Execution Requirements
New standard for how every trade executes its work on site: survey control and layout, verifying existing conditions before fabricating or cutting, utility locating and protection, cutting and patching, protection of installed work, progress cleaning, starting and adjusting, and removal of nonconforming work. The technical standards point here instead of each restating these duties.
Showing changes from Initial revision
to Rev 1
in Execution Requirements.
+---
+title: Execution Requirements
+category: General Requirements
+description: >
+ When to use: the general obligations that govern how every trade executes its work on the site of any construction contract, read together with every technical standard on the project. States once the survey control the Owner furnishes or the Contractor establishes, the preservation of control points, who performs the layout and how it is verified before construction proceeds, the verification of existing dimensions and conditions before fabrication and before cutting into existing work and the notice of a discrepancy, the existing-conditions survey of the areas the Work affects, the public one-call notification and the private locating, potholing, and protection of existing utilities before excavation, the project-wide cutting and patching rules including the proposal required before structural, weather-resistant, fire-rated, water-retaining, and operating elements are cut, the scanning before coring, the patching standard and who decides a disputed match, the protection of installed work and the responsibility for damage, progress cleaning during the Work, the general obligation to start and adjust equipment only after the manufacturer's checks, and the removal of nonconforming work as a physical act, so that the technical standards and the discipline umbrellas carry only what is specific to their trade.
+ Not intended for: the survey and layout data submittals and their interval and format ([[sync/construction-progress-documentation]], which also owns the pre-construction photographs); the abandonment of existing utilities and the installation of new ones ([[sync/site-utilities]]) and the utility cutoff that is part of demolition ([[sync/selective-demolition]], [[sync/building-demolition]]); the firestop systems themselves ([[sync/firestopping]]); final cleaning at substantial completion ([[sync/closeout-procedures]]); dust and noise control as a site operation and every temporary facility ([[sync/temporary-facilities-and-controls]]); the plant shutdown, outage, and tie-in regime of an operating facility ([[sync/maintenance-of-plant-operations]]); engineered excavation support and dewatering ([[sync/excavation-support-and-dewatering]]); the equipment-specific startup and the functional testing that each equipment standard and [[sync/commissioning]] own; the nonconformance notice, disposition, and log ([[sync/submittal-and-quality-procedures]], [[sync/quality-requirements]]); and the Contractor's safety program, which is means and methods.
+---
+
+# Scope {toc}
+
+## This standard establishes the general execution requirements that apply to every trade on the project: the survey control and the layout of the Work, the verification of existing conditions and the locating of existing utilities before work begins, cutting and patching, the protection of installed work, progress cleaning, the general obligation in starting and adjusting equipment, and the physical removal of nonconforming work, on any project and under any Division of the Specifications. {note}
+
+## Every technical standard assumes that the lines and levels it is built to are right, that the slab it cores has been scanned, that the finish it is installed over is protected afterward, and that the debris it generates leaves the site. Each of those is an obligation that belongs to no single trade, and a project manual that states them inside one discipline's umbrella and not another's leaves the Contractor to argue about which trade's rules apply to a core through a floor that carries both conduit and pipe. This standard states each obligation once, project-wide, and the discipline umbrellas keep only the additions specific to their trade. {note}
+
+## The Contractor shall comply with this standard in addition to any execution requirement stated in a technical standard or in a discipline umbrella standard.
+
+## Where a technical standard states a more stringent requirement for its own product or assembly, that requirement shall govern for that product or assembly.
+
+## Where a requirement of this standard conflicts with the Agreement, the General Conditions, or the Supplementary Conditions, those documents shall govern.
+
+## The following are outside the scope of this standard: {note}
+
+- The survey and layout data submittals, their interval and their format, and the pre-construction photograph program, which [[sync/construction-progress-documentation]] governs; this standard states the duty to lay out and to verify, and that standard carries the record
+- The abandonment, capping, and installation of site utilities, which [[sync/site-utilities]] governs, and the utility identification and cutoff that is part of a demolition scope, which [[sync/selective-demolition]] and [[sync/building-demolition]] govern
+- The through-penetration firestop systems and fire-resistive joint systems that restore a rated assembly after it is cut, which [[sync/firestopping]] governs
+- Final cleaning before the substantial completion inspection, which [[sync/closeout-procedures]] governs
+- Dust suppression and noise control as site operations, temporary enclosures, temporary heat, and every other temporary facility, which [[sync/temporary-facilities-and-controls]] governs
+- The Owner's operating constraints, shutdown and outage requests, and tie-ins and cutovers on an operating facility, which [[sync/maintenance-of-plant-operations]] governs
+- Engineered excavation support, underpinning, and designed dewatering, which [[sync/excavation-support-and-dewatering]] governs
+- The startup checks, the manufacturer's field services, and the performance tests of a particular item of equipment, which its equipment standard and the discipline umbrella for its trade govern, and the functional testing of systems, which [[sync/commissioning]] governs
+- The notice of nonconforming work, its disposition, and the nonconformance log, which [[sync/submittal-and-quality-procedures]] and [[sync/quality-requirements]] govern
+- The Contractor's safety program, the competent person, and the protective systems for excavations, which are the Contractor's means and methods under the law that governs them
+
+# Execution Terms {toc}
+
+## The following terms are used in this standard with the meanings given here: {note}
+
+- Survey control is the set of horizontal control points and vertical benchmarks, with their coordinates and elevations on the project datum, from which the Work is laid out
+- A benchmark is a monumented point of known elevation on the project datum, and a control point is a monumented point of known horizontal position on the project coordinate system
+- Layout is the transfer of the lines, levels, and dimensions of the Contract Documents to the site by staking, marking, and offsetting from the survey control
+- The layout record is the Contractor's written and sketched record of the control used, the points set, the offsets, and the checks made, kept as the layout proceeds
+- A field dimension is a dimension measured on the site from constructed or existing work, as distinct from a dimension read from the Contract Documents
+- The one-call center is the notification service the law of the jurisdiction establishes through which an excavator notifies the operators of underground facilities before digging, and a locate is an operator's marking of its facility in response
+- Private utility locating is the locating of underground facilities the one-call center does not cover, which on an Owner's property are the Owner's own lines downstream of the point of service
+- A pothole is a hand-dug or vacuum-excavated test hole that exposes a utility to confirm its horizontal position, its depth, its size, and its material before excavation proceeds near it
+- The tolerance zone is the horizontal band on either side of the marked location of a utility within which the law of the jurisdiction requires careful excavation, and within which this standard requires hand or vacuum excavation
+- Cutting is the removal of a part of existing or newly installed construction to accommodate the Work, by sawing, coring, drilling, chipping, or demolition, and patching is the restoration of what was cut
+- A natural break is a corner, a change of plane, a change of material, a control joint, or another line at which a change in a finish is not seen as a patch
+- An operating element is a pipe, a duct, a raceway, a cable, a conduit, a structure, or a piece of equipment that is in service for the Owner or for another trade at the time it is to be cut
+- Protection is the temporary covering, barricading, enclosing, or restriction of access that keeps installed work from damage by weather, by traffic, and by the trades that follow
+- Progress cleaning is the collection and removal of debris, waste, and surplus material, and the cleaning of surfaces, during the Work, as distinct from the final cleaning at substantial completion
+- Starting and adjusting is the first operation of an item of equipment after installation and the setting of it to the operating condition the Contract Documents require
+
+# Referenced Standards {toc}
+
+## The execution of the Work shall comply with the latest adopted edition of each of the following unless a specific edition is cited or the Contract Documents direct otherwise.
+
+## Where referenced documents conflict, the more stringent requirement shall govern unless the Engineer of Record directs otherwise in writing.
+
+| Standard | Title |
+|----------|-------|
+| AIA A201 | General Conditions of the Contract for Construction |
+| EJCDC C-700 | Standard General Conditions of the Construction Contract |
+| ConsensusDocs 200 | Standard Agreement and General Conditions Between Owner and Constructor |
+| ASCE 38 | Standard Guideline for Investigating and Documenting Existing Utilities |
+| ASCE 75 | Standard Guideline for Recording and Exchanging Utility Infrastructure Data |
+| CGA Best Practices | Common Ground Alliance Best Practices Guide for Damage Prevention |
+| APWA Uniform Color Code | Uniform Color Code for Temporary Marking of Underground Utility Locations |
+| 29 CFR 1926.651 | Specific Excavation Requirements (Underground Installations) |
+| 49 CFR Part 196 | Protection of Underground Pipelines from Excavation Activity |
+| IBC Chapter 33 | Safeguards During Construction |
+| ACI 228.2R | Report on Nondestructive Test Methods for Evaluation of Concrete in Structures |
+| ACI 562 | Code Requirements for Assessment, Repair, and Rehabilitation of Existing Concrete Structures |
+
+## Every state has an underground facility damage prevention law that establishes the one-call center, the advance notice an excavator gives, the time the operators have to mark, the life of a locate, the tolerance zone, and the excavator's duties within it, and the laws differ in each of those. The notice periods and the tolerance zone in this standard are the project's requirements; the law of the jurisdiction sets the floor beneath them and is what controls where it is stricter. {note}
+
+# Submittals {toc}
+
+## Execution Submittals {toc}
+
+### The Contractor shall submit the following, each at the time this standard states for it:
+
+- The cutting and patching proposal for each element the Elements Requiring a Proposal article names, before that element is cut
+- The one-call ticket for each excavation, and the private locating report where private locating is required, before excavation begins in the area covered
+- The pothole log, listing each pothole with its location, the utility exposed, its depth, size, and material, and the date, before excavation proceeds across or along the utility
+- The existing-conditions survey of each area the Work affects, where the datasheet requires one, before work begins in that area
+- The notice of a discrepancy between the Contract Documents and a field dimension or an existing condition, within the period indicated in the Discrepancy Notice article
+
+```datasheet
+label: Execution Submittals Required
+type: checkbox
+options:
+ - Cutting and patching proposals
+ - One-call tickets and private locating reports
+ - Pothole log
+ - Existing-conditions surveys of affected areas
+ - Discrepancy notices
+default:
+ - Cutting and patching proposals
+ - One-call tickets and private locating reports
+ - Pothole log
+ - Discrepancy notices
+constraint: all_of
+```
+
+### Execution submittals shall be transmitted and tracked through the submittal procedure of [[sync/submittal-and-quality-procedures]].
+
+### The layout record and the survey data of as-placed work shall be submitted on the interval and in the format [[sync/construction-progress-documentation]] establishes.
+
+### Each of these submittals is a record of a condition that disappears: the slab before it is cored, the trench before it is backfilled, the wall before it is opened. A proposal reviewed after the cut, or a pothole log written from memory after the pipe was hit, records nothing anyone can act on, which is why each is tied to the moment before the work rather than to a monthly cycle. {note}
+
+# Field Engineering and Layout {toc}
+
+## Survey Control {toc}
+
+### The survey control from which the Work is laid out shall be furnished as indicated in the datasheet.
+
+```datasheet
+label: Survey Control Furnished
+type: radio
+options:
+ - Owner-furnished benchmarks and control points, with their coordinates and elevations
+ - Owner-furnished primary benchmark and baseline, secondary control established by the Contractor
+ - Contractor-established control from the recorded property survey and the published datum
+```
+
+### Owner-furnished control, with every benchmark and control point monumented and its coordinates and elevations listed, puts the Owner's surveyor behind the datum and leaves the Contractor nothing to establish, which is the arrangement on a site the Owner's design surveyor has already controlled for the design and the one on which a layout dispute has a reference both parties accept. A primary benchmark and a baseline alone give the Contractor the datum and leave the densification of control around the site to the Contractor, which suits a large site where the control the design needed is not the control the construction needs. Control the Contractor establishes from the recorded property survey and the published datum costs the Owner nothing up front and costs the Contractor a licensed survey before the first stake, and it leaves the question of whether the control matches the design datum to be discovered at the first tie-in to existing work. {note}
+
+### Where the Owner furnishes survey control, the benchmarks and control points shall be as shown on [[drawing: the civil survey control plan]].
+
+### Where the Owner furnishes survey control, the Contractor shall verify the furnished benchmarks and control points against each other before using them, and shall report in writing any closure or discrepancy exceeding the tolerance of the layout that depends on them before proceeding.
+
+### Where the Contractor establishes the survey control, the Contractor shall establish it under the responsible charge of a land surveyor licensed in the jurisdiction of the project, tied to the recorded property survey and to the published vertical datum the Contract Documents name, and shall furnish the control data to the Engineer of Record before the first layout is made from it.
+
+### The Contractor shall furnish, at no cost to the Owner, the additional benchmarks and control points the layout of the Work requires beyond those furnished, each referenced to the furnished control.
+
+## Preservation and Replacement of Control {toc}
+
+### The Contractor shall protect every benchmark, control point, property corner, and survey monument on or adjoining the site from disturbance for the duration of the Work.
+
+### The Contractor shall not disturb or remove a benchmark, a control point, or a survey monument without the Engineer of Record's written acceptance of the replacement control, set and referenced before the original is disturbed.
+
+### Where a benchmark, a control point, a property corner, or a survey monument is disturbed or destroyed by the Contractor or by anyone under the Contractor, the Contractor shall have it re-established by a land surveyor licensed in the jurisdiction, at no cost to the Owner, and shall furnish the surveyor's record of the re-establishment.
+
+### A property corner is a legal monument, and its re-establishment is a boundary survey, not a construction layout: the surveyor retraces the record, ties the adjoining monuments, and sets the corner where the evidence puts it, which is a day's work and a sealed document where the original was a pin in the ground. The control points the Contractor set for its own use are cheaper to lose and are replaced from the furnished control, but a lost benchmark that was the only tie to the design datum costs every elevation on the project a re-check. {note}
+
+## Layout of the Work {toc}
+
+### The Contractor shall lay out the Work from the survey control, to the lines, levels, and dimensions of the Contract Documents, and shall be responsible for the accuracy of the layout.
+
+### Layout shall be performed by the party indicated in the datasheet.
+
+```datasheet
+label: Layout Performed By
+type: radio
+options:
+ - "The Contractor's field engineer under the Contractor's direction"
+ - "A licensed land surveyor for the primary layout, the Contractor's forces for the secondary layout"
+ - "A licensed land surveyor for all layout"
+```
+
+### Layout by the Contractor's own field engineer is the arrangement on most building and plant sites, and it costs the Owner nothing beyond the layout record, at the price of an error discovered by the trade that builds on it. A licensed surveyor for the primary layout, which is the building corners, the structure baselines, the column lines, the invert of the first pipe in each run, and the finished grades at control, puts an independent party behind the dimensions every other dimension is measured from and leaves the offsets, the secondary lines, and the in-structure layout to the Contractor, and it is what a project with tight boundary setbacks, a tie-in to an existing hydraulic profile, or a structure that cannot tolerate an error at its base tends to require. A licensed surveyor for all layout is the arrangement on linear civil work, where the layout is the construction, and it is priced as a survey crew on the site for the duration. {note}
+
+### Where the parties disagree whether a particular layout is primary or secondary, the Engineer of Record shall make the determination.
+
+### The Contractor shall verify the layout of each structure, foundation, equipment pad, pipe run, and utility against the Contract Documents and against the survey control before concrete is placed, before pipe is laid, and before any element that depends on the layout is built, and shall record the verification in the layout record.
+
+### The Contractor shall keep the layout record current as the layout proceeds and shall make it available to the Engineer of Record on request at the site.
+
+### A layout error found at the verification costs a crew an hour; the same error found when the pipe reaches the wall costs a wall. The verification is the Contractor's own check and is not a review by the Engineer of Record, whose observation of a layout does not relieve the Contractor of responsibility for it. {note}
+
+### Observation of a layout, or of the Work built on it, by the Owner or the Engineer of Record shall not relieve the Contractor of responsibility for the accuracy of the layout or for the correction of Work built out of position.
+
+### The layout tolerance for each element of the Work shall be the tolerance the technical standard governing that element states, and where that standard states none, the tolerance of the reference standard it cites.
+
+### The Contractor shall record the as-placed location and elevation of each buried, embedded, and concealed element before it is covered, and shall submit the record under [[sync/construction-progress-documentation]].
+
+# Existing Conditions {toc}
+
+## Verification of Field Dimensions and Conditions {toc}
+
+### Before fabricating an element that must fit existing or previously constructed work, the Contractor shall measure the field dimensions that govern the fit and shall fabricate to the field dimensions.
+
+### Before cutting into, connecting to, or building on existing work, the Contractor shall examine the existing work and the conditions under which the new Work is to be performed, and shall verify that the existing work is as the Contract Documents show it and that the conditions permit the Work to be installed as specified.
+
+### The Contract Documents describe an existing building or plant from record drawings, a field survey of what could be seen, and a limited number of openings, and they are wrong somewhere on every renovation. The verification is what converts a wrong dimension into a notice before the steel is cut, rather than into a field modification after it arrives. {note}
+
+### Where a technical standard requires an examination of the substrate or the conditions before its work begins, that examination shall be made in addition to the verification this article requires, and the acceptance of the conditions by the installer that the technical standard provides shall apply.
+
+### Proceeding with the Work over an existing condition the Contractor examined, or could have examined, shall constitute the Contractor's acceptance of that condition as suitable for the Work, except for a condition that could not be discovered without destructive investigation.
+
+## Discrepancy Notice {toc}
+
+### Where a field dimension or an existing condition differs from the Contract Documents in a way that affects the Work, the Contractor shall notify the Engineer of Record in writing within the period indicated in the datasheet after discovering it, stating the discrepancy, the Work affected, and the Contractor's proposed resolution.
+
+```datasheet
+label: Discrepancy Notice Period
+type: range
+unit: business days
+options:
+ min: 1
+ max: 10
+ setpoints: [1, 2, 3, 5, 10]
+constraint: max
+```
+
+### The Contractor shall not proceed with the Work affected by a discrepancy until the Engineer of Record has issued written direction, except for the work needed to make the area safe or to keep an operating element in service.
+
+### A short period keeps the discrepancy in front of the Engineer of Record while the crew is still in the area and the correction is a sketch, and it is met by a Contractor who reports the finding on the day and the resolution later; a longer period lets the Contractor report once with a worked proposal and leaves the crew idle or redeployed in the meantime. The period is set against how much of the Work is on the critical path through the existing building and against how far away the Engineer of Record is. {note}
+
+### Work performed on a discrepant condition without the notice this article requires shall be corrected at the Contractor's cost where the correction would not have been needed had the notice been given.
+
+### Where a discrepancy changes the cost or the time of the Work, the Contractor's notice under this article shall constitute the notice of a differing site condition, and the adjustment shall be made under [[sync/contract-modification-procedures]].
+
+## Existing-Conditions Survey of Affected Areas {toc}
+
+### Before beginning work in an existing building, structure, pavement, or landscaped area, or adjoining one, the Contractor shall document the existing condition of the area as indicated in the datasheet.
+
+```datasheet
+label: Existing-Conditions Survey of Affected Areas
+type: radio
+options:
+ - Written and photographic survey made jointly by the Contractor and the Owner, signed by both
+ - Written and photographic survey made by the Contractor and furnished to the Owner
+ - Pre-construction photographs only
+```
+
+### A joint survey signed by both parties is the baseline neither can later dispute, and it is what an Owner with a finished building, an occupied facility, or a neighbor's property on the line wants, at the cost of walking the area together before the work begins and again after. A survey the Contractor makes alone is accepted on most projects and is the Contractor's own protection against a claim for damage that was there before, at the cost of being the Contractor's record when the dispute arrives. Photographs alone are the pre-construction photograph program under [[sync/construction-progress-documentation]], which records the site and not the condition of each surface, and they suit a greenfield site where there is nothing to damage. {note}
+
+### The survey shall record, for each surface, finish, pavement, structure, and planting in the affected area, its condition and every existing crack, settlement, stain, and damage, so that a condition claimed afterward can be compared to it.
+
+### A requirement to restore an area to its condition before the Work is unenforceable without a record of that condition. The survey is that record, and the restoration obligation in the Protection of Installed Work section and in the technical standards is measured against it. {note}
+
+### Where the parties disagree whether a condition existed before the Work, and the survey does not settle it, the Engineer of Record shall make the initial determination.
+
+## Locating Existing Utilities {toc}
+
+### Before excavating, drilling, driving, or trenching at any location, the Contractor shall notify the one-call center of the jurisdiction within the advance period and by the method the law of the jurisdiction requires, shall obtain the ticket, and shall not begin until each operator has marked its facilities or reported that it has none in the area.
+
+### The Contractor shall renew each one-call ticket before it expires under the law of the jurisdiction, and shall request a re-mark where the marks have been disturbed, obliterated, or removed before the excavation is complete.
+
+### Existing underground utilities within the limits of the Work shall be as shown on [[drawing: the existing conditions plans]], which record the utilities known to the Owner and the Engineer at the time of design and not every utility present.
+
+### Utilities on the Owner's property that the one-call center does not cover shall be located as indicated in the datasheet.
+
+```datasheet
+label: Private Utility Locating on the Owner's Property
+type: radio
+options:
+ - "By a private utility locating service engaged by the Contractor, over the full limits of the Work"
+ - "By the Owner's forces from the Owner's records, marked before the Contractor excavates"
+ - "By potholing only, at each crossing of a recorded utility, with no geophysical locating"
+```
+
+### The one-call center marks the public operators' lines to the point of service and stops there; everything beyond it on a plant site, which is the yard piping, the duct banks, the drain lines, the process piping, and the control cable, is the Owner's, and no operator marks it. A private locating service engaged by the Contractor sweeps the full limits of the Work with electromagnetic and ground-penetrating methods and marks what it finds to the quality level of the standard guideline for investigating existing utilities, at the cost of a service that finds the conductive and shallow lines and misses the deep nonmetallic ones. The Owner's own forces locating from the Owner's records know the plant and cost the Contractor nothing, and they mark what the records show, which on an old plant is not what is there. Potholing from the plans alone, with no geophysical locating, exposes each line the plans show where the excavation will cross it and finds nothing the plans omit, and it suits a short run through an area the plans describe well. {note}
+
+### Where a private locating service is required, its marks shall carry the quality level of ASCE 38 the service achieved at each location, and its report shall be submitted before excavation begins in the area.
+
+### Marks placed by any party shall follow the APWA Uniform Color Code, and the Contractor shall maintain the marks for the duration of the excavation they serve.
+
+## Potholing and Excavation Near Utilities {toc}
+
+### Within the tolerance zone on either side of the marked location of a utility, or within the zone indicated in the datasheet, whichever is wider, the Contractor shall excavate by hand or by vacuum excavation only, and shall not use mechanical excavating equipment until the utility has been exposed and its position confirmed.
+
+```datasheet
+label: Hand or Vacuum Excavation Zone Around a Located Utility
+type: range
+unit: in. each side of the mark
+options:
+ min: 18
+ max: 48
+ setpoints: [18, 24, 30, 36, 48]
+constraint: min
+```
+
+### Before crossing a located utility, excavating parallel to one within the zone, or drilling, driving, or boring beneath one, the Contractor shall pothole the utility to expose it and to confirm its horizontal position, its depth, its size, and its material, and shall record each pothole in the pothole log.
+
+### The damage prevention laws set a tolerance zone of between eighteen and thirty inches on either side of the mark, and the project's zone is set no narrower than the law's and wider where the consequence of a strike is high: a pressure main in a street, a medium-voltage duct bank, a transmission main whose shutdown drains a tank, or a plant drain whose contents the excavation would release. A wider zone costs hand excavation over more of the trench and buys the margin that a mark placed from a record drawing, rather than from a signal, needs. {note}
+
+### A utility exposed by a pothole shall be supported, protected from the excavating equipment, and backfilled around in a manner that does not load or displace it, under the backfill requirements of [[sync/earthwork]].
+
+### Where the Contractor encounters a utility that is not shown on the existing conditions plans and was not marked, the Contractor shall stop excavation at that location, shall protect the utility, and shall notify the Owner and the Engineer of Record under the Discrepancy Notice article before proceeding.
+
+### Where the Contractor encounters a utility whose position, depth, or size differs from the existing conditions plans and the marks by more than the tolerance zone, the Contractor shall notify the Engineer of Record under the Discrepancy Notice article before the Work that depends on the utility's location proceeds.
+
+## Protection of Utilities and Damage {toc}
+
+### The Contractor shall protect every existing utility within the limits of the Work, whether shown, marked, or found, from damage, displacement, and loss of support for the duration of the Work.
+
+### The Contractor shall not interrupt an existing utility serving the Owner, an occupant, or the public except under an outage the Owner has approved under [[sync/maintenance-of-plant-operations]] or, for a public utility, under the arrangement the serving utility and the Contractor have made in writing.
+
+### The Contractor shall repair, at no cost to the Owner, damage to a utility that was shown on the existing conditions plans, was marked, or was exposed by a pothole, and shall bear the cost the utility's operator incurs in restoring service.
+
+### Damage to a utility that was not shown, was not marked, could not have been found by the locating this standard requires, and was not in a position a careful excavator would have anticipated shall be a differing site condition under [[sync/contract-modification-procedures]], and the Contractor shall nonetheless make the repair when directed, on terms adjusted under that standard.
+
+### Where a damaged utility carries gas, a hazardous liquid, electricity, or communications, the Contractor shall notify the operator and the emergency services the law of the jurisdiction requires immediately on the damage, and shall not attempt a repair of such a utility except as the operator directs.
+
+### A struck line that was marked is the excavator's; a struck line that no one could have found is the Owner's; and the line in between, which was not marked but was where anyone would have expected a line to be, is the dispute. The locating, the potholing, and the pothole log are what move a line from the middle category into one of the other two before the strike rather than after it. {note}
+
+# Cutting and Patching {toc}
+
+## Elements Requiring a Proposal {toc}
+
+### The Contractor shall not cut any of the elements indicated in the datasheet until the Engineer of Record has reviewed a cutting and patching proposal for that element and has returned it without objection.
+
+```datasheet
+label: Elements Requiring a Cutting and Patching Proposal
+type: checkbox
+options:
+ - Structural members, foundations, and bearing walls
+ - Roofing, waterproofing, air barriers, and other weather-resistant or water-resistant elements
+ - Fire-resistance-rated assemblies and smoke barriers
+ - Water-retaining structures, their liners, and their waterstops
+ - Operating elements in service
+ - Exterior finishes and finishes exposed to view in occupied areas
+default:
+ - Structural members, foundations, and bearing walls
+ - Roofing, waterproofing, air barriers, and other weather-resistant or water-resistant elements
+ - Fire-resistance-rated assemblies and smoke barriers
+ - Water-retaining structures, their liners, and their waterstops
+ - Operating elements in service
+constraint: all_of
+```
+
+### The elements on the list are the ones a cut can compromise in a way the patch does not restore: a structural member loses capacity, a roof loses its warranty, a rated assembly loses its listing, a basin wall loses its watertightness at the waterstop, and an operating line loses the service it carries. Each needs a decision before the saw starts about where the cut goes, what holds the load or the water meanwhile, and how the element is restored, and the proposal is that decision in writing. Finishes exposed to view are listed for an Owner whose occupied spaces are finished to a standard that a patch, however well matched, would not meet, and leaving them unchecked lets a trade cut and patch an ordinary wall on its own judgment. {note}
+
+### The cutting and patching proposal shall describe the element to be cut, the extent and location of the cut, the reason, the method and the equipment, the temporary support or protection to be provided during the cut, the sequence and the time, the products and the method of patching, the party performing each part of the work, and, for an operating element, the outage or the bypass under which the cut is made.
+
+### Where the proposal concerns a structural member, a foundation, or a bearing wall, it shall include the structural Engineer of Record's written approval of the cut, or shall be reviewed by the structural Engineer of Record before it is returned.
+
+### The Engineer of Record's review of a cutting and patching proposal shall not relieve the Contractor of responsibility for the structural adequacy, the weather resistance, the fire resistance, the watertightness, or the continued operation of the element cut.
+
+### Where the Work requires a cut through an element on the list for which the Contract Documents show the opening, the proposal shall address the method, the support, and the patching only, and the location and extent shown shall govern.
+
+## Scanning Before Coring and Drilling {toc}
+
+### Before coring or drilling into a concrete element of the kind indicated in the datasheet, the Contractor shall locate the embedded reinforcement, post-tensioning tendons, conduit, piping, and other embedded items in the area of the core with a scanning instrument operated by a person trained in its use, and shall mark the core location clear of them.
+
+```datasheet
+label: Scanning Before Coring or Drilling
+type: radio
+options:
+ - Every existing concrete element
+ - Every existing concrete element and every new concrete element with embedded conduit or piping
+ - Post-tensioned, prestressed, and elevated concrete elements only
+default: Every existing concrete element
+```
+
+### Scanning every existing element is the practice on a renovation, where no one knows with certainty what is in the slab, and it costs a technician with a ground-penetrating radar or a cover meter for an hour at each location. Extending it to new elements with embedded conduit or piping protects the Contractor's own embedded work, which the as-placed record locates only as well as it was kept, and suits a plant slab that is a route for conduit and drain lines as much as a floor. Limiting it to post-tensioned, prestressed, and elevated elements covers the cases in which a strike is dangerous or structural and leaves a core through a slab on grade to the as-built record, which is accepted where the record is trusted and the embedded items are few. {note}
+
+### The Contractor shall not cut, nick, drill, or core a post-tensioning tendon or a prestressing strand under any circumstances, and where a scan shows a tendon or strand in the path of a required core, the Contractor shall relocate the core under the Discrepancy Notice article.
+
+### Structural members shall not be cut, notched, drilled, or cored except where the structural drawings show the opening or the structural Engineer of Record has approved it in writing.
+
+### Where a core or a drilled hole strikes reinforcement the scan did not show, the Contractor shall stop, shall report the strike to the Engineer of Record before continuing, and shall make the repair the structural Engineer of Record directs at no cost to the Owner.
+
+## Performing the Cutting {toc}
+
+### Cutting shall be performed by methods that do not impair the strength, the weather resistance, the fire resistance, the watertightness, or the operation of the construction cut, and by saw, core drill, or other method that produces a neat opening of the minimum size the Work requires.
+
+### Cutting of an element adjoining a space in use shall be performed with the dust, water, noise, and vibration controls the Owner's use of that space requires, under [[sync/temporary-facilities-and-controls]] and, on an operating facility, under [[sync/maintenance-of-plant-operations]].
+
+### Where cutting an element in service requires an interruption of the service it carries, the interruption shall be made only under an outage approved under [[sync/maintenance-of-plant-operations]], and the element shall be returned to service before the end of the approved outage.
+
+### The Contractor shall provide the temporary support, shoring, bracing, enclosure, or weather protection the cut requires, in place before the cut is made and maintained until the patch has reached the condition the proposal states.
+
+### Where cutting exposes an element to weather, the Contractor shall close the opening against weather at the end of each working day and whenever work on it is not in progress.
+
+### The trade whose Work requires a cut shall bear the cost of the cutting and of the patching, including the cost of the temporary support and protection, unless the Contract Documents assign it otherwise.
+
+### The cost rule exists because the trade that needs the hole and the trade that patches it are rarely the same, and the patch is the step that is skipped when nobody has priced it. Putting it on the trade that cut puts it on the party that chose where and how large to cut. {note}
+
+## Patching and Restoration {toc}
+
+### Each cut shall be patched with materials matching the adjacent undisturbed construction in material, thickness, texture, color, and finish, by a trade qualified in the finish being restored, and the finish shall be carried to the extent indicated in the datasheet.
+
+```datasheet
+label: Extent of Refinishing at a Patch
+type: radio
+options:
+ - To the limits of the patch, blended into the adjoining finish
+ - To the nearest natural break on every side of the patch
+ - Over the entire surface plane in which the patch lies
+default: To the nearest natural break on every side of the patch
+```
+
+### A patch blended at its own edges is the least costly and shows under most lighting on most finishes, and it is accepted in a mechanical room, a tunnel, or a space whose finish is utilitarian. Refinishing to the nearest natural break, which on a painted wall is the corner and on a tile floor the grout line that bounds a whole course, makes the patch disappear on most finishes at the cost of refinishing a strip or a panel rather than a spot, and it is the practice most finish trades follow unasked. Refinishing the whole plane is what a finish with no natural breaks, such as a monolithic floor, a stretched ceiling, or a wall seen in raking light, needs for the patch not to show, and it is priced as a refinish of the room. {note}
+
+### A patch in a fire-resistance-rated assembly or a smoke barrier shall restore the assembly's rating with a listed firestop system or a listed repair detail under [[sync/firestopping]], and where the patch is larger than any listed firestop system covers, with construction matching the rated assembly's listing.
+
+### A patch in a roofing, waterproofing, or air barrier element shall be made with the materials and the details the manufacturer of the existing system requires for the continuation of its warranty, and where the existing system carries a manufacturer's warranty, the Contractor shall give the manufacturer the notice and obtain the inspection the warranty requires before the patch is covered.
+
+### A patch in a water-retaining structure shall restore the watertightness of the structure, with the waterstop, the repair material, and the detail the structural Engineer of Record approves, and the structure shall be tested for leakage under the technical standard governing it before it is returned to service.
+
+### A patch in a structural member or a foundation shall be made with the materials and the detail the structural Engineer of Record approves, and shall restore the member's capacity.
+
+### A patch in an exterior wall, a floor, or a pavement shall be flush with the adjoining surface and shall carry the same drainage, slope, and expansion provisions as the adjoining construction.
+
+### Where the parties disagree whether a patch matches the adjacent construction or is finished to the required extent, the Engineer of Record shall make the initial determination, and the Contractor shall redo the patch the Engineer of Record rejects at no cost to the Owner.
+
+### Openings left by the removal of an element shall be patched as this article requires, whether or not new Work occupies the opening.
+
+# Protection of Installed Work {toc}
+
+## Protection by the Installing Trade and Thereafter {toc}
+
+### The Contractor shall protect every element of the Work from damage, weather, soiling, and deterioration from the time it is installed until substantial completion, or until the Owner accepts a portion of the Work under [[sync/closeout-procedures]], whichever is earlier.
+
+### The protection of an element shall be as its technical standard requires, and where that standard requires none, shall be the covering, barricading, enclosure, or restriction of access that keeps the element in the condition in which it was accepted.
+
+### Finished floors, stair treads, and thresholds in the path of construction traffic shall be protected by a covering that is maintained until the traffic ends, and a covering that traps moisture shall not be left on a finish that is damaged by it.
+
+### Installed equipment, piping, ductwork, raceways, and devices shall be covered or closed against the entry of water, dust, debris, and foreign material whenever work on them is not in progress, and the covering shall remain in place until the system is cleaned for startup.
+
+### Loads shall not be placed on a slab, a deck, a roof, a tank, or a structure beyond what it is designed to carry at its age and condition, and the Contractor shall obtain the structural Engineer of Record's written acceptance before storing material or placing equipment on a structure that is not designed for that load.
+
+### The protection the technical standards require is specific to the product: a membrane wants a walkway pad, a floor wants a breathable covering, a switchboard wants a dry room. This standard adds the obligation that is not specific to any product, which is that the trade that follows is responsible for what it walks on, leans a ladder against, and cuts next to, and that the Contractor is responsible for all of them. {note}
+
+## Responsibility for Damage {toc}
+
+### Damage to installed work shall be repaired, or the damaged element replaced where the Engineer of Record determines that a repair would not restore it, at no cost to the Owner, by a trade qualified in the work damaged, to the condition the technical standard requires for new work.
+
+### The cost of repairing or replacing damaged work shall be borne by the party whose operations caused the damage, and the Contractor shall remain responsible to the Owner for the repair whether or not that party can be identified or made to pay.
+
+### Where the party whose operations caused the damage cannot be identified, the cost shall be borne as indicated in the datasheet.
+
+```datasheet
+label: Cost of Damage by an Unidentified Party Borne By
+type: radio
+options:
+ - The Contractor
+ - Apportioned among the prime contractors by the Owner
+```
+
+### Under a single prime contract every trade on the site is under the Contractor, and the Contractor bears damage it cannot trace, which is the arrangement that makes the Contractor police the site. Under multiple prime contracts or where the Owner's separate contractors work alongside the Contractor, damage no one admits to is apportioned by the Owner among the primes present in the area at the time, under the contract structure [[sync/summary-of-work-and-work-restrictions]] states, which gives every prime a reason to protect the others' work and leaves the Owner to referee. {note}
+
+### Where the parties disagree whether a condition is damage, whether a repair restores the element, or which operations caused the damage, the Engineer of Record shall make the initial determination.
+
+## Removal of Protection {toc}
+
+### The Contractor shall remove the temporary protection from each element of the Work before the substantial completion inspection, or before the Owner accepts the portion of the Work containing it, and shall repair any damage the protection or its removal caused.
+
+### Protection removed to permit a later trade's work shall be replaced by that trade on the same day, and the element shall not be left unprotected overnight.
+
+### Protective films, coatings, and labels that a manufacturer requires to be removed within a stated time after installation shall be removed within that time, whether or not the protection of the element is otherwise continued.
+
+### A protective film left on a window or a metal panel past the manufacturer's time bakes on and becomes the damage it was meant to prevent, and a floor covering left down through a wet season rots the floor beneath it. Protection has a life, and the removal is part of it. {note}
+
+# Progress Cleaning {toc}
+
+## Cleaning During the Work {toc}
+
+### The Contractor shall clean each work area, and shall collect debris, waste, surplus material, and packaging into containers, at the interval indicated in the datasheet while construction activity occurs in that area.
+
+```datasheet
+label: Work Area Cleaning Interval
+type: range
+unit: working days
+options:
+ min: 1
+ max: 5
+ setpoints: [1, 2, 3, 5]
+default: 1
+constraint: max
+```
+
+### Daily cleaning is what nearly every project requires and what an occupied facility, a plant in operation, and a finish trade following a rough trade all need; a longer interval is accepted on a remote site in the earthwork and structure phases, where the debris is a stockpile and not a hazard, and it is priced as fewer labor hours against a site that looks and works like it. {note}
+
+### The Contractor shall remove debris and waste from the site in closed containers, and shall not permit a container to overflow, to be left open where its contents can be blown or washed from it, or to remain on the site after the Work it served is complete.
+
+### Debris, waste, and surplus material shall be removed from the site to a disposal or recycling facility permitted to receive it under the law of the jurisdiction, and shall not be burned, buried, or washed into a drain on the site.
+
+### Hazardous and regulated waste generated by the Work shall be handled, manifested, and disposed of as the law of the jurisdiction requires, and the Contractor shall furnish the manifests to the Owner on request.
+
+### The Contractor shall keep every stair, corridor, exit, roadway, and access route on the site clear of material and debris, and shall not store material in one.
+
+### Cleaning shall be performed by methods that do not damage the surface cleaned and that do not spread dust into an occupied area, an operating area, or an area in which a finish is being applied.
+
+### The Contractor shall clean the interior of every enclosed space and the surfaces of every element to be concealed, and shall remove the debris from inside walls, chases, plenums, pipe trenches, tanks, and equipment, before the space or the element is enclosed, covered, or closed.
+
+### A chase closed with the offcuts inside it, a trench backfilled over a lunch wrapper, and a tank sealed with a glove in the sump are each found at startup, if at all, and opened at a cost out of all proportion to the sweep that would have prevented them. The cleaning before enclosure is the one cleaning that cannot be made up later. {note}
+
+### Where a technical standard requires a cleaning of its product before startup, before finishing, or before acceptance, that cleaning shall be performed in addition to the progress cleaning this section requires.
+
+## Site Condition and the Owner's Remedy {toc}
+
+### The Contractor shall keep the site, the adjoining public ways, and the areas of the Owner's property the Contractor uses free of accumulated debris, waste, mud tracked from the site, and surplus material, and shall remove material tracked or blown onto a public way on the day it occurs.
+
+### Where the parties disagree whether an area has been cleaned or a site kept free of debris as this section requires, the Engineer of Record shall make the initial determination.
+
+### Where the Contractor does not clean an area or remove debris as this section requires, the Owner may give the Contractor written notice stating the period indicated in the datasheet, after which the Owner may have the cleaning performed by others and deduct the cost from sums due the Contractor.
+
+```datasheet
+label: Notice Before the Owner Cleans at the Contractor's Cost
+type: range
+unit: hours
+options:
+ min: 24
+ max: 120
+ setpoints: [24, 48, 72, 120]
+constraint: exact
+```
+
+### A short notice is what an Owner operating the facility, or occupying it, needs to have the condition corrected before it interferes with the operation; a longer notice gives the Contractor a shift to put its own crew on it and suits a site with no one but the Contractor on it. The remedy is a backcharge and not a stop-work, which is what keeps it usable for a condition that is a nuisance and not a hazard. {note}
+
+### Final cleaning before the substantial completion inspection, and the standard to which it is performed, shall be as [[sync/closeout-procedures]] requires, and progress cleaning under this section shall not be a substitute for it.
+
+### Dust suppression, noise control, and the temporary enclosures and barriers that confine dust and debris shall be as [[sync/temporary-facilities-and-controls]] requires.
+
+# Starting and Adjusting {toc}
+
+## General Obligation in Starting Equipment {toc}
+
+### The Contractor shall not start any item of equipment for the first time until the installation has been checked against the manufacturer's written installation instructions, the checks the manufacturer requires before first operation have been performed and recorded, the lubricants and fluids have been placed, and the protection against the entry of debris has been removed and the equipment cleaned.
+
+### Where the technical standard governing an item of equipment requires the manufacturer's field representative to inspect the installation, to certify it, or to be present at startup, the Contractor shall not start that equipment until that representative has done so.
+
+### The Contractor shall adjust each item of equipment and each system, after it is started, to operate within the manufacturer's published limits and to the condition the Contract Documents require, and shall record the settings made.
+
+### The Contractor shall repair or replace, at no cost to the Owner, equipment damaged by a start made before the checks this article requires, or made without the manufacturer's representative where one is required, and the manufacturer's refusal of warranty for such a start shall not relieve the Contractor of the warranty the technical standard requires.
+
+### The startup checks for a particular item of equipment, the content of the startup report, the manufacturer's field services, and the release of the equipment to performance testing are stated in the equipment standard and in the discipline umbrella standard for its trade, and the functional testing of the systems it forms is stated in [[sync/commissioning]]. This section states only the obligation that holds for every item of equipment on the project, including the ones whose standard says nothing about startup: nothing is switched on until it has been checked, and the party that switched it on early owns what happens. {note}
+
+# Removal of Nonconforming Work {toc}
+
+## Removal and Replacement as a Physical Act {toc}
+
+### Where the disposition of a nonconformance under [[sync/submittal-and-quality-procedures]] or the corrective action under [[sync/quality-requirements]] requires the removal of nonconforming Work, the Contractor shall remove it, shall remove the Work of other trades that must be disturbed to reach it, shall replace both with Work conforming to the Contract Documents, and shall patch, protect, and clean under this standard, at no cost to the Owner.
+
+### The notice of a nonconformance, the decision whether it is removed, accepted, or repaired, and the record of that decision are the procedure, and they belong to the quality standards. This standard states what the removal is when it is ordered, which is cutting, patching, protection, and cleaning like any other, and carried out under the same rules. {note}
+
+### Nonconforming Work shall not be concealed before its disposition is decided, and Work that conceals a nonconformance without the disposition shall be removed under this article to expose it.
+
+# Coordination with the Discipline Umbrellas and the Technical Standards {toc}
+
+## The discipline umbrella standards, [[sync/common-work-results-electrical]], [[sync/common-work-results-mechanical]], and [[sync/common-work-results-process]], state the sleeve and penetration, protection, cleaning, and startup requirements specific to their trades, and some of them restate parts of the cutting and patching rules of this standard. Where a restatement differs, this standard governs the project-wide rule and the umbrella governs the addition specific to its trade. {note}
+
+## Where a discipline umbrella standard or a technical standard and this standard address the same subject, the more stringent requirement shall govern unless the Contract Documents direct otherwise.
+
+## The Contractor shall include in each subcontract and purchase order the layout verification, discrepancy notice, utility locating, cutting and patching, protection, progress cleaning, and starting requirements of this standard that apply to the subcontractor's or supplier's scope.
+
+## The Contractor shall reconcile the execution requirements of each technical standard with this standard and shall report in writing, before the preconstruction conference under [[sync/project-management-and-coordination]], any conflict between them.
+
+## A subcontractor that saw only the technical section for its trade learns of the scanning rule when it has already cored the slab, and of the cleaning interval when the backcharge arrives. Flowing the requirements into the subcontract is what makes them the subcontractor's obligation and not only the Contractor's. {note}