title: Site Grading and Subgrade Preparation
…118 unchanged lines
### An independent geotechnical testing agency shall perform all compaction, moisture, and density testing.
−### The testing agency shall be engaged and paid by the Owner unless the Contract Documents assign that responsibility otherwise. {note}
+### The testing agency shall be engaged and paid by the Owner unless the Contract Documents assign that responsibility otherwise.
### The testing agency shall report results to the Owner, the geotechnical engineer of record, and the Contractor within the timeframe established at the preconstruction meeting.
### Field density testing shall be performed by the nuclear method (ASTM D6938) or the sand-cone method (ASTM D1556).
−### The nuclear gauge shall be correlated to the sand-cone method when results are disputed or when the geotechnical engineer requires verification. {note}
+### The nuclear gauge shall be correlated to the sand-cone method when results are disputed or when the geotechnical engineer requires verification.
## Subgrade Approval {toc}
…52 unchanged lines
## Stockpiles shall be located clear of drainage courses, the building footprint, and traffic, and shall be protected from erosion in accordance with [[sync/erosion-and-sediment-control]].
−## Stockpile height shall be limited because piles that are too tall compact their own lower lifts, exclude oxygen, and kill the soil organisms that make topsoil valuable for reuse. {note}
+## Stockpile height shall be limited because piles that are too tall compact their own lower lifts, exclude oxygen, and kill the soil organisms that make topsoil valuable for reuse.
```datasheet
…113 unchanged lines
## Required Density by Zone {toc}
−### Compaction shall be specified by zone rather than as a single site-wide value; a uniform high value over-compacts landscape soil so plants cannot establish, while a single low value under-protects the building pad against settlement. {note}
+### Compaction shall be specified by zone rather than as a single site-wide value; a uniform high value over-compacts landscape soil so plants cannot establish, while a single low value under-protects the building pad against settlement.
### The building pad subgrade shall be compacted to the percentage of maximum dry density below over the depth specified by the geotechnical report, typically the top 12 in.
…35 unchanged lines
## Moisture Conditioning {toc}
−### Soil compacted dry or wet of optimum moisture cannot reach its maximum dry density and settles later; the specification must state an acceptable moisture window and require correction by wetting or aeration when soil falls outside it. {note}
+### Soil compacted dry or wet of optimum moisture cannot reach its maximum dry density and settles later; the specification must state an acceptable moisture window and require correction by wetting or aeration when soil falls outside it.
### Subgrade and fill soils shall be moisture-conditioned to within the window below of optimum moisture content (ASTM D2216) at the time of compaction.
…9 unchanged lines
step: 1
default: 0
−setpoints: [-2, 0, 2]
+setpoints: [-3, -2, 0, 2, 4]
```
…71 unchanged lines
## Over-Excavation and Replacement {toc}
−### When proof-rolling or density testing reveals unsuitable material below grade, the depth of over-excavation and the acceptable replacement material must be defined in advance, or every soft spot becomes a change order and an RFI. {note}
+### When proof-rolling or density testing reveals unsuitable material below grade, the depth of over-excavation and the acceptable replacement material must be defined in advance, or every soft spot becomes a change order and an RFI.
### Where unsuitable material is identified, the Contractor shall over-excavate to the depth directed by the geotechnical engineer and replace it with compacted select or structural fill.
### Over-excavated areas shall be proof-rolled at the base of excavation before replacement fill is placed.
−### Where native soils across the site are uniformly poor and chemical or mechanical modification is the primary remedy, that work shall be performed under [[sync/soil-stabilization]] rather than specified inline here, to avoid contradictory requirements. {note}
+### Where native soils across the site are uniformly poor and chemical or mechanical modification is the primary remedy, that work shall be performed under [[sync/soil-stabilization]] rather than specified inline here, to avoid contradictory requirements.
# Proof Rolling {toc}
…186 unchanged lines
## Subgrade that has frozen after acceptance shall be allowed to thaw, then re-proof-rolled and re-tested before the next layer is placed.