title: Roof and Facade Fall Protection Anchorage
…54 unchanged lines
## Action Submittals {toc}
−### The Contractor shall submit the following action submittals for review before fabrication or installation: {note}
+### The Contractor shall submit the following action submittals for review before fabrication or installation:
- Shop drawings showing each anchor location, type, mounting detail, and connection to the building structure
…20 unchanged lines
## Informational Submittals {toc}
−### The Contractor shall submit the following informational submittals: {note}
+### The Contractor shall submit the following informational submittals:
- Qualified-person and competent-person credentials for the anchorage designer and installer
…12 unchanged lines
## Closeout Submittals {toc}
−### The Contractor shall submit the following closeout submittals before final acceptance: {note}
+### The Contractor shall submit the following closeout submittals before final acceptance:
- A system certification letter, PE-sealed, stating rated capacity, user count, and intended duty for each anchor and lifeline
…32 unchanged lines
# Structural Capacity Basis {toc}
−## The capacity basis is the single most important decision in anchorage design and shall be selected and stated explicitly for each anchor. {note}
+## The capacity basis is the single most important decision in anchorage design and shall be selected and stated explicitly for each anchor.
### The prescriptive basis rates each anchor at 5,000 lb (22.2 kN) per attached worker for personal fall arrest, per OSHA 29 CFR 1926.502(d)(15) and 29 CFR 1910.140; this is the default for single-user roof maintenance anchors. {note}
…9 unchanged lines
## A travel-restraint-only anchor rated below the arrest capacity shall be permanently marked "RESTRAINT ONLY" so it cannot be mistaken for an arrest anchor.
−### A restraint anchor that is clipped into beyond its restraint radius becomes an arrest anchor and can fail; marking and layout shall prevent this misuse. {note}
+### A restraint anchor that is clipped into beyond its restraint radius becomes an arrest anchor and can fail; marking and layout shall prevent this misuse.
## The structural engineer of record shall confirm in writing that the supporting deck, framing, parapet, or concrete element carries the anchor reactions in both shear and tension.
…327 unchanged lines
### A davit base socket is a permanent sleeve cast into a concrete parapet or welded to structural steel that receives a portable davit mast for window-cleaning or BMU operations. {note}
−### Davit socket and tie-back locations must be coordinated jointly by the structural engineer and the facade or BMU access consultant, because a misplaced socket cannot be relocated after construction. {note}
+### Davit socket and tie-back locations must be coordinated jointly by the structural engineer and the facade or BMU access consultant, because a misplaced socket cannot be relocated after construction.
## Davit base sockets shall be located by coordinated structural and facade-access drawings before concrete placement or steel fabrication.
…107 unchanged lines
# Installation {toc}
−## Installation shall follow the manufacturer's instructions, the sealed shop drawings, and the sealed calculations for every anchor. {note}
+## Installation shall follow the manufacturer's instructions, the sealed shop drawings, and the sealed calculations for every anchor.
## Anchors shall be installed in the locations shown on the coordinated layout plan [[drawing: roof anchorage layout]].
…35 unchanged lines
# Inspection and Re-Certification {toc}
−## Anchorage that is not on a written inspection schedule goes uninspected; the contract documents shall state the inspection and re-certification intervals so the owner receives a program, not just hardware. {note}
+## Anchorage that is not on a written inspection schedule goes uninspected; the contract documents shall state the inspection and re-certification intervals so the owner receives a program, not just hardware.
### Annual visual inspection is the minimum interval; a five-year proof-load re-certification is the industry-standard interval for permanent commercial anchors in the United States. {note}
…65 unchanged lines
- Replacement inspection tags
```