Shallow Foundations (Spread and Strip Footings)

Rev 1 · Updated Jun 13, 2026 · View history

1 Scope

1.1This standard specifies the execution and quality assurance of shallow foundations — spread footings, continuous wall footings, combined footings, and strap footings — that bear directly on soil or rock within a few feet of finish grade.
1.2This standard governs forming, bearing-surface preparation, lean-concrete sub-bases, reinforcement and dowel layout, anchor-bolt and embedded-plate setting, keyways and construction joints, bearing inspection, and acceptance of shallow foundation work.
NOTE This standard is an execution specification, not a structural design document; the footing schedule prepared by the Engineer of Record and the project geotechnical report govern all dimensions, reinforcement, bearing pressures, and elevations. (1.3)
NOTE The contractor builds what the drawings and schedule require; this standard tells the contractor how to execute and verify that work to a defensible quality. Where a value here conflicts with the footing schedule or geotechnical report, those engineering deliverables govern. (1.4)
NOTE Concrete materials, mix proportioning, admixtures, conveying, placing, consolidation, finishing, curing, and cylinder testing are specified once for all cast-in-place work in Cast In Place Concrete and are incorporated here by reference rather than restated. (1.5)
NOTE Reinforcing-bar material, fabrication, bending, splicing, and placement tolerances are specified in Concrete Reinforcement; this standard specifies only footing-specific bar layout, cover, and dowel embedment. (1.7)
NOTE Deep foundation elements — driven piles, drilled shafts, continuous-flight-auger piles, micropiles, and helical piles — are outside this standard and are covered by Deep Foundations. (1.8)
NOTE Slabs-on-grade, including thickened slab edges that function as integral grade beams, are covered by Slab On Grade and are not within this standard. (1.9)
NOTE Excavation, dewatering, subgrade proof-rolling, and placement and compaction of engineered fill beneath footings are covered by Earthwork; this standard begins at the prepared, accepted bearing surface. (1.10)
NOTE Below-grade waterproofing membranes and foundation drainage are covered by Below Grade Waterproofing; precast grade beams by Precast Concrete; tilt-up panel footing ledges by Tilt Up Concrete; and permanent earth-retaining structures by Retaining Walls. (1.11)

2 Referenced Standards

2.1Materials, design, and execution shall comply with the latest adopted edition of each of the following unless a specific edition is cited or a more recent edition is mandated by the authority having jurisdiction.
2.2Where referenced standards conflict, the more stringent requirement shall govern unless the Engineer of Record directs otherwise in writing.
Standard Title
ACI CODE-318-25 Building Code Requirements for Structural Concrete and Commentary
ACI 301-20 Specifications for Concrete Construction
ACI 117-10 (R2015) Specification for Tolerances for Concrete Construction and Materials
ACI 336.2R-88 (R2002) Suggested Analysis and Design Procedures for Combined Footings and Mats
IBC 2021 (Section 1808) International Building Code — Foundation and Soil Investigations
IBC 2021 (Section 1809) International Building Code — Shallow Foundations
ASCE/SEI 7-22 Minimum Design Loads and Associated Criteria for Buildings and Other Structures
ASTM A615/A615M Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement
ASTM A706/A706M Deformed and Plain Low-Alloy Steel Bars for Concrete Reinforcement
ASTM C150/C150M Portland Cement
ASTM C94/C94M Ready-Mixed Concrete
ASTM C39/C39M Compressive Strength of Cylindrical Concrete Specimens
ASTM D1557 Laboratory Compaction Characteristics of Soil Using Modified Effort
ASTM D1586/D1586M Standard Penetration Test (SPT) and Split-Barrel Sampling of Soils

3 Submittals

3.1.1The Contractor shall submit the following action submittals for review and acceptance before placing footing concrete:
  • Concrete mix designs for each specified compressive strength, with the geotechnical sulfate-exposure class addressed.
  • Reinforcement placing drawings showing bar size, spacing, cover, dowel layout, and lap/development lengths for each footing type.
  • Anchor-bolt and embedded-plate setting drawings, including template details and the steel fabricator's bolt-pattern coordination.
  • Footing layout and excavation plan keyed to the footing schedule, identifying each bearing elevation and any stepped-footing transitions.
  • Proposed lean-concrete (mud-mat) sub-base locations and thickness where used.
Action Submittalscheckbox
Concrete mix designs (per specified strength)
Reinforcement placing drawings
Anchor-bolt / embedded-plate setting drawings
Footing layout and excavation plan
Lean-concrete sub-base plan
NOTE Informational submittals document conditions and qualifications; the Engineer reviews them for record and to confirm field readiness, but they do not by themselves authorize work. (3.2)
3.2.1The Contractor shall submit the following informational submittals:
  • Geotechnical report excerpts establishing the allowable bearing pressure and bearing stratum for each footing area.
  • Qualifications of the special inspection and testing agency performing bearing and concrete inspection.
  • Bearing-surface inspection reports for each footing, signed by the geotechnical engineer of record or their authorized representative.
  • Aggregate-base and engineered-fill compaction test reports beneath footings, referencing Earthwork.
Informational Submittalscheckbox
Geotechnical report excerpts (bearing pressure / stratum)
Testing agency qualifications
Bearing-surface inspection reports
Subgrade / fill compaction test reports
NOTE Closeout submittals are the record set delivered at completion so the Owner can document what was actually built and verify acceptance. (3.3)
3.3.1The Contractor shall submit the following closeout submittals before final acceptance of foundation work:
  • Concrete cylinder break reports (7-day and 28-day) for all footing placements.
  • As-built footing elevations and anchor-bolt locations where they deviate from the schedule within tolerance.
  • Signed bearing-inspection and pre-pour inspection records for all footings.
Closeout Submittalscheckbox
Cylinder break reports (7-day and 28-day)
As-built footing / anchor-bolt locations
Signed bearing and pre-pour inspection records

4 Quality Assurance

NOTE The bearing-inspection hold point is the single highest-value quality control step for shallow foundations: once concrete is placed, the bearing condition can no longer be verified, so it must be confirmed and signed off before any concrete or reinforcement covers the bearing surface. (4.1)
NOTE A footing sized for an assumed bearing pressure is only as good as the soil it actually rests on. Variable fill, soft pockets, organic seams, perched water, and over-excavation all defeat the design assumption. The pre-pour bearing inspection catches these before they are buried. (4.2)
4.3The bearing surface of every footing shall be inspected and accepted in writing by the geotechnical engineer of record or their authorized representative before reinforcement is set or concrete is placed.
4.4The contractor shall not place lean concrete, reinforcement, or footing concrete on any bearing surface until the bearing inspection sign-off for that footing has been obtained.
4.5Where the inspected bearing condition does not match the allowable bearing pressure assumed on the footing schedule, the contractor shall stop work on that footing and obtain written direction from the Engineer of Record before proceeding.
4.6A pre-pour inspection shall verify footing dimensions, bearing elevation, reinforcement size and spacing, cover, dowel layout, anchor-bolt template, and form condition.
4.7The pre-pour inspection shall be documented for each footing or footing group.
4.8Special inspection of shallow foundations shall be performed by a qualified agency in accordance with IBC 2021 Chapter 17 and the project statement of special inspections.
4.9The testing agency shall sample and test footing concrete in accordance with Cast In Place Concrete; at minimum, one set of cylinders shall be taken per 50 CY of concrete placed or per day of placement, whichever yields more sets.
4.10Concrete represented by any cylinder set whose 28-day average compressive strength falls below the specified f'c shall be evaluated in accordance with ACI 318-25, and the Engineer of Record shall determine acceptance, additional testing, or remediation.
NOTE Mock-ups and pre-construction conferences are coordination tools, not contractual obligations on the foundation subcontractor; they are most useful where anchor-bolt patterns are complex or where stepped footings on a sloped site introduce sequencing risk. (4.11)

5 Geotechnical Basis and Bearing

NOTE The allowable bearing pressure governs the plan dimensions of every footing; it is established by the geotechnical engineer from the soil investigation. (5.1)
5.2The allowable bearing pressure shall not be assumed or interpolated by the contractor; it shall be taken from the project geotechnical report or the footing schedule.
NOTE Allowable bearing pressure (the net allowable soil bearing capacity) is the pressure the soil can carry safely after accounting for overburden, groundwater, and an appropriate factor of safety. IBC Table 1806.2 gives prescriptive presumptive values by soil class — roughly 1,500 psf for clay or silt up to 4,000 psf for sandy gravel — but a site-specific geotechnical report almost always governs and commonly falls in the 1,500 to 6,000 psf range, with competent rock far higher. (5.3)
5.4The allowable bearing pressure used for each footing area shall be the value stated in the project geotechnical report or on the footing schedule, not a presumptive code value, unless the building official has explicitly accepted presumptive values for the project.
NOTE Standard Penetration Test N-values reported in the geotechnical investigation, obtained per ASTM D1586, are the primary field data behind the allowable bearing pressure. (5.5)
5.6The contractor shall not rely on visual soil assessment in lieu of the geotechnical report to determine allowable bearing pressure.
Allowable Bearing Pressure (per geotechnical report)range
psf
150010000
Default: 2000 psf
Per drawings — footing schedule / geotechnical report
5.7Footing depth shall satisfy the deepest of three controls: the minimum embedment below adjacent finished grade, the local frost-protection depth, and the elevation of the competent bearing stratum identified in the geotechnical report.
NOTE The bottom of exterior footings and footings in unheated areas shall be placed below the local frost-protection depth established by the authority having jurisdiction. (5.8)
NOTE Frost depth varies dramatically by region — effectively zero in the deep South to 48 inches or more across the northern tier — and a footing bottom above frost depth is subject to frost heave. The Engineer of Record translates the local frost depth into a bottom-of-footing elevation on the drawings; the contractor builds to that elevation. (5.9)
Minimum Footing Embedment Below Adjacent Graderange
in
1872
Default: 24 in
Per drawings — footing schedule
Frost-Protection Depth (bottom of footing below grade)range
in
072
Default: 36 in
Per drawings — footing schedule (per AHJ frost depth)
5.10Where the bearing stratum is reached at a varying elevation, footings shall be stepped or deepened as directed by the Engineer of Record rather than founded partly on bearing soil and partly on fill.

6 Footing Types and Configurations

NOTE Footing type is selected by the Engineer of Record from the column and wall layout, load eccentricity, proximity to property lines, and soil bearing; each type addresses a specific geometric or load condition, and mis-forming or mis-locating one defeats the design intent in the field. (6.1)
NOTE The five common shallow-foundation configurations each address a different geometry. Choosing among them is a design decision, but mis-forming or mis-locating one defeats that decision in the field. (6.2)
NOTE Isolated spread footings support a single column and are reinforced in two directions; square footings carry uniform bar spacing each way, while rectangular footings concentrate a band of reinforcement under the column in the short direction per ACI 318-25. (6.2.1)
NOTE Continuous strip (wall) footings run beneath bearing and shear walls, carrying continuous longitudinal reinforcement plus transverse bars; they distribute wall loads as a line load rather than a point load. (6.2.2)
NOTE Combined footings carry two or more columns on one footing where individual footings would overlap or where a column sits against a property line, and may be rectangular or trapezoidal in plan to balance bearing pressure. (6.2.3)
NOTE Strap (cantilever) footings tie a property-line column footing to an interior footing with a rigid strap beam so the eccentric edge load is balanced and bearing pressures are kept near uniform, per ACI 336.2R. (6.2.4)
NOTE Stepped footings accommodate sloped sites by stepping the bearing elevation; each step is limited by code, and horizontal reinforcement must be lapped continuously across each step. (6.2.5)
NOTE Thickened spread footings with an integral pedestal carry a formed concrete pier between footing and steel column, common for industrial and pre-engineered metal buildings. (6.2.6)
Footing Typeselect
Isolated spread (column) footing
Continuous strip (wall) footing
Combined footing (two or more columns)
Strap / cantilever footing
Stepped footing
Spread footing with integral pedestal
6.3Stepped footings shall step at a slope no steeper than 1 vertical to 2 horizontal between adjacent bearing elevations, in accordance with IBC 2021 Section 1809.
6.4Horizontal reinforcement in stepped footings shall be lapped continuously across each step so that the footing acts as a single continuous element.

7 Materials

NOTE Footing concrete strength is selected by the Engineer of Record for structural demand and exposure; 3,000 psi is the common default for light residential work and 4,000 psi for commercial and industrial footings, with higher strengths and sulfate-resistant cement where the geotechnical report identifies aggressive soils. (7.1)
NOTE ACI 318-25 sets 2,500 psi as the absolute minimum for structural concrete, but durability — not strength — frequently controls the mix. Sulfate exposure classes from the geotechnical report drive cement type and supplementary cementitious materials, specified through the mix design under Cast In Place Concrete. (7.2)
7.2.1Footing concrete shall be normalweight ready-mixed concrete furnished and tested in accordance with ASTM C94 and Cast In Place Concrete.
7.2.2Portland cement shall conform to ASTM C150; Type I/II is the baseline, and a sulfate-resistant type shall be furnished where the geotechnical sulfate-exposure class requires it.
7.2.3The specified compressive strength f'c shall not be less than 2,500 psi for any structural footing, in accordance with ACI 318-25.
Specified Compressive Strength (f'c) at 28 Daysselect
2500
3000
4000
4500
5000
NOTE Reinforcing bar grade is a design selection; Grade 60 deformed bar to ASTM A615 is the corpus default, with ASTM A706 low-alloy bar required where weldability or seismic ductility is specified for dowels and starter bars. (7.3)
7.3.1Footing reinforcement shall be deformed bar conforming to ASTM A615 Grade 60 unless the structural drawings specify otherwise.
7.3.2Reinforcement that will be welded, or that is required to meet seismic ductility provisions of ACI 318-25 Chapter 18, shall conform to ASTM A706.
Reinforcing Bar Specificationradio
ASTM A615 Grade 60 (standard)
ASTM A706 Grade 60 (weldable / seismic)
NOTE Lean concrete used for a mud-mat sub-base is plain, unreinforced, low-strength concrete whose purpose is to provide a clean, stable working surface for setting reinforcement — it is not a structural element. (7.4)
7.4.1Lean concrete for mud-mat sub-bases shall have a specified compressive strength of 2,000 to 2,500 psi and shall be placed without reinforcement.

8 Reinforcement, Cover, and Dowels

NOTE Concrete cast against and permanently exposed to earth requires more cover than formed concrete because the soil interface is irregular and aggressive; the most common footing detailing error is defaulting to beam cover instead of the cast-against-earth value. (8.1)
NOTE ACI 318-25 requires 3 inches of cover for concrete cast against and permanently exposed to earth — the bottom and sides of a footing poured neat against the excavation or against a mud-mat. Formed faces later exposed to weather require 2 inches. Specifying and verifying the correct cover is what keeps the steel protected for the life of the structure. (8.2)
8.2.1Concrete cover over reinforcement cast against and permanently exposed to earth shall be not less than 3 inches, in accordance with ACI 318-25.
8.2.2Concrete cover over formed footing faces exposed to weather or earth after form removal shall be not less than 2 inches.
Concrete Cover — Cast Against Earthrange
in
34
Default: 3 in
Concrete Cover — Formed Faces Exposed to Weatherrange
in
1.53
Default: 2 in
NOTE Footing bar size and spacing are set by the structural design; the layout below is the field deliverable, and reinforcement that cannot develop its required length within the footing must be resolved before the pour, not discovered at it. (8.3)
NOTE Footing bars are typically #4 through #8. One-way strip footings carry a minimum of two longitudinal bars and temperature-and-shrinkage steel of 0.0018 times the gross area for Grade 60 per ACI 318-25. The governing geometry constraint is that the footing must be thick enough to develop the bottom bars — development length plus cover plus the diameter of the transverse bar. (8.4)
8.4.1Footing reinforcement shall be placed at the size, spacing, and distribution shown on the reinforcement placing drawings and footing schedule.
8.4.2Bottom reinforcement shall be supported on bar chairs, dobies, or precast cover blocks sized to maintain the specified cover above the bearing surface or mud-mat; reinforcement shall not be laid directly on soil.
8.4.3One-way strip footings shall contain not less than two continuous longitudinal bars and temperature-and-shrinkage reinforcement of not less than 0.0018 times the gross concrete area for Grade 60 bar, per ACI 318-25.
8.4.4Footing thickness shall be sufficient to develop the bottom reinforcement, accommodating the required development length plus cover plus the diameter of the transverse bar; where it is not, mechanical couplers or standard hooks shall be provided as detailed by the Engineer of Record.
Primary Footing Bar Sizeselect
#4
#5
#6
#7
#8
Per drawings — footing schedule
Footing Bar Spacing (each way)range
in
618
Default: 12 in
Per drawings — footing schedule
Footing Thicknessrange
in
1236
Default: 18 in
Per drawings — footing schedule
NOTE Column and wall dowels transfer load from the superstructure into the footing and must be embedded to develop their required length; short dowels are a recurring source of field rework. (8.5)
8.5.1Column and wall dowels shall match the size and number shown on the structural drawings and shall be embedded in the footing to develop their required tension or compression length per ACI 318-25.
8.5.2Dowels shall be tied in position and supported so they do not displace during concrete placement; field-bending or repositioning of dowels to fit columns is not permitted without the Engineer of Record's written approval.
Column / Wall Dowel Embedmentrange
in
1248
Default: 24 in
Per drawings — footing schedule

9 Anchor Bolts and Embedded Plates

NOTE Anchor bolts set by hand routinely drift out of tolerance, and a bolt pattern that exceeds tolerance forces field reaming or base-plate rework and cascades RFIs to the steel fabricator; a rigid template is the single most effective control. (9.1)
NOTE Anchor-bolt spacing and the location of the bolt group relative to column gridlines are tight tolerances because the steel base plate is fabricated to fixed hole patterns. Setting bolts to a template that is secured to the formwork — not to loose string lines — is what keeps the steel erectable. (9.2)
9.2.1Anchor bolts and embedded plates shall be set using a rigid template, secured to the formwork or footing forms, that fixes both the bolt-group pattern and its location relative to column gridlines before concrete is placed.
9.2.2Anchor-bolt projection above the top of concrete shall match the steel fabricator's requirements, accounting for base-plate thickness, leveling nuts, and grout space.
9.2.3Anchor bolts shall be set within a spacing tolerance of ±1/16 inch bolt-to-bolt within a group and a location tolerance of ±1/8 inch on the group centerline relative to the established column gridline, unless the structural drawings specify tighter tolerances.
9.2.4Anchor bolts and embedded plates shall be cleaned of concrete and protected from damage until the supported steel is erected.
9.2.5Anchor-bolt threads shall be protected during the pour.
Anchor Bolt Diameterselect
0.75
0.875
1.0
1.25
1.5
Per drawings — anchor-bolt schedule
Anchor Bolt Setting Methodradio
Rigid template secured to formwork
Cast-in template with leveling provision
Anchor Bolt Group Centerline Tolerancerange
in
0.06250.25
Default: 0.125 in

10 Keyways and Construction Joints

NOTE Shear transfer between a footing and the wall or stem above it is not automatic; a keyway or a roughened, intentionally bonded construction joint must be specified, or the joint becomes a smooth plane that cannot transfer horizontal shear. (10.1)
NOTE At the footing-to-stem-wall interface, the second pour bonds to the first only as well as the joint is prepared. A formed keyway provides a mechanical shear key; alternatively, a roughened construction joint to a full amplitude provides shear-friction capacity. Dowels across the joint develop tension. The detail must be on the drawings and built as shown. (10.2)
10.2.1A keyway or an intentionally roughened construction joint shall be provided at the footing-to-stem-wall or footing-to-grade-beam interface as detailed by the Engineer of Record.
10.2.2Where a roughened construction joint is used in lieu of a keyway, the surface shall be intentionally roughened to a full amplitude of approximately 1/4 inch and cleaned of laitance before the subsequent placement.
10.2.3Vertical dowels crossing the construction joint shall be sized, spaced, and embedded as shown on the structural drawings to develop the required shear-friction and tension across the joint.
Footing-to-Wall Shear Transferradio
Formed keyway
Roughened construction joint (≈1/4 in amplitude)
Both keyway and dowels
Per drawings — footing-to-wall detail
Keyway Widthrange
in
1.56
Default: 2 in
Per drawings — footing-to-wall detail
Keyway Depthrange
in
1.54
Default: 1.5 in
Per drawings — footing-to-wall detail

11 Lean-Concrete Sub-Base (Mud-Mat)

NOTE A mud-mat protects reinforcement cover and alignment on soft or wet subgrade, where bars set on loose soil sink, lose cover, and drift out of position; it is a working surface, not a structural layer. (11.1)
NOTE On firm, dry subgrade a mud-mat is optional. On soft or saturated soil it earns its cost: a thin lean-concrete slab gives a clean, level surface that holds chairs and keeps the bottom mat at the right elevation. The decision should follow a soil-condition trigger rather than contractor preference. (11.2)
11.2.1A lean-concrete mud-mat shall be provided where the subgrade is soft, where groundwater is within 12 inches of the bearing elevation, or where the geotechnical report or drawings require it.
11.2.2Where used, the mud-mat shall be a minimum of 3 inches thick and shall extend not less than 3 inches beyond the footing perimeter to provide working clearance.
11.2.3Reinforcement shall not be placed directly on a subgrade that is soft enough to displace under foot or equipment traffic; a mud-mat or equivalent stable working surface shall be provided first.
Lean-Concrete Mud-Matradio
Required (soft / wet subgrade)
Not required (firm, dry subgrade)
Per geotechnical recommendation
Mud-Mat Thicknessrange
in
36
Default: 3 in

12 Tolerances

NOTE Footing dimensional tolerances follow ACI 117 and matter because a footing that is mislocated, undersized, or out of plumb at the pedestal can shift bearing pressure, reduce cover, or prevent the supported column from landing on its base. (12.1)
12.1.1Footing location, plan dimensions, top elevation, and thickness shall be within the tolerances of ACI 117 unless the structural drawings specify tighter limits.
12.1.2Reduction of any footing plan dimension below the scheduled dimension shall not be permitted; oversizing within the excavation is acceptable provided cover and reinforcement position are maintained.
12.1.3Pedestals and formed stem walls cast monolithically or jointed to footings shall be plumbed within the ACI 117 tolerance for the formed surface.
Footing Plan-Dimension Tolerancerange
in
02
Default: 2 in

13 Installation

NOTE Footing execution proceeds from accepted bearing surface to verified embeds in a fixed sequence; skipping the verification steps is where defects become permanent. (13.1)
NOTE The execution sequence is: prepare and obtain acceptance of the bearing surface, place any mud-mat, set and tie reinforcement and dowels to the correct cover, set anchor-bolt templates and embeds, complete the pre-pour inspection, then place concrete under Cast In Place Concrete. Each gate exists because the condition it checks cannot be verified after the next step covers it. (13.2)
13.2.1The contractor shall coordinate excavation, dewatering, and subgrade preparation with Earthwork so that the bearing surface presented for inspection is the surface on which the footing will bear.
13.2.2Loose, disturbed, or over-excavated material at the bearing surface shall be removed and replaced with lean concrete or compacted engineered fill as directed by the geotechnical engineer before reinforcement is set.
13.2.3Water shall be removed from footing excavations and concrete shall not be placed in standing water or on a frozen or frost-affected bearing surface.
13.2.4Reinforcement, dowels, anchor-bolt templates, and embedded plates shall be set, tied, and secured against displacement before concrete placement begins.
13.2.5The pre-pour inspection shall be completed and signed before concrete placement begins.
13.2.6Footing concrete shall be placed, consolidated, finished, and cured in accordance with Cast In Place Concrete; this standard does not restate those requirements.
13.2.7Concrete shall be placed continuously within each footing; planned construction joints shall occur only where shown on the drawings and shall be prepared as specified for keyways and construction joints.
NOTE Backfill placed against a footing or stem wall before the concrete has gained adequate strength can crack or displace the element; a strength gate prevents premature loading. (13.3)
13.3.1Backfill shall not be placed against footings or stem walls, and surcharge loads shall not be applied, until the concrete has attained at least 70 percent of its specified compressive strength, verified by 7-day cylinder breaks or by maturity, and until any required bracing is in place.
13.3.2A hold point for inspection shall be observed before backfill is placed against foundation elements, and backfill operations shall be coordinated with Below Grade Waterproofing where waterproofing or drainage is installed.
Minimum Strength Before Backfill / Surchargerange
% f'c
50100
Default: 70 % f'c

14 Eccentricity and Overturning

NOTE Footings carrying combined axial load and moment — from frame action, wind, or seismic demand — must be checked for the bearing-pressure distribution across the base, not just the average pressure; a footing that looks adequate on average can overstress one edge or partially uplift. (14.1)
NOTE For a footing under axial load plus moment, keeping the load resultant within the middle third of the base (eccentricity not exceeding B/6) keeps the entire base in compression. Larger moments, common in seismic design, may allow partial uplift only with a documented analysis. Footings subject to significant moment are a design responsibility, but specifications that never require the check invite undersized footings. (14.2)
14.2.1Footings subject to combined axial load and moment shall be designed by the Engineer of Record for the resulting non-uniform bearing-pressure distribution and for overturning stability.
14.2.2Where the load resultant on an eccentrically loaded footing falls outside the middle third of the base, the partial-uplift condition shall be supported by a documented analysis from the Engineer of Record, in accordance with ASCE/SEI 7-22 load combinations.
14.2.3The contractor shall not substitute a symmetric footing for a combined or strap footing shown on the drawings, as these types exist specifically to manage eccentric loading.

15 Delivery, Storage, and Handling

NOTE Footing materials are largely delivered just in time, but reinforcement and embeds staged on site must be protected so that what is installed still meets the material specifications. (15.1)
15.1.1Reinforcing bar shall be stored off the ground on supports and protected from contaminants that would impair bond, in accordance with Concrete Reinforcement.
15.1.2Anchor bolts, embedded plates, and templates shall be stored to protect threads and faying surfaces from damage, corrosion, and concrete contamination until set.
15.1.3Ready-mixed concrete shall be delivered, discharged, and tested within the time and condition limits of ASTM C94 and Cast In Place Concrete.

16 Warranty

NOTE Foundation defects surface slowly and are expensive to access once a structure is built over them, so the warranty obligation centers on workmanship and on correcting deficiencies revealed by acceptance testing and inspection. (16.1)
16.1.1The Contractor shall warrant footing work against defective materials and workmanship for the period stated in the Contract, and shall correct concrete that fails to meet the specified compressive strength as determined under ACI 318-25.
16.1.2The Contractor shall remain responsible for correcting footing defects attributable to placing on unaccepted bearing surfaces, omitted bearing inspections, or backfill placed before the required strength was attained.

17 Spare Materials and Records

NOTE Shallow foundations are buried in service, so the durable deliverable is the record set; spare physical materials are minimal. (17.1)
17.1.1The Contractor shall deliver to the Owner the complete record set of bearing-inspection reports, pre-pour inspection records, cylinder break reports, and as-built footing and anchor-bolt locations.
17.1.2The Contractor shall retain unused project-specific embed templates until final acceptance in case anchor-bolt rework is directed.

Edit this page