Cast-in-Place Site Concrete Structures

Rev 1 · Updated Jun 14, 2026 · View history

Build a datasheet from this standard Start a project with this standard already attached — one click, no setup.
Use in a project

1 Scope

NOTE This Standard covers cast-in-place reinforced concrete structures that are civil and utility site scope rather than building structural scope; these structures are formed and poured in place at their final location, as distinct from precast structures fabricated at a plant and set in a single lift, and the applications gathered here share a working environment - they sit in soil, carry or convey drainage water, host pipe and conduit penetrations, and are frequently exposed to weather and deicing salts. (1.1)
NOTE Typical applications covered by this Standard include the following. (1.2)
  • Drainage headwalls and wingwalls at culvert and storm outfalls
  • Cast-in-place utility vaults - pull vaults, splice vaults, and meter vaults
  • Trench-interceptor walls and cast-in-place channel liners
  • Culvert end walls and junction chambers where multiple pipes converge
  • Catch basin collars and cast-in-place adjustment rings to bring precast units to grade
  • Yard drainage sumps and outfall aprons with integral curbs
  • Low walls (under 4 ft of exposed face) integral to drainage or utility routing
NOTE This Standard is a child of Cast In Place Concrete and inherits its material and mix-design requirements; the parent standard governs building cast-in-place work - the structural frame, foundations, and slabs - and is the authoritative reference for concrete materials, mix qualification, formwork practice, and field testing; this Standard does not restate those material rules in full but adopts them and adds the site-specific requirements that building concrete does not address: exposure classification for buried and water-contact conditions, formed pipe and conduit penetrations, vault and headwall configurations, waterstopped construction joints, and backfill sequencing; where a material or testing requirement here is silent, the parent standard governs. (1.3)
1.4Cast-in-place site concrete shall be designed and constructed in accordance with ACI CODE-318-25 and ACI 301-20 as adopted by the authority having jurisdiction.
1.5Concrete cast-in-place site structures subject to a building permit shall comply with IBC Chapter 19 as adopted by the authority having jurisdiction.
NOTE Several adjacent standards own work that is easy to conflate with this Standard: building structural concrete belongs to Cast In Place Concrete; isolated mechanical and electrical equipment pads belong to Concrete Pads; site retaining walls carrying significant retained-soil surcharge belong to Retaining Walls; precast manholes, vaults, and box culverts supplied from a plant belong to Utility Manholes And Handholes; storm pipe, inlet sizing, and network layout belong to Storm Drainage; and the excavation and backfill operations around these structures belong to Earthwork. (1.6)
NOTE Where a single structure is part cast-in-place and part precast, the Contract Documents shall identify unambiguously which portions are governed by this Standard and which by Utility Manholes And Handholes. (1.7)
NOTE Catch basin collars and adjustment rings poured onto precast base units are the common mixed case; combining cast-in-place forming procedures with precast plant tolerances on the same element produces conflicting requirements, and the scope split must be explicit on the drawings so the requirements do not collide. (1.8)

2 Referenced Standards

2.1Materials, design, and construction shall comply with the latest adopted edition of each of the following unless a specific edition is cited in the Contract Documents.
2.2Where referenced standards conflict, the more stringent requirement shall govern unless the Engineer of Record directs otherwise in writing.
Standard Title
ACI CODE-318-25 Building Code Requirements for Structural Concrete and Commentary
ACI 301-20 Specifications for Structural Concrete
ACI 117-10 (R2015) Specification for Tolerances for Concrete Construction and Materials
ACI 305R-20 Guide to Hot Weather Concreting
ACI 306R-16 Guide to Cold Weather Concreting
ACI 347R-14 Guide to Formwork for Concrete
ASTM C33/C33M Standard Specification for Concrete Aggregates
ASTM C39/C39M Compressive Strength of Cylindrical Concrete Specimens
ASTM C94/C94M Standard Specification for Ready-Mixed Concrete
ASTM C138/C138M Density, Yield, and Air Content (Gravimetric) of Concrete
ASTM C143/C143M Slump of Hydraulic-Cement Concrete
ASTM C150/C150M Standard Specification for Portland Cement
ASTM C172/C172M Sampling Freshly Mixed Concrete
ASTM C231/C231M Air Content of Freshly Mixed Concrete by the Pressure Method
ASTM C260/C260M Air-Entraining Admixtures for Concrete
ASTM C309 Liquid Membrane-Forming Compounds for Curing Concrete
ASTM C494/C494M Chemical Admixtures for Concrete
ASTM C618 Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete
ASTM C1064/C1064M Temperature of Freshly Mixed Hydraulic-Cement Concrete
ASTM A615/A615M Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement
ASTM A706/A706M Deformed and Plain Low-Alloy Steel Bars for Concrete Reinforcement
ASTM F1554 Anchor Bolts, Steel, 36, 55, and 105-ksi Yield Strength
OSHA 29 CFR 1926.703 Requirements for Cast-in-Place Concrete
IBC Chapter 19 Concrete (International Building Code, 2024)

3 Submittals

3.1.1The Contractor shall submit the following action submittals for review and acceptance before placing concrete:
  • Concrete mix design for each strength and exposure class, with the supplier's qualification data (trial batch or field test record per ACI 301-20)
  • Aggregate source and gradation report per ASTM C33
  • Admixture product data - air-entraining (ASTM C260), chemical (ASTM C494), and any supplementary cementitious materials (ASTM C618)
  • Reinforcing steel shop drawings and bar bending schedule (coordinate with Concrete Reinforcement)
  • Formwork design for walls over 8 ft tall or where lateral pressure exceeds code-default assumptions, stamped by a licensed engineer
  • Penetration and embed layout drawings showing cast-in sleeves, knockouts, anchor hardware, and conduit stubs coordinated against the civil, mechanical, and electrical drawings
  • Waterstop product data and joint-layout drawing for below-grade structures
  • Curing compound product data (ASTM C309) where membrane curing is proposed
Action Submittalscheckbox
Concrete mix design (per strength and exposure class)
Aggregate source and gradation report
Admixture and SCM product data
Reinforcing shop drawings and bar bending schedule
Formwork design (engineer-stamped where required)
Penetration and embed layout drawings
Waterstop product data and joint layout
Curing compound product data
NOTE Informational submittals document that the delivered materials and field conditions match what was accepted; they are recorded but do not by themselves hold the work. (3.2)
3.2.1The Contractor shall submit the following informational submittals:
  • Concrete delivery tickets per ASTM C94 showing batch time, mix designation, water added, and quantities
  • Field test reports - slump, air content, temperature, and cylinder strength results
  • Cold-weather or hot-weather placement plan when triggered by ambient or concrete temperature limits
  • Backfill release records showing concrete age or field-cured cylinder strength before backfill against walls
Informational Submittalscheckbox
Concrete delivery tickets
Field test reports (slump, air, temperature, strength)
Hot-weather placement plan
Cold-weather placement plan
Backfill release records
NOTE Closeout submittals are delivered at completion and become part of the project record for the owner's future operation and maintenance of the structure. (3.3)
3.3.1The Contractor shall submit the following closeout submittals:
  • Record drawings showing as-built penetration locations, invert elevations, and cast-in hardware
  • Consolidated field test reports with the Engineer's acceptance status for each placement
  • Curing and sealer application records for exposed structures
Closeout Submittalscheckbox
Record drawings (as-built penetrations and inverts)
Consolidated field test reports
Curing and sealer application records

4 Quality Assurance

NOTE A pre-pour inspection hold point is the single most important quality control on site concrete structures because reinforcement placement, cover, penetration and sleeve locations, anchor hardware, and waterstop continuity are all permanently buried by the pour and cannot be corrected once concrete is placed; several of the most expensive field failures - cored penetrations through reinforced walls, missing waterstop at a cold joint, mislocated anchor bolts - trace directly to a pour that proceeded without a verified inspection. (4.1)
4.2A pre-pour inspection hold point shall be established for each structure, and concrete shall not be placed until the Engineer or designated inspector has verified reinforcement, cover, penetrations, embeds, and waterstop continuity.
NOTE This Standard specifies the work and the contractor's quality control; the independent special inspector's role - continuous or periodic inspection, sampling oversight, and reporting to the authority having jurisdiction - is governed by Special Inspections And Testing, which is complementary to this Standard: this Standard says what to build and test, that standard says who independently verifies it. (4.3)
4.4The independent inspection and testing program shall be administered in accordance with Special Inspections And Testing.
4.5Field testing shall be performed by a technician certified as an ACI Concrete Field Testing Technician Grade I or equivalent.
4.6The concrete supplier shall hold current NRMCA plant certification or shall demonstrate equivalent production quality control acceptable to the Engineer.
4.6.1One composite sample shall be obtained for each 50 cubic yards placed or for each day's pour, whichever is more frequent, per ACI 301-20.
4.6.2Each composite sample shall include slump (ASTM C143), air content (ASTM C231), concrete temperature (ASTM C1064), and a set of strength cylinders.
4.6.3Each strength set shall consist of a minimum of two cylinders tested at 28 days and one cylinder tested at 7 days (ASTM C39), with sampling per ASTM C172.
Field Test Sampling Frequencyselect
One sample per 50 CY or per day's pour, whichever is more frequent
One sample per 25 CY or per day's pour, whichever is more frequent
One sample per 100 CY or per day's pour, whichever is more frequent
Strength Test Cylinders per Setradio
Two at 28 days plus one at 7 days
Two at 28 days plus two at 7 days
Three at 28 days plus one at 7 days

5 Environmental and Service Conditions

NOTE Exposure classification is the decision that drives mix selection for site structures and is where site concrete diverges most from building concrete; building interior concrete typically sees benign exposure, but site structures sit in soil that may be sulfate-bearing, are in frequent contact with drainage water, and - for headwalls, aprons, and curbs - are fully exposed to freeze-thaw cycling and deicing salts; ACI CODE-318-25 Table 19.3.1 classifies exposure in four categories and the governing category sets the maximum water-cementitious ratio and the minimum compressive strength; the most common error on site work is to reuse the building interior mix without re-evaluating exposure. (5.1)
5.2The exposure class for each structure shall be determined from ACI CODE-318-25 Table 19.3.1 based on the project geotechnical report and the structure's service condition.
5.2.1The freezing-and-thawing (W) class shall be assigned per the structure's exposure to moisture and freeze-thaw cycling, with deicing-salt-exposed surfaces classified no lower than W2.
5.2.2The sulfate (S) class shall be assigned from the water-soluble sulfate content of soil and groundwater reported in the project geotechnical report.
5.2.3The corrosion-protection (C) class shall be assigned based on exposure to chlorides from deicing chemicals, brackish water, or seawater.
Freezing and Thawing Exposure Class (W)radio
W0 - not exposed to freezing
W1 - exposed, not in continuous contact with water
W2 - exposed, in contact with water and deicing chemicals
Sulfate Exposure Class (S)radio
S0 - negligible (< 0.10% water-soluble sulfate in soil)
S1 - moderate (0.10 to 0.20%)
S2 - severe (0.20 to 2.00%)
S3 - very severe (> 2.00%)
Corrosion Protection Exposure Class (C)radio
C0 - dry or protected from moisture
C1 - exposed to moisture, no external chloride source
C2 - exposed to moisture and an external chloride source
NOTE Concrete placement is governed by ambient and concrete temperature and the limits are not optional; concrete placed too hot loses workability, flash-sets, and develops plastic shrinkage cracking; placed too cold, it gains strength slowly and is vulnerable to freezing before it has set; ACI 301-20 sets a concrete temperature window at the point of discharge, and exceeding either bound triggers a documented placement plan under ACI 305R (hot weather) or ACI 306R (cold weather). (5.3)
5.3.1Concrete temperature at the point of discharge shall be maintained between 50 °F and 90 °F unless a placement plan establishes otherwise.
5.3.2When ambient temperature exceeds 90 °F or concrete temperature approaches the upper limit, a hot-weather placement plan per ACI 305R shall be submitted and followed.
5.3.3When ambient temperature falls below 40 °F, a cold-weather placement plan per ACI 306R shall be submitted and followed, and no concrete shall be permitted to freeze before reaching 500 psi.

6 Concrete Materials and Mix

NOTE Compressive strength shall be selected from the structural design and the governing exposure class, not chosen uniformly across all site concrete; for lightly loaded site walls and aprons 3,000 psi is adequate, the 80% case for buried utility vaults and headwalls is 3,500 psi, walls subject to vehicular surcharge or severe freeze-thaw warrant 4,000 psi, and specifying 5,000 psi across all site concrete without an exposure or load basis is a common overspecification that raises mix cost and - because the higher cementitious content increases heat of hydration - can actually increase cracking in thin site walls; all strengths are verified at 28 days by ASTM C39. (6.1)
6.1.1The specified compressive strength shall be not less than the minimum required by the governing exposure class in ACI CODE-318-25 Table 19.3.2.1.
Specified Compressive Strength (f'c) at 28 Daysradio
3000
3500
4000
5000
NOTE The water-cementitious materials ratio is capped by exposure class and that ceiling - not workability - governs the maximum; a lower w/cm produces a denser, less permeable paste that resists sulfate attack, chloride ingress, and freeze-thaw scaling; ACI CODE-318-25 Table 19.3.2.1 sets the maximum w/cm by exposure class: general site concrete at W1/C1 is limited to 0.50, soil-contact concrete in moderate sulfate or freeze-thaw Class 2 is limited to 0.45, and severe exposure (C2, S2, W2) is limited to 0.40; workability shortfalls at a low w/cm are corrected with a water reducer, never by adding water at the truck. (6.2)
6.2.1The maximum water-cementitious materials ratio shall not exceed the limit for the governing exposure class.
Maximum Water-Cementitious Materials Ratio (w/cm)radio
0.50 - general site concrete (W1 / C1)
0.45 - soil contact, moderate sulfate or freeze-thaw
0.40 - severe exposure (C2, S2, W2)
NOTE Cement type depends on the sulfate exposure read from the geotechnical report; Type I/II portland cement (ASTM C150) is the general-purpose choice and carries the moderate-sulfate resistance of Type II; where the geotechnical report shows high water-soluble sulfate in soil or groundwater (Class S2 or S3), Type V sulfate-resisting cement is required to prevent sulfate attack on the buried structure; the cement decision must be made from the geotechnical data, not assumed. (6.3)
6.3.1The cement type shall be selected per ASTM C150 to match the governing sulfate exposure class.
Portland Cement Typeradio
Type I/II - general purpose, moderate sulfate resistance
Type V - high sulfate resistance (S2 / S3 soils)
NOTE Supplementary cementitious materials improve durability and reduce heat of hydration; replacing a portion of the portland cement with Class F fly ash (ASTM C618) reduces permeability, improves sulfate resistance, and lowers the heat of hydration that drives early cracking in thicker pours; a 15 to 25% Class F replacement by weight of cementitious material is the 80% case; Class C fly ash up to 25% is acceptable where sulfate exposure is low but is less effective against sulfate attack and should not be the choice for S2/S3 soils; slag cement and silica fume are alternatives where specified by the mix designer. (6.4)
Supplementary Cementitious Materialradio
Class F fly ash, 15 to 25% replacement
Class C fly ash, up to 25% replacement
Slag cement, per mix design
None
NOTE Air entrainment is mandatory for exposed site concrete in freeze-thaw climates and is one of the most frequently omitted requirements; headwalls, curb aprons, and exposed wall faces take the full force of freeze-thaw cycling and deicing salts, and without entrained air (ASTM C260) the surface scales rapidly; the target air content is keyed to the nominal maximum aggregate size and freeze-thaw severity per ACI CODE-318-25 Table 19.3.3.1: 5.0 to 7.0% for 3/4 in. aggregate, 4.0 to 6.0% for 1-1/2 in. aggregate; interior-only, protected structures may be placed without entrained air; air content is verified in the field by ASTM C231. (6.5)
6.5.1Concrete for surfaces exposed to freeze-thaw cycling shall be air-entrained to the target content for the nominal maximum aggregate size.
Target Air Contentselect
5.0 to 7.0 (3/4 in. max aggregate, freeze-thaw)
4.0 to 6.0 (1-1/2 in. max aggregate, freeze-thaw)
None - interior or protected, not freeze-thaw exposed
NOTE Slump at the point of discharge is limited to control segregation, with a higher ceiling permitted only when a high-range water reducer is used; a conventional mix is limited to 4 in. slump at discharge; a high-range water-reducing admixture (HRWRA, ASTM C494 Type F or G) produces a flowable mix without adding water, permitting up to 8 in. slump for congested reinforcement or deep wall forms; the HRWRA path preserves the low w/cm, while adding water at the truck to gain workability does not and is prohibited. (6.6)
6.6.1Slump at the point of discharge shall not exceed 4 in. without a high-range water-reducing admixture, or 8 in. with an approved Type F or G HRWRA.
6.6.2Water shall not be added to the concrete at the point of discharge to increase slump.
Maximum Slump at Point of Dischargeradio
4 (no HRWRA)
8 (with approved Type F/G HRWRA)

7 Reinforcement and Cover

NOTE Reinforcement grade and minimum bar sizes follow standard practice; Grade 60 deformed bars (ASTM A615) are the standard choice, low-alloy A706 bars are specified where the structure is in a seismic design category that requires them or where reinforcement is to be welded, and procurement, fabrication, and placement submittals are covered by Concrete Reinforcement - this Standard sets only the grade and the cover required by the site exposure. (7.1)
7.1.1Reinforcing bars shall conform to ASTM A615/A615M Grade 60 unless welding or seismic detailing requires ASTM A706/A706M low-alloy bars.
7.1.2Walls less than 8 in. thick shall be reinforced with no smaller than #4 bars.
Reinforcing Steel Specificationradio
ASTM A615 Grade 60 (standard)
ASTM A706 low-alloy (weldable / seismic)
NOTE Concrete cover is the durability margin for buried structures and is set by ACI 318, not by convenience; cover protects reinforcement from corrosion; ACI CODE-318-25 Table 20.5.1.3.1 requires 3 in. of cover for concrete cast against and permanently exposed to earth, 2 in. for formed surfaces exposed to weather or soil (for #6 bars and larger), and 1-1/2 in. for formed surfaces not exposed to weather; the cast-against-earth case - footings and slabs poured directly on subgrade with no form - is the condition most often shorted. (7.2)
7.2.1Concrete cover for reinforcement shall be provided per ACI CODE-318-25 Table 20.5.1.3.1 for the cast condition of each surface.
Minimum Concrete Coverselect
3 (cast against and permanently exposed to earth)
2 (formed, exposed to weather or soil)
1.5 (formed, not exposed to weather)

8 Formwork

NOTE Formwork must resist the fluid pressure of fresh concrete and hold dimensional tolerance; fresh concrete behaves as a fluid until it sets, exerting lateral pressure on the forms that increases with placement rate and wall height; ACI 347R gives the design loads, lateral pressure formulas, and stripping criteria; job-built plywood forms and modular panel systems are both acceptable for routine site structures, but walls over 8 ft tall, or any form where the lateral pressure exceeds code-default assumptions, require a formwork design stamped by a licensed engineer; OSHA 29 CFR 1926.703 sets the federal safety requirements for formwork, shoring, and form removal. (8.1)
8.1.1Formwork shall be designed and constructed per ACI 347R to resist the lateral pressure of fresh concrete at the planned placement rate.
8.1.2Formwork for walls over 8 ft tall, or where lateral pressure exceeds code-default assumptions, shall be designed and stamped by a licensed engineer.
8.1.3Formwork, shoring, and form removal shall comply with OSHA 29 CFR 1926.703.
8.1.4Formed surfaces shall be constructed to the dimensional tolerances of ACI 117.
Formwork Systemradio
Job-built plywood forms
Modular steel or aluminum panel forms
Proprietary headwall / vault form system
Engineer-designed formwork (walls over 8 ft or high pressure)
NOTE Formwork stripping shall be governed by strength or temperature, never by calendar days alone; specifying a stripping time as a flat number of hours invites failure because a 24-hour stripping rule that is fine in summer is far too early on a cold-weather pour where the concrete has not gained enough strength to hold its own shape; early stripping causes surface spalling, sloughing, and form blowouts; ACI 347R Table 3 ties minimum stripping time to ambient temperature and gained strength; vertical surfaces may be stripped after a minimum of 12 hours at 50 °F or above, but never before the concrete has reached the strength that lets it carry its own weight and the stripping forces. (8.2)
8.2.1Vertical formwork shall not be stripped until the concrete has reached the strength required by ACI 347R Table 3 for the placement temperature, and in no case earlier than 12 hours after placement at 50 °F or above.
8.2.2On cold-weather placements, formwork shall not be stripped until the concrete has reached a minimum of 70% of the specified f'c.

9 Jointing and Waterstops

NOTE Construction joints in below-grade structures shall be waterstopped because an unstopped cold joint is the most common leak path in site concrete; a construction joint is the planned interface between two placements, and below grade that interface is a direct path for groundwater infiltration into a vault or junction chamber and for exfiltration out of a water-conveying structure; a waterstop cast into the joint blocks that path; a flat PVC dumbbell waterstop, minimum 6 in. wide, is the standard for accessible joints; a hydrophilic swellable rubber strip (typically 3/4 in. by 3/8 in.) is the alternative for joints too tight or congested to place a PVC stop, and it expands on contact with water to seal the joint. (9.1)
9.1.1Construction joints in below-grade structures shall receive a continuous waterstop.
9.1.2PVC dumbbell waterstop shall be a minimum of 6 in. wide.
9.1.3PVC dumbbell waterstop shall be continuous and spliced by heat-welding, not overlapping.
9.1.4Where joint geometry prevents PVC placement, a hydrophilic swellable rubber waterstop strip shall be used in lieu of PVC.
9.1.5Construction joint surfaces shall be roughened and cleaned, and an approved bonding agent shall be applied before the adjoining placement.
Waterstop Type (Below-Grade Construction Joints)radio
PVC dumbbell, 6 in. wide
PVC dumbbell, 9 in. wide
Hydrophilic swellable rubber strip (3/4 in. x 3/8 in.)
9.1.6Construction joint locations shall be as indicated, coordinated with the waterstop layout. construction joint locations

10 Penetrations and Embedded Hardware

NOTE Pipe and conduit penetrations shall be cast in, not cored after the pour, and their locations shall be coordinated against the civil, mechanical, and electrical drawings before placement; a penetration cast into the form - a sleeve, a knockout, or a blockout - is clean, located, and detailed for sealing, while the same penetration drilled after the pour through a reinforced wall is expensive, cuts reinforcement, and weakens the structure; sleeve and knockout locations must be reconciled against every trade's drawings before the pour because a missed penetration discovered after stripping is a core-drilling problem that never performs as well as a cast-in opening. (10.1)
10.1.1Pipe and conduit penetrations shall be cast in place using sleeves, knockouts, or blockouts; coring after placement shall not be used except where specifically accepted by the Engineer.
10.1.2Penetration locations shall be coordinated against the civil, mechanical, and electrical drawings and verified at the pre-pour inspection.
10.1.3Cast-in pipe sleeve locations and inverts shall be as indicated. pipe sleeve schedule and inverts
Pipe Penetration Methodradio
Cast-in sleeve (steel or PVC)
Cast-in knockout / blockout
Cored after placement (Engineer accepted only)
Pipe Sleeve Annular Sealradio
Modular mechanical link-seal
Non-shrink grout pack
Hydrophilic sealant and backer rod
NOTE Cast-in anchor hardware and conduit stubs shall be set before the pour because adding them afterward requires core drilling that never matches cast-in performance; anchor bolts for frames and grates, lifting inserts, conduit brackets, grounding electrode conductors, and conduit stubs into vaults all perform best when cast into the concrete with the reinforcement, and drilled-and-epoxied or cored-and-grouted retrofits are weaker and leak-prone; anchor bolts conform to ASTM F1554 - Grade 36 for general anchorage, Grade 55 where higher strength is required; grounding and conduit elements must be coordinated with the electrical drawings and set before the pour. (10.3)
10.3.1Anchor bolts shall conform to ASTM F1554 Grade 36 or Grade 55 as required by the connection design and shall be cast in place.
10.3.2Cast-in conduit stubs and grounding electrode conductors shall be positioned and secured before placement, coordinated with the electrical drawings.
Cast-In Anchor Bolt Graderadio
ASTM F1554 Grade 36
ASTM F1554 Grade 55
Cast-In Hardware Providedcheckbox
Frame / grate anchor bolts
Lifting inserts
Conduit stubs and brackets
Grounding electrode conductor

11 Configurations

NOTE This Standard covers a family of cast-in-place site structures formed with job-built or modular forms; the configurations below share materials and execution but differ in geometry and in which features apply - a headwall needs wingwall flare and surface sealer, a vault needs a lid pocket and waterstopped joints, an apron needs integral curbs and energy dissipation; the structure type drives which of the optional features in this Standard are invoked. (11.1)
Structure Typeselect
Headwall with wingwalls (culvert / outfall end)
Utility vault (pull, splice, or meter)
Trench-interceptor wall / channel liner
Catch basin collar / adjustment ring
Junction chamber
Outfall apron with integral curbs
Low wall integral to utility routing
NOTE Headwalls and wingwalls are formed at the outlet end of a culvert or storm outfall with the wingwalls flared to retain the embankment and guide flow; a headwall caps the pipe end and supports the embankment while the wingwalls flare out from it to hold back the fill and direct the discharge; the flare angle is a hydraulic and grading decision, with 30° and 45° being the common values; headwalls are fully exposed and so invoke the air-entrainment and surface-sealer requirements of this Standard, and they are formed with job-built forms or reusable proprietary headwall form systems. (11.2)
Wingwall Flare Angleradio
30
45
90 (straight / U-type)
NOTE Cast-in-place utility vaults are rectangular below-grade structures with a lid or frame pocket, pipe penetrations, and a floor sump; pull, splice, and meter vaults are box structures formed in place where a precast unit will not fit the configuration or the site constraints; they invoke the full below-grade feature set of this Standard - waterstopped construction joints, sealed pipe penetrations, and cast-in hardware for the lid frame and any grounding or conduit; a floor sump is provided so water that does enter can be pumped or drained rather than standing on equipment. (11.3)
Vault Floor Sumpradio
Cast-in sump with drain connection
Cast-in sump, pumped
No sump
NOTE Outfall aprons with integral curbs dissipate flow energy at a storm outfall and are fully exposed concrete; an apron slab with integral curbs spreads and slows the discharge at a storm outfall so the receiving channel is not scoured; because the apron is wet, exposed, and salt-affected, it invokes air entrainment and a penetrating surface sealer; aprons are formed with standard curb and gutter forms. (11.4)

12 Curing and Surface Treatment

NOTE Curing controls the moisture and temperature that let concrete gain strength and durability; concrete that dries too soon loses strength and surface durability and is prone to shrinkage cracking; a minimum of 7 consecutive days of moist curing at 50 °F or above is required; where continuous moisture is impractical after stripping, a liquid membrane-forming curing compound (ASTM C309 Type 1-D or Type 2) is an accepted alternative, applied promptly after form removal to seal moisture into the concrete. (12.1)
12.1.1Concrete shall be moist-cured for a minimum of 7 consecutive days at 50 °F or above.
12.1.2Where membrane curing is used, a curing compound conforming to ASTM C309 Type 1-D or Type 2 shall be applied within 20 minutes of form stripping.
Curing Methodradio
Moist cure, 7 days minimum
Membrane-forming compound (ASTM C309 Type 1-D / Type 2)
Moist cure followed by membrane compound
NOTE Exposed site concrete shall receive a penetrating surface sealer because unprotected concrete in wet-dry and freeze-thaw cycling degrades quickly; headwalls, aprons, curbs, and exposed wall faces live in repeated wetting and drying and, in cold climates, freeze-thaw with deicing salts; unsealed, they carbonate and admit chlorides and the surface scales and spalls; a penetrating silane or siloxane sealer soaks into the surface and repels water without changing the appearance and is the standard protection for exposed site concrete; for below-grade vaults where watertightness is the priority, a crystalline waterproofing admixture batched into the mix is the alternative - it grows crystals that block water through the concrete body rather than at the surface. (12.2)
12.2.1Exposed surfaces of headwalls, aprons, curbs, and walls shall receive a penetrating silane or siloxane sealer after curing is complete.
Surface Protectionradio
Penetrating silane sealer (exposed surfaces)
Penetrating siloxane sealer (exposed surfaces)
Crystalline waterproofing admixture (below-grade vaults)
None (interior / protected)

13 Installation and Backfill

NOTE Concrete placement shall follow the accepted mix, temperature, and slump requirements and consolidation shall be by mechanical vibration; placement is where the accepted mix design is either realized or undone, with concrete placed at the accepted slump and temperature, deposited so it does not segregate, and consolidated by internal mechanical vibration to remove entrapped air and fill the form against the reinforcement and embeds; over-vibration that drives entrained air out of a freeze-thaw mix is as harmful as under-consolidation. (13.1)
13.1.1Concrete shall be placed within the accepted slump and temperature limits and consolidated by mechanical vibration without segregation.
13.1.2Concrete shall be deposited in horizontal layers and shall not be allowed to free-fall in a manner that causes segregation.
NOTE Backfill against walls shall not begin until the concrete has reached minimum age or strength because premature backfill can crack or overturn a wall that has not yet reached working strength; a freshly poured wall has little strength to resist lateral load, and heavy compaction equipment working against the wall transmits lateral pressure that can crack the wall or push it off its footing before the concrete is strong enough to act as designed; within 3 ft of the wall, only hand compaction is permitted until the structure reaches full strength; backfill material and the earthwork operation itself are governed by Earthwork and, for drainage behind the wall, by Foundation Drainage. (13.2)
13.2.1Machine compaction of backfill against structure walls shall not begin until the concrete is a minimum of 7 days old or has reached 75% of the specified f'c, confirmed by field-cured cylinders.
13.2.2Within 3 ft of a wall, backfill shall be placed and compacted by hand methods only until the structure has reached its full specified strength.
13.2.3Backfill shall be placed in balanced lifts on opposing sides of a structure to avoid unbalanced lateral loading.
Backfill Release Criterionradio
7 days minimum age
75% of f'c by field-cured cylinder
Whichever is achieved first

14 Field Quality Control

NOTE Field acceptance rests on the measured properties of the fresh and hardened concrete sampled at the rate set under Quality Assurance; the field tests are the evidence that the concrete delivered and placed is the concrete that was accepted; slump, air content, and temperature are measured on the fresh concrete at the point of discharge; strength is measured on cylinders cured and broken under ASTM C39; a placement that fails an acceptance test is evaluated by the Engineer, who may require cores, additional curing, or removal. (14.1)
14.1.1Fresh concrete shall be tested for slump, air content, and temperature at the point of discharge for each composite sample.
14.1.2Compressive strength acceptance shall be evaluated per ACI 301-20, with the average of any three consecutive strength tests equaling or exceeding f'c and no single test falling more than 500 psi below f'c.
14.1.3Concrete represented by strength tests that fail the acceptance criteria shall be evaluated by the Engineer, who may require core testing per ASTM C39 or corrective action.
Strength Acceptance Basisradio
ACI 301-20 statistical acceptance (3-test average)
Single-cylinder minimum per pour

15 Warranty

NOTE The warranty covers leakage at joints and penetrations, surface scaling, cracking beyond tolerance, and reinforcement corrosion staining traceable to insufficient cover or defective placement; the one-year period is the common default; the warranty does not relieve the Contractor of latent-defect liability under the Contract. (15.1)
15.1.1The Contractor shall warrant the work against defects in materials and workmanship for the warranty period.
15.1.2The warranty shall cover leakage at construction joints and penetrations, surface scaling, and cracking beyond the tolerances of ACI 117.
Warranty Periodradio
1
2
5

Edit this page

SynC Standards are reference material provided for informational purposes only and as a guide. They are not engineering, architectural, or legal advice and are not a substitute for the judgment of a licensed design professional. It is the responsibility of the user to determine the applicability of any standard to a specific project and to verify all requirements against the governing codes, manufacturer data, and project conditions. SynC does not render professional services and forms no professional relationship by publishing this content. Provided "as is," without warranty of any kind, including fitness for a particular purpose. See our Terms of Use for the complete terms.

This standard is published by SynC and licensed under Creative Commons Attribution-ShareAlike 4.0. You may share and adapt it, including commercially, provided you give credit, link to the license, indicate any changes, and license your adaptations under the same terms. Keep the attribution and notice below with any copy — it includes the warranty disclaimer the license requires you to retain.

Attribution & reuse notice — keep this with any copy:
"Cast-in-Place Site Concrete Structures." SynC Standards. Licensed under CC BY-SA 4.0 (https://creativecommons.org/licenses/by-sa/4.0/). Source: https://synergyinconstruction.com/wiki/sync/site-concrete-structures — reference material only; not professional engineering advice and provided without warranty. Verify against governing codes and have a licensed professional review before use.