SynC · SynC Standards
Bidding Procedures
Contents
- 1Scope
- 2Bidding Terms
- 3Referenced Standards
- 4Distribution of the Bidding Documents
- 4.1Official Source and Plan Holders of Record
- 4.2Bidder's Examination of the Documents
- 5Pre-Bid Conference and Site Visits
- 5.1Pre-Bid Conference
- 5.2Site Visits
- 6Bidder Questions and Addenda
- 6.1Questions and Interpretations
- 6.2Addenda
- 7Pre-Bid Substitution Requests
- 7.1Request Window
- 7.2Content, Judgment, and Answer
- 8Bid Form and Bid Content
- 8.1Preparation of the Bid
- 8.2Items the Bid Form Carries
- 8.3Subcontractor Listing
- 8.4Bid Security
- 9Modification and Withdrawal of Bids
- 9.1Before the Bid Time
- 9.2After the Bid Opening
- 9.3Withdrawal for Mistake
- 10Receipt and Opening of Bids
- 10.1Bid Time, Place, and Medium
- 10.2Opening of the Bids
- 11Evaluation and Award
- 11.1Responsiveness and Responsibility
- 11.2Bidder's Qualification Statement
- 11.3Basis of Award
- 11.4Rejection of Bids and Notice of Award
- 11.5Documents Due from the Successful Bidder
- 12Coordination with the Owner's Instruments and the Technical Standards
Download
Build a datasheet from this standard
Start a project with this standard already attached — one click, no setup.
Use in a project
1 Scope
NOTE This standard establishes the procedure by which the bidding documents reach bidders, bidders examine the Work and ask questions, the Engineer answers by addendum, bids are prepared, secured, submitted, modified, withdrawn, received, opened, evaluated, and awarded, and the successful bidder delivers the documents the Agreement requires, on any project the Engineer bids for the Owner and under any Division of the Specifications. (1.1)
NOTE The instructions to bidders are usually the Owner's instrument, issued ahead of the technical sections, and on a public project they are often fixed by ordinance or by the Owner's procurement office. This standard exists because the Engineer assembles the project manual the bid is priced from, administers the questions, the addenda, the pre-bid conference, the opening, and the tabulation, and is the party the bidders deal with from the day the documents issue to the notice of award, and because a bidder who is handed only the technical sections finds there the procedure that binds its bid. (1.2)
NOTE The bidding phase produces no Work and a great deal of exposure: a bid that is late by a minute, unsigned, or missing an addendum acknowledgment is rejected, a bid that is low by a transposed figure is held or forfeited, and an Owner who answers one bidder's question privately has given that bidder an advantage the others can protest. Each procedure in this standard is written so that the result of a bidding-phase event is certain before it happens. (1.3)
1.4 Bidders shall comply with this standard in preparing and submitting bids, and the successful bidder shall comply with it until the Agreement is executed.
1.5 Where the Owner issues its own instructions to bidders or its own bid form, those instruments shall govern, and this standard shall supplement them.
1.6 Where a requirement of this standard conflicts with the Agreement, the General Conditions, or the Supplementary Conditions, those documents shall govern.
1.7 Where the procurement law governing the Owner sets a requirement of the bidding phase differently from this standard, that law shall govern, and a field of the datasheet that the law fixes shall be completed to match the law.
NOTE The following are outside the scope of this standard: (1.8)
- The advertisement or invitation to bid, which the Owner issues, which states the bid time and place, the official source of the documents, and the deposit, and which this standard refers to and does not write
- The form, the penal sums, the surety qualification, and the execution of the performance bond, the payment bond, and the bid bond, which Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds governs
- The coverages, the limits, the additional insureds, and the certificates of insurance, which Insurance RequirementsInsurance RequirementsResolves to the current adopted revision.sync/insurance-requirements governs
- The content of a substitution request, the comparable-product and or-equal rules, and the judgment of equality of a proposed product, before or after award, which Product RequirementsProduct RequirementsResolves to the current adopted revision.sync/product-requirements governs
- The pricing, measurement, and acceptance rules for unit prices, alternates, and allowances, which Payment ProceduresPayment ProceduresResolves to the current adopted revision.sync/payment-procedures governs
- Proposal requests, change orders, claims, and every change to the Contract after award, which Contract Modification ProceduresContract Modification ProceduresResolves to the current adopted revision.sync/contract-modification-procedures governs
- The ownership, the confidentiality, the permitted use, and the disposition of the bidding documents, including the disposition by a bidder not awarded the Contract, which Document Confidentiality And Ai UseDocument Confidentiality and AI UseResolves to the current adopted revision.sync/document-confidentiality-and-ai-use governs
- What the Work is, how it is let, the Owner's occupancy, and the restrictions on access to the premises, which Summary Of Work And Work RestrictionsSummary of Work and Work RestrictionsResolves to the current adopted revision.sync/summary-of-work-and-work-restrictions governs and which a bidder reads to price the Work and to visit the site
- The preconstruction conference, the request-for-information procedure, and the communication platform after award, which Project Management And CoordinationProject Management and CoordinationResolves to the current adopted revision.sync/project-management-and-coordination governs
- The Agreement, the General Conditions, and the Supplementary Conditions, which are the Owner's contract instruments and are bound in the project manual as issued
2 Bidding Terms
NOTE The following terms are used in this standard with the meanings given here: (2.1)
- A bidder is a person or an entity that submits a bid directly to the Owner; a sub-bidder submits a price to a bidder and is not a bidder for the purpose of this standard
- A bid is the bidder's complete and signed offer on the bid form, with the bid security and the other items the bid form requires attached, to perform the Work for the prices and within the time stated in it
- The bidding documents are the advertisement or invitation, the instructions to bidders including this standard, the bid form and its attachments, the bid bond form, and the proposed Contract Documents, including the drawings, the specifications, and every addendum issued before the bid time
- The advertisement or invitation is the Owner's notice that bids are requested, which states the project, the bid time and place, the official source of the documents, and the deposit, and which the Owner issues
- An addendum is a written or graphic document the Engineer issues before the bid time that changes, clarifies, or interprets the bidding documents and becomes part of them
- A plan holder is a party recorded by the official source as having obtained the bidding documents, and the plan holders list is that record
- The bid time is the date and the hour stated in the advertisement or invitation, as changed by addendum, after which bids are not received
- A responsive bid is a bid that conforms in every material respect to the bidding documents as submitted at the bid time, without a qualification, a condition, or an omission that affects the price, the time, or the scope of the Work
- A responsible bidder is a bidder the Owner determines has the capability, the capacity, the experience, the integrity, and the financial and surety resources to perform the Work within the Contract Time
- An informality is a minor deviation in a bid from the form or the procedure required that does not affect the price, the time, or the scope of the Work and gives the bidder no advantage over the others
- Bid security is the bid bond, the check, or the other instrument submitted with a bid that secures the bidder's obligation, if awarded the Contract, to execute the Agreement and to furnish the bonds and the insurance the Contract Documents require
- The holding period is the period after the bid opening during which each bid remains open and irrevocable and the Owner can accept it
- The successful bidder is the bidder to whom the Owner issues the notice of award, and it becomes the Contractor when the Agreement is executed
- The base bid is the price for the Work without any alternate, and an alternate is an amount stated in the bid for adding to or deducting from the Work a portion the bid form describes, which the Owner accepts or declines at award
3 Referenced Standards
3.1 The bidding procedure shall comply with the latest adopted edition of each of the following unless a specific edition is cited or the bidding documents direct otherwise.
3.2 Where referenced documents conflict with one another, the bidding documents shall state which governs, and where they do not, the Engineer shall resolve the conflict by addendum.
| Standard | Title |
|---|---|
| AIA A701 | Instructions to Bidders |
| AIA A310 | Bid Bond |
| AIA A305 | Contractor's Qualification Statement |
| EJCDC C-111 | Advertisement for Bids for Construction Contract |
| EJCDC C-200 | Instructions to Bidders for Construction Contract |
| EJCDC C-410 | Bid Form for Construction Contract |
| EJCDC C-430 | Bid Bond (Penal Sum Form) |
| EJCDC C-435 | Bid Bond (Damages Form) |
| EJCDC C-451 | Qualifications Statement |
| EJCDC C-510 | Notice of Award |
NOTE The published instructions to bidders, bid forms, and bid bonds in the table are companions to their publishers' agreements and general conditions, and a project that uses one publisher's agreement ordinarily uses the same publisher's bidding forms so that the definitions and the award procedure line up. A public Owner commonly issues its own instructions and bid form in their place. The procurement law of every state, and the ordinances of many counties, cities, and districts, fix for a public Owner the minimum bid security, the public opening, the responsibility criteria, the listing rules, and the protest procedure, and those rules differ from one jurisdiction to the next, which is why this standard defers to them and models none of them. (3.3)
4 Distribution of the Bidding Documents
4.1 Official Source and Plan Holders of Record
4.1.1 Bidders shall obtain the bidding documents from the official source named in the advertisement or invitation, and a set so obtained is the complete set for the purpose of this standard.
4.1.2 The official source shall record, for each party that obtains the bidding documents, the organization, the contact person, the address, the telephone number, the e-mail address, and the date obtained, and that record shall be the plan holders list.
4.1.3 The Engineer shall make the plan holders list available to any plan holder on request.
4.1.4 Printed sets, where the advertisement or invitation offers them, shall be furnished on the deposit and refund terms it states, and the electronic set shall be the set of record where both are issued.
4.1.5 Each bidder shall be responsible for verifying that its set is complete against the table of contents of the project manual and the drawing index, and for obtaining every addendum before the bid time.
4.1.6 A bidder that obtained the bidding documents from a source other than the official source, or that is not on the plan holders list, shall bear the risk of an incomplete or superseded set, and the absence of its name from the list shall not excuse the omission of an addendum from its bid.
NOTE A plan room, a reprographics firm, or a sub-bidder that redistributes the set is not the official source, and the Engineer has no way to reach a bidder it does not know about when an addendum issues. The list is what connects the addendum to the bidder; a bidder who bypasses the list has bypassed the addendum. On a public project the list is also the Owner's record of who was given the opportunity to bid. (4.1.7)
4.1.8 The ownership, the confidentiality, the permitted use, and the disposition of the bidding documents, including by a bidder that is not awarded the Contract, shall be as Document Confidentiality And Ai UseDocument Confidentiality and AI UseResolves to the current adopted revision.sync/document-confidentiality-and-ai-use requires, and this standard adds nothing to those requirements.
4.2 Bidder's Examination of the Documents
4.2.1 Before submitting a bid, each bidder shall examine the bidding documents in full, including the addenda, the Agreement, the General Conditions, the Supplementary Conditions, and every technical standard, and shall visit the site to the extent this standard permits.
4.2.3 A bidder that discovers a conflict, an error, an ambiguity, or an omission in the bidding documents shall report it to the Engineer in writing before the deadline for bidder questions, and a bidder that does not shall not rely on it as the basis of a claim after award except as the General Conditions allow.
4.2.4 The reports of subsurface and physical conditions that the Owner makes available to bidders, and the extent to which a bidder relies on them, shall be as the Supplementary Conditions state, and a bidder that wants to make its own explorations shall request access under the Site Visits article of this standard.
5 Pre-Bid Conference and Site Visits
5.1 Pre-Bid Conference
5.1.1 A pre-bid conference shall be held or not held as indicated in the datasheet.
Pre-Bid Conferenceradio
● Held
○ Not held
5.1.2 The time and the place of the pre-bid conference shall be as stated in the advertisement or invitation, as changed by addendum.
5.1.3 Attendance at the pre-bid conference shall be as indicated in the datasheet.
Attendance at the Pre-Bid Conferenceradio
○ Mandatory
○ Not mandatory
5.1.4 Where attendance is mandatory, each bidder shall be represented for the entire conference by a person who signs the attendance record, and the Owner shall not consider a bid from a bidder not so represented.
5.1.5 The Engineer shall conduct the pre-bid conference, shall record the attendance and the questions raised, and shall issue the attendance record and every answer of substance by addendum to every plan holder.
5.1.6 A statement made at the pre-bid conference or during a site visit, by the Owner, the Engineer, or anyone else, shall not modify or interpret the bidding documents unless it is confirmed by addendum.
NOTE A conference is held on nearly every project of consequence because it is the one occasion on which every bidder hears the same description of the Work, the site, the operating constraints, and the schedule, and because the questions it raises are the ones that turn into addenda. Mandatory attendance ensures that every bidder has seen an operating plant, a confined site, or an occupied building before pricing it, and it is used on work where a bid from a bidder who has not seen the site is a bid the Owner does not want; it costs the Owner the bids of qualified contractors who could not attend on the day, and it costs each bidder a trip at its own expense before it has decided to bid. Attendance that is not mandatory keeps the field open and leaves the Owner to accept the bid of a contractor that has only read the drawings. Not holding a conference suits a small or repetitive scope on a site the bidders already know, and it leaves every question to the written channel alone. (5.1.7)
5.2 Site Visits
5.2.1 Bidders' access to the site for examination before bidding shall be as indicated in the datasheet.
Site Access for Biddersradio
○ Open during the hours the advertisement or invitation states, without appointment
○ By appointment with the Owner's representative
○ Escorted visit following the pre-bid conference only
NOTE A greenfield site with a public road frontage is open to anyone who wants to look at it, and an appointment is a formality. An operating water or wastewater plant, a secured industrial site, and an occupied building are entered only through the Owner's gate, by people the Owner has screened, with an escort who keeps them away from the process, and an appointment is the only way in. Limiting the visit to the escorted tour after the conference puts every bidder through the site once, on one day, with one escort, at the least cost to the Owner's operating staff, and it denies the bidder who wants a second look, or who missed the conference, any view of the site at all. (5.2.2)
5.2.3 During a site visit, bidders shall comply with the access, screening, security, and safety rules of the Owner and with the premises restrictions of Summary Of Work And Work RestrictionsSummary of Work and Work RestrictionsResolves to the current adopted revision.sync/summary-of-work-and-work-restrictions, and the Owner may remove a visitor who does not.
5.2.4 A bidder shall not operate the Owner's equipment, open an enclosure or a hatch, enter a confined space, or interfere with the Owner's operations during a site visit.
5.2.5 A bidder that wants to perform its own exploration, sampling, or testing on the site before bidding shall request the Owner's written permission through the Engineer, shall perform that work at its own cost under the conditions the Owner sets, shall restore the site, and shall furnish a copy of the results to the Engineer on request.
5.2.6 Each bidder shall bear its own cost of visiting the site and of any investigation it makes.
6 Bidder Questions and Addenda
6.1 Questions and Interpretations
6.1.1 A bidder shall submit every question about the meaning or the intent of the bidding documents in writing to the Engineer, through the channel the advertisement or invitation names, and shall not seek an interpretation from the Owner's staff, the Owner's operators, or any consultant directly.
6.1.2 Questions shall be received by the Engineer not later than the number of days before the bid time indicated in the datasheet.
Deadline for Bidder Questionsrange
Not less than
days before the bid time
357101421
6.1.3 The Engineer shall answer, by addendum, every question received by the deadline that calls for an interpretation or a change of the bidding documents, and shall answer a question received after the deadline only where the answer can issue by the last addendum date.
6.1.4 An interpretation or a correction of the bidding documents shall be made only by addendum, and an oral or written statement that is not an addendum shall not bind the Owner.
NOTE The question deadline is set back from the bid time by the days the Engineer needs to answer, the Owner needs to review the answer, and the addendum needs to reach the bidders before the last addendum date. A deadline a few days before bid lets bidders ask about what they found while pricing, and it leaves the Engineer answering the last questions by addendum on the last permitted day, which is when an answer that changes the scope postpones the bid. A deadline two or three weeks before bid gives the Engineer time to issue considered answers and gives bidders time to price them, and it closes the channel before the sub-bids, in which most of the real questions arise, have come in. (6.1.5)
6.2 Addenda
6.2.1 The Engineer shall issue each addendum in writing to every plan holder on the list, by the same means the bidding documents were distributed, and shall number and date each addendum in sequence.
6.2.2 The last addendum shall issue not later than the number of days before the bid time indicated in the datasheet, except an addendum that postpones the bid time or withdraws the invitation to bid.
Last Addendum Before the Bid Timerange
Not less than
days before the bid time
12345710
6.2.3 Where an addendum that changes the Work, the price, or the time is needed after the last addendum date, the Owner shall postpone the bid time by addendum so that the interval indicated in the datasheet is restored.
6.2.4 The Owner may postpone the bid time, by addendum issued before the bid time, for any reason, and may withdraw the invitation to bid by addendum at any time before the bid opening.
6.2.5 Where the bid time is postponed, every deadline in this standard that is stated in days before the bid time shall be recomputed from the postponed bid time unless the postponing addendum states otherwise.
NOTE Three or four days before the bid time is the interval the published instructions and many public procurement rules carry, and it is the least time in which a bidder and its sub-bidders can absorb a change and reprice. A longer interval, a week or more, suits a project whose sub-bids are assembled over several days and keeps a late addendum from reaching the bidders after the sub-bids are in; it also moves the question deadline earlier by the same amount. A one or two day interval is practical only on a small project with few sub-bids, and it is the interval at which an addendum that changes anything of substance is answered by a postponement. (6.2.6)
6.2.7 Each addendum shall become part of the bidding documents on issue and part of the Contract Documents on award.
6.2.8 Each bidder shall acknowledge receipt of every addendum, by number and date, in the space the bid form provides.
6.2.9 A bid that fails to acknowledge an addendum that changed the price, the time, or the scope of the Work is nonresponsive, and a bid that fails to acknowledge an addendum that changed none of them may be accepted with the omission waived as an informality where the procurement law governing the Owner allows.
NOTE The acknowledgment is the bidder's statement that it priced the addendum, and the rule that a missing acknowledgment of a price-changing addendum is fatal is what keeps a low bidder from arguing afterward that it never received the change it did not price. The waiver for an addendum that changed nothing of substance avoids rejecting a low bid for a clerical omission, and it is the waiver most protest decisions turn on, which is why it is written to the content of the addendum rather than to the Owner's discretion. (6.2.10)
7 Pre-Bid Substitution Requests
7.1 Request Window
7.1.1 Requests for the acceptance of a substitute product before the bid time shall be received or not received as indicated in the datasheet.
Pre-Bid Substitution Requestsradio
● Received and answered by addendum
○ Not received before the bid time
7.1.2 Where pre-bid substitution requests are received, a request shall be received by the Engineer not later than the number of days before the bid time indicated in the datasheet.
Pre-Bid Substitution Request Windowrange
Not less than
days before the bid time
710141521
NOTE Receiving substitution requests before bid settles, in the open and for every bidder at once, which products beyond the ones named are acceptable, and it moves the argument over equality from the submittal stage, where a rejection costs the Contractor the time it has already spent, to the bidding stage, where a rejection costs nothing. It costs the Engineer a review of each request in the busiest days of the bidding period, which is why the window closes ahead of the question deadline. Declining to receive them before bid keeps the bidding period short and leaves every substitution to the procedure of Product RequirementsProduct RequirementsResolves to the current adopted revision.sync/product-requirements after award, where the Contractor carries the risk that a product it priced is rejected. The window is set so that the Engineer's answer can issue by the last addendum date with time for every bidder to price it. (7.1.3)
7.2 Content, Judgment, and Answer
7.2.1 The content of a substitution request, the data it carries, and the judgment of whether the proposed product is equal to the one specified shall be as Product RequirementsProduct RequirementsResolves to the current adopted revision.sync/product-requirements requires, and the Engineer shall apply the same judgment before bid as after award.
7.2.2 The Engineer shall list, by addendum, each product accepted before bid, naming the manufacturer, the product, and the technical standard it is accepted under, and shall not answer a request to the requester alone.
7.2.3 A product not named in the bidding documents and not listed as accepted in an addendum is not accepted before bid, and a bidder that bases its bid on such a product shall bear the risk that it is rejected after award under Product RequirementsProduct RequirementsResolves to the current adopted revision.sync/product-requirements.
7.2.4 Acceptance of a product by addendum shall be acceptance of the product as a basis for bidding only, and the product shall remain subject to the submittal review of Submittal And Quality ProceduresSubmittal and Quality ProceduresResolves to the current adopted revision.sync/submittal-and-quality-procedures and to every requirement of the governing technical standard.
8 Bid Form and Bid Content
8.1 Preparation of the Bid
8.1.1 Each bid shall be submitted on the bid form bound in the bidding documents, or on the Owner's bid form where the Owner issues one, without alteration to the printed text.
8.1.2 The bidder shall complete every blank on the bid form, shall state each price in both words and figures where the form provides for both, and shall sign the form in ink or by the electronic signature the submission medium provides.
8.1.3 Where a price stated in words and the same price stated in figures differ, the words shall govern, and where a unit price and its extension differ, the unit price shall govern and the extension and the total shall be corrected.
8.1.4 The bid shall be signed by a person authorized to bind the bidder, and the bidder shall furnish evidence of that authority with the bid where the bidder is a corporation, a limited liability company, a partnership, or a joint venture.
8.1.5 A bidder shall hold, at the bid time, every contractor's license, registration, and prequalification that the law of the jurisdiction of the project requires of a bidder on the Work, and shall state the license number on the bid form where the form provides for it.
8.1.6 A bid that qualifies, conditions, or limits the offer, that alters the bid form, or that offers an alternate the bid form did not request is nonresponsive, and a bidder that wants to propose a different way of performing the Work shall do so by a question before the deadline or by a substitution request within its window.
8.2 Items the Bid Form Carries
8.2.1 The bid form shall carry the items indicated in the datasheet, and the bidder shall complete each of them:
- The base bid, as a lump sum for the Work or as the total of the unit price schedule, as the bid form states
- The unit price schedule, where the Work or a part of it is paid by measured quantity, with the Owner's estimated quantities, the bidder's unit prices, and the extensions
- The alternates, each priced as an addition to or a deduction from the base bid as the bid form states
- The allowances, carried in the base bid in the amounts the bid form states
- The bid schedule, stating the Contract Time the bidder offers where the bid form invites a time, or acknowledging the Contract Time the Agreement states
- The listed subcontractors, where the Subcontractor Listing article of this standard requires them with the bid
- The acknowledgment of every addendum by number and date
- The bid security, attached to the bid form
- The bidder's qualification statement, where the Bidder's Qualification Statement article of this standard requires it with the bid
- The affidavits and certifications that the procurement law governing the Owner requires of a bidder, such as a statement of non-collusion
Bid Form Contentcheckbox
☑ Base bid
☐ Unit price schedule
☐ Alternates
☐ Allowances
☐ Bid schedule
☐ Listed subcontractors
☑ Addenda acknowledgment
☑ Bid security
☐ Bidder's qualification statement
☐ Statutory affidavits and certifications
8.2.2 The pricing, the measurement, and the acceptance rules for unit prices, alternates, and allowances shall be as Payment ProceduresPayment ProceduresResolves to the current adopted revision.sync/payment-procedures states, and the bid form shall carry each item as that standard defines it.
8.2.3 A bidder shall price every alternate and every unit price item the bid form carries, and a bid that leaves an alternate or a unit price blank is nonresponsive unless the bid form marks that item as optional.
NOTE An unpriced alternate leaves the Owner unable to compare that bid with the others on any combination that includes the alternate, and an unpriced unit price leaves a line item with no price when the quantity runs. The rule is stated here so that a bidder who leaves a line blank knows the consequence before the opening rather than at it. (8.2.4)
8.3 Subcontractor Listing
8.3.1 The bidder shall identify its subcontractors as indicated in the datasheet.
Subcontractor Listingradio
○ Not required before award
○ Required with the bid for the trades the bid form names
○ Required after the bid opening on the Owner's request
8.3.2 Where listing is required after the bid opening, the bidder shall deliver the list within seven days after the Owner's written request.
NOTE Listing with the bid, for the trades the Owner names, binds the bidder to the subcontractors whose prices it used, and it is the rule the procurement law of several states imposes on public work to end the practice of shopping a subcontractor's price after the award; it puts the general bidder under pressure to receive and compare sub-bids before its own bid is due, which is why the last hour before a bid opening is what it is. Listing on request after the opening gives the Owner the same information for the apparent low bidders without the bid-day scramble, and it leaves the days between the opening and the listing open to the shopping the listing was meant to prevent. Not requiring a list before award leaves the subcontractors to the Owner's review of the successful bidder's organization under the General Conditions, which is the usual arrangement on private work. (8.3.3)
8.3.4 A bidder shall not substitute another subcontractor for one it listed without the Owner's written consent, which the Owner shall not withhold where the listed subcontractor is unable or unwilling to perform, and the substitution shall be governed by the procurement law governing the Owner where that law addresses it.
8.4 Bid Security
8.4.1 Bid security shall be required or not required as indicated in the datasheet.
Bid Securityradio
● Required
○ Not required
8.4.2 Where bid security is required, each bid shall be accompanied by bid security in one of the forms indicated in the datasheet, made payable to the Owner.
Bid Security Formcheckbox
Any of:
☑ Bid bond
☑ Certified check
☑ Cashier's check
☐ Irrevocable letter of credit
8.4.3 The bid security shall be in the amount of the percentage indicated in the datasheet of the base bid, or of the base bid plus every additive alternate where the bid form so states, or in the fixed amount the advertisement or invitation states in place of a percentage.
Bid Security Amountrange
Not less than
% of the bid
12510
NOTE A bid bond is the form nearly every bidder uses, because it costs the bidder nothing beyond its surety relationship and ties up no cash, and because it is the form on which the surety has already decided that the bidder is bondable for the Work, which is information the Owner wants. A certified or cashier's check puts the Owner's security in hand without a claim against a surety, and it ties up the bidder's cash for the holding period, which a small contractor feels; it is also the form a bidder without a surety line uses, and a bid on a check from a bidder who then cannot furnish a performance bond is the case the security exists for. A letter of credit is rare on construction bids and is accepted where the Owner's procurement rules admit it. The amount is set by statute for most public Owners, at five or ten percent in most jurisdictions, and by the Owner's own rule on private work, against the cost of re-letting the Work when the low bidder walks away; the amount is a floor the bidder's security meets or exceeds. Where bid security is not required, which is the usual arrangement on small private work and on work bid to a short list the Owner knows, the Owner's remedy against a bidder who refuses to sign is a claim for the difference, which it rarely pursues. (8.4.4)
8.4.5 A bid bond shall be written on the Owner's bid bond form, or on a published form such as AIA A310 or EJCDC C-430 where the bidding documents so state, shall be executed by the bidder and by the surety's attorney-in-fact with the power of attorney attached, and shall be issued by a surety meeting the qualification requirements of Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds.
8.4.6 The Owner shall retain the bid security of the bidders it is considering for award until the Agreement has been executed and the bonds and the insurance certificates have been received, or until the holding period expires, whichever is earlier, and shall return the bid security of every other bidder within seven days after the bid opening.
8.4.7 Where the successful bidder fails to execute the Agreement or to deliver the documents due under this standard within the time indicated in the datasheet, the Owner may annul the award, and the bid security shall be forfeited to the Owner to the extent the bid bond form, or the procurement law governing the Owner, provides.
NOTE The two published bid bond forms differ in what the Owner recovers: a penal sum form pays the full amount of the bond on the bidder's default, and a damages form pays the difference between the defaulting bid and the price the Owner finally contracts for, up to the amount of the bond. Which form the Owner uses is settled in the bidding documents, and this standard states the forfeiture by reference to the form rather than choosing between them. (8.4.8)
9 Modification and Withdrawal of Bids
9.1 Before the Bid Time
9.1.1 A bidder may modify or withdraw its bid by a written notice, signed by the person who signed the bid or by another person with evidence of authority, received at the place of receipt before the bid time.
9.1.2 A modification shall state the change to the bid without disclosing the bid amount on the face of the notice, shall be sealed and marked as a modification where paper bids are received, and shall be read with the bid it modifies.
9.1.3 A bid that has been withdrawn before the bid time may be resubmitted before the bid time, and a withdrawn bid that is not resubmitted shall be returned to the bidder unopened.
9.2 After the Bid Opening
9.2.1 Each bid shall remain open and irrevocable, and the Owner may accept it, for the holding period after the bid opening indicated in the datasheet.
Bid Holding Periodrange
days after the bid opening
30456090120180
NOTE The holding period is the Owner's time to check the bids, confirm the funding, take the award to its board or council, and issue the notice of award, and a period shorter than that cycle produces an award the low bidder is no longer bound to honor. Sixty days is the period the published instructions carry and fits an Owner whose governing body meets monthly; ninety days or more fits a public Owner whose award depends on a funding approval or a second body's vote, and a longer period is used where a loan closing follows the bid. Every day of the period is price risk the bidder and its sub-bidders carry, on material whose quotes are good for thirty days, and a long period is paid for in the bids. (9.2.2)
9.2.3 A bidder shall not modify or withdraw its bid after the bid time, except as the Withdrawal for Mistake article of this standard allows, and a bidder that refuses to execute the Agreement within the holding period shall forfeit its bid security as the Bid Security article provides.
9.2.4 Where the Owner has not issued a notice of award within the holding period, each bidder may withdraw its bid by written notice, and a bid not withdrawn shall remain open until the bidder withdraws it or the Owner awards or rejects it.
9.2.5 The Owner may request in writing, before the holding period expires, that the bidders extend it, and a bidder that declines the extension shall be released from its bid without forfeiture.
9.3 Withdrawal for Mistake
9.3.1 The withdrawal of a bid after the bid opening on account of a mistake in it shall be governed by the procurement law governing the Owner, and where that law is silent, by this article.
9.3.2 A bidder that claims a mistake shall give the Owner written notice within three business days after the bid opening, stating the mistake and how it occurred, and shall furnish with the notice the worksheets, the sub-bids, and the other evidence from which the bid was prepared.
9.3.3 The Owner may permit a bidder to withdraw its bid without forfeiture of the bid security where the bidder shows that the mistake is a clerical or an arithmetical error, that it is material to the bid, that it was made in good faith, and that it is evident from the bidder's own worksheets, and not where the mistake is one of judgment in estimating the cost or the quantity of the Work.
9.3.4 A bidder permitted to withdraw for a mistake shall not be permitted to correct its bid, and shall not be awarded the Contract or a subcontract on the Work if the Work is re-let.
NOTE The distinction between a clerical mistake and a mistake of judgment is the line every jurisdiction draws: a transposed figure, a dropped line in an addition, or a sub-bid entered in the wrong column is evident from the worksheets and is forgiven, because holding a bidder to a bid it never meant to make benefits no one; a sub-bid that turned out low, a quantity that was underestimated, or a scope that was misread is the bidder's risk and is the mistake the bid security exists to answer for. The rule against correcting the bid, and against re-bidding the Work after withdrawing, is what keeps a claimed mistake from becoming a second look at the competitors' prices. (9.3.5)
10 Receipt and Opening of Bids
10.1 Bid Time, Place, and Medium
10.1.1 Bids shall be received at the place, until the date and the hour, and in the medium that the advertisement or invitation states, as changed by addendum.
10.1.2 A paper bid shall be submitted in a sealed opaque envelope marked with the project name, the bidder's name and address, and the words sealed bid, and where that envelope is enclosed in a delivery service's envelope, the outer envelope shall be marked the same way.
10.1.3 An electronic bid, where the Owner's designated portal receives bids, shall be uploaded complete, with every attachment the bid form requires, before the bid time the portal records, and the bidder shall bear the risk of a transmission that is not complete at that time.
10.1.4 The bid time shall be determined by the clock the Owner designates at the place of receipt, or by the portal's recorded time for an electronic bid, and the Owner shall not receive a bid after that time.
10.1.5 A bid received after the bid time shall not be considered and shall be returned to the bidder unopened, and the risk of delay in delivery, by any carrier or any network, shall be the bidder's.
10.1.6 A bid received by facsimile, by e-mail, or by any medium other than the one the advertisement or invitation states shall not be considered.
NOTE A minute is a minute. The bidders who were on time priced the Work against a deadline, the late bidder who is let in has had the use of that minute, and the opening that excuses a late bid has given every other bidder an argument. The rule costs the Owner an occasional low bid from a bidder whose courier was stuck, and it is the rule every public Owner is bound to and nearly every private Owner adopts, because the alternative is a protest from the bidder who was on time. (10.1.7)
10.2 Opening of the Bids
10.2.1 Bids shall be opened as indicated in the datasheet.
Bid Openingradio
○ Public, opened and read aloud at the bid time and place
○ Private, opened by the Owner and the Engineer, results furnished after evaluation
NOTE A public opening, at which each bid is opened and the bidder, the base bid, the alternates, and the presence of the bid security and the addenda acknowledgments are read aloud, is the rule the procurement law of nearly every jurisdiction imposes on a public Owner, and it is what lets the bidders see for themselves that the bids were received as submitted. A private opening keeps the bid prices from the competitors, which a private Owner who expects to negotiate with the low bidder, or to bid the Work again, values, and it leaves each bidder relying on the Owner's tabulation for what the others bid. (10.2.2)
10.2.3 Where the opening is public, the Engineer shall announce each bidder's name, base bid, and alternate prices, and whether bid security and the addenda acknowledgments are present, and shall not announce whether a bid is responsive or which bidder is low.
10.2.4 The Engineer shall prepare a tabulation of every bid received, listing the bidder, the base bid, each alternate, each unit price where the bid is on unit prices, the bid security, and the addenda acknowledged, and shall furnish the tabulation to every bidder and to any plan holder that requests it.
10.2.5 The bids and the tabulation shall be available for inspection by bidders after the opening as the procurement law governing the Owner requires, and on private work as the Owner directs.
NOTE A tabulation that is read aloud is checked on the spot by everyone in the room, and a tabulation that goes out afterward is checked by the bidders who did not win, which is why it lists the elements of responsiveness and not only the prices. The announcement does not declare a low bidder because the low bid at the reading is not always the responsive low bid after the review, and a declaration made at the table is the one the bidder relies on in the protest. (10.2.6)
11 Evaluation and Award
11.1 Responsiveness and Responsibility
11.1.1 The Owner shall determine the responsiveness of each bid on its face as submitted at the bid time, and shall not permit a bidder to cure a defect that affects the price, the time, or the scope after the opening.
11.1.2 The Owner may waive an informality in a bid, and may permit a bidder to correct an informality after the opening, where the procurement law governing the Owner allows, and a waiver granted to one bidder shall be available on the same terms to every bidder.
11.1.3 The Owner shall determine the responsibility of the apparent low bidder, and of any other bidder it considers for award, from the bidder's qualification statement, from the references and the records it names, from the Owner's own records of the bidder's prior work, and from any other evidence the Owner obtains, and shall give a bidder it proposes to find not responsible written notice of the grounds and an opportunity to respond before the award.
11.1.4 A protest of a determination of responsiveness or responsibility, or of the award, shall follow the procedure of the procurement law governing the Owner, or, where no law governs, the procedure the Owner's instructions to bidders state.
NOTE Responsiveness is a question about the bid and responsibility is a question about the bidder, and the two are decided differently: responsiveness is read off the document at the moment of opening and cannot be fixed afterward, because any fix after the other bids are known is a second bid; responsibility is a judgment about capacity and record that the Owner reaches after the opening, on evidence, and the bidder is heard before it is made. A bid rejected as nonresponsive for a defect the Owner could have waived, and a bidder found not responsible without notice, are the two decisions that lose protests. (11.1.5)
11.2 Bidder's Qualification Statement
11.2.1 Each bidder shall submit a qualification statement as indicated in the datasheet.
Bidder's Qualification Statementradio
○ Submitted with the bid
○ Submitted on the Owner's request after the bid opening
○ Not required, bidders prequalified before the bidding documents were issued
○ Not required
11.2.2 Where the qualification statement is submitted on request, the bidder shall deliver it within seven days after the Owner's written request.
NOTE A statement submitted with every bid gives the Owner the evidence it needs on the day of the opening and is the arrangement a public Owner with a fixed award schedule uses, at the cost of a statement from every bidder, including the ones that were never in contention. A statement requested after the opening from the bidders in contention is the lighter arrangement, and it delays the award by the days the request and the review take. Prequalification moves the whole inquiry before the documents issue, so that every bidder is one the Owner has already accepted, and it is the arrangement for work that only a few contractors can perform; it costs the Owner a prequalification procedure and the bidders an application before they have seen the Work. No statement at all is the arrangement on small private work where the Owner invited the bidders it already knows. (11.2.3)
11.2.4 The qualification statement shall be made on the Owner's form, or on a published form such as AIA A305 or EJCDC C-451 where the bidding documents so state, and shall be signed and dated by an officer of the bidder.
11.2.5 The qualification statement shall state:
- The bidder's legal name, form of organization, principal office, and years in business under that name
- The contractor's licenses and registrations the bidder holds in the jurisdiction of the project
- Projects of similar scope, size, and complexity the bidder completed within the number of years the form states, each with the owner's and the engineer's reference contacts, the contract amount, and the completion date
- Projects under way, with their contract amounts and percentages complete
- The individuals the bidder proposes as its project manager and its superintendent, with their experience on similar work
- The major items of construction equipment the bidder owns or will lease for the Work
- A letter from the bidder's surety confirming the bidder's bonding capacity for the Work, and the bidder's financial statement where the form requires it
- The bidder's safety record for the period the form states, including its experience modification rate
- Every contract on which the bidder was terminated for default, failed to complete, or was the subject of a claim on its performance bond within the period the form states
- Litigation and arbitration involving the bidder's construction contracts within the period the form states
11.2.6 The Owner may require the apparent low bidder to furnish, within seven days after a written request, evidence beyond the qualification statement on any matter bearing on its responsibility, including the qualification statements of its proposed subcontractors for the trades the Owner names.
11.3 Basis of Award
11.3.1 The Contract, if awarded, shall be awarded on the basis indicated in the datasheet.
Basis of Awardradio
○ Lowest responsive bid from a responsible bidder on the base bid
○ Lowest responsive bid from a responsible bidder on the base bid plus the alternates the Owner accepts, taken in the order listed on the bid form
○ Lowest responsive bid from a responsible bidder on the base bid plus any combination of alternates the Owner accepts
○ Best value to the Owner under the evaluation criteria and weights stated in the bidding documents
NOTE Award on the base bid alone is the simplest basis and the one most procurement laws presume, and it leaves the alternates to be accepted or declined after the low bidder is known, so the alternates cannot change who is low. Award on the base bid plus alternates taken in the listed order lets the Owner fit the Work to its budget on bid day, and the fixed order is what keeps the Owner from choosing the combination that favors a particular bidder; it is the basis most public Owners that use alternates are required to use. Award on any combination of alternates gives the Owner the most freedom and is open to the objection that the combination was chosen after the prices were known, which a public Owner's law commonly forbids and a private Owner accepts. Best value weighs price against stated criteria such as experience, schedule, and approach, and is available to a public Owner only where its procurement law authorizes it; it produces the contractor the Owner wants at the cost of an evaluation that has to be documented well enough to survive the low bidder's protest. (11.3.2)
11.3.3 Where the award is on the base bid plus alternates, the Owner shall name the alternates it accepts in the notice of award, and the acceptance of a further alternate after award shall be governed by Payment ProceduresPayment ProceduresResolves to the current adopted revision.sync/payment-procedures.
11.3.4 Where the Work is bid on unit prices, the bids shall be compared on the sum of the extended prices for the Owner's estimated quantities, and the Owner may reject a bid whose unit prices are materially unbalanced in relation to the cost of the items they cover.
11.3.5 Where the basis of award is best value, the evaluation criteria, their weights, and the method of scoring shall be stated in the bidding documents before bids are received, and no criterion shall be added or reweighted after the opening.
11.3.6 Where two or more responsive bids from responsible bidders are equal on the basis of award, the Owner shall break the tie by the method the procurement law governing the Owner prescribes, or, where none applies, by a drawing of lots in the presence of the tied bidders.
11.4 Rejection of Bids and Notice of Award
11.4.1 The Owner may reject any or all bids, may reject a bid from a bidder it finds not responsible, may reject a bid it finds materially unbalanced, and may re-advertise the Work, in each case to the extent the procurement law governing the Owner allows.
11.4.2 The Owner shall reject every bid submitted by a bidder that submitted more than one bid for the same Work under its own name or another, and may reject the bids of bidders it finds to have colluded in preparing them.
11.4.3 The Owner shall not negotiate the price of the Work with a bidder before award, except with the lowest responsive bidder from a responsible bidder where every bid exceeds the Owner's budget and the procurement law governing the Owner, or on private work the bidding documents, permits it.
11.4.4 The Owner shall issue the notice of award to the successful bidder in writing within the holding period, naming the Contract Sum, the alternates accepted, and the documents due and the time for delivering them under this standard.
NOTE A notice of award is an acceptance of the bid, not the Contract, and the Agreement is formed when both parties have executed it. The interval between the two is when the bonds and the insurance are placed, and the documents-due procedure of this standard is what closes it on a schedule. (11.4.5)
11.5 Documents Due from the Successful Bidder
11.5.1 The successful bidder shall deliver to the Owner the documents indicated in the datasheet:
- The Agreement, executed by the successful bidder, in the number of counterparts the notice of award states
- The performance bond and the payment bond, executed and accompanied by the power of attorney, on the form and in the penal sums that Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds requires
- The certificates of insurance and the endorsements that Insurance RequirementsInsurance RequirementsResolves to the current adopted revision.sync/insurance-requirements requires, evidencing every coverage in force
- Evidence of the authority of the person who executes the Agreement for the successful bidder
- The business license, tax registration, or other registration the jurisdiction of the project requires of a contractor before it contracts for the Work
- The list of subcontractors, where the Subcontractor Listing article of this standard requires it after the opening and it has not been furnished
Documents Due from the Successful Biddercheckbox
☑ Executed Agreement
☑ Performance bond and payment bond
☑ Certificates of insurance and endorsements
☐ Evidence of signing authority
☐ Business license or registration
☐ List of subcontractors
11.5.2 The successful bidder shall deliver the documents due within the number of days after the notice of award indicated in the datasheet.
Time to Deliver the Documents Duerange
Not more than
days after the notice of award
71014152130
NOTE Ten to fifteen days is the time the published instructions carry, and it is enough for a bidder whose surety and insurer were lined up when it bid, which the bid bond shows the surety was. A shorter time is met only by a bidder who has the bonds in draft before the award; a longer time, three or four weeks, suits an out-of-state bidder who has to register before it can contract, and it holds the start of the Work for that long. The time is measured from the notice of award because that is the first day the bidder knows it has the Work, and the forfeiture of the bid security for missing it is what gives the period its force. (11.5.3)
11.5.4 The Owner shall execute the Agreement and return a fully executed counterpart to the Contractor within fourteen days after receiving the documents due and finding them in order, and shall issue the notice to proceed as the Agreement provides.
11.5.5 Where the successful bidder fails to deliver the documents due within the indicated time, the Owner may annul the award and forfeit the bid security as the Bid Security article of this standard provides, and may award the Contract to the next lowest responsive bidder from a responsible bidder within the holding period, or re-advertise the Work.
NOTE The bonds and the insurance certificates are reviewed on receipt, and the defects that surface there, a bond on the wrong form, a surety that is not qualified, a certificate that omits an endorsement, are the ones Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds and Insurance RequirementsInsurance RequirementsResolves to the current adopted revision.sync/insurance-requirements describe, and they are corrected while the bidder still has an award to lose. (11.5.6)
12 Coordination with the Owner's Instruments and the Technical Standards
12.1 The Engineer shall reconcile this standard with the Owner's instructions to bidders, the advertisement or invitation, the bid form, the Agreement, the General Conditions, and the Supplementary Conditions before the bidding documents issue, and shall resolve a conflict found after issue by addendum.
12.2 Where a technical standard places a requirement on a bidder before bid, such as a tolerance confirmed achievable by a producer or a certification confirmed available in the project's market, that requirement shall be met through the question and substitution procedures of this standard, within their deadlines.
NOTE A bidder reads the advertisement, the instructions, the bid form, and the technical sections as one set, and a deadline that appears in two of them with two values is the deadline the bidder missed. Stating each deadline once, in this standard, and leaving the advertisement to carry the bid time and place, is what keeps the Owner's instruments and the Engineer's from drifting apart. (12.3)
This standard is written and maintained by SynC and licensed under Creative Commons Attribution 4.0. You may share and adapt it, including commercially, provided you credit SynC Standards, link to the license, and indicate any changes. Each standard is drafted from cited sources under published authoring rules, reviewed before adoption, and corrected in the open. Keep the attribution and notice below with any copy; it carries the warranty notice the license asks you to retain.
"Bidding Procedures," SynC Standards, revision 1. Licensed under CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Source: https://synergyinconstruction.com/standards/general/bidding-procedures. Reference material only; not professional engineering advice and provided without warranty. Verify against governing codes and have a licensed professional review before use.