title: Electrical Power Monitoring and Metering
…9 unchanged lines
portable or temporary power-quality recorders; protective relaying with incidental metering
(specify under switchgear protection); thermal-energy or water metering; control wiring and
− enclosures covered by [[syncs/building-automation-system]].
+ enclosures covered by [[sync/building-automation-system]].
---
…529 unchanged lines
## Switchboard-mounted and panelboard-mounted meters shall be coordinated with the switchboard or panelboard manufacturer for factory-installed or field-installed mounting.
−### A meter mounted in the door or compartment of a switchboard affects the equipment listing and arrangement, so its mounting is coordinated with the gear manufacturer rather than improvised in the field. See [[syncs/low-voltage-switchboards]] and [[syncs/low-voltage-panelboards]]. {note}
+### A meter mounted in the door or compartment of a switchboard affects the equipment listing and arrangement, so its mounting is coordinated with the gear manufacturer rather than improvised in the field. See [[sync/low-voltage-switchboards]] and [[sync/low-voltage-panelboards]]. {note}
## Branch-circuit power monitoring modules that clip onto the panelboard bus shall be factory-installed by the panelboard manufacturer where the design requires bus-bar mounting.
…56 unchanged lines
## The energy monitoring software platform shall be identified in the Contract Documents and its data ingestion requirements coordinated with the meter selection.
−### Whether the EPMS is provided by the meter manufacturer, by a third party, or integrated into the building automation system determines the protocol and register map the meters must support; selecting meters before the platform risks an incompatible pairing. See [[syncs/building-automation-system]]. {note}
+### Whether the EPMS is provided by the meter manufacturer, by a third party, or integrated into the building automation system determines the protocol and register map the meters must support; selecting meters before the platform risks an incompatible pairing. See [[sync/building-automation-system]]. {note}
## The energy monitoring software shall produce energy and demand reports at hourly, daily, monthly, and annual granularity where required by the adopted energy code.
…41 unchanged lines
## Voltage transformer primary fuses shall be installed and verified before the meter is energized.
−## Meter wiring shall be identified at each termination in accordance with [[syncs/equipment-labeling]].
+## Meter wiring shall be identified at each termination in accordance with [[sync/equipment-labeling]].
## Communication wiring shall be installed separately from power conductors to limit electrical noise on the data circuit.
−## Meters serving motor control equipment shall be coordinated with the equipment served per [[syncs/motor-control-centers]].
+## Meters serving motor control equipment shall be coordinated with the equipment served per [[sync/motor-control-centers]].
# Testing and Commissioning {toc}
…83 unchanged lines
default: 2
```