1 Scope

NOTE This standard covers concrete slabs on ground that serve as building floors: the design basis recorded for them, the subbase and the supporting surface beneath them, the vapor retarder decision and the sequence it fixes, the crack-control strategy and the reinforcement or fibers within the slab, thickened edges, joint layout and load transfer, joint filling, flatness and levelness, the pre-placement verification, and acceptance of the finished floor. (1.1)
NOTE A slab on ground is supported continuously by the soil beneath it, and that single fact separates it from every other concrete element in the building. It does not span, so its thickness is set by wheel and post loads against the stiffness of the subgrade rather than by bending between supports. It shrinks against the friction of the ground it sits on, so it cracks unless the cracks are given somewhere to form. And it is the one element whose top surface is the finished product: the flatness a lift truck feels, the joint edge a pallet jack strikes, and the moisture a flooring adhesive sees are all properties of the slab itself. The decisions this standard records are the ones that determine whether those properties are designed or accidental. (1.2)
NOTE The structural design of the slab, its thickness, its reinforcement, its joint spacing, and the loads it carries, is performed by the Engineer of Record under ACI 360R and recorded on the contract documents. This standard records the design basis the Engineer of Record selected, states how the slab is built to that design, and states how the finished floor is verified; it does not produce the design, and no value in it substitutes for a project-specific analysis. (1.3)
NOTE The work of the following standards applies to slabs on ground and is not restated here. (1.4)
  • The concrete: mixture classes, specified strength, the drying shrinkage limit, delivery, placement, consolidation, hot- and cold-weather protection, field testing, and strength acceptance, under Cast In Place ConcreteCast-in-Place ConcreteResolves to the current adopted revision.sync/cast-in-place-concrete
  • Reinforcing steel products, grades, bending, splices, cover, and corrosion protection, under Concrete ReinforcementConcrete ReinforcementResolves to the current adopted revision.sync/concrete-reinforcement
  • Bar supports and chairs, and the embedded plates and anchor rods cast into the slab, under Concrete AccessoriesConcrete Accessories and EmbedsResolves to the current adopted revision.sync/concrete-accessories
  • Edge forms, bulkheads, blockouts, and release agents, under Concrete FormworkConcrete Formwork and AccessoriesResolves to the current adopted revision.sync/concrete-formwork
  • Curing methods and duration, surface finishing, evaporation retarder, and surface-defect acceptance, under Concrete Curing And FinishingConcrete Curing and FinishingResolves to the current adopted revision.sync/concrete-curing-and-finishing
  • The vapor retarder product, its ASTM E1745 class and permeance, its position, laps, seams, penetration sealing, repair, and protection before the pour, under Vapor Barriers Under SlabUnder-Slab Vapor BarriersResolves to the current adopted revision.sync/vapor-barriers-under-slab
  • Preformed compressible filler materials and waterstops, under Concrete Joints And WaterstopsConcrete Construction Joints and WaterstopsResolves to the current adopted revision.sync/concrete-joints-and-waterstops
  • Excavation, fill, compaction, proof rolling, and acceptance of the subgrade, under EarthworkEarthworkResolves to the current adopted revision.sync/earthwork
  • The material, lift placement, and compaction of a dense-graded aggregate base, under Aggregate Base CourseAggregate Base CourseResolves to the current adopted revision.sync/aggregate-base-course
  • Spread and strip footings and the foundation walls the slab abuts, under Shallow FoundationsShallow Foundations (Spread and Strip Footings)Resolves to the current adopted revision.sync/shallow-foundations
  • Prestressing strand, anchorages, sheathing, stressing, and stressing records of a post-tensioned slab, under Post Tensioned ConcretePost-Tensioned ConcreteResolves to the current adopted revision.sync/post-tensioned-concrete
  • Equipment pads and housekeeping pads cast on the slab, under Concrete PadsConcrete Equipment PadsResolves to the current adopted revision.sync/concrete-pads
  • Grinding, densifying, and polishing of the hardened surface, under Polished ConcretePolished Concrete FlooringResolves to the current adopted revision.sync/polished-concrete
  • Assessment and repair of cracks and defects in the hardened slab, under Concrete Repair And RestorationConcrete Repair and RestorationResolves to the current adopted revision.sync/concrete-repair-and-restoration
NOTE Moisture testing of the slab before a floor covering is installed, and any topical moisture mitigation applied to the hardened surface, are specified by the standard for the covering: Resilient FlooringResilient FlooringResolves to the current adopted revision.sync/resilient-flooring, Wood FlooringWood FlooringResolves to the current adopted revision.sync/wood-flooring, CarpetCarpetResolves to the current adopted revision.sync/carpet, and Resinous FlooringResinous FlooringResolves to the current adopted revision.sync/resinous-flooring each state the test method, the limit, and the mitigation they require. This standard governs the conditions that let the slab dry from one face only: the vapor retarder beneath it and the sequence of its placement. (1.5)
NOTE Exterior pavements, aprons, sidewalks, and curbs are governed by Concrete PavingConcrete Paving, Curbs, and SidewalksResolves to the current adopted revision.sync/concrete-paving; elevated slabs, structural mats, and transfer slabs that span to a frame or resist column loads are governed by Cast In Place ConcreteCast-in-Place ConcreteResolves to the current adopted revision.sync/cast-in-place-concrete and the structural drawings. (1.6)
1.7 Slabs on ground shall comply with Cast In Place ConcreteCast-in-Place ConcreteResolves to the current adopted revision.sync/cast-in-place-concrete except as modified by this standard.
1.8 Where this standard and a standard it references conflict, the more stringent requirement shall govern unless the Engineer of Record directs otherwise in writing.
1.9 The Contractor shall not reduce the slab thickness, the reinforcement, the subbase thickness, or the dowel size shown on the contract documents, and shall not widen the joint spacing shown, without the written approval of the Engineer of Record.

2 Referenced Standards

2.1 Materials, design, construction, and testing shall comply with the latest adopted edition of each of the following unless a specific edition is cited.
2.2 Where the contract documents, the adopted building code, or a referenced standard conflict, the more stringent requirement shall govern unless the Engineer of Record directs otherwise in writing.
Standard Title
ACI 117 Specification for Tolerances for Concrete Construction and Materials
ACI 223R Guide for the Use of Shrinkage-Compensating Concrete
ACI 224.3R Joints in Concrete Construction
ACI 301 Specifications for Concrete Construction
ACI 302.1R Guide to Concrete Floor and Slab Construction
ACI 302.2R Guide for Concrete Slabs that Receive Moisture-Sensitive Flooring Materials
ACI 318 Building Code Requirements for Structural Concrete and Commentary
ACI 360R Guide to Design of Slabs-on-Ground
ACI 544.4R Guide to Design with Fiber-Reinforced Concrete
ASTM A36/A36M Carbon Structural Steel
ASTM A615/A615M Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement
ASTM A820/A820M Steel Fibers for Fiber-Reinforced Concrete
ASTM A1064/A1064M Carbon-Steel Wire and Welded Wire Reinforcement, Plain and Deformed, for Concrete
ASTM C920 Elastomeric Joint Sealants
ASTM C1116/C1116M Fiber-Reinforced Concrete
ASTM C1609/C1609M Flexural Performance of Fiber-Reinforced Concrete (Using Beam With Third-Point Loading)
ASTM D2240 Rubber Property, Durometer Hardness
ASTM D7508/D7508M Polyolefin Chopped Strands for Use in Concrete
ASTM E1155 Determining FF Floor Flatness and FL Floor Levelness Numbers
ICC IBC International Building Code (Chapter 19, Concrete)
PTI DC10.5 Standard Requirements for Design and Analysis of Shallow Post-Tensioned Concrete Foundations on Expansive Soils
PTI M10.2 Specification for Unbonded Single Strand Tendons

3 Submittals

3.1 Action Submittals

3.1.1 The Contractor shall submit the following for review and acceptance before the subbase is placed beneath the first slab and before any slab concrete is placed:
  • Slab placement and joint layout plan, drawn over the floor plan, showing the sequence and limits of each placement, construction joint locations, contraction joint lines and spacing, isolation joints at columns, walls, footings, pads, pits, and penetrations, the joints that receive load-transfer devices, the strike-off method and placement widths, and the sawing method and target timing
  • Reinforcement placing drawings for the slab, showing the welded wire reinforcement sheet designation and lap, or the bar size and spacing, the position of the reinforcement within the slab thickness, the support plan, and the treatment of the reinforcement at each joint
  • Fiber product data for steel or synthetic macrofibers, with the proposed dosage, the batching and mixing procedure, and an ASTM C1609/C1609M test report at that dosage in the project mixture
  • Product data for load-transfer devices, including dowel diameter and length, plate dowel geometry, baskets, sleeves, and alignment hardware
  • Product data for the semi-rigid joint filler or elastomeric sealant, including hardness, cure time, and the manufacturer's required slab age before filling
  • Material source and gradation for a subbase that is not a dense-graded aggregate base
  • Trial placement plan, where a trial placement is required, giving its location, size, equipment, and the measurements to be taken on it
Action Submittals Requiredcheckbox
☑ Slab placement and joint layout plan
☑ Reinforcement placing drawings for the slab
☐ Fiber product data, dosage, and ASTM C1609 report
☑ Load-transfer device product data
☑ Joint filler or sealant product data
☐ Subbase material source and gradation
☐ Trial placement plan
3.1.2 Slab concrete shall not be placed until the submittals covering that placement have been reviewed and returned.

3.2 Informational Submittals

3.2.1 The Contractor shall submit the following before the first slab is placed, or as each item is produced:
  • Subbase surface survey for each placement area, showing the measured elevation against the design elevation on the grid the Engineer of Record accepts
  • Pre-placement verification record for each placement, made in accordance with this standard
  • Trial placement report, where a trial placement is required, with the F-numbers measured on it and the sawing timing observed
  • Saw-cutting log recording, for each placement, the time of final finishing and the time each contraction joint was cut
  • Qualification of the party performing the floor flatness and levelness survey, and the calibration record for the instrument used
Informational Submittals Requiredcheckbox
☑ Subbase surface survey for each placement area
☑ Pre-placement verification record for each placement
☐ Trial placement report
☑ Saw-cutting log
☑ Floor survey party qualification and instrument calibration

3.3 Closeout Submittals

3.3.1 The Contractor shall submit the following before the slab work is accepted:
  • Floor flatness and levelness reports per ASTM E1155 for every test section, identifying the section, the date and time of placement and of measurement, the overall and local F-numbers, and conformance to the specified values
  • As-built joint layout, recording every departure from the accepted joint layout plan
  • Joint filling record, giving the slab age at filling, the product, and the lots used for each placement
  • Record of every random crack reported to the Engineer of Record, with its location, measured width, and the disposition directed
  • Thickness verification record for each placement
Closeout Submittals Requiredcheckbox
☑ Floor flatness and levelness reports per ASTM E1155
☑ As-built joint layout
☑ Joint filling record
☑ Random crack reports and dispositions
☑ Thickness verification record

4 Quality Assurance

4.1 Pre-Slab Conference

4.1.1 A conference shall be held before the subbase is placed beneath the first slab.
4.1.2 The conference shall be attended by the Contractor's superintendent, the concrete subcontractor and the finishing foreman, the ready-mixed concrete supplier, the testing agency, the sawing subcontractor, the flooring installer where a moisture-sensitive covering is scheduled on the slab, and the Engineer of Record.
4.1.3 The conference agenda shall cover the subbase and its surface tolerance, the vapor retarder decision and the sequence it fixes, the placement sequence and strike-off method, the reinforcement or fiber and its support, the joint layout and the sawing method and timing, the load-transfer devices, the F-numbers and how they will be measured, the finishing and curing method assigned to the scheduled floor covering, the strength required before construction traffic, and the procedure for reporting random cracks.
NOTE A floor is built in one pass by a crew that cannot stop to consult the documents, and the decisions that govern its quality are the ones every party in the room has to carry out in the same order on the same day. The conference exists so that the finishing foreman, the saw operator, and the testing technician have agreed on timing before the first truck arrives rather than at the first joint. (4.1.4)

4.2 Trial Placement

NOTE A trial placement is a production-sized panel built with the production crew, mixture, equipment, and method before the floor itself, and measured as the floor will be measured. It costs a day and a panel of concrete, and it buys the F-numbers, the sawing window, and the finishing timing for the actual mixture and the actual weather instead of the values assumed in the plan. It earns its cost where the specified tolerances are tighter than the crew has recently achieved, where the mixture carries fibers or a shrinkage limit the finishers have not worked with, or where the floor will remain exposed as the finished surface. (4.2.1)
4.2.2 Whether a trial placement is required before the first production slab shall be as indicated in the datasheet.
Trial Placement Before Production Slabsradio
○ Required before the first production placement
● Not required
4.2.3 Where a trial placement is required, it shall be of not less than the area indicated in the datasheet and shall be built with the same subbase, vapor retarder, reinforcement or fiber, mixture, crew, equipment, strike-off method, and finishing and curing method as the production slabs.
Trial Placement Arearange
Not less than
ft²
50010001500200030005000
4.2.4 The trial placement shall be surveyed for F-numbers and its contraction joints cut by the production method, and the results shall be reviewed with the Engineer of Record before the first production placement.
4.2.5 Where the Engineer of Record accepts the trial placement in writing, it shall remain as part of the work; otherwise the Contractor shall remove it at no cost to the Owner.

4.3 Floor Survey

4.3.1 The floor flatness and levelness survey shall be performed by the party indicated in the datasheet.
Party Performing the Floor Flatness and Levelness Surveyradio
● Independent testing agency engaged by the Owner
○ Independent testing agency engaged by the Contractor
○ Contractor's own personnel using a calibrated instrument
NOTE An Owner-engaged agency makes the survey an acceptance test independent of the party whose work it measures, at the Owner's cost; a Contractor-engaged agency keeps the same instrument and procedure on the Contractor's side of the contract, which suits a floor the Contractor is also responsible for correcting; the Contractor's own personnel can survey within the 72 hour window on a remote site where no agency is available, at the cost of an acceptance record produced by the party it judges. (4.3.2)
4.3.3 The survey instrument shall be of a type ASTM E1155 permits and shall carry a calibration record not older than one year at the time of the survey.

5 Design Basis

NOTE ACI 360R sizes a slab on ground for the loads that cross it against the stiffness of the ground that supports it. Three inputs decide the outcome: the modulus of subgrade reaction, the loads, and the crack-control strategy, because the strategy fixes the joint spacing and the joint spacing fixes how much of the slab's capacity is spent on shrinkage restraint before any load is applied. (5.1)
5.2 The modulus of subgrade reaction used in the slab design shall be as indicated in the datasheet.
Modulus of Subgrade Reactionrange
pci
25500
Per drawings — the geotechnical report (deferred by default)
NOTE The modulus is a measure of how much the ground deflects under a loaded plate, and it is the single most influential soil input to slab thickness. It is a property of the prepared subgrade together with the subbase, not of the native soil alone, which is why a granular subbase is specified even where bearing is already adequate: it raises the effective modulus and, more importantly, makes it uniform across the floor. (5.3)
5.4 The slab design shall be based on the uniform loads, rack and post loads, and vehicle wheel and axle loads indicated on the structural general notes.
5.5 The crack-control strategy for the slab shall be as indicated in the datasheet.
Crack-Control Strategyradio
○ Plain concrete, with cracking controlled by contraction joints alone
○ Welded wire reinforcement
○ Deformed reinforcing bars
○ Steel fiber reinforcement
○ Synthetic macrofiber reinforcement
○ Shrinkage-compensating concrete
○ Post-tensioned, unbonded tendons
NOTE A slab on ground cracks because the concrete shrinks while the ground holds it still, and every strategy on the list is a different answer to where that crack goes. A plain slab puts it at a closely spaced contraction joint and relies on nothing else, which is economical where the floor is lightly and uniformly loaded and the joint count is acceptable. Welded wire and deformed bars do not stop the crack from forming; they hold it tight between joints so it stays narrow, and they permit the joints to be spaced farther apart at the cost of placing and supporting steel. Steel and synthetic macrofibers do the same job distributed through the section, with no steel to chair and no position to verify, at the cost of a mixture that batches and finishes differently and a surface on which fibers can show. Shrinkage-compensating concrete expands against its reinforcement during the first days and then shrinks back to roughly its original length, so the slab arrives at service with little net shrinkage and few joints, at the cost of a cement the supplier has to source and a curing regime that cannot be shortened. Post-tensioning puts the slab in compression so it does not crack at all and needs no contraction joints, and it is the strategy for large jointless floors and for slabs that must bridge expansive or compressible soil, at the cost of a stressing operation and tendon layout the other strategies do not need. (5.6)
5.7 Where the slab is of shrinkage-compensating concrete, the concrete, its reinforcement, and the curing it requires shall conform to ACI 223R.
5.8 Where the slab is post-tensioned, strand, anchorages, sheathing, and stressing shall conform to Post Tensioned ConcretePost-Tensioned ConcreteResolves to the current adopted revision.sync/post-tensioned-concrete and to PTI M10.2.
5.9 Where a post-tensioned slab also serves as the foundation of the building on expansive or compressible soil, it shall be designed in accordance with PTI DC10.5.

6 Slab Thickness

6.1 The slab thickness shall be as indicated in the datasheet.
Slab Thicknessrange
in
3.524
Per drawings — the slab-on-grade schedule on the structural drawings (deferred by default)
6.2 The slab thickness shall be not less than the prescriptive minimum that Adopted Building CodeAdopted Building CodeParameterEach project supplies its own value.adopted-building-code sets for a concrete floor slab on ground.
NOTE Thickness is the design output, not a rule of thumb. It is set by the governing wheel, post, or uniform load against the modulus of subgrade reaction, and it is the dimension that a high spot in the subbase silently reduces exactly where a loaded wheel will find it. The thickness tolerance and the subbase surface tolerance are therefore specified together, because the second is what protects the first. (6.3)
6.4 The thickness of the placed slab shall be within the tolerance ACI 117 specifies for slabs on ground.
6.5 Slab thickness shall be verified for each placement as this standard requires under Field Quality Control.

7 Slab Edge at the Building Perimeter

NOTE The relation between the slab edge and the foundation decides whether the floor moves with the building or independently of it. A turned-down edge makes the slab its own perimeter foundation, which is the usual construction for a pre-engineered metal building or a lightly loaded single-story structure on competent soil. A free edge separated from the foundation wall by a full-depth isolation joint lets the floor shrink and curl without dragging on a wall that is not moving, which is why it is the usual detail where the building has its own footings. An edge resting on a ledge or haunch cast into the foundation keeps the slab edge from settling with the backfill beside the wall while a bond breaker still lets it move horizontally. A doweled edge ties the slab to the wall for load transfer where the wall and the slab are designed to act together, and it restrains the slab in return. (7.1)
7.2 The slab edge at the building perimeter shall be as indicated in the datasheet.
Slab Edge at the Building Perimeterradio
○ Monolithic turned-down edge serving as an integral grade beam
○ Free edge separated from the foundation by a full-depth isolation joint
○ Edge bearing on a foundation ledge or haunch over a bond breaker
○ Edge doweled to the foundation wall
7.3 Turned-down edge and thickened edge dimensions and reinforcement shall be as shown on the foundation plan and slab edge details.
7.4 A turned-down edge that serves as the perimeter foundation of the building shall bear below Frost DepthFrost DepthParameterEach project supplies its own value.frost-depth, or shall be designed as a frost-protected shallow foundation in accordance with Adopted Building CodeAdopted Building CodeParameterEach project supplies its own value.adopted-building-code.
7.5 Thickened slab sections beneath interior bearing walls, rack post lines, and equipment shall be located as shown on the foundation plan.
7.6 Turned-down edges and thickened sections shall be placed monolithically with the slab they stiffen.
7.7 Where a thickened section cannot be placed monolithically with the slab, the Contractor shall notify the Engineer of Record, who shall direct in writing the location and the load transfer at the resulting construction joint.
7.8 Bars in a turned-down edge or thickened section shall be furnished, bent, and spliced under Concrete ReinforcementConcrete ReinforcementResolves to the current adopted revision.sync/concrete-reinforcement and positioned as the slab edge details show.
7.9 Where the slab edge bears on a ledge or haunch, a bond breaker shall be placed on the bearing surface before the slab is placed, and no reinforcement shall cross from the slab into the foundation.

8 Subgrade Beneath the Slab

NOTE Uniform support matters more to a slab on ground than strong support. A slab does not span, so when a soft pocket, an uncompacted trench, or a lens of organic material settles under a loaded panel the slab follows it and cracks, and the crack looks exactly like a shrinkage crack. Such cracks are routinely blamed on the concrete. The only defense is a subgrade that was compacted, proof-rolled, and accepted before anything was placed on it, and that was not disturbed afterward. (8.1)
8.2 The subgrade shall be excavated or filled, compacted, proof-rolled, and accepted in accordance with EarthworkEarthworkResolves to the current adopted revision.sync/earthwork before any material is placed on it.
8.3 Where soft or yielding areas are found after the subgrade was accepted, the Contractor shall correct them under EarthworkEarthworkResolves to the current adopted revision.sync/earthwork before placing anything over them.
8.4 Backfill of utility trenches crossing beneath the slab shall be compacted under EarthworkEarthworkResolves to the current adopted revision.sync/earthwork to the target for fill beneath slabs and shall be accepted before it is covered.
8.5 Where the geotechnical report requires lime, cement, or fly ash treatment of the subgrade, the treatment shall be performed under Soil StabilizationSoil Stabilization and ModificationResolves to the current adopted revision.sync/soil-stabilization.
8.6 Where Seasonal High Groundwater ElevationSeasonal High Groundwater ElevationParameterEach project supplies its own value.seasonal-high-groundwater-elevation lies within 2 ft of the underside of the slab, the Engineer of Record shall determine whether an under-slab drainage layer is required, and any drainage layer shall be as specified under SubdrainageSubdrainageResolves to the current adopted revision.sync/subdrainage.
8.7 Where no subbase is provided, the subgrade surface shall be fine-graded to the elevation tolerance this standard sets for the subbase surface.

9 Granular Subbase

NOTE A subbase buys three things at once: a uniform, higher modulus of subgrade reaction across the whole floor; a capillary break between the soil and the slab; and a working platform that trucks, pump hoses, and finishers can operate on without rutting the subgrade. A dense-graded crushed aggregate base provides all three and trims to a tight surface. An open-graded crushed stone layer provides the strongest capillary break and drains, but its surface cannot be trimmed to tolerance or walked on without displacing stone, so it is finished with a fine-graded choker course on which the vapor retarder lies. A cushion of sand or screenings alone gives the trimmable surface and some protection to the retarder without the stiffness or the drainage of a stone layer. No subbase at all places the slab on the prepared subgrade, which the geotechnical engineer of record permits where the subgrade is granular, uniform, and already drains. (9.1)
9.2 The subbase beneath the slab shall be of the type indicated in the datasheet.
Subbase Typeradio
● Dense-graded crushed aggregate base
○ Open-graded crushed stone capillary break with a fine-graded choker course at the surface
○ Fine-graded compactible cushion of sand or stone screenings only
○ No subbase, with the slab placed on the prepared subgrade
9.3 The subbase thickness shall be as indicated in the datasheet.
Subbase Thicknessrange
in
224
Per drawings — the slab-on-grade section on the structural drawings or the geotechnical report (deferred by default)
9.4 A dense-graded crushed aggregate base shall be furnished, placed in lifts, and compacted in accordance with Aggregate Base CourseAggregate Base CourseResolves to the current adopted revision.sync/aggregate-base-course.
9.5 Open-graded crushed stone shall be placed in lifts not exceeding 6 in. and shall be compacted with vibratory equipment until the surface no longer moves under the compactor, as confirmed by the geotechnical engineer of record.
9.6 A choker course or cushion shall be a fine-graded, compactible material placed and compacted to a surface that the vapor retarder can be laid on and walked on without displacement.
9.7 The finished subbase surface shall be within the elevation tolerance indicated in the datasheet of the design elevation.
Subbase Surface Elevation Tolerancerange
Not more than
in
0.250.50.751
NOTE A high spot in the subbase takes its height out of the slab, and a low spot is paid for in concrete; a tolerance of three-quarters of an inch is the common pairing with the ACI 117 thickness tolerance, and a tighter value is set where the slab is thin, where the floor is a defined-traffic floor whose thickness governs its stiffness, or where the quantity of concrete is being controlled closely. (9.8)
9.9 The finished subbase surface shall be surveyed on the grid the Engineer of Record accepts, and the survey shall be submitted before the vapor retarder or the slab is placed over it.
9.10 Construction traffic on the finished subbase shall be limited to the vehicles the placement plan identifies, and ruts, displaced material, and contamination shall be regraded and recompacted before the slab is placed.
9.11 At the time concrete is placed, the subbase or subgrade surface beneath the slab shall be damp, with no standing water, mud, ice, snow, or frozen material.
9.12 Where no vapor retarder is provided, the subbase or subgrade surface shall be wetted before concrete is placed so that it does not absorb water from the concrete, with no free water remaining on the surface at placement.
NOTE A dry absorptive base pulls water out of the bottom of the slab as it is placed, which stiffens the bottom, starves the hydration there, and sets up the moisture gradient that curls the slab; a saturated base supplies water the slab cannot shed and keeps the bottom wet for months. Damp with no free water is the condition between the two. (9.13)

10 Vapor Retarder Beneath the Slab

NOTE Whether a vapor retarder is placed beneath the slab is a design decision about where the slab is allowed to dry, not a detail. With a retarder directly beneath it the slab dries upward only, which takes longer but ends, and the floor covering above it sees no soil moisture. Without one the slab dries from both faces and curls less, but soil moisture moves through it indefinitely, so any adhesive, coating, or covering above it is exposed to that moisture for the life of the floor. ACI 302.1R and ACI 302.2R work through the choice as a sequence of questions about the floor covering, the occupancy, and the soil, and ASTM F710 requires an effective retarder beneath any slab that will receive resilient flooring. (10.1)
10.2 Whether a vapor retarder is provided beneath the slab shall be as indicated in the datasheet.
Vapor Retarder Beneath the Slabradio
● Provided
○ Not provided
NOTE A retarder is omitted where the slab will remain bare or will receive only a breathable covering, where the space is unconditioned, and where the geotechnical engineer of record confirms that the subbase drains and the soil carries no moisture source the slab needs protection from; the floors of an open warehouse, an unconditioned industrial bay, or a covered loading area are the usual cases. Omitting it where any adhered or coated finish is later installed converts a saved roll of polyethylene into a flooring failure. (10.3)
10.4 Where a moisture-sensitive floor covering, coating, or adhesive is scheduled on the slab, a vapor retarder shall be provided beneath it unless the Engineer of Record directs otherwise in writing.
10.5 Where a vapor retarder is provided, its product, class, permeance, position, laps, seams, penetration sealing, repair, and protection before the pour shall conform to Vapor Barriers Under SlabUnder-Slab Vapor BarriersResolves to the current adopted revision.sync/vapor-barriers-under-slab.
10.6 The vapor retarder shall not be placed until the subbase surface has been accepted and surveyed.
10.7 Where termiticide soil treatment is specified, it shall be applied and accepted under Soil Treatment For Termite ControlSoil Treatment for Termite ControlResolves to the current adopted revision.sync/soil-treatment-for-termite-control before the membrane is laid over the treated soil.
10.8 Bar supports, dowel baskets, edge forms, and stakes shall be set on the vapor retarder without puncturing it, and punctures made by supports, stakes, or traffic shall be repaired under Vapor Barriers Under SlabUnder-Slab Vapor BarriersResolves to the current adopted revision.sync/vapor-barriers-under-slab before concrete is placed.
NOTE A retarder directly beneath the slab removes the base that would otherwise absorb bleed water, so a mixture placed on it bleeds longer, finishes later, and curls more than the same mixture on a granular base. The adjustments that compensate, a lower water content, a larger aggregate, and a cementitious content that does not depend on the base to take water away, are mixture decisions made under Cast In Place ConcreteCast-in-Place ConcreteResolves to the current adopted revision.sync/cast-in-place-concrete with the retarder in view. (10.9)

11 Concrete for the Slab

11.1 Slab concrete shall be the slab-on-grade mixture class specified under Cast In Place ConcreteCast-in-Place ConcreteResolves to the current adopted revision.sync/cast-in-place-concrete, with the specified compressive strength, the drying shrinkage limit, the water-cementitious materials ratio, and the nominal maximum aggregate size assigned to that class.
11.2 Where the contraction joint spacing exceeds 30 times the slab thickness, or where the slab will remain exposed as the finished floor, the Engineer of Record shall assign a drying shrinkage limit to the slab mixture class under Cast In Place ConcreteCast-in-Place ConcreteResolves to the current adopted revision.sync/cast-in-place-concrete.
NOTE Strength is the property a cylinder measures and shrinkage is the property a floor exhibits, and the two are set by different parts of the mixture. A floor cracks between its joints, curls at them, and spalls along them in proportion to how much water and paste it carried, not to how many pounds per square inch it reached, so a slab mixture is controlled through its water content, its aggregate volume, and a measured shrinkage limit where joint spacing or an exposed finish makes shrinkage the governing property. (11.3)
11.4 Where fibers are part of the crack-control strategy, the slab concrete shall also conform to ASTM C1116/C1116M.

12 Reinforcement Within the Slab

NOTE Reinforcement in a slab on ground controls the width of the cracks that form; it does not prevent them. A light mat of welded wire or bars adds nothing to the slab's capacity to carry load and nothing to its resistance to cracking; its entire value is in holding a crack closed after it opens, which it does only if it is in the upper part of the slab where the crack opens widest and only if it is still there, in that position, after the concrete is placed. (12.1)

12.2 Welded Wire Reinforcement

12.2.1 Welded wire reinforcement in the slab shall conform to ASTM A1064/A1064M and shall be furnished in the form indicated in the datasheet.
Welded Wire Reinforcement Formradio
● Flat sheets
○ Rolls
NOTE Reinforcement from a roll holds the curvature it was wound to, and in a slab the spring-back lifts the mat off its supports and up through the surface in one place while it lies on the subbase in another; flat sheets lie where they are chaired, which is why ACI 301 requires them and rolls are selected only for the lightest mats, where the Contractor will flatten and secure them in a way the Engineer of Record accepts. (12.2.2)
12.2.3 Where rolls are selected, the reinforcement shall be flattened before placement and tied to its supports so that no part of the mat rises above or falls below its specified position during concrete placement.
12.2.4 The welded wire reinforcement sheet designation shall be as indicated in the datasheet.
Welded Wire Reinforcement Sheet Designationtext
Enter value...
Per drawings — the slab-on-grade schedule on the structural drawings (deferred by default)
12.2.5 Sheets shall be lapped not less than one spacing of the cross wires plus 2 in. for plain wire, and not less than the lap length ACI 318 requires for deformed wire, and the laps shall be tied.

12.3 Deformed Bars

12.3.1 Deformed bars in the slab shall be furnished, bent, and spliced under Concrete ReinforcementConcrete ReinforcementResolves to the current adopted revision.sync/concrete-reinforcement.
12.3.2 The bar designation shall be as indicated in the datasheet.
Reinforcing Bar Designationrange
36
Per drawings — the slab-on-grade schedule on the structural drawings (deferred by default)
12.3.3 The bar spacing in each direction shall be as indicated in the datasheet.
Reinforcing Bar Spacing Each Wayrange
in
624
Per drawings — the slab-on-grade schedule on the structural drawings (deferred by default)

12.4 Position and Support

12.4.1 Welded wire reinforcement and bars in the slab shall be positioned at the depth below the finished surface indicated in the datasheet.
Reinforcement Depth Below the Finished Surfacerange
in
1.522.533.54
NOTE A shrinkage crack opens widest at the top of the slab and narrows toward the bottom, so the steel that holds it closed belongs in the upper part of the section, 2 in. below the surface on a slab of ordinary thickness and at about one-third of the depth on a thick one. Placed higher it loses its cover and rusts at the first crack; placed at mid-depth or below it is simply not where the crack is. (12.4.2)
12.4.3 Reinforcement shall be supported on bar supports furnished under Concrete AccessoriesConcrete Accessories and EmbedsResolves to the current adopted revision.sync/concrete-accessories, spaced not more than the distance indicated in the datasheet in each direction.
Bar Support Spacing Beneath Slab Reinforcementrange
Not more than
in
24303648
12.4.4 Bar supports bearing on the vapor retarder shall have plate or precast bases that do not puncture the membrane.
12.4.5 Reinforcement shall not be laid on the subbase or the vapor retarder and lifted during concrete placement.
NOTE Reinforcement lifted into position by hand from beneath the fresh concrete ends up wherever the hook left it, which the record of every cored slab shows is the bottom. Supports close enough that a finisher's weight between them does not push the mat down are the only method that puts the steel where the design assumes it. (12.4.6)
12.4.7 The position of the reinforcement within the slab shall be within the tolerance of ACI 117.

12.5 Reinforcement at Contraction Joints

12.5.1 The treatment of the reinforcement at contraction joints shall be as indicated in the datasheet.
Reinforcement at Contraction Jointsradio
● Discontinued at every contraction joint
○ Continued through the joint with alternate wires or bars cut
○ Continued through the joint without interruption
NOTE Steel that crosses a contraction joint restrains it, and a joint that cannot open does not relieve the shrinkage, which then cracks the panel somewhere else. Discontinuing the reinforcement at every joint lets the joint work and relies on dowels or aggregate interlock for load transfer across it. Cutting alternate wires or bars halves the restraint while keeping some steel across the joint to hold it from opening wide, a compromise used where no dowels are provided and the joint will be filled. Continuing the reinforcement without interruption is the detail for a joint that is intended not to open, which makes sense only where the design accepts cracking between joints or where the steel area is large enough to hold those cracks tight. (12.5.2)
12.5.3 Reinforcement shall not cross an isolation joint.
12.5.4 Reinforcement shall be stopped at construction joints, with load transferred by the devices this standard requires, unless the accepted joint layout plan shows it continuing.

12.6 Fiber Reinforcement

12.6.1 Steel fibers shall conform to ASTM A820/A820M and shall be of the type indicated in the datasheet.
Steel Fiber Type per ASTM A820select
Type I, cold-drawn wire
Type II, cut sheet
Type III, melt-extracted
Type IV, mill cut
Type V, modified cold-drawn wire
NOTE Cold-drawn wire fibers, usually with hooked or crimped ends, give the highest residual strength per pound and are the type the floor market is built around; cut sheet and mill-cut fibers are shorter and stiffer, pump and finish more easily, and deliver less post-crack toughness per pound; melt-extracted fibers are the corrosion-resistant stainless product for an exposed or aggressive environment; modified cold-drawn wire covers the proprietary geometries that trade anchorage against fiber count at a fixed dosage. (12.6.2)
12.6.3 Where steel fibers are the crack-control strategy, the dosage shall be not less than that indicated in the datasheet.
Steel Fiber Dosagerange
Not less than
lb/yd³
15100
12.6.4 Synthetic macrofibers shall conform to ASTM D7508/D7508M.
12.6.5 Where synthetic macrofibers are the crack-control strategy, the dosage shall be not less than that indicated in the datasheet.
Synthetic Macrofiber Dosagerange
Not less than
lb/yd³
312
NOTE Steel fibers and synthetic macrofibers occupy different parts of the dosage scale for the same crack-control effect because they differ by roughly an order of magnitude in density, so a dosage is meaningful only beside the fiber it was set for; the design value that compares them is the residual strength the fiber-reinforced concrete develops in the ASTM C1609/C1609M beam test at the proposed dosage. (12.6.6)
12.6.7 The fiber type and dosage shall provide the residual strength under ASTM C1609/C1609M that the slab design under ACI 360R and ACI 544.4R requires, as demonstrated by the test report submitted.
12.6.8 Fibers shall be added to the mixture and mixed by the method the fiber manufacturer publishes, so that they are distributed through the load without balling.
12.6.9 A load in which fiber balls are observed at discharge shall be rejected at the Contractor's cost.
12.6.10 Whether microsynthetic fibers for plastic shrinkage control are included in the slab mixture shall be as indicated in the datasheet.
Microsynthetic Fibers for Plastic Shrinkage Controlradio
○ Included
○ Not included
NOTE Fibrillated or monofilament microsynthetic fibers at a fraction of a pound per cubic yard hold the surface together during the first hours, while the concrete is plastic and evaporation is pulling it apart; they do nothing for drying shrinkage cracking afterward and are not a crack-control strategy, which is why they are specified as a separate decision and never in place of one. (12.6.11)

12.7 Post-Tensioned Slabs

12.7.1 A post-tensioned slab shall be placed on a friction-reducing layer of two sheets of polyethylene, or the alternative layer the slab design specifies, laid over the subbase or the vapor retarder.
12.7.2 Tendon profile, spacing, and anchorage locations shall be as shown on the tendon layout drawings.
12.7.3 A post-tensioned slab shall have no contraction joints, and its construction joints and pour strips shall be located where the tendon layout drawings show them.

12.8 Shrinkage-Compensating Slabs

12.8.1 A shrinkage-compensating slab shall carry the reinforcement, in the position, that ACI 223R requires for the expansion the mixture is designed to develop.
12.8.2 Joint spacing and the slip layer beneath a shrinkage-compensating slab shall be as ACI 223R requires and as shown on the joint layout.

13 Joints

NOTE A slab on ground is going to crack, and the joint layout is the choice of where. Contraction joints create planes of weakness so that the shrinkage cracks form in straight lines beneath a saw cut instead of wandering across the floor. Isolation joints separate the slab from the columns, walls, footings, and pads that would otherwise hold it still while it shrinks, so that the restraint of those elements does not crack the field. Construction joints close out each placement and are the one joint type located by the crew's production rate rather than by the shrinkage of the slab, which is why they are made to coincide with the contraction joint lines. ACI 224.3R and ACI 302.1R set out the mechanisms; the layout that applies them is drawn for each floor. (13.1)
13.2 Joint locations shall be as shown on the slab joint layout on the structural drawings.

13.3 Contraction Joints

13.3.1 Contraction joints shall be spaced so that the distance between joints does not exceed the multiple of the slab thickness indicated in the datasheet, measured in consistent units.
Contraction Joint Spacing as a Multiple of Slab Thicknessrange
Not more than
× slab thickness
2060
NOTE At 24 to 36 times the thickness, which is 2 to 3 ft of spacing for each inch of slab, a plain slab of ordinary shrinkage cracks at its joints and nowhere else; a mixture with a measured shrinkage limit, a fiber-reinforced slab, or a slab with a shrinkage-reducing admixture is carried to the upper end of that band or beyond it. Every foot added to the spacing is a joint removed from the floor and a foot added to the opening of the joints that remain, so a wider spacing is paid for in dowels, in filler, and in the width the filler has to bridge. (13.3.2)
13.3.3 Contraction joint panels shall have a ratio of long side to short side not exceeding the value indicated in the datasheet.
Panel Aspect Ratiorange
Not more than
long side : short side
11.251.5
NOTE A long narrow panel cracks across its middle because the shrinkage along its long dimension accumulates faster than the joints at its ends can relieve it; panels kept close to square crack at their joints. (13.3.4)
13.3.5 Contraction joints shall run through the corners of column isolation joints and shall align with column lines.
13.3.6 Contraction joints shall be continuous across the slab from edge to edge, or from an edge to an isolation joint, and shall not stop within a panel.
13.3.7 A contraction joint or a diagonal reinforcing bar shall be provided at every re-entrant corner in the slab, as the joint layout shows.
13.3.8 Contraction joints shall be formed by the method indicated in the datasheet.
Contraction Joint Sawing Methodradio
○ Conventional wet-cut sawing to one-quarter of the slab thickness
○ Early-entry dry-cut sawing to the depth the saw manufacturer specifies for the slab thickness
○ Preformed plastic insert strip placed in the plastic concrete
NOTE A conventional saw cuts a quarter of the thickness and has to wait until the concrete is hard enough not to ravel, which on a hot day is after the slab has already cracked somewhere else; an early-entry saw cuts a shallower joint within an hour or two of finishing, before the shrinkage stress develops, and relies on the still-weak concrete to crack beneath its shallower cut; a preformed insert pressed into the plastic concrete needs no sawing at all and leaves a joint edge that is harder to fill and more easily damaged, which keeps it to floors without hard-wheeled traffic. (13.3.9)
13.3.10 Contraction joints shall be cut as soon as the concrete supports the saw without raveling the cut edge, and in every case within the time after final finishing indicated in the datasheet.
Time After Final Finishing Within Which Contraction Joints Are Cutrange
Not more than
hours
124681224
NOTE Cutting too late is the single most common joint failure on a floor. Shrinkage stress builds from the moment the slab stops bleeding, and in hot or windy weather a conventional saw cannot get on the slab before the first random crack forms; the window is set against the sawing method and the weather, and the trial placement is where it is confirmed. (13.3.11)
13.3.12 Where a random crack forms before the contraction joints are cut, the Contractor shall notify the Engineer of Record before cutting the joints in that panel.

13.4 Isolation Joints

13.4.1 A full-depth isolation joint shall be provided around every column, at every wall, footing, and foundation the slab abuts except where the slab edge is doweled to or bears on the foundation, around every equipment pad, pit, trench drain, and sump, and around every pipe, conduit, and duct that penetrates the slab.
NOTE Anything that holds the slab while it shrinks becomes the origin of a crack. Columns are the classic case: without an isolation joint a crack radiates diagonally from each column corner across the panel, and no reinforcement in the slab stops it. The joint is full depth so that nothing at the bottom of the section restrains what the top is free to do. (13.4.2)
13.4.3 Isolation joints shall be filled with a preformed compressible filler of the thickness indicated in the datasheet, extending the full depth of the slab.
Isolation Joint Filler Thicknessrange
in
0.250.3750.50.751
13.4.4 The preformed compressible filler shall conform to Concrete Joints And WaterstopsConcrete Construction Joints and WaterstopsResolves to the current adopted revision.sync/concrete-joints-and-waterstops.
13.4.5 Column isolation joints shall be of the shape indicated in the datasheet.
Column Isolation Joint Shaperadio
○ Diamond, turned 45° to the contraction joint lines
○ Circular
○ Square, with the contraction joints run to its corners
NOTE A diamond turned to the joint lines puts a corner of the isolation joint on each contraction joint, so the joints meet the column and the panel has no re-entrant corner; a circular isolation joint has no corners to crack from and is the detail for a floor that stays exposed, at the cost of a formed circle; a square boxout aligned with the contraction joints is the simplest to form and works only where the joints are run to its corners, because a square with a joint arriving at the middle of a side leaves a re-entrant corner that cracks. (13.4.6)
13.4.7 Where an isolation joint is sealed, the top of the filler shall be recessed to the depth the sealant manufacturer requires.

13.5 Construction Joints

13.5.1 Construction joints shall be located at the limits of each placement as the accepted joint layout plan shows, and each shall coincide with a contraction joint line.
13.5.2 Construction joint faces shall be formed straight and vertical by bulkheads furnished under Concrete FormworkConcrete Formwork and AccessoriesResolves to the current adopted revision.sync/concrete-formwork and set true to line.
13.5.3 Where a placement is interrupted long enough that the concrete in place reaches initial set, the Contractor shall terminate the placement at a bulkhead on a planned joint line and shall notify the Engineer of Record.

13.6 Load Transfer Across Joints

NOTE Where a loaded wheel crosses a joint, the two panels either deflect together or the loaded edge drops below the unloaded one, and every pass of the wheel then strikes the far edge. Hard wheels on a pallet jack or a lift truck spall an undoweled joint within months. A load-transfer device makes the two panels deflect together while still letting the joint open as the slab shrinks, which is the combination that aggregate interlock alone loses as soon as the joint opens more than a few hundredths of an inch. (13.6.1)
13.6.2 The joints that receive load-transfer devices shall be as indicated in the datasheet.
Joints Receiving Load-Transfer Devicesradio
○ Construction joints only
○ Construction joints and the contraction joints in areas of hard-wheeled traffic
○ All construction and contraction joints
○ No joints
NOTE A construction joint is a formed, full-depth separation with no aggregate interlock at all, so it is doweled on nearly every floor that carries anything on wheels; contraction joints keep their interlock until they open, which on a floor with light traffic is enough, and on a floor with hard wheels is not, so they are doweled where the traffic runs and left to interlock elsewhere; doweling every joint is the choice for a floor whose traffic pattern is not known or will change; no devices at all suits a slab that carries foot traffic and pneumatic tires only. (13.6.3)
13.6.4 The load-transfer device shall be as indicated in the datasheet.
Load-Transfer Deviceradio
○ Smooth round dowel bars
○ Plate dowels, square or diamond
○ Tapered plate dowels
○ Keyed joint
○ Aggregate interlock only, without a device
NOTE A smooth round dowel is the least expensive device and the one most sensitive to alignment, because a bar skewed in the joint locks it as the slab shrinks; a square or diamond plate dowel in a sleeve lets the joint move both along and across the bar, so it tolerates the misalignment that locks a round bar and can be used at a joint where panels shrink in two directions; a tapered plate keeps its bearing tight as the joint opens, which holds the deflection down at a joint that will open wide; a keyed joint transfers load through the concrete key itself and loses that transfer as soon as the joint opens, so it serves only a lightly loaded floor; aggregate interlock without a device serves where no hard wheel will cross the joint. (13.6.5)
13.6.6 Dowel diameter shall be as indicated in the datasheet.
Dowel Diameterrange
in
0.50.6250.750.87511.251.5
Per drawings — the slab joint details on the structural drawings (deferred by default)
13.6.7 Dowel length shall be as indicated in the datasheet.
Dowel Lengthrange
in
1224
Per drawings — the slab joint details on the structural drawings (deferred by default)
13.6.8 Dowel spacing along the joint shall be as indicated in the datasheet.
Dowel Spacing Along the Jointrange
in
1224
Per drawings — the slab joint details on the structural drawings (deferred by default)
13.6.9 Smooth round dowels shall be plain round bars conforming to ASTM A36/A36M or ASTM A615/A615M, with sawn ends free of burrs.
13.6.10 One half of the length of each smooth dowel shall be coated or sleeved so that it does not bond to the concrete.
13.6.11 Plate dowels shall be installed in the sleeves or pockets the manufacturer furnishes, so that the plate can move in the plane of the slab as the joint opens.
13.6.12 Dowels shall be held parallel to the slab surface and perpendicular to the joint, within the alignment tolerance of ACI 117, by baskets staked to the subbase or by the bulkhead form.
13.6.13 Dowels shall not be inserted into fresh concrete after placement.
13.6.14 The shipping wires that hold a dowel basket square shall be cut before concrete is placed.
13.6.15 Where a keyed joint is indicated, the key shall be formed to the profile the joint details show, and a keyed joint shall not be used where hard-wheeled vehicles will cross it unless the Engineer of Record directs otherwise in writing.

13.7 Joint Filling and Sealing

NOTE Whether a joint is filled depends on what crosses it. A hard wheel striking an unfilled saw cut chips the joint edge on every pass; a semi-rigid filler supports those edges from inside the cut and is the only treatment that protects them. A joint that carries no hard wheels can be sealed to keep water and debris out of it or simply left open. The filler that supports an edge is also the one that cannot stretch, so it has to go in after the slab has done most of its shrinking, or the joint opens and splits it. (13.7.1)
13.7.2 Contraction and construction joints shall receive the treatment indicated in the datasheet.
Contraction and Construction Joint Treatmentradio
○ Semi-rigid epoxy or polyurea filler, full depth of the saw cut
○ Elastomeric sealant over a backer rod
○ Left open and unfilled
NOTE A semi-rigid filler supports the joint edge against wheel impact and is installed full depth without a backer rod, at the cost of a product that cannot follow a joint that keeps opening; an elastomeric sealant follows joint movement and keeps the joint clean and watertight but is soft and offers the edge no support; an open joint costs nothing and collects whatever falls into it, which suits a floor that is covered, bare under foot traffic only, or scheduled for a later finish that fills the joints itself. (13.7.3)
13.7.4 Where hard-wheeled vehicles will cross a joint, that joint shall receive a semi-rigid filler unless the datasheet indicates otherwise.
13.7.5 Semi-rigid filler shall be a two-component epoxy or polyurea with a Shore A hardness of not less than 80 when tested in accordance with ASTM D2240, installed full depth of the saw cut without a backer rod, overfilled, and shaved flush with the floor surface after cure.
13.7.6 Elastomeric sealant shall conform to ASTM C920 and shall be installed over a backer rod to the width-to-depth ratio the sealant manufacturer requires.
13.7.7 Joints shall not be filled until the slab has reached the age indicated in the datasheet.
Slab Age Before Joints Are Filledrange
Not less than
days
286090120180
NOTE Most of a slab's drying shrinkage occurs in its first months, and a joint filled early is pulled apart as the joint continues to open; delaying the filling as long as the construction schedule permits leaves less movement for the filler to absorb, at the cost of a floor whose joints stay unprotected until the filler goes in. (13.7.8)
13.7.9 Immediately before filling, joints shall be cleaned of curing compound, laitance, and debris by dry sawing or sandblasting and shall be vacuumed.
13.7.10 Spalled joint edges shall be repaired with the filler manufacturer's repair material before the joint is filled.

14 Floor Flatness and Levelness

NOTE Floor flatness and levelness are specified by F-numbers because a straightedge cannot measure a floor. FF describes bumpiness over short distances, the waviness a lift truck mast amplifies into sway; FL describes tilt over longer distances, the slope that leaves a rack leg short of the floor. Both are measured by the procedure of ASTM E1155 as an overall value for the whole floor and a minimum local value for each test section, because a floor can average well and still carry a hump that stops a pallet jack. A defined-traffic floor, where very narrow aisle trucks run on fixed wheel paths between high racks, is measured differently: along the wheel paths themselves, by F-min numbers that bound the change in elevation across and along each path. (14.1)
14.2 The floor surface class shall be as indicated in the datasheet.
Floor Surface Classradio
● Random-traffic floor, measured by overall and local F-numbers per ASTM E1155
○ Defined-traffic floor, measured along the wheel paths by F-min numbers
14.3 The overall flatness of a random-traffic floor shall be not less than the FF value indicated in the datasheet.
Overall Flatness FFrange
Not less than
FF
1520253035404550607080100
14.4 The overall levelness of a random-traffic floor shall be not less than the FL value indicated in the datasheet.
Overall Levelness FLrange
Not less than
FL
101520253035405060
14.5 The local flatness of each test section shall be not less than the FF value indicated in the datasheet.
Local Flatness FFrange
Not less than
FF
101315172024253035405070
14.6 The local levelness of each test section shall be not less than the FL value indicated in the datasheet.
Local Levelness FLrange
Not less than
FL
710121315172025303540
NOTE The F-number ladder tracks what runs on the floor. A slab that will be covered by a thick finish or that carries foot traffic only is built to the low end; an office or retail floor under a thin covering needs the flatness that keeps a resilient tile from telegraphing every bump; a warehouse with lift trucks in open aisles needs the flatness that keeps the mast from swaying and the levelness that keeps the racks plumb; and a floor that stays exposed as the finished surface is built to the number its owner can see. Local values are set at roughly two-thirds of the overall values, so that an individual section can be rougher than the floor's average without being bad enough to notice. Each step up the ladder is paid for in the strike-off method, in narrower placement strips, in the crew's skill, and in the number of sections that fail and are ground. (14.7)
14.8 The F-min tolerance of a defined-traffic floor shall be not less than the value indicated in the datasheet, applied along and across each wheel path.
Defined-Traffic F-minrange
Not less than
F-min
506075100125150
14.9 The aisle and wheel-path locations of a defined-traffic floor shall be as shown on the defined-traffic aisle layout.
14.10 Floor flatness and levelness shall be measured in accordance with ASTM E1155 within 72 hours after the completion of finishing of each placement and before the placement is loaded.
NOTE Measured later than 72 hours, the survey records curling at the joints rather than the surface the finishers produced, and a slab that was within tolerance when it was finished can then fail a test that no finishing could have passed; measuring early fixes responsibility for the as-finished surface on the finishing crew and for later curling on the mixture and the curing. (14.11)
14.12 Levelness shall not be applied to a slab placed on a designed slope, and such areas shall be evaluated for flatness only and for conformance to the slope shown on the floor drainage plan.
14.13 Test sections outside the specified tolerances shall be corrected by grinding, by removal and replacement, or by another method the Engineer of Record accepts in writing, at the Contractor's cost.

15 Placement and Finishing Coordination

15.1 Pre-Placement Verification

15.1.1 Immediately before concrete is placed in each slab area, the Contractor shall verify and record the items indicated in the datasheet.
Verification Required Before Slab Concrete Is Placedcheckbox
☑ Subbase surface is surveyed, accepted, and within tolerance
☑ Subbase or subgrade surface is damp with no free water, mud, ice, or frozen material
☑ Vapor retarder is complete, lapped, sealed at penetrations, and repaired
☐ Reinforcement or fiber dosage matches the placing drawings and the mixture submittal
☑ Reinforcement is at its specified depth on supports at the specified spacing
☑ Dowels are aligned and baskets are staked with shipping wires cut
☑ Isolation joint filler is in place at every column, wall, pad, pit, and penetration
☑ Edge forms and bulkheads are set to line and grade and braced
☐ Embedded items, sleeves, and anchor rods are set and secured
☑ Saw, blades, and crew are on site and the sawing window is agreed
☑ Curing materials are on site in the quantity the placement needs
☐ Testing agency technician is present at the point of discharge
15.1.2 Concrete shall not be placed until every deficiency found in the verification has been corrected.
15.1.3 The verification record shall identify the placement, the date, and the person who performed it.

15.2 Placement Sequence and Strike-Off

15.2.1 Slab concrete shall be placed in the sequence, within the limits, and by the strike-off method the accepted placement plan states.
15.2.2 Each panel bounded by construction joints shall be placed continuously, without a cold joint within the panel.
15.2.3 Equipment and personnel routes across the vapor retarder and the placed reinforcement shall be limited to those the placement plan shows, and reinforcement displaced by traffic shall be restored to position before the concrete reaches it.
NOTE The strike-off method is what the F-numbers are bought with. A laser-guided screed or a vibrating truss screed riding on set forms produces a flat strip; hand strike-off from wet screeds produces whatever the screed-setter's eye produces. Long narrow placement strips with the screed riding on hard edge forms are how a tight tolerance is reached, and a wide placement finished from the middle is how a loose one is. (15.2.4)

15.3 Finishing and Curing

15.3.1 Finishing and curing of the slab shall be performed under Concrete Curing And FinishingConcrete Curing and FinishingResolves to the current adopted revision.sync/concrete-curing-and-finishing, with the finish and the curing method that standard assigns to the scheduled floor covering.
15.3.2 Water shall not be added to the surface to aid finishing.
15.3.3 Finishing operations shall not begin while bleed water is present on the surface.
NOTE Troweling bleed water back into the surface traps it under a dense skin, and the blisters and delaminations that result appear weeks later as the trapped water tries to leave. The finishers' waiting for the sheen to go is the step most often skipped on a cold day and most often regretted. (15.3.4)

15.4 Protection and Loading

15.4.1 Rubber-tired construction equipment shall not operate on the slab, and no material shall be stockpiled on it, until the slab concrete has attained the fraction of its specified compressive strength indicated in the datasheet, demonstrated by field-cured specimens from that placement or by the maturity method.
Fraction of Specified Compressive Strength Before Construction Trafficrange
Not less than
%
5060707580100
NOTE Early loading drives a wheel across joints that have not yet been cut or filled and over concrete that has not reached the strength the dowels bear on, and the joint edges it breaks are the ones the finished floor will show for its life. (15.4.2)
15.4.3 Saw cuts shall be kept free of debris, and shall be covered or taped where other trades work over the slab, until the joints are filled.
15.4.4 The slab surface shall be protected from staining, impact, point loads, and the dragging of steel and equipment until the slab work is accepted.

16 Field Quality Control

16.1 The thickness of each placement shall be verified by comparing the subbase surface survey with the finished floor survey at the same grid points.
16.2 Where the survey comparison indicates a thickness below the tolerance of ACI 117, the Engineer of Record shall direct cores at the locations and number the Engineer of Record selects, taken and tested at the Contractor's cost.
16.3 Random cracks wider than the width indicated in the datasheet shall be reported to the Engineer of Record, who shall direct their evaluation and repair under Concrete Repair And RestorationConcrete Repair and RestorationResolves to the current adopted revision.sync/concrete-repair-and-restoration.
Random Crack Width Above Which the Crack Is Reportedrange
Not more than
in
0.0040.0080.0120.0160.020.03
NOTE A hairline crack in a bare warehouse floor is a cosmetic record of where the shrinkage went; the same crack beneath a resilient tile or an epoxy coating telegraphs through the finish and keeps moving under it, which is why the width at which a crack is reported is set by what the floor will carry rather than by the structural significance of the crack, which for a slab on ground is usually nil. (16.4)
16.5 The cost of evaluating and repairing a random crack attributable to late sawing, inadequate curing, premature loading, or a defect in the subbase placed under this standard shall be borne by the Contractor, and the Engineer of Record shall make the initial determination of the cause.
16.6 Joints shall be inspected for spalling, raveling, and curling before they are filled, and the inspection shall be recorded in the joint filling record.

17 Delivery, Storage, and Handling

17.1 Reinforcing steel for the slab shall be delivered, stored, and handled under Concrete ReinforcementConcrete ReinforcementResolves to the current adopted revision.sync/concrete-reinforcement.
17.2 Fibers shall be delivered in the manufacturer's packaging in the quantity per package the batching procedure relies on, and shall be stored dry until batched.
17.3 Dowels, plate dowels, baskets, and sleeves shall be stored off the ground, with debonding coatings intact and free of rust that reduces the section or roughens the sliding surface.
17.4 Joint filler and sealant shall be stored within the temperature limits the manufacturer publishes and shall not be used past the published shelf life.
17.5 Preformed compressible filler shall be stored flat and protected from moisture and crushing.

18 Warranty

18.1 The Contractor shall warrant the slab work against defects in materials and workmanship for the period indicated in the datasheet, running from the date of substantial completion.
Installation Warranty Periodrange
Not less than
years
123510
18.2 The warranty shall cover random cracking wider than the reporting width, spalling or raveling of joint edges, separation, splitting, or debonding of joint filler and sealant, curling that lifts a joint edge beyond the local levelness tolerance, and settlement of the slab attributable to the subbase placed under this standard.
18.3 The warranty shall not cover damage caused by loads exceeding the design basis recorded on the contract documents, by vehicle or equipment impact, by settlement of a subgrade prepared under a scope other than the Contractor's, or by chemical attack the slab was not designed to resist.
18.4 Whether the Contractor returns within the warranty period to refill joints shall be as indicated in the datasheet.
Joint Refill Visit Within the Warranty Periodradio
○ Required once, after the first year of the warranty period
○ Not required
NOTE Joint filler installed at an age of a few months is installed into a joint that is still opening, and some separation from the joint face is the expected result rather than a defect; a scheduled return to refill the separated joints after the first year costs a day of work and leaves the floor with filler that is bonded to the joint it will serve, where leaving it to the warranty claim process costs the same work plus the dispute over whether the separation is a defect. (18.5)
18.6 Where a warranty repair is performed, the repaired work shall be warranted for the full original warranty period running from the date of the repair, or for the remainder of the original period, whichever ends later.
18.7 The Contractor shall bear the cost of a warranty repair and of removing and reinstalling floor covering, racks, and equipment to gain access for it, except where the Owner's own forces caused the condition repaired.