1 Scope
NOTE This specification covers the selection, procurement, installation, splicing, termination, and field acceptance testing of shielded medium-voltage power cable rated 5 kV through 35 kV for primary distribution systems in commercial, institutional, and industrial facilities. (1.1)
NOTE The scope encompasses single-conductor and multi-conductor extruded-dielectric cable insulated with ethylene-propylene rubber (EPR, Type MV-105) or cross-linked polyethylene (XLPE, Type MV-90), in voltage classes of 5 kV, 15 kV, 25 kV, and 35 kV, installed in concrete-encased duct bank, conduit, cable tray, underground vaults, or by direct burial. (1.2)
NOTE Primary feeders in scope run from the utility point of delivery or facility substation to medium-voltage switchgear, unit substations, motor control centers, and transformer primaries, on campus distribution loops and industrial plant primary systems where power is distributed above 2,000 V. (1.3)
NOTE A medium-voltage cable failure interrupts the entire downstream distribution served by the feeder, and the dominant failure modes — termination and splice workmanship, shield discontinuity, and damage during pulling — are introduced during installation rather than manufacture. The requirements of this standard reflect that consequence and concentrate on the field operations that determine in-service reliability. (1.4)
NOTE This standard does not cover low-voltage cable rated 600 V and below, the raceway and civil duct-bank systems that house MV cable, the switchgear and interrupter equipment fed by the cable, capacitor-bank feeders, high-voltage transmission cable above 46 kV, or bare overhead and aerial covered conductors. (1.6)
2 Referenced Standards
2.1Equipment, materials, and installation shall comply with the latest adopted edition of each of the following unless a specific edition is cited.
2.2Where referenced standards conflict, the more stringent requirement shall govern unless the Engineer of Record directs otherwise in writing.
| Standard |
Title |
| UL 1072 |
Medium-Voltage Power Cables |
| ICEA S-93-639 / ANSI/NEMA WC74 |
5-46 kV Shielded Power Cable for Transmission and Distribution of Electric Energy |
| ICEA S-97-682 / ANSI/NEMA WC71 |
Shielded Utility Cable Rated 5 through 46 kV |
| AEIC CS8 |
Extruded Dielectric Shielded Power Cables Rated 5 through 46 kV |
| IEEE 48 |
Test Procedures and Requirements for AC Cable Terminations 2.5 kV through 765 kV |
| IEEE 404 |
Cable Joints for Extruded Dielectric Cable Rated 5000 V through 46,000 V |
| IEEE 400 |
Field Testing and Evaluation of the Insulation of Shielded Power Cable Systems Rated 5 kV and Above |
| IEEE 400.2 |
Field Testing of Shielded Power Cable Systems Using Very Low Frequency (VLF) (less than 1 Hz) |
| IEEE 835 |
Power Cable Ampacity Tables |
| IEEE 1202 |
Flame-Propagation Testing of Wire and Cable |
| NFPA 70 (NEC) Article 310 |
Conductors for General Wiring (ampacity tables 310.60(C)) |
| NFPA 70 (NEC) Article 328 / 340 |
Type MV Medium Voltage Cable |
| ASTM B8 |
Concentric-Lay-Stranded Copper Conductors, Hard, Medium-Hard, or Soft |
| ASTM B496 |
Compact Round Concentric-Lay-Stranded Copper Conductors |
3 Submittals
3.1 Action Submittals
NOTE The Contractor shall submit the following action submittals for review before fabrication or procurement: (3.1.1)
- Product data for the proposed cable, identifying voltage class, insulation level, insulation type, conductor size and material, shield type, and jacket material
- Cable construction cross-section drawing showing conductor, conductor shield, insulation, insulation shield, metallic shield, and jacket with stated thicknesses
- Manufacturer's published ampacity and derating data for the proposed installation configuration
- Manufacturer's maximum pulling tension and minimum bend radius for the proposed cable
- Product data for splice kits and termination kits, identifying type, voltage class, and conductor size range, with IEEE 404 and IEEE 48 class designation
- Cable pulling plan identifying pull points, calculated tension and sidewall bearing pressure, lubricant, and feed/take-up arrangement
☑ Cable product data (class, insulation level/type, size, shield, jacket)
☑ Cable construction cross-section with layer thicknesses
☑ Ampacity and derating data for installation configuration
☑ Maximum pulling tension and minimum bend radius
☑ Splice and termination kit data with IEEE 404/IEEE 48 class
☑ Cable pulling plan with calculated tension and sidewall pressure
NOTE The Contractor shall submit the following informational submittals: (3.2.1)
- Manufacturer's certified factory test reports per ICEA S-93-639 and AEIC CS8 for each reel furnished
- Certification that the cable is UL 1072 listed as Type MV for cable installed within buildings or structures
- Qualification records for splicing and terminating technicians per the Quality Assurance requirements
- Cable reel logs identifying reel number, length, and footage marker correlation for each run
☑ Certified factory test reports (ICEA S-93-639 / AEIC CS8)
☑ UL 1072 Type MV listing certification
☑ Splicer/terminator qualification records
☑ Cable reel logs with footage correlation
3.3 Closeout Submittals
NOTE The Contractor shall submit the following closeout submittals before final acceptance: (3.3.1)
- Field acceptance test reports for each cable run, including insulation resistance, shield continuity, and VLF withstand results
- Record drawings showing as-installed cable routing, splice locations, and termination points
- Cable identification schedule correlating circuit designations to installed runs
☑ Field acceptance test reports (IR, shield continuity, VLF)
☑ As-installed record drawings with splice/termination locations
☑ Cable identification schedule
4 Quality Assurance
4.1Cable manufacturers shall be regularly engaged in the production of shielded medium-voltage cable to ICEA S-93-639 or ICEA S-97-682 and shall hold current UL 1072 listing for the products furnished.
NOTE Splicing and terminating are the operations most determinative of in-service reliability, because removing the semiconducting shield and reconstructing the electrical-stress geometry by hand at every joint and termination introduces stress concentrations that the factory dielectric never sees. This standard therefore qualifies the technician, not only the materials. (4.2)
4.2.1Cable splices and terminations shall be made only by technicians certified by the splice and termination kit manufacturer for the specific kit, voltage class, and conductor size installed.
4.2.2The Contractor shall submit documented evidence of at least three years of medium-voltage cable splicing and terminating experience for each technician performing the work.
4.2.3Semiconducting shield material shall be removed only with manufacturer-approved scoring and removal tools, and shall never be removed by knife scoring that notches the insulation.
4.3Each cable run, splice, and termination shall be field tested and accepted before the feeder is energized.
4.4A single voltage class, insulation type, and shield construction should be standardized across a project wherever the system voltage permits, so that one set of splice kits, termination kits, and trained technicians serves the entire installation.
5 Environmental and Service Conditions
NOTE The voltage class of the cable shall match the system nominal operating voltage; a 13.8 kV system requires 15 kV class cable, not 5 kV class cable. (5.1)
NOTE The most common error in medium-voltage cable specification is selecting a voltage class below the system operating voltage. Voltage class denotes the system band the cable insulation geometry is designed for, not a withstand margin. The 15 kV class is by far the most common for US campus, healthcare, university, and large commercial primary distribution because the prevalent 13.2 kV and 13.8 kV systems fall within it. (5.2)
5.2.1The cable voltage class shall be selected to equal or exceed the system nominal voltage band as scheduled.
○ 5 kV (systems 2.4-4.16 kV)
● 15 kV (systems 4.16-13.8 kV)
○ 25 kV (systems 14.4-22 kV)
○ 35 kV (systems 23-34.5 kV)
NOTE Insulation level expresses how long the cable insulation must tolerate the phase-to-phase voltage appearing across an unfaulted phase during a ground fault, which depends on the system grounding and the protective relaying. The 100% level suits solidly grounded systems that clear a fault in one minute or less; 133% suits systems that clear within one hour or are impedance/resistance grounded; 173% suits ungrounded systems or those that operate faulted indefinitely. (5.3)
NOTE Most facility systems are not solidly grounded with sub-minute fault clearing, so the default insulation level for the typical facility application is 133%. Specifying 100% level on a system that does not meet its grounding and clearing conditions under-insulates the cable for the fault duty it will actually see. (5.4)
5.4.1The insulation level shall be selected to match the system grounding configuration and fault-clearing time as scheduled.
5.4.2The insulation level shall not be specified below 133% unless the system is solidly grounded with fault clearing of one minute or less.
○ 100% (solidly grounded, fault cleared in 1 min or less)
● 133% (impedance/resistance grounded or fault cleared in 1 hr or less)
○ 173% (ungrounded or indefinite faulted operation)
NOTE The installation method governs the ampacity derating, the required jacket and armor, and the mechanical protection the cable receives, so it shall be established before conductor size is finalized. (5.5)
5.5.1The installation method shall be coordinated with Underground Ductbank and applied as the basis for ampacity derating. ● Concrete-encased duct bank
○ Conduit only
○ Cable tray
○ Direct buried
○ Underground vault routing
Per drawings — MV cable routing plan
5.6The default design value for soil thermal resistivity (RHO) in direct-buried and duct-bank ampacity calculations is 90 °C·cm/W; values above 90 °C·cm/W reduce ampacity and require a larger conductor for the same load.
5.7The designer shall verify the actual site soil RHO and use measured values when available for direct-buried and duct-bank ampacity calculations.
6 Cable Construction
NOTE Insulation type is the central material choice. EPR (Type MV-105) operates at 105 °C and XLPE (Type MV-90) at 90 °C; the 15 °C higher operating temperature of EPR yields a meaningful ampacity advantage, and EPR is more flexible and easier to terminate in the confined manholes and switchgear cubicles typical of facility work. EPR is therefore the 80% default for institutional and facility primary feeders, while XLPE remains a valid lower-cost choice for straightforward duct-bank runs. (6.1)
6.1.1The insulation type shall be EPR (Type MV-105) or XLPE (Type MV-90) as scheduled, and the type selected shall be consistent across all cable furnished for a given feeder.
● EPR / ethylene-propylene rubber (MV-105, 105 °C)
○ XLPE / cross-linked polyethylene (MV-90, 90 °C)
NOTE Insulation thickness is fixed by the ICEA S-93-639 / NEMA WC74 tables for the selected voltage class and insulation level and shall never be specified below the standard minimum. For 15 kV at 133% level, the minimum is 175 mils for both EPR and XLPE; the specifier shall confirm the value for the actual class and level against the current edition. (6.2)
6.2.1Insulation thickness shall equal or exceed the ICEA S-93-639 / NEMA WC74 minimum for the specified voltage class and insulation level.
NOTE Conductor material for facility primary feeders is standardly copper, which is the default; aluminum is a cost-driven alternative that, for equal ampacity, requires a larger conductor and correspondingly larger conduit. (6.3)
6.3.1The conductor material shall be copper or aluminum as scheduled.
NOTE Conductor stranding shall comply with ASTM B8 for concentric round or ASTM B496 for compact round; compact round is commonly specified for medium-voltage cable to reduce overall diameter and improve the seal of pre-molded fittings. (6.4)
6.4.1Conductor stranding shall be Class B concentric round, compact round, or compressed as scheduled, complying with ASTM B8 or ASTM B496.
○ Class B concentric round (ASTM B8)
● Compact round (ASTM B496)
○ Compressed
NOTE The metallic shield carries charging and fault return current and establishes the ground reference around the insulation. A helical copper tape shield is the standard construction for shielded feeders; concentric neutral construction is used where the system neutral must be continuously grounded along the entire run, as in some direct-buried distribution. The two are not interchangeable: they have different fault-current return capacity and different installation handling. (6.5)
6.5.1The metallic shield shall be copper tape or concentric neutral as scheduled.
● Copper tape shield (5 mil, helical)
○ Concentric neutral (full neutral)
○ Concentric neutral (one-third neutral)
NOTE Copper tape shield shall be a minimum of 5 mil thick applied helically; the overlap determines the fault-return path quality, with 12.5% being the minimum and 25% commonly specified for a more robust return path. (6.6)
6.6.1Copper tape shield overlap shall be a minimum of 12.5%, and shall be 25% where scheduled for enhanced fault-return capacity.
○ 12.5% overlap (minimum)
● 25% overlap
NOTE Concentric neutral sizing shall be a full neutral for direct-buried runs; a one-third neutral is acceptable only for duct-bank runs where the available fault current is limited by system relay coordination. (6.7)
NOTE The jacket protects the shield and insulation from the installation environment and governs flame and smoke behavior inside buildings; the material shall be selected for the installation environment and any flame or low-smoke requirement. (6.8)
6.8.1The cable jacket shall be PVC, LLDPE, HDPE, or LSZH as scheduled.
6.8.2Where PVC jacket is specified, the minimum jacket thickness shall be 80 mils for cables up to approximately 1.5 in outside diameter per ICEA S-93-639.
● PVC
○ LLDPE
○ HDPE
○ LSZH (low-smoke zero-halogen)
6.9Cable installed in cable tray or conduit inside buildings shall meet the FT4 flame-propagation requirement of IEEE 1202.
NOTE Cable configuration is single-conductor or multi-conductor. Single-conductor construction is the dominant choice at 15 kV and above and for most facility feeders; multi-conductor (3C or 3C with ground) is common at 5 kV for compact branch feeders in tighter routing. (6.10)
6.10.1The cable configuration shall be single-conductor or multi-conductor as scheduled.
● Single-conductor
○ Three-conductor (3C)
○ Three-conductor with ground (3C+G)
6.11Cable installed within buildings or structures shall be UL 1072 listed as Type MV; utility-class cable manufactured only to ICEA S-97-682 shall not be used inside structures unless it also carries the UL 1072 Type MV listing required by the NEC.
7 Ampacity and Conductor Sizing
NOTE Conductor size shall be established from the NEC Table 310.60(C) series and IEEE 835 for the actual installation configuration, with all applicable derating applied. Common facility feeders fall between 4/0 AWG and 500 kcmil copper; for reference, 4/0 AWG copper EPR 15 kV in duct is approximately 260-290 A and 500 kcmil approximately 370-400 A before derating, with the exact value set by the installation conditions. (7.1)
7.1.1The conductor size shall be selected from NEC Table 310.60(C) and IEEE 835 for the scheduled installation configuration and shall carry the connected load after derating.
7.1.2All applicable derating factors shall be applied, including conduit fill above three current-carrying conductors, elevated ambient soil temperature, parallel duct groupings, and soil RHO above 90 °C·cm/W.
#2 AWG
#1 AWG
1/0 AWG
2/0 AWG
4/0 AWG
250 kcmil
350 kcmil
500 kcmil
750 kcmil
1000 kcmil
Per drawings — MV one-line diagram
NOTE Cable ampacity shall be coordinated with the served transformer kVA, the fuse or relay protection, and the cable impedance, so that the feeder cable is not the thermal weak link of the circuit even when the overcurrent device is correctly sized. (7.2)
7.2.1The feeder cable ampacity shall coordinate with the upstream protective device rating and the downstream transformer kVA such that the cable is protected against overload and short circuit.
NOTE The cable shall not exceed its temperature limits in any operating state: 90 °C continuous for XLPE and 105 °C for EPR, 130 °C (XLPE) or 140 °C (EPR) emergency overload, and 250 °C short-circuit. (7.3)
8 Terminations and Splices
NOTE Terminations and splices are engineered fittings, not generic field assemblies; using a misclassed or generic fitting is a leading cause of in-service medium-voltage cable failure. Terminations shall be selected by class per IEEE 48 and splices by type per IEEE 404, matched to the cable construction, voltage class, and conductor size. (8.1)
8.1.1Cable terminations shall comply with IEEE 48 and shall be selected by class for the indoor or outdoor service condition.
8.1.2Cable splices and joints shall comply with IEEE 404 and shall be rated for the cable voltage class and conductor size.
NOTE Termination type is selected for the service condition. Heat-shrink and cold-shrink terminations are common for both indoor and outdoor use; pre-molded (push-on) terminations and separable connectors suit dead-front equipment interfaces; fluid-filled terminations serve specific outdoor applications. (8.2)
8.2.1The termination type shall be heat-shrink, cold-shrink, pre-molded, or fluid-filled as scheduled, and shall be IEEE 48 Class 1 for outdoor or wet-location terminations.
○ Heat-shrink
● Cold-shrink
○ Pre-molded (push-on)
○ Separable connector (dead-front)
● Indoor (Class 2 / Class 3 per IEEE 48)
○ Outdoor / wet location (Class 1 per IEEE 48)
NOTE Splice type shall match the cable construction and the splice location, which may be a manhole, a direct-buried location, or a vault. (8.3)
8.3.1The splice type shall be heat-shrink, cold-shrink, or pre-molded as scheduled, complying with IEEE 404.
○ Heat-shrink
● Cold-shrink
○ Pre-molded
8.4Every metallic shield shall be grounded at terminations, and shield continuity and ground resistance shall be verified, because an ungrounded or poorly grounded shield is both a personnel hazard and a cause of accelerated insulation aging.
8.4.1The metallic shield shall be grounded at every termination.
8.4.2Shield ground continuity shall be verified after termination.
8.5Adequate cable slack shall be left at each termination point — typically 10 to 15 ft per termination in manholes — so that terminations can be made, future re-terminations are possible, and minimum bend radius is preserved at the tails.
9 Installation
9.1Medium-voltage cable insulation and semiconducting layers are permanently damaged by exceeding the minimum bend radius or the maximum sidewall bearing pressure during pulling, so these limits shall be calculated and observed throughout installation.
9.1.1The minimum installation bend radius shall be not less than 12 times the overall cable diameter for single-conductor unarmored cable, or the manufacturer's published value where greater.
818
Default: 12 x diameter
9.1.2The maximum pulling tension on copper conductors shall not exceed 0.008 times the conductor circular-mil area, expressed in pounds, or the manufacturer's published maximum where lower.
9.1.3The sidewall bearing pressure shall not exceed 300 lb/ft, or the manufacturer's published limit where lower.
9.1.4Cable shall be pulled with a manufacturer-approved lubricant compatible with the jacket and shall be monitored with a tension-measuring device during the pull.
9.2Cable shall be installed only when the cable temperature is above the manufacturer's minimum installation temperature, because jacket and insulation are susceptible to cracking when pulled cold.
9.3Each cable run, splice, and termination shall be identified at every accessible point — manholes, vaults, and equipment terminations — with the circuit designation, so that runs can be traced and isolated for maintenance.
9.3.1Each cable shall be tagged with a permanent, legible circuit identification at every manhole, vault, pull point, and termination.
NOTE Spare conduits shall be reserved in the duct bank, and adequate bending and racking room shall be provided in manholes, in coordination with
Underground Ductbank, so that cable can be pulled, racked, and terminated without violating bend-radius limits.
(9.4) 10 Testing
NOTE Field acceptance testing proves the integrity of the installed system after the operations most likely to have damaged it, and is performed before energization. The required tests are insulation resistance, shield continuity, and an AC withstand by the VLF method. (10.1)
10.1.1Each cable run shall be insulation-resistance tested conductor-to-shield before and after the withstand test, and the results compared for consistency.
10.1.2Shield continuity and shield ground resistance shall be verified for each cable run.
NOTE DC hipot testing shall not be used on XLPE- or EPR-insulated medium-voltage cable, because DC voltage injects and traps space charge in extruded dielectric, causing latent dielectric damage and post-test failures. The acceptance withstand shall instead use the very-low-frequency (VLF) AC method of IEEE 400.2. (10.2)
10.2.1Each cable run shall be subjected to a VLF AC withstand test at 0.1 Hz, at 2.5 times U0 (the phase-to-ground rated voltage) for 60 minutes, per IEEE 400 and IEEE 400.2.
10.2.2DC hipot test voltage and DC acceptance criteria shall not be applied to XLPE- or EPR-insulated cable.
● VLF AC withstand at 0.1 Hz (IEEE 400.2)
○ Power-frequency AC withstand
○ Tan-delta diagnostic (supplemental)
10.2.3A cable that fails the withstand test shall not be energized; the fault shall be located, the affected splice or termination remade or the cable section replaced, and the run retested before acceptance.
11 Delivery, Storage, and Handling
NOTE Cable shall be delivered on reels with each end sealed against moisture ingress, because moisture in the conductor strand or under the shield migrates along the cable and degrades the insulation over its life. (11.1)
11.1.1Cable ends shall be sealed with manufacturer-supplied moisture-resistant end caps at delivery and shall remain sealed until termination or splicing.
11.1.2Reels shall be stored on a firm, well-drained surface, protected from mechanical damage, and shall not be stacked or dropped.
11.1.3Cable shall be protected from prolonged direct sunlight and from temperatures outside the manufacturer's storage range during storage on site.
12 Warranty
NOTE The Contractor shall warrant the installed cable system, including all splices and terminations, against defects in materials and workmanship for the project warranty period, and shall repair or replace failed cable, splices, or terminations at no cost to the Owner during that period. (12.1)
12.1.1The Contractor shall warrant the cable, splices, and terminations against defects in materials and workmanship for a minimum of one year from Substantial Completion, or the longer period scheduled.
13 Spare Parts
NOTE A reserve of splice and termination kits matched to the installed cable should be turned over to the Owner, so that an in-service failure can be repaired without waiting on procurement of voltage-class-specific kits. (13.1)
13.1.1The Contractor shall furnish to the Owner spare splice and termination kits matched to the installed cable voltage class and conductor size as scheduled.