flashing data conforming to AAMA 711 or AAMA 714
Substrate list with required primer and preparation for each
Air barrier continuity shop drawings with keyed transition details
Manufacturer system compatibility documentation
Exterior wall flame propagation compliance evidence
Samples of primary membrane, transition membrane, and primer

3.2 Informational Submittals

NOTE Informational submittals establish who is qualified to do the work and how it will be proven, and they are due early enough that a deficiency can still be corrected by substitution rather than by demolition. (3.2.1)
3.2.2 The Contractor shall submit the following for the Engineer of Record's information before air barrier work begins:
  • Installer accreditation, licensing, and certification records for the air barrier contractor and for each installer who will work on the plane
  • A written air barrier quality control plan describing inspection hold points, the field adhesion test protocol and acceptance value for each substrate, and the record forms to be used
  • A whole-building air leakage test plan prepared by the testing agency, describing the test method, equipment and crew, the enclosure area calculation, the treatment of intentional openings, the test pressure differential, the number and location of pressure taps, and the acceptance target
  • Qualifications of the whole-building air leakage testing agency and of the individual who will direct the test
  • The manufacturer's field service schedule identifying who will attend and at which milestones
  • A sequencing plan identifying, for each transition type, which trade installs each component and in what order
Informational Submittals Requiredcheckbox
Installer accreditation, licensing, and certification records
Air barrier quality control plan with inspection hold points
Whole-building air leakage test plan
Testing agency qualifications
Manufacturer field service schedule
Transition sequencing and trade responsibility plan
Cold weather or hot weather application procedures

3.3 Closeout Submittals

NOTE The closeout package is the only durable record that the concealed portion of the plane was built as specified, since none of it can be re-examined once the cladding is on. (3.3.1)
3.3.2 At Substantial Completion the Contractor shall submit the following before the air barrier work is accepted:
  • The whole-building air leakage test report, recording the method, the enclosure area, the measured leakage rate normalized to enclosure area at the specified test pressure, the determination against the acceptance target, and the location, cause, repair, and re-test result for every leak addressed
  • Field adhesion test records identifying each test location, substrate, recorded value, mode of failure, and result
  • Daily installation and inspection records, including ambient and substrate temperature and substrate moisture at the time of each application
  • The manufacturer's field reports from each site visit
  • Executed installer and manufacturer warranties
  • As-built transition details for every condition where the field condition differed from the approved shop drawing
  • Air leakage site detection records where diagnostic evaluation was performed
Closeout Submittals Requiredcheckbox
Whole-building air leakage test report
Field adhesion test records
Daily installation and inspection records
Manufacturer field reports
Executed installer and manufacturer warranties
As-built transition details for field-modified conditions
Air leakage site detection records
Turnover of unopened repair materials

4 Installer Qualification and Site Quality Assurance

4.1 Installer Accreditation

NOTE The work that determines whether an air barrier performs — laps, terminations, transitions, and detailing at penetrations — is also the work that becomes unreachable first. Where the enclosure schedule closes in the wall before the whole-building test, installer qualification is the only quality control that acts before the evidence is buried. (4.1.1)
NOTE The Air Barrier Association of America Site Quality Assurance Program accredits the contracting company, certifies the individual installers, and assigns an independent licensed auditor to the project. Manufacturer licensing programs instead qualify the installer for one named system and tie the system warranty to that qualification. The two mechanisms verify different things, and a project may require either or both. (4.1.2)
4.1.3 The air barrier installer shall meet the qualification basis indicated in the datasheet for the system being installed.
Installer Qualification Basisradio
ABAA-accredited contractor employing ABAA-certified installers
Manufacturer-trained and licensed installer for the specified system
Either ABAA accreditation or manufacturer licensing
Both ABAA accreditation and manufacturer licensing
Documented project experience record without third-party accreditation or manufacturer licensing
4.1.4 The air barrier installer shall have completed air barrier installations of comparable material type, wall area, and transition complexity, and shall submit a record of those projects.
4.1.5 A certified or licensed installer shall be present on site whenever air barrier or transition work is in progress.

4.2 ABAA Site Quality Assurance Program Audits

NOTE The program's site audits are performed by an auditor licensed by the association and independent of both the contractor and the manufacturer, and the audit count scales with the installed air barrier area. Where the Owner has no other independent observer on the enclosure, this is the mechanism that supplies one. (4.2.1)
4.2.2 Where the datasheet indicates the ABAA Site Quality Assurance Program applies, the Contractor shall enroll the project, shall permit the licensed auditor access to the work, and shall issue the daily installer reports the program requires.
ABAA Site Quality Assurance Programradio
Required — project enrolled, independent licensed auditor site audits performed
Not required
4.2.3 Where the datasheet indicates the program applies, the Contractor shall correct every deficiency the auditor records, and shall include the audit reports in the closeout submittals.
4.2.4 The cost of program enrollment and of the audits shall be borne by the Contractor.

4.3 Manufacturer Field Services

NOTE Manufacturer system warranties are commonly conditioned on documented site visits by the manufacturer's technical representative. A visit that was never scheduled is a warranty that was never earned, and the omission is normally discovered only when a claim is made. (4.3.1)
4.3.2 The Contractor shall schedule and coordinate the air barrier manufacturer's field visits at the milestones indicated in the datasheet.
Manufacturer Field Visit Milestonescheckbox
Preinstallation conference
Mockup construction
Start of field installation
First installation of each transition type
Periodic visits during installation
Final inspection before cover-up
4.3.3 The manufacturer's technical representative shall record each visit in a written field report identifying the work observed, any nonconforming condition, and the corrective action directed.
4.3.4 The manufacturer's technical representative shall confirm in writing that the installation conforms to the requirements on which the system warranty depends.

4.4 Preinstallation Conference

NOTE Discontinuities originate far more often in unclear trade boundaries than in defective materials. A transition detail that three subcontractors each believe another is installing is a hole in the plane that no product selection can close. (4.4.1)
NOTE The purpose of the conference is to fix on paper, before any material is installed, which trade installs each component of each transition, in what sequence, and how responsibility for continuity is handed off at each boundary. (4.4.2)
4.4.3 The Contractor shall convene a preinstallation conference before air barrier work begins where the datasheet indicates the conference is required.
Preinstallation Conferenceradio
Required before air barrier work begins
Not required
4.4.4 The Contractor shall require attendance by the Engineer of Record, the air barrier manufacturer's technical representative, the air barrier installer, and the installer of every adjacent trade whose work touches or penetrates the air barrier plane, including waterproofing, roofing, fenestration, cladding, sheet metal flashing, joint sealants, and the mechanical, electrical, and structural trades whose work penetrates the wall.
4.4.5 The conference shall resolve, in writing, the trade responsibility and installation sequence for each transition type shown on the approved shop drawings.
4.4.6 The Contractor shall distribute the written record of the conference to every attendee and shall include it in the closeout submittals.

4.5 Air Barrier Mockup

NOTE A mockup converts an argument about workmanship into a physical benchmark that both the Engineer of Record and the manufacturer have accepted, and it exposes detailing problems while the correction still costs a day rather than a facade. (4.5.1)
4.5.2 The Contractor shall construct an air barrier mockup of the type indicated in the datasheet.
Mockup Typeradio
Freestanding mockup constructed away from the building
In-place mockup constructed in the work and permitted to remain if accepted
Not required
4.5.3 The mockup shall be of the area indicated in the datasheet.
Mockup Wall Arearange
ft²
50500
4.5.4 The mockup shall incorporate the transition conditions indicated in the datasheet, each built with the materials, sequence, and workmanship proposed for the work.
Mockup Transition Conditionscheckbox
Wall field of the primary air barrier
Sheathing joint or substrate joint
Inside corner and outside corner
Window or door perimeter with sill, jamb, and head flashing
Round penetration
Irregular penetration or clustered penetrations
Movement joint
Wall-to-roof or parapet transition
Wall-to-foundation transition at the grade line
Cladding attachment through the plane
4.5.5 The mockup shall be reviewed and accepted in writing by the Engineer of Record and the manufacturer's technical representative before field installation begins, and shall thereafter establish the standard of workmanship for the work.
4.5.6 The Contractor shall perform a field adhesion test on the mockup, using the method and acceptance value specified for field quality control, before the mockup is submitted for acceptance.
4.5.7 The accepted mockup shall remain undisturbed and available for comparison until the air barrier work is accepted.

5 Air Leakage Performance

NOTE Air barrier performance is defined at three scales, and passing at one scale does not imply passing at the next. A material can meet its permeance limit and leak badly as an assembly if its laps and terminations are poor; an assembly can meet its limit and the building still leak if the transitions between assemblies are discontinuous. Each scale therefore has its own limit, its own test method, and its own point in the schedule at which it is proven. (5.1)

5.2 Product Qualification Basis

NOTE Material qualification tests air moving through the material itself, with no laps, fasteners, or accessories present. Assembly qualification tests a representative wall specimen including its laps, seams, fasteners, and accessory transitions, before and after structural loading cycles, so it captures the detailing that the material test cannot. The permitted assembly leakage is an order of magnitude above the material limit; that gap is the allowance for field jointing. (5.2.1)
5.2.2 The air barrier shall be qualified on the basis indicated in the datasheet before it is installed.
Product Qualification Basisradio
Material air permeance (ASTM E2178)
Assembly air leakage (ASTM E2357)
Both material and assembly qualification
5.2.3 Qualification test reports shall be issued by a laboratory accredited for the test method and shall identify the specific product and, for assembly qualification, the specific substrate and accessory set tested.

5.3 Material Air Permeance

NOTE The material limit is the threshold that separates an air barrier material from an ordinary building material, and it is the floor every product forming part of the plane must clear. (5.3.1)
5.3.2 Where material qualification is indicated in the datasheet, each material forming part of the continuous air barrier shall have an air permeance not greater than the limit indicated in the datasheet, tested in accordance with ASTM E2178 at a pressure differential of 75 Pa.
Material Air Permeance Limitrange
cfm/ft² at 75 Pa
0.0010.0020.004
NOTE The material air permeance limit of 0.004 cfm/ft² at 75 Pa is the maximum the commercial energy code permits; tighter limits are selectable where the project energy model or Owner program requires them. (5.3.3)

5.4 Assembly Air Leakage

NOTE Assembly qualification is performed on a representative wall specimen that includes the substrate, the primary material, the laps and seams, the fasteners, and the accessory transitions, conditioned by sustained, cyclic, and gust wind loading before and after the leakage measurement. It is the closest laboratory analogue to what the wall will actually be. (5.4.1)
5.4.2 Where assembly qualification is indicated in the datasheet, the air barrier assembly shall have an average air leakage not greater than the limit indicated in the datasheet, tested in accordance with ASTM E2357 at a pressure differential of 75 Pa.
Assembly Air Leakage Limitrange
cfm/ft² at 75 Pa
0.010.020.04
5.4.3 Assembly qualification by ASTM E1677 or ASTM E283 shall be acceptable where the adopted energy code permits that method for the assembly in question.

5.5 Whole-Building Air Leakage Target

NOTE The whole-building measurement is the only one that captures the continuity of the enclosure as actually built, including every transition, every penetration, and every trade handoff. It is also the only one that arrives too late to be cheap to fix, which is why the target belongs in the contract from the outset rather than in a change order. (5.5.1)
5.5.2 The completed enclosure shall be tested and shall not exceed the whole-building air leakage target indicated in the datasheet, normalized to the enclosure area at the specified test pressure differential.
Whole-Building Air Leakage Targetrange
cfm/ft²
0.050.10.150.250.30.4
NOTE The target of 0.40 cfm/ft² at 75 Pa is the ceiling the commercial energy code sets for the tested thermal envelope. Federal and Owner programs commonly set 0.25 cfm/ft², and enclosures designed to passive-building criteria are commonly held near 0.05 cfm/ft². Where the project energy model assumes a leakage rate, the target should be set to the modeled value. (5.5.3)
5.5.4 The enclosure area against which the measured leakage is normalized shall be calculated by the testing agency, shall be submitted with the test plan, and shall be accepted by the Engineer of Record before the test is performed.
5.5.5 Where a test pressure differential other than 75 Pa is indicated in the datasheet, the target air leakage rate shall be stated at that pressure differential.

6 Control Layer Role and Vapor Permeance

6.1 Air Barrier and Water-Resistive Barrier Relationship

NOTE Whether one product carries both the air and water control functions is an independent decision from which material type is used, and it changes what must be submitted, what must be tested, and how the plane is lapped. A combined plane must additionally resist liquid water and must be shingle-lapped so that water reaching it drains out; a discrete air barrier behind a separate water-resistive barrier need not, but adds a second plane whose own continuity must be detailed. (6.1.1)
6.1.2 The relationship between the air barrier and the water-resistive barrier shall be as indicated in the datasheet.
Air Barrier and Water-Resistive Barrier Relationshipradio
Combined — the air barrier also serves as the water-resistive barrier
Separate — a discrete water-resistive barrier is provided in addition to the air barrier
6.1.3 The air barrier and the water-resistive barrier shall be lapped shingle-fashion so that water reaching either plane drains down and out to the exterior and not into the assembly.

6.2 Water Penetration Resistance of the Combined Plane

6.2.1 Where the air barrier also serves as the water-resistive barrier, it shall resist water penetration under the weather protection provisions of the adopted building code.
6.2.2 Where the air barrier also serves as the water-resistive barrier, water penetration resistance shall be demonstrated by the test basis indicated in the datasheet.
Water Penetration Test Basisradio
AATCC 127 hydrostatic pressure test
ASTM D779 dry indicator method
ASTM E331 static water penetration of the opening assembly
Not applicable — a separate water-resistive barrier is provided
NOTE The hydrostatic pressure test measures the head of water a sheet material resists before it wets through, and is the usual basis for sheet and fabric-type barriers. The static water penetration test measures an assembled opening under simultaneous air pressure and water spray, and is the usual basis where the qualification is of the opening rather than of the field material. The two answer different questions and are not interchangeable. (6.2.3)

6.3 Vapor Permeance Class

NOTE Vapor class is the most consequential material property after continuity, and it is independent of air permeance: a material can be nearly airtight at any vapor permeance. The wrong vapor class traps moisture inside the assembly and decays it even when the air barrier itself is flawless. (6.3.1)
NOTE Vapor retarder class follows from measured permeance by the desiccant method of ASTM E96: Class I is 0.1 perm or less, Class II is greater than 0.1 perm and not more than 1.0 perm, and Class III is greater than 1.0 perm and not more than 10 perms. A material above 10 perms is vapor permeable and is not a vapor retarder. (6.3.2)
NOTE Where the dominant seasonal vapor drive is outward, an exterior air barrier of low vapor permeance places a condensing surface on the cold side of the insulation and prevents the assembly from drying outward, so a vapor-permeable exterior air barrier is used with any vapor retarder placed toward the warm side. Where the dominant drive is inward, the same reasoning inverts and a vapor-impermeable exterior air barrier resists the inward drive. The governing question in both cases is where the dew point falls within the assembly, which depends on the insulation type, the insulation position relative to the air barrier, and the interior and exterior design conditions. (6.3.3)
6.3.4 The vapor permeance class of the air barrier shall be as indicated in the datasheet.
Air Barrier Vapor Permeance Classradio
Vapor permeable (greater than 10 perms)
Vapor semi-permeable, Class III vapor retarder (greater than 1.0 perm and not more than 10 perms)
Vapor retarder, Class II (greater than 0.1 perm and not more than 1.0 perm)
Vapor retarder, Class I (0.1 perm or less)
6.3.5 The Engineer of Record shall evaluate the wall assembly for condensation control, establishing the dew point location within the assembly under the project design conditions, before the vapor permeance class is fixed.
6.3.6 Vapor permeance reported in product data shall identify the ASTM E96 procedure used, because the desiccant and water methods yield materially different values for the same material.

7 Fire Performance of the Wall Assembly

NOTE Most air barrier membranes, primers, and adhesives are organic and therefore combustible, which brings the wall assembly they are part of within the flame propagation provisions of the building code. This is a property of the assembly, not of the membrane alone, and it constrains which membrane may be used long before any air leakage requirement does. (7.1)

7.2 Surface Burning Characteristics

7.2.1 The air barrier material, its primers, and its accessories shall have a flame spread index not greater than 25 and a smoke-developed index not greater than 450 when tested in accordance with ASTM E84.
7.2.2 Surface burning indices shall be reported for the material as installed, including its primer, at the thickness and on the substrate proposed for the work.

7.3 Vertical and Lateral Flame Propagation

NOTE The building code requires the exterior wall assembly of a building of noncombustible construction type above a stated height to be tested to NFPA 285 acceptance criteria where the assembly contains a combustible water-resistive barrier or other combustible component. Compliance is established for a specific tested assembly — substrate, air barrier, insulation, cavity, and cladding together — so substituting any component can void it. (7.3.1)
NOTE A water-resistive barrier that is the only combustible component in the assembly is exempt from the flame propagation test where its peak heat release rate, total heat release, and effective heat of combustion measured per ASTM E1354 and its indices measured per ASTM E84 are all within the limits the code sets for that exemption. (7.3.2)
7.3.3 Compliance with the vertical and lateral flame propagation provisions of the adopted building code shall be established on the basis indicated in the datasheet.
Flame Propagation Compliance Basisradio
Assembly tested to NFPA 285 acceptance criteria
Engineering analysis extending a tested assembly, sealed by a registered design professional
Exempt — combustible water-resistive barrier within the code exemption limits
Exempt — no combustible component in the exterior wall assembly
Not applicable — construction type or building height outside the provision
7.3.4 The Contractor shall not substitute any component of an exterior wall assembly whose flame propagation compliance depends on a tested assembly or an engineering analysis without submitting revised evidence of compliance for that assembly.

8 Air Barrier Materials

8.1 Primary Air Barrier Type

NOTE Fluid-applied membranes are sprayed or rolled to form a seamless film that conforms to irregular substrates and complex geometry with no laps in the field, at the cost of a thickness and cure that depend on application technique and on ambient conditions at the moment of application. (8.1.1)
NOTE Self-adhered sheet membranes arrive at a factory-controlled thickness and go on quickly and fully adhered, but every lap and termination is a discrete joint, and the adhesive requires a clean, dry, and usually primed substrate to grip. (8.1.2)
NOTE Mechanically-fastened sheets cover large areas quickly, tolerate damper substrates than adhesives do, and are the most economical option per unit area, but the fasteners penetrate the plane and the seam tapes must be rolled to seal. (8.1.3)
NOTE Integrated and board sheathings make the face of the sheathing itself the air barrier, eliminating a separate membrane and the labor to install it, and moving all of the work to sealing the joints, the fastener heads, and the transitions. (8.1.4)
NOTE Closed-cell spray polyurethane foam can act as air barrier, water-resistive barrier, vapor retarder, and insulation in a single application, but is intolerant of substrate moisture, requires overspray control, and requires its own thermal or ignition barrier where it is exposed. (8.1.5)
NOTE No type is inherently superior. The selection turns on the substrate, on the sequencing and weather exposure the schedule imposes, on the labor available to execute the detailing, and on whether the same product is also carrying the water and vapor control functions. (8.1.6)
8.1.7 The primary air barrier material type shall be as indicated in the datasheet, and shall be installed as a system with the accessories the manufacturer supplies or approves for it.
Primary Air Barrier Typeradio
Fluid-applied membrane
Self-adhered sheet membrane
Mechanically-fastened sheet
Integrated or board sheathing with sealed joints
Closed-cell spray polyurethane foam

8.2 Fluid-Applied Membrane Thickness

NOTE Cured film thickness is the single controllable variable that determines whether a fluid-applied membrane performs as tested, and it is the one most easily lost to fast application over a large area. (8.2.1)
8.2.2 Fluid-applied membranes shall be applied to achieve not less than the minimum cured film thickness indicated in the datasheet, verified across the wall field.
Fluid-Applied Minimum Cured Film Thicknessrange
mils
1080
8.2.3 Where no minimum cured film thickness is indicated in the datasheet, the air barrier manufacturer's published minimum cured film thickness for the substrate and exposure shall govern, and that value shall be stated in the product data submittal.
8.2.4 Wet film thickness shall be measured with a gauge during application at the frequency stated in the quality control plan, and cured film thickness shall be verified before the membrane is covered.

8.3 Sheet Membrane Laps and Seams

8.3.1 Sheet membrane laps shall be not less than the minimum lap width indicated in the datasheet, shall be shingle-lapped to shed water, and shall be rolled to full adhesion across the full width of the lap.
Sheet Membrane Minimum Lap Widthrange
in.
22.5346
8.3.2 Where no minimum lap width is indicated in the datasheet, the air barrier manufacturer's published minimum lap width for the product shall govern, and that value shall be stated in the product data submittal.
8.3.3 Seams in sheet membranes shall be treated by the method indicated in the datasheet.
Sheet Membrane Seam Treatmentradio
Integral adhesive lap, rolled
Seam tape over the lap, rolled
Liquid-applied seam sealer over the lap
Not applicable — no sheet membrane in the system
Manufacturer's standard (by default)
8.3.4 Fluid-applied membranes shall maintain a wet edge at coating joints, or shall be lapped onto cured membrane by the width the manufacturer publishes for a cold joint.

8.4 Mechanical Fasteners Through the Plane

NOTE Every fastener through a mechanically-fastened sheet is a designed penetration of the plane, sealed by the compression of a plate or a cap against the membrane rather than by a separate sealant. Substituting an unplated fastener converts each one into an unsealed hole. (8.4.1)
8.4.2 Fasteners securing mechanically-fastened sheets shall be of the type indicated in the datasheet and shall be installed at the spacing and pattern the manufacturer publishes for the design wind pressure.
Mechanically-Fastened Sheet Fastener Typeradio
Plastic cap nail
Plastic cap staple
Screw with plastic reinforcing plate
Screw with metal plate and sealing washer
Not applicable — no mechanically-fastened sheet in the system
Manufacturer's standard (by default)
8.4.3 Fasteners shall not be driven so as to tear, dish, or cut the membrane, and torn fastener locations shall be patched with the manufacturer's repair material before cover-up.

8.5 Accessory Materials

NOTE Incompatible accessories are a leading cause of premature failure. A sealant that will not bond to a fluid-applied membrane, or a primer whose solvent attacks a self-adhered adhesive, opens exactly the transitions the accessory was chosen to seal, and the failure appears months after the work is concealed. (8.5.1)
8.5.2 Transition membranes, primers, termination mastics, seam tapes, flashings, sealants, and fasteners shall be supplied by the primary air barrier manufacturer or explicitly approved by that manufacturer in writing as compatible with the primary material.
8.5.3 The Contractor shall not substitute an accessory from another source without written compatibility confirmation from the primary air barrier manufacturer.
8.5.4 The accessory materials indicated in the datasheet shall be provided as part of the air barrier system.
Accessory Materials Providedcheckbox
Self-adhered transition membrane
Liquid-applied transition and detailing membrane
Substrate primer
Termination mastic and reglet sealant
Seam tape
Opening flashing conforming to AAMA 711 or AAMA 714
Fasteners with reinforcing plates or sealing washers
Preformed inside and outside corner boots
Preformed penetration boots
Through-wall flashing compatible with the primary material

8.6 Exposure Window Before Cover-Up

NOTE Ultraviolet exposure degrades most air barrier membranes: the polymer embrittles, adhesives lose tack, and laps begin to lift. The published exposure period is a durability limit tied to test data, not a recommendation, and a membrane past it has to be evaluated rather than assumed sound. (8.6.1)
8.6.2 The air barrier shall not remain exposed to sunlight, weather, or construction traffic longer than the exposure period indicated in the datasheet before it is covered by cladding, insulation, or a protection course.
Maximum Exposure Before Cover-Uprange
months
136912
8.6.3 Where no exposure period is indicated in the datasheet, the air barrier manufacturer's published maximum exposure period shall govern, and that value shall be stated in the product data submittal.
8.6.4 Where the air barrier has remained exposed beyond the permitted period, the Contractor shall have the manufacturer's technical representative evaluate the membrane, and shall repair or replace every area the representative identifies as degraded.
8.6.5 Where the parties disagree whether an exposed area is degraded, the Engineer of Record shall make the initial determination.
8.6.6 The cost of evaluation, repair, or replacement of a membrane exposed beyond the permitted period shall be borne by the Contractor, except where the exposure resulted from a delay for which the Contract Documents assign responsibility elsewhere.

9 Continuity and Transitions

NOTE Continuity is the requirement that makes an air barrier work, and the transitions are where it is won or lost. Every place the plane crosses a change of material, a change of direction, a building system, or a boundary between trades is a designed detail or it is a hole. (9.1)
9.2 The air barrier plane shall be drawn as a single unbroken line on the shop drawings for every wall section and every transition condition.
9.3 Every transition shall bridge its gap with a material fully adhered to both surfaces it connects, wide enough to accommodate the anticipated movement, and lapped in the direction of water drainage.

9.4 Tie-In to the Roof Air Barrier

NOTE The wall-to-roof joint at the parapet is among the most failure-prone transitions in the enclosure: two trades, two membranes, and a change of plane meet at an exposed and wind-loaded location, usually at different times in the schedule. (9.4.1)
9.4.2 The wall air barrier shall be made continuous with the roof air barrier at the parapet or eave using a transition membrane lapped and fully adhered to both planes.
9.4.3 The Contractor shall sequence the wall-to-roof transition with the roofing work specified in Membrane RoofingMembrane RoofingResolves to the current edition.sync/membrane-roofing so that the upper membrane laps over the lower to shed water and the air seal is unbroken across the joint.
9.4.4 The wall-to-roof and parapet transition shall be constructed wall-to-roof and parapet transition details.

9.5 Tie-In to Below-Grade Waterproofing

NOTE The above-grade air barrier and the below-grade waterproofing are selected for different loads and are rarely the same chemistry, so the band where they overlap near grade needs a transition material verified compatible with both. It is also commonly installed by two different subcontractors weeks apart. (9.5.1)
9.5.2 The wall air barrier shall be lapped and sealed to the below-grade waterproofing specified in Below Grade WaterproofingBelow-Grade WaterproofingResolves to the current edition.sync/below-grade-waterproofing so that the air and water control layers are continuous from foundation to roof.
9.5.3 The Contractor shall verify the compatibility of the air barrier, the transition material, and the below-grade waterproofing with both manufacturers in writing before the transition is installed.
9.5.4 The grade-line transition shall be constructed grade-line transition detail.

9.6 Tie-In to Windows, Doors, and Curtain Walls

NOTE The perimeter of every opening is a transition between the wall air barrier and a manufactured unit, and on most of the perimeter it becomes unreachable as soon as the interior trim or the exterior cladding closes over it. (9.6.1)
9.6.2 The wall air barrier shall be sealed continuously to the frame of every window, door, and curtain wall around the full perimeter of the opening, using transition membranes or flashings conforming to AAMA 711 for self-adhered products or AAMA 714 for liquid-applied products.
9.6.3 The Contractor shall complete and inspect the perimeter air seal before the unit's interior trim or exterior cladding is installed.
9.6.4 The sill shall be flashed to drain incidental water out to the wall drainage plane, and the jamb and head flashings shall lap shingle-fashion over the sill flashing.
9.6.5 Movement at the opening perimeter joint shall be accommodated by sealant and backing specified in Joint SealantsJoint SealantsResolves to the current edition.sync/joint-sealants, coordinated with the fenestration work specified in GlazingGlass and GlazingResolves to the current edition.sync/glazing and Glazed Curtain WallsGlazed Curtain WallsResolves to the current edition.sync/glazed-curtain-walls.
9.6.6 Opening perimeter air seals shall be constructed window and door perimeter air seal details.

9.7 Movement Joints and Changes of Plane

NOTE A rigid bead of sealant buttered across a moving joint will tear on the first significant cycle. A joint that moves needs a bridging material that can move with it, either a looped membrane or a backer-and-sealant joint designed for the anticipated movement range. (9.7.1)
9.7.2 Substrate joints, inside and outside corners, and changes of plane shall be bridged with the manufacturer's transition membrane, sized to accommodate the anticipated movement.
9.7.3 Expansion, deflection, and seismic joints shall be bridged with a transition membrane looped or bellowed to absorb the design movement without tension on the adhesive.
9.7.4 The Contractor shall not bridge a movement joint with a rigid sealant bead applied directly across the joint.

9.8 Penetrations of the Air Barrier

NOTE Penetrations are individually trivial and collectively a major leakage path, and they concentrate exactly where the mechanical, electrical, and structural trades cross the wall — usually after the air barrier installer has demobilized. (9.8.1)
9.8.2 Every penetration of the air barrier, including pipes, conduits, ducts, structural members, cladding supports, and anchors, shall be sealed continuously to the air barrier.
9.8.3 Round penetrations shall be sealed by the method indicated in the datasheet.
Round Penetration Sealing Methodradio
Preformed boot
Self-adhered transition membrane
Liquid-applied detailing membrane
Compatible sealant with backing
9.8.4 Irregular and clustered penetrations shall be sealed by the method indicated in the datasheet.
Irregular Penetration Sealing Methodradio
Liquid-applied detailing membrane
Self-adhered transition membrane
Compatible sealant with backing
Preformed boot modified in the field to the manufacturer's written instruction
9.8.5 A penetration that moves relative to the wall, and a group of penetrations too closely spaced to detail individually, shall be sealed with a flexible boot or membrane that accommodates the movement rather than with a rigid sealant bead.
9.8.6 Each penetration shall be sealed as it is installed and shall not be deferred to a later trade, because penetrations become inaccessible once cladding and interior finishes are placed.
9.8.7 Penetrations made after the air barrier is complete shall be sealed by the air barrier installer using the manufacturer's repair materials and method.

10 Installation

10.1 Substrate Preparation

NOTE Adhesion governs the performance of every adhered air barrier, and adhesion to a contaminated, damp, dusty, or frosted substrate fails predictably. Most field adhesion failures are traceable to substrate condition rather than to the membrane. (10.1.1)
10.1.2 The substrate shall be clean, dry, and sound, and shall be free of dust, frost, standing water, oil, curing compounds, form release agents, laitance, and projections, before the air barrier is applied.
10.1.3 The Contractor shall verify that substrate moisture is within the air barrier manufacturer's published limit, by the manufacturer's stated method, and shall record the result before application.
10.1.4 The Contractor shall fill and strike gaps, voids, and offsets in the substrate that exceed the membrane's published bridging capacity.
10.1.5 Concrete and masonry substrates shall be cured to the age and the moisture condition the air barrier manufacturer publishes before the membrane is applied.
10.1.6 Where the parties disagree whether a substrate is acceptable to receive the air barrier, the Engineer of Record shall make the initial determination.

10.2 Priming

NOTE Primer serves two different purposes that are easily confused: it can be an adhesion promoter required on every substrate the system contacts, or it can be a remedy required only on substrates that will not otherwise hold the adhesive. Which of the two the project intends changes the labor, the schedule, and the cost, so it is specified rather than left to the field. (10.2.1)
10.2.2 Primer shall be applied to the extent indicated in the datasheet.
Primer Application Extentradio
Prime all substrates receiving the air barrier
Prime only substrates for which the air barrier manufacturer requires primer
Prime only where a field adhesion test on the unprimed substrate fails to meet the acceptance value
Not applicable — the system requires no primer on any substrate present
10.2.3 Primer shall be applied at the coverage rate the manufacturer publishes for the substrate, and the membrane shall be applied within the primer's published open time.
10.2.4 Primed areas not covered within the primer's open time shall be re-primed before the membrane is applied.

10.3 Ambient and Substrate Conditions

NOTE Fluid-applied membranes will not cure correctly below their minimum application temperature or on a wet substrate, and self-adhered adhesives lose tack as temperature falls. Both failures are invisible on the day of application and become visible at the first adhesion test or the first wind event. (10.3.1)
10.3.2 The air barrier shall be installed only within the ambient temperature, substrate temperature, and humidity ranges the manufacturer publishes for the product.
10.3.3 The air barrier shall not be applied to a wet, frozen, or frost-covered substrate.
10.3.4 Where work proceeds outside the manufacturer's published ranges, the Contractor shall use the manufacturer's cold-weather or hot-weather products and procedures, and shall submit those procedures before that work begins.
10.3.5 The Contractor shall record ambient temperature, substrate temperature, and substrate moisture at the start of each application and at each significant change in conditions.

10.4 Application of the Wall Field

10.4.1 The air barrier shall be applied continuously across the wall field at the thickness or coverage rate the manufacturer publishes, with no skips, holidays, pinholes, fishmouths, blisters, or unadhered areas.
10.4.2 Sheet membranes shall be rolled out smooth and shall be pressed or rolled into full contact to expel entrapped air, with no wrinkles, bridging, or fishmouths at laps.
10.4.3 Fluid-applied membranes shall be applied in the number of coats and in the directions the manufacturer publishes, and thin or missed areas shall be recoated to the specified cured thickness before the membrane is covered.
10.4.4 Closed-cell spray polyurethane foam used as the air barrier shall be applied in lift thicknesses not exceeding the manufacturer's published maximum, and adjacent surfaces shall be masked against overspray.

10.5 Transitions to Adjacent Work

10.5.1 Each transition shall be installed in accordance with the approved transition detail, fully adhered to both surfaces it connects.
10.5.2 Transitions shall be installed in the sequence established at the preinstallation conference.
10.5.3 Each transition shall be inspected and accepted before it is concealed by cladding, insulation, or finishes.

10.6 Protection Before Cover-Up

NOTE An installed air barrier is a working surface that following trades will lean ladders against, run lines across, walk on at scaffold levels, and fasten through. Damage is expected rather than exceptional, and the schedule should assume a repair pass before cover-up. (10.6.1)
10.6.2 The Contractor shall protect the installed air barrier from physical damage, from prolonged exposure beyond the permitted period, and from contamination by following trades until it is permanently covered.
10.6.3 The Contractor shall inspect the air barrier for damage immediately before cover-up and shall repair every defect found using the manufacturer's repair material and method.
10.6.4 Repairs shall be lapped onto sound, clean, and where required primed membrane by not less than the specified minimum lap width.

11 Field Quality Control

11.1 Field Adhesion Testing

NOTE Adhesion testing confirms what visual inspection cannot: that the membrane is actually bonded and will not delaminate and billow under wind pressure. A failed test also carries diagnostic information the test value alone does not — the mode of failure distinguishes a substrate problem from a primer problem from a cohesive failure within the membrane. (11.1.1)
11.1.2 The Contractor shall perform field adhesion testing of adhered air barrier membranes by the method indicated in the datasheet.
Field Adhesion Test Methodradio
ASTM D4541 portable pull-off adhesion tester
ASTM D7234 pull-off adhesion for coatings on concrete
ASTM D3330 Method F 90-degree peel
11.1.3 Field adhesion tests shall be performed at not less than the frequency indicated in the datasheet, and at not less than one test for each substrate type on each floor.
Field Adhesion Test Frequencyrange
ft² of wall area per test
250050001000020000
11.1.4 Field adhesion tests shall meet not less than the minimum adhesion value indicated in the datasheet for the substrate tested.
Minimum Field Adhesion Valuerange
psi
5101620304060
11.1.5 Where no minimum adhesion value is indicated in the datasheet, the air barrier manufacturer's published minimum adhesion value for each substrate shall govern, and those values shall be stated in the product data submittal.
11.1.6 Each test shall be witnessed by the Engineer of Record or the Engineer of Record's representative, and shall be recorded with the location, substrate, recorded value, and mode of failure.
11.1.7 Where a test fails to meet the acceptance value, the Contractor shall determine the cause, shall test outward from the failed location to establish the extent of the affected area, and shall repair the entire affected area rather than the test location alone.
11.1.8 The cost of the additional testing and of the repair following a failed adhesion test shall be borne by the Contractor.
11.1.9 Each test location shall be repaired with the manufacturer's repair material after the test, and shall be recorded as repaired.

11.2 Whole-Building Air Leakage Testing

NOTE The whole-building test is the only verification in this standard that measures the finished product rather than a proxy for it, and it is the one that catches the discontinuities no product test can reach. Its value depends almost entirely on when it is run: a test performed while transitions are still accessible produces repairs, and a test performed after the cladding is complete mostly produces a report. (11.2.1)
11.2.2 The completed enclosure shall be tested for whole-building air leakage where the datasheet indicates the test is required.
Whole-Building Air Leakage Testradio
Required
Not required
11.2.3 The whole-building air leakage test shall be performed in accordance with the test method indicated in the datasheet.
Whole-Building Test Methodradio
ASTM E3158
ASTM E779
ASTM E1827
NOTE ASTM E3158 was developed for large and multizone enclosures and is the method most commercial buildings are tested under. ASTM E779 and ASTM E1827 were written for single-zone and smaller enclosures, and the energy code generally permits any of the three where the tested floor area is small. Where the enclosure is multizone or the tested area is large, the method should be E3158. (11.2.4)
11.2.5 The whole-building air leakage test shall be performed by the party indicated in the datasheet.
Whole-Building Test Performed Byradio
Independent third-party testing agency engaged by the Contractor
Independent third-party testing agency engaged by the Owner
Contractor's own forces, witnessed by the Engineer of Record
11.2.6 The whole-building air leakage test shall be performed at the test pressure differential indicated in the datasheet.
Whole-Building Test Pressure Differentialrange
Pa
255075
11.2.7 The Contractor shall schedule the whole-building air leakage test after the enclosure is complete and weather-tight and, where the construction sequence permits, while transitions remain accessible for repair.
11.2.8 The Contractor shall prepare the building for the test as the accepted test plan requires, including sealing intentional openings, and shall restore every temporary seal after the test.
11.2.9 The testing agency shall issue a report identifying the method, the enclosure area, the measured leakage rate at the specified pressure differential, and the determination against the acceptance target.

11.3 Air Leakage Site Detection and Remediation

NOTE Locating a leak is a different exercise from measuring one, and it uses different instruments. ASTM E1186 collects the practices that find leakage sites while the enclosure is held under pressure — smoke or fog tracers, infrared thermography, chamber pressurization, and tracer gas among them — each with its own reach and its own blind spots. Thermography needs a temperature differential across the enclosure and loses leaks whose air has already equalized in temperature; tracer methods are precise but slow over large surfaces. (11.3.1)
11.3.2 Where the measured whole-building air leakage exceeds the acceptance target, the testing agency shall locate the leakage sites in accordance with ASTM E1186 using the methods indicated in the datasheet.
Air Leakage Site Detection Methodscheckbox
Smoke or theatrical fog tracer under pressurization
Infrared thermography under pressurization
Chamber or zonal pressurization diagnostics
Anemometer traverse at suspected sites
Tracer gas
Acoustic leak detection
11.3.3 Where the measured whole-building air leakage exceeds the acceptance target, the Contractor shall repair the leakage sites the testing agency identifies, and the enclosure shall then be handled by the remedy indicated in the datasheet.
Remedy Where the Air Leakage Target Is Exceededradio
Repair and re-test until the acceptance target is met
Repair and re-test once, then diagnostic evaluation and repair without further re-test
Repair with diagnostic evaluation, no re-test
Report the result, no repair required
11.3.4 The cost of leakage site detection, of the repairs, and of every re-test following a result that exceeds the acceptance target shall be borne by the Contractor.
11.3.5 The Contractor shall record the location, apparent cause, repair method, and re-test result for each leakage site addressed, and shall include those records in the closeout submittals.

11.4 Inspection Before Concealment

NOTE Air barrier defects are concealed early and are expensive to reach afterward, so the inspection regime has to be front-loaded into hold points rather than deferred to a punch list. A punch list cannot reach behind cladding. (11.4.1)
11.4.2 Each lap, termination, transition, and penetration shall be inspected and accepted before it is concealed by cladding, insulation, or interior finishes.
11.4.3 The Contractor shall give the Engineer of Record notice before concealing any portion of the air barrier, at the notice interval the Contract Documents establish.
11.4.4 Work concealed without the required inspection shall be uncovered for inspection at the Contractor's expense where the Engineer of Record directs.

12 Cleaning and Repair

NOTE Cured air barrier materials, primers, and mastics are difficult to remove from finished surfaces without damaging them, so removal is an immediate operation rather than a closeout one. (12.1)
12.2 The Contractor shall keep the air barrier and its accessories clean during installation and shall remove overspray, primer, mastic, and adhesive from glazing, finished masonry, and surfaces exposed to view before the material cures.
12.3 Damage to the air barrier shall be repaired with the air barrier manufacturer's repair material and method, lapped onto sound and, where required, primed membrane.
12.4 The Contractor shall turn over unopened repair materials of each primary and accessory product used in the work, in the manufacturer's sealed containers, labeled with the product name and the area of the work in which it was used.

13 Warranty

13.1 Contractor Warranty

13.1.1 The Contractor shall warrant the air barrier installation against air leakage attributable to defective joints, transitions, terminations, or penetrations, against delamination, and against defects in materials and workmanship, for the period indicated in the datasheet from the date of Substantial Completion.
Installer Warranty Periodrange
years
125
13.1.2 The Contractor shall bear the cost of correcting moisture damage to the wall assembly attributable to air leakage through the installed air barrier during the warranty period, including the cost of removing and reinstalling cladding, insulation, and finishes required to reach the defect.
13.1.3 Work repaired under warranty shall be warranted for a full warranty term running from the date of the repair, or for the unexpired remainder of the original term, whichever ends later.

13.2 Manufacturer System Warranty

NOTE A manufacturer system warranty covers the membrane together with its matched accessories, and it is conditioned on the accredited or licensed installer, the matched accessory set, and the documented field visits. Those conditions are usually satisfied or missed during construction and verified only at claim time. (13.2.1)
13.2.2 The Contractor shall provide the air barrier manufacturer's system warranty covering the primary membrane and the matched accessories for the period indicated in the datasheet.
Manufacturer System Warranty Periodrange
years
5101520
13.2.3 Where no manufacturer system warranty period is indicated in the datasheet, the period the air barrier manufacturer offers for the specified system shall govern, and that period shall be stated in the product data submittal.
13.2.4 The Contractor shall satisfy every condition on which the manufacturer system warranty depends, and shall submit the manufacturer's written confirmation that those conditions have been met.

14 Delivery, Storage, and Handling

NOTE Fluid-applied materials, primers, and adhesives are both temperature-sensitive and shelf-life-limited. Material stored too cold will not apply at the specified rate, material stored too warm will skin or flow, and material stored too long will not cure at all — and none of the three is apparent from the container. (14.1)
14.2 Air barrier materials shall be delivered to the site in the manufacturer's original sealed and labeled containers and rolls, with the lot number and the shelf-life expiration date legible.
14.3 Air barrier materials shall be stored off the ground, under cover, and within the temperature range the manufacturer publishes for storage.
14.4 Fluid-applied material, primer, sealant, or mastic past its shelf-life expiration date shall be removed from the site and shall not be used.
14.5 Self-adhered membrane rolls shall be stored on end, protected from heat that would cause the adhesive to flow, and kept dry so that the release liner and the adhesive are undamaged.
14.6 Primers, sealants, and mastics shall be stored, handled, and applied in accordance with their safety data sheets, away from ignition sources, and with the manufacturer's ventilation requirements observed during application.

Edit this page

SynC Standards are reference material provided for informational purposes only and as a guide. They are not engineering, architectural, or legal advice and are not a substitute for the judgment of a licensed design professional. It is the responsibility of the user to determine the applicability of any standard to a specific project and to verify all requirements against the governing codes, manufacturer data, and project conditions. SynC does not render professional services and forms no professional relationship by publishing this content. Provided "as is," without warranty of any kind, including fitness for a particular purpose. See our Terms of Use for the complete terms.

This standard is published by SynC and licensed under Creative Commons Attribution-ShareAlike 4.0. You may share and adapt it, including commercially, provided you give credit, link to the license, indicate any changes, and license your adaptations under the same terms. Keep the attribution and notice below with any copy — it includes the warranty disclaimer the license requires you to retain.

Attribution & reuse notice — keep this with any copy:
"Air Barriers." SynC Standards. Licensed under CC BY-SA 4.0 (https://creativecommons.org/licenses/by-sa/4.0/). Source: https://synergyinconstruction.com/wiki/sync/air-barriers — reference material only; not professional engineering advice and provided without warranty. Verify against governing codes and have a licensed professional review before use.