Snow Melt Systems
Contents
- 1Scope
- 1.1Boundary of Work
- 1.2Terms Used in This Standard
- 2Referenced Standards
- 3Submittals
- 3.1Action Submittals
- 3.2Closeout Submittals
- 4Quality Assurance
- 4.1Installer Qualifications
- 4.2Product Conformance and Listing
- 4.3Pre-Placement Conference
- 5Design Basis
- 5.1Heat Source
- 5.2Snow Melting Class
- 5.3Design Surface Heat Flux
- 6Hydronic Circuit
- 6.2Tubing
- 6.3Circuit Hydraulics
- 6.4Heat Transfer Fluid
- 6.5Manifolds
- 7Electric Heating Elements
- 7.2Heating Element Form
- 7.3Electrical Supply and Protection
- 7.4Cold Leads and Connections
- 8Controls
- 8.1Control Type
- 8.2Setpoints and Sequence
- 8.3Control Panel Enclosure
- 9Pavement Assembly and Embedment
- 9.1Insulation Beneath the Heated Pavement
- 9.2Embedment Depth and Attachment
- 10Testing
- 10.1Hydronic Tubing Pressure Test
- 10.2Electric Insulation Resistance Test
- 10.3Functional Test
- 11Installation
- 11.1Placement Sequence
- 11.2Record Drawings
- 12Delivery, Storage, and Handling
- 13Warranty
- 14Spare Parts
Download
Build a datasheet from this standard
Start a project with this standard already attached — one click, no setup.
Use in a project
1 Scope
1.1 Boundary of Work
NOTE This standard governs the elements that heat an outdoor pavement from within: the hydronic tubing or the electric heating cable or mat embedded in it, the manifolds or the power connections at its edge, the sensors and the controller that decide when it runs, the insulation beneath it, and the tests that prove the embedded element before the pavement closes over it. It begins at the manifold connections or the junction boxes at the pavement edge and ends at the finished surface. (1.1.1)
NOTE The surfaces in scope are walks, plazas, entrance aprons, exterior stairs and ramps, accessible routes, drives, loading dock approaches, and parking aprons, whether finished in cast-in-place concrete, asphalt, or unit pavers over a concrete or aggregate base. (1.1.2)
NOTE A snow melt element is the one part of a pavement that cannot be reached after the pavement is placed. Every other defect in a hardscape is repaired by cutting out a panel; a tube or cable that was crushed by a vibrator, nicked by a saw, or never tested is found in the first storm and is repaired by removing the pavement. The weight this standard gives to layout, attachment, cover, and testing before placement follows from that. (1.1.3)
NOTE The plant that supplies a hydronic circuit, the piping that reaches the manifold, the electrical distribution that reaches the junction box, and the pavement itself are each governed by their own standard. This standard states what it needs from each at the boundary and does not restate them. (1.1.4)
- De-icing cable on roofs, in gutters, and in downspouts, and trace heating of piping and vessels: Electric Heat TracingElectric Heat TracingResolves to the current adopted revision.sync/electric-heat-tracing.
- Boilers, heat exchangers, circulating pumps, and expansion tanks and air separators of the hydronic plant: BoilersBoilersResolves to the current adopted revision.sync/boilers, Heat ExchangersHeat ExchangersResolves to the current adopted revision.sync/heat-exchangers, HVAC PumpsHVAC PumpsResolves to the current adopted revision.sync/hvac-pumps, and Expansion Tanks And Air SeparatorsExpansion Tanks and Air SeparatorsResolves to the current adopted revision.sync/expansion-tanks-and-air-separators.
- The distribution piping between the plant and the snow melt manifold, its joints, and its pressure test: Hydronic PipingHydronic PipingResolves to the current adopted revision.sync/hydronic-piping.
- Balancing valves, strainers, and the glycol makeup package: Hydronic SpecialtiesHydronic SpecialtiesResolves to the current adopted revision.sync/hydronic-specialties.
- Cleaning, flushing, passivation, and the initial glycol charge of the loop: Hydronic Cleaning And FlushingHydronic System Cleaning and FlushingResolves to the current adopted revision.sync/hydronic-cleaning-and-flushing.
- Interior radiant floor heating: Radiant Heating And Cooling PanelsRadiant Heating and Cooling PanelsResolves to the current adopted revision.sync/radiant-heating-and-cooling-panels.
- The concrete pavement, its mixture, jointing, finishing, and curing: Concrete PavingConcrete Paving, Curbs, and SidewalksResolves to the current adopted revision.sync/concrete-paving; the asphalt pavement: Asphalt PavingAsphalt PavingResolves to the current adopted revision.sync/asphalt-paving; the permeable paver section: Permeable PavingPermeable PavingResolves to the current adopted revision.sync/permeable-paving.
- Branch circuit conductors and raceways to the junction boxes, and the panelboard that supplies them: Conductors And CablesConductors and CablesResolves to the current adopted revision.sync/conductors-and-cables, Raceways And ConduitRaceways and ConduitResolves to the current adopted revision.sync/raceways-and-conduit, and PanelboardsPanelboardsResolves to the current adopted revision.sync/panelboards.
- The building automation system that supervises the snow melt controller: Building Automation SystemBuilding Automation SystemResolves to the current adopted revision.sync/building-automation-system.
- Firestopping where tubing, leads, or conduit enter the building through a rated assembly: FirestoppingFirestoppingResolves to the current adopted revision.sync/firestopping.
- Functional performance testing under the commissioning plan: CommissioningTotal Building CommissioningResolves to the current adopted revision.sync/commissioning.
1.1.5 The extent of each heated area, the circuit boundaries, and the locations of the manifolds and junction boxes shall be as indicated on the snow melt plan.
1.1.6 The pavement in which the elements of each heated area are embedded shall be as indicated on the civil paving plans and sections.
1.2 Terms Used in This Standard
NOTE The following terms carry the meanings given here throughout this standard: (1.2.1)
- Snow melting class: the performance classification of ASHRAE Handbook, HVAC Applications, Snow Melting and Freeze Protection, from Class I, which allows snow to accumulate on the surface during a storm and melts it afterward, through Class II, which keeps the surface passable with some accumulation during heavy snowfall, to Class III, which keeps the surface free of snow and ice throughout the storm
- Snow-free area ratio: the fraction of the heated surface kept free of snow during the design storm, which the handbook fixes at 0 for Class I, 0.5 for Class II, and 1.0 for Class III
- Design frequency: the percentage of the annual snowfall hours at the design station during which the design heat flux is not exceeded
- Design surface heat flux: the heat delivered at the pavement surface, in Btu/h·ft², that the snow melting class and the design frequency require at the design station, before the losses from the back and edges of the pavement are added
- Idle mode: operation of the system between storms at a reduced output that holds the pavement at a set temperature so that melting begins without a cold start
- After-run: continued operation after the sensor reports the surface dry or the precipitation ended, so that meltwater evaporates rather than refreezing
- Ground-fault protection of equipment: a residual-current trip that de-energizes a circuit when the leakage current reaches the setting, intended to protect the heating element and the pavement, and distinct from the personnel protection of a ground-fault circuit interrupter
2 Referenced Standards
2.1 Equipment, materials, and installation shall comply with the latest adopted edition of each of the following unless a specific edition is cited.
2.2 Where referenced standards conflict, the more stringent requirement shall govern unless the Engineer of Record directs otherwise in writing.
| Standard | Title |
|---|---|
| ASHRAE Handbook, HVAC Applications | Snow Melting and Freeze Protection |
| NFPA 70 | National Electrical Code (Article 426, Fixed Outdoor Electric Deicing and Snow-Melting Equipment) |
| UL 515 | Electrical Resistance Trace Heating for Commercial Applications |
| UL 1673 | Electric Space Heating Cables |
| IEEE 515.1 | Testing, Design, Installation, and Maintenance of Electrical Resistance Trace Heating for Commercial Applications |
| NEMA 250 | Enclosures for Electrical Equipment (1000 Volts Maximum) |
| ASTM F876 | Crosslinked Polyethylene (PEX) Tubing |
| ASTM F877 | Crosslinked Polyethylene (PEX) Hot- and Cold-Water Distribution Systems |
| ASTM F2623 | Polyethylene of Raised Temperature (PE-RT) SDR 9 Tubing |
| ASTM F1960 | Cold Expansion Fittings with PEX Reinforcing Rings for Use with Crosslinked Polyethylene (PEX) Tubing |
| ASTM F1807 | Metal Insert Fittings Utilizing a Copper Crimp Ring for SDR9 Crosslinked Polyethylene (PEX) Tubing and SDR9 Polyethylene of Raised Temperature (PE-RT) Tubing |
| ASTM C578 | Rigid, Cellular Polystyrene Thermal Insulation |
| ASTM D3321 | Use of the Refractometer for Field Test Determination of the Glycol-Base Concentration of Engine Coolant |
| ASTM D1177 | Freezing Point of Aqueous Engine Coolants |
3 Submittals
3.1 Action Submittals
3.1.1 The Contractor shall submit the following for the Engineer of Record's review and return before any tubing, heating cable, mat, manifold, or controller is ordered:
- Product data for the tubing or the heating cable or mat, the manifolds or the power connection kits, the controller, the sensors, the insulation, and the heat transfer fluid, each with its listing or its product standard conformance
- A heat flux calculation for each heated area, stating the snow melting class, the design frequency, the design station and its weather data, the resulting design surface heat flux, the back and edge loss allowance, and the installed output
- For a hydronic system, a circuit schedule listing every circuit with its length, its design flow, its pressure drop, and its manifold connection, with the supply temperature, the temperature drop, and the glycol type and concentration the schedule assumes
- For an electric system, a circuit schedule listing every heating circuit with its element type, its length or its mat dimensions, its supply voltage, its rated wattage and amperage, its branch circuit, and the ground-fault protection device that serves it
- Shop drawings showing the layout of every circuit to scale, the spacing, the depth below the finished surface, the manifold, junction box, and sensor locations, the insulation extent, and every pavement joint overlaid on the layout, with each joint crossing detailed
- The controller sequence of operation, with the activation, after-run, idle, and high limit setpoints the controller will be shipped with, and the points exposed to the building automation system
- For a hydronic system, the freeze point of the glycol solution at the selected concentration, from the fluid supplier's published table
- The qualifications of the installer and, for an electric system, of the electrician who will make the connections
Action Submittals Requiredcheckbox
☑ Product data with listings
☑ Heat flux calculation per heated area
☑ Hydronic circuit schedule
☑ Electric circuit schedule
☑ Circuit layout shop drawings with joints overlaid
☑ Controller sequence of operation and setpoints
☑ Glycol freeze point at the selected concentration
☑ Installer and electrician qualifications
3.1.2 No embedded element shall be placed in a pavement until the shop drawings for that heated area have been returned by the Engineer of Record.
NOTE The shop drawing with the joints overlaid is the submittal that prevents the common failure. A contraction joint sawn across a tube cuts it, an isolation joint that a cable bridges without a sleeve shears it when the panels move, and neither is visible once the pavement is finished. The overlay is where those crossings are found while the layout can still be moved. (3.1.3)
3.2 Closeout Submittals
3.2.1 The Contractor shall submit the following before the work of this standard is accepted:
- Record drawings of each heated area, dimensioned from fixed site features, showing the as-installed route of every circuit, its identification, the depth below the finished surface, and the manifold, junction box, splice, and sensor locations
- A photographic record of every heated area taken after the elements were secured and before the pavement was placed, with a dimensioned reference in each frame
- The pressure test record for each hydronic circuit, or the insulation resistance and element resistance record for each electric circuit, at each stage this standard requires
- The functional test record
- Operation and maintenance data, including the sequence of operation, the setpoints as left, the glycol type, concentration, and freeze point, and the seasonal startup and shutdown procedure
- Warranty documentation for the embedded elements, the controller, and the sensors
Closeout Submittals Requiredcheckbox
☑ Record drawings of each heated area
☑ Photographic record before pavement placement
☑ Pressure test or insulation resistance records at each stage
☑ Functional test record
☑ Operation and maintenance data
☑ Warranty documentation
NOTE The record drawing and the photographs are the only map of an element that no one will see again. A future core, a bollard footing, a sign post, or a utility repair in a heated pavement is located against them, and a pavement without them is a pavement no one can safely cut. (3.2.2)
4 Quality Assurance
4.1 Installer Qualifications
4.1.1 Hydronic tubing, manifolds, and the circuit connections shall be installed by an installer trained by the tubing manufacturer for embedded snow melt installation, who shall submit the manufacturer's current training certificate.
4.1.2 Electric heating cable and mats shall be laid out and secured by the installer and shall be connected, tested, and energized by an electrician licensed in the jurisdiction, working to the manufacturer's installation instructions.
4.1.3 The installer shall have installed not less than three embedded snow melt systems of the selected heat source within the preceding five years, and shall submit those project references on request.
4.1.4 Where the parties disagree whether a reference project is comparable, the Engineer of Record shall make the initial determination.
4.2 Product Conformance and Listing
4.2.1 PEX tubing shall conform to ASTM F876 and ASTM F877, and PE-RT tubing shall conform to ASTM F2623, each marked by the manufacturer with the standard, the size, the pressure and temperature rating, and the oxygen barrier where one is furnished.
4.2.2 Electric heating cable and mats shall be listed by a nationally recognized testing laboratory for embedded deicing and snow melting use under UL 515 or UL 1673 as applicable to the product, and the listing shall name the pavement material in which the product is embedded.
4.2.3 Electric heating elements embedded in asphalt shall be listed for asphalt embedment at the placement temperature of the asphalt, and an element not so listed shall not be placed in asphalt.
4.2.4 Every electric heating element, power connection kit, splice kit, end seal, and controller in a heating circuit shall be a component of one manufacturer's listed system.
4.2.5 The electric installation shall comply with Adopted Electrical CodeAdopted Electrical CodeParameterEach project supplies its own value.adopted-electrical-code and with the amendments of the Authority Having Jurisdiction, and shall be made available for the inspections that authority requires.
NOTE The listing is what proves the element survives the pavement. An asphalt lift is placed at a temperature that softens the insulation on a cable listed only for concrete, and a mat whose listing names concrete has not been evaluated for the compaction loads of a paver bed. The listing names the material because the material is the test condition. (4.2.6)
4.3 Pre-Placement Conference
4.3.1 Before the elements of any heated area are laid out, the Contractor shall convene a conference attended by the snow melt installer, the pavement contractor, the electrician where the system is electric, the mechanical contractor where the system is hydronic, and the Engineer of Record.
4.3.2 The conference agenda shall cover the circuit layout against the pavement joint plan, the depth below the finished surface and how it will be held during placement, the attachment method, the pavement placement method and the equipment that will run over the elements, the hold points at which the Engineer of Record is notified, and the test required at each stage.
4.3.3 The decisions settled at the conference shall be recorded in the minutes and shall be incorporated into the shop drawings before layout begins.
5 Design Basis
5.1 Heat Source
5.1.1 The heat source of each snow melt system shall be as indicated in the datasheet.
Heat Sourceradio
○ Hydronic, glycol solution in embedded tubing
○ Electric, resistance heating cable or mat
NOTE No heat source is the norm across projects, because the answer follows the plant and the area. A hydronic system has a higher first cost in tubing, manifolds, and the plant that serves it, and a lower operating cost wherever a fuel-fired or waste-heat source is available, and it is the usual choice for a large area on a site that already has a hydronic plant or where one is being installed. An electric system has a lower first cost, no plant, no fluid, and no freezing risk when it is off, and a higher operating cost at any electricity price above the cost of fuel heat, and it draws a connected load that a large area can push past the available service. It is the usual choice for a small area, for a site without a hydronic plant, and for a retrofit where tubing cannot be run back to a plant. (5.1.2)
5.2 Snow Melting Class
5.2.1 The snow melting class of each heated area shall be as indicated in the datasheet.
Snow Melting Classselect
Class I
Class II
Class III
NOTE The class sets the snow-free area ratio and, with the design frequency, the design heat flux, so it is the first design decision and the one the output follows from. Class I, with a snow-free area ratio of 0, lets snow accumulate during the storm and melts it afterward, at the lowest output and the lowest operating cost, and suits a surface that can be closed during a storm. Class II, with a ratio of 0.5, keeps the surface passable during all but the heaviest snowfall at a moderate output, and suits walks, plazas, and drives that are in use through a storm. Class III, with a ratio of 1.0, keeps the surface free of snow and ice throughout the storm at the highest output, and suits a surface where any accumulation is a hazard or a stoppage: an emergency entrance, an accessible ramp, a loading dock on a slope, a helipad approach. No class is the norm across projects, because the same project often holds a Class III ramp beside a Class II walk. (5.2.2)
5.2.3 The design frequency of each heated area shall be as indicated in the datasheet.
Design Frequencyrange
Not less than
%
7590959899
5.3 Design Surface Heat Flux
5.3.1 The design surface heat flux of each heated area shall be the value indicated in the datasheet, calculated in accordance with ASHRAE Handbook, HVAC Applications, Snow Melting and Freeze Protection.
Design Surface Heat Fluxrange
Not less than
Btu/h·ft²
50400
Derived — the snow melting class, the design frequency, and the ASHRAE Handbook design data for the snow melting station nearest the site (by default)
NOTE The surface flux follows from the class, the frequency, and the station, so it is derived rather than chosen. The handbook tabulates, for each listed station and each class, the surface flux not exceeded at each frequency, and a calculation from the local snowfall rate, air temperature, wind speed, and humidity gives the same answer for a site that is not listed. The value is the flux at the surface; the installed output of the tubing or the cable is that flux plus the losses from the back and the edges of the pavement, which depend on the insulation selected under this standard. (5.3.2)
5.3.3 The installed output of each heated area shall be not less than the design surface heat flux plus the back and edge losses calculated for the pavement section and the insulation selected, and the calculation shall state the loss allowance used.
5.3.4 Where the heat source is electric, the installed watt density shall be the installed output converted at 3.412 Btu/h per watt, and shall not exceed 120 W/ft² of heated area, the limit of NFPA 70 426.20(A).
5.3.5 Where the heat source is hydronic, the tubing spacing, the depth below the finished surface, the supply temperature, and the circuit flow shall together deliver the installed output at the design surface temperature, as shown in the heat flux calculation.
6 Hydronic Circuit
NOTE Requirements in this section apply where the heat source selected under Design Basis is hydronic. (6.1)
6.2 Tubing
6.2.1 The tubing material shall be as indicated in the datasheet.
Tubing Materialselect
PEX-a
PEX-b
PEX-c
PE-RT
NOTE The three PEX types differ in the crosslinking process and in the result. PEX-a is crosslinked in the melt and is the most flexible of the four, bends to the tightest radius, recovers from a kink when heated, and is joined by cold expansion fittings under ASTM F1960; it carries the highest price. PEX-b is crosslinked after extrusion by moisture cure, is stiffer, is joined by crimp or clamp fittings under ASTM F1807, and costs less. PEX-c is crosslinked by electron beam and sits between the two in flexibility and price. PE-RT is not crosslinked, is as flexible as PEX-b, can be joined by heat fusion, and is rated under ASTM F2623 for the temperature and pressure of a snow melt circuit. No material is the norm across projects, because the choice turns on the fitting system the manifold uses and on the bend radius the layout needs at the circuit ends. (6.2.2)
6.2.3 Tubing shall be furnished with an oxygen diffusion barrier as indicated in the datasheet.
Oxygen Diffusion Barrierradio
● Barrier tubing
○ Non-barrier tubing
NOTE Oxygen diffuses through the wall of an unbarriered polyolefin tube and into the fluid, where it corrodes every ferrous component in the loop: the pump volute, the expansion tank, the heat exchanger shell, the manifold where it is steel. A barrier layer in the tube wall stops that, and nearly every snow melt circuit is connected to a plant that contains ferrous parts, which is why barrier tubing is the default. Non-barrier tubing is chosen where the whole loop, plant included, is non-ferrous or where the fluid treatment program under HVAC Water TreatmentHVAC Water TreatmentResolves to the current adopted revision.sync/hvac-water-treatment is designed to scavenge the oxygen. (6.2.4)
6.2.5 The tubing nominal size shall be as indicated in the datasheet.
Tubing Nominal Sizerange
in
0.50.6250.751
6.2.6 The tubing spacing on centers shall be as indicated in the datasheet.
Tubing Spacing on Centersrange
in
46891012
NOTE Size and spacing are selected together with the supply temperature and the depth, and the heat flux calculation is where the combination is proved. A larger tube carries more flow at the same pressure drop and allows a longer circuit and a smaller manifold, and costs more per foot; a smaller tube bends more easily at the circuit ends. Closer spacing delivers more output at a given supply temperature and evens the surface temperature between the tubes, at more tube per square foot; wider spacing suits a low output class and a deeper embedment, where the pavement spreads the heat before it reaches the surface. Neither value has a norm across projects. (6.2.7)
6.2.8 Each circuit shall be one continuous length of tubing from the supply manifold to the return manifold, and no fitting, coupling, or splice shall be embedded in the pavement.
6.2.9 Where a tube is damaged before the pavement is placed, the circuit shall be replaced in its entirety, and the damaged tube shall not be repaired with an embedded coupling.
6.2.10 Tubing shall be rated by its manufacturer for continuous service at the design supply temperature and the system working pressure, and for the glycol type and concentration selected under Heat Transfer Fluid.
6.3 Circuit Hydraulics
6.3.1 The circuit length shall not exceed the value indicated in the datasheet.
Circuit Lengthrange
Not more than
ft
150200250300350400500600700
Derived — the tubing nominal size, the design flow per circuit, and the circuit pressure drop limit stated in the heat flux calculation (by default)
6.3.2 Circuits served from one manifold shall be of lengths within 10 percent of one another, or shall be balanced at the manifold so that each circuit receives its design flow.
NOTE The circuit length is a consequence of the tube size and the flow the output demands, which is why it is derived. A circuit that is too long for its tube either starves at the design flow or needs a pump head the plant was not sized for, and a manifold that serves circuits of unequal length delivers most of the flow to the shortest unless each is balanced. Keeping the circuits on a manifold within a narrow band of length is what makes the balancing valves able to even the flow without throttling one circuit to a trickle. (6.3.3)
6.3.4 The design supply temperature of each system shall be as indicated in the datasheet.
Design Supply Temperaturerange
°F
90160
Per drawings — the snow melt system schedule on the mechanical drawings (deferred by default)
6.3.5 The design circuit temperature drop of each system shall be as indicated in the datasheet.
Design Circuit Temperature Droprange
°F
1040
Per drawings — the snow melt system schedule on the mechanical drawings (deferred by default)
NOTE The supply temperature and the temperature drop are system-sized quantities that the mechanical engineer sets with the plant, the tube spacing, and the depth, and they sit on the schedule beside the flow and the head the plant has to deliver. A high supply temperature lets wider spacing or deeper embedment reach the output, and is limited by the tube rating and by the thermal stress it puts into the pavement; a large temperature drop reduces the flow and the pump but leaves the return end of each circuit cooler than the supply end, which shows as a strip that melts last. (6.3.6)
6.4 Heat Transfer Fluid
6.4.1 The glycol type of the snow melt loop shall be as indicated in the datasheet.
Glycol Typeradio
● Inhibited propylene glycol
○ Inhibited ethylene glycol
NOTE Propylene glycol is the default because a snow melt loop lies under a surface that people, pets, and stormwater cross, and a leak from it reaches the ground. Propylene glycol is of low toxicity and is the fluid most jurisdictions accept near a storm inlet or a planting bed; it is more viscous than ethylene glycol at the same freeze point, so it carries more pumping power and a lower heat transfer coefficient. Ethylene glycol transfers heat better and pumps more easily, and is toxic if ingested, so it is chosen where the loop is isolated from the ground and from any potable connection and the Owner accepts the handling requirements. (6.4.2)
6.4.3 The glycol concentration by volume of the snow melt loop shall be as indicated in the datasheet.
Glycol Concentration by Volumerange
%
3060
Derived — the freeze protection required at Site Ambient Temperature MinimumSite Ambient Temperature MinimumParameterEach project supplies its own value.site-ambient-temperature-minimum, from the fluid supplier's published freeze point table (by default)
NOTE The concentration follows from the site's minimum temperature and the fluid supplier's table, so it is derived rather than chosen. A snow melt loop is unlike a building loop in that it sits idle in a pavement at the outdoor temperature for days at a time, so it is protected to the freeze point, at which no ice crystals form, rather than to the burst point, at which slush is tolerated, because slush in a tube under a pavement blocks the circuit at the moment the system is called on. Each additional five percent of glycol lowers the heat transfer and raises the pumping power, which is why the concentration is taken from the table rather than rounded up. (6.4.4)
6.4.5 The glycol shall be an inhibited formulation intended for closed hydronic service, and uninhibited or automotive glycol shall not be used.
6.4.6 Where the snow melt loop is served from a hydronic system that does not itself carry the glycol solution selected here, a heat exchanger furnished under Heat ExchangersHeat ExchangersResolves to the current adopted revision.sync/heat-exchangers shall separate the two fluids, and the glycol type and concentration selected here shall apply to the snow melt side only.
6.4.7 The initial glycol charge, the verification of the concentration by refractometer under ASTM D3321, and the freeze point under ASTM D1177 shall be performed under Hydronic Cleaning And FlushingHydronic System Cleaning and FlushingResolves to the current adopted revision.sync/hydronic-cleaning-and-flushing against the type and concentration selected here.
6.5 Manifolds
6.5.1 The manifold location shall be as indicated in the datasheet.
Manifold Locationselect
Heated space within the building
Below-grade vault at the pavement edge
Above-grade insulated enclosure at the pavement edge
NOTE A manifold inside the building is protected from freezing, flooding, and traffic and is reached from the mechanical room, and it needs the supply and return legs of every circuit to run back through the wall, which lengthens each circuit by the distance from the pavement to the manifold and fixes the circuit count the wall penetration can carry. A below-grade vault at the pavement edge keeps the circuits short and the manifold out of sight, and it sits at the outdoor temperature, collects water unless it drains, and is reached through a lid that must carry the traffic over it. An above-grade enclosure is reached without lifting a lid and stays above the water, and it stands in the hardscape where it is seen and struck. No location is the norm across projects. (6.5.2)
6.5.3 Each manifold shall be furnished with the accessories indicated in the datasheet.
Manifold Accessoriescheckbox
☑ Isolation valve on each circuit supply and return
☑ Balancing valve with flow indicator on each circuit
☑ Purge and drain valve on each manifold
☑ Manual air vent on each manifold
☑ Supply and return thermometers
☐ Supply and return pressure gauges
NOTE The isolation valves are what let a circuit be found and shut off when it leaks, the balancing valves are what even the flow across circuits of unequal length, and the purge valves are what let each circuit be filled and bled on its own; without them a manifold of ten circuits is filled by chasing air from one circuit into the next. The thermometers show the operator whether the loop is delivering the design temperature drop, which is the one reading that distinguishes a plant problem from a circuit problem. (6.5.4)
6.5.5 Manifolds shall be of brass, stainless steel, or an engineered polymer rated by the manufacturer for the glycol type and concentration selected and for the design supply temperature, and shall have circuit connections of the fitting system the tubing manufacturer lists for the tubing selected.
6.5.6 Where a manifold is in a vault or an enclosure at the pavement edge, the vault or enclosure shall drain to daylight or to a storm connection, shall be insulated on every face, and shall have a lid or door rated for the traffic over it.
6.5.7 Where a manifold is outside the building, the supply and return piping between the building and the manifold shall be insulated and shall carry the glycol solution selected under this standard, so that no water-filled section lies outdoors.
6.5.8 Each circuit shall be tagged at the manifold with the circuit identification shown on the record drawings.
7 Electric Heating Elements
NOTE Requirements in this section apply where the heat source selected under Design Basis is electric. (7.1)
7.2 Heating Element Form
7.2.1 The heating element form shall be as indicated in the datasheet.
Heating Element Formselect
Single-conductor constant-wattage cable, cut to a designed length
Twin-conductor constant-wattage cable, fixed output per foot
Self-regulating parallel-resistance cable
Mineral-insulated metal-sheathed cable, factory terminated
Factory-assembled mat with cable at a fixed spacing
NOTE A single-conductor constant-wattage cable is a series resistor whose output depends on its length, so each circuit is cut to the length the design calls for and both ends return to the junction box; it gives the designer the most freedom and the installer the most to get wrong. A twin-conductor cable has both conductors in one jacket, delivers a fixed output per foot at its rated voltage, and terminates at one end, which simplifies the layout. A self-regulating cable reduces its output as it warms, which limits the slab temperature and lets the cable be overlapped, at a higher cost per foot and a startup inrush the circuit has to carry. A mineral-insulated cable has a metal sheath and is rated for the highest asphalt placement temperatures and for direct burial, and it is factory terminated to length and cannot be cut in the field. A mat carries cable pre-spaced on a mesh and is unrolled over the area, which is the fastest installation on a regular shape and the hardest to fit around an obstruction. No form is the norm across projects. (7.2.2)
7.2.3 Each heating cable or mat shall be marked by its manufacturer at the intervals its listing requires with the product identification, the rated voltage, and the rated output per foot or per square foot.
7.2.4 Heating cable shall not be cut, shortened, or spliced in the field except as the manufacturer's listing permits, and the resistance of each cut-to-length circuit shall be verified against the design value before the cable is secured.
7.2.5 Adjacent runs of heating cable shall be spaced not less than 1 in on centers, and a cable shall not cross or overlap itself unless the listing permits it.
7.3 Electrical Supply and Protection
7.3.1 The supply voltage of the heating circuits shall be as indicated in the datasheet.
Heating Circuit Supply Voltagerange
V
120208240277347480600
Per drawings — the panel schedules on the electrical drawings (deferred by default)
7.3.2 Snow melt heating circuits shall be treated as continuous loads, and the branch circuit conductors and the overcurrent device shall be rated for not less than 125 percent of the connected load.
7.3.3 Each branch circuit supplying embedded snow melt equipment shall be provided with ground-fault protection of equipment in accordance with NFPA 70 426.28, with a trip setting of 30 mA unless the heating element manufacturer's listing requires a different setting.
NOTE Ground-fault protection of equipment is set at 30 mA, not the 5 mA of personnel protection, because a long embedded heating cable has a capacitive leakage that trips a 5 mA device on a dry day. A 30 mA trip still opens the circuit when the insulation on a cable in the pavement breaks down, which is the fault the protection exists to catch before the cable burns open and the pavement is cut to find it. (7.3.4)
7.3.5 Each snow melt system shall have a disconnecting means in accordance with NFPA 70 426.50 that opens every ungrounded conductor of the heating circuits and the controller, located within sight of the controller or lockable in the open position.
7.3.6 Caution markings identifying the presence of embedded electric snow melting equipment shall be posted in accordance with NFPA 70 426.13 at the controller and at each junction box at the pavement edge.
7.3.7 The connected load of each electric snow melt system shall be confirmed against the service and panelboard capacity shown on the electrical drawings before the heating elements are ordered, and the Contractor shall report any shortfall to the Engineer of Record in writing.
NOTE A heated area at the watt density Class II or III demands draws a load that is easy to underestimate: a few thousand square feet at the upper end of the common density range is a load in the hundreds of amperes, running through the night of a storm. The confirmation is required before ordering because a shortfall found after the cable is in the pavement is corrected by a service upgrade. (7.3.8)
7.4 Cold Leads and Connections
7.4.1 Each heating circuit shall terminate in a factory-made or listed field-assembled power connection with nonheating cold leads, and the transition from the heating section to the cold lead shall be located within the pavement where the listing requires it or in the junction box where the listing permits it.
7.4.2 Cold leads shall leave the pavement in a raceway in accordance with NFPA 70 426.22, bushed at the pavement end, sized for the leads it carries, and routed to a junction box at the pavement edge, and the raceway from the junction box onward shall be furnished under Raceways And ConduitRaceways and ConduitResolves to the current adopted revision.sync/raceways-and-conduit.
7.4.3 Junction boxes serving embedded heating circuits shall be located above the finished grade or in a listed enclosure where their location is below it, and shall be accessible without removing pavement.
7.4.4 No splice in a heating cable shall be embedded in the pavement unless it is made with the manufacturer's listed splice kit for embedded service and its location is recorded on the record drawings.
7.4.5 Where a heating element or its cold leads cross a pavement expansion or isolation joint, the crossing shall be made with the slack, the sleeve, or the loop the manufacturer's instructions require so that the joint movement is not carried by the element.
7.4.6 The equipment grounding conductor of each heating circuit shall be connected to the metal sheath or braid of the heating element at each power connection, and the sheath or braid shall be continuous through every splice.
8 Controls
8.1 Control Type
8.1.1 The control type of each snow melt system shall be as indicated in the datasheet.
Control Typeselect
Manual switch with run timer
Aerial snow sensor
Pavement-mounted snow and ice sensor
Aerial and pavement-mounted sensors in combination
Building automation system initiation with a pavement-mounted sensor
NOTE A manual switch with a run timer costs the least and starts the system only when someone decides to, which on an unstaffed site means after the snow is on the ground. An aerial sensor on a pole or a roof detects precipitation and air temperature and starts the system as the snow begins to fall, before it reaches the pavement, and it cannot see drifting snow, blown snow, or meltwater that refreezes on the surface. A pavement-mounted sensor reads the surface temperature and the moisture on it, so it responds to whatever is on the pavement from any source and holds the system on until the surface is dry, and it starts only once moisture reaches the sensor. The combination starts on the aerial sensor and runs on the pavement sensor, which is the earliest start and the surest finish, at the cost of two sensors and the wiring to both. Initiation from the building automation system puts the start decision in the operator's hands or the system's weather feed with the pavement sensor to confirm the condition, and suits a campus that already supervises its snow operations. No type is the norm across projects. (8.1.2)
8.1.3 Where a pavement-mounted sensor is selected, the sensor shall be set in the pavement at the location indicated on the snow melt plan, flush with the finished surface, in a heated area away from the pavement edge, from drains, and from any place where snow is plowed or stored.
8.1.4 Where an aerial sensor is selected, the sensor shall be mounted where it is exposed to falling precipitation, clear of roof overhangs, exhaust discharges, and tree cover, at the location indicated on the snow melt plan.
NOTE A sensor that reads the wrong place runs the system for the wrong reason. A pavement sensor at a drain reads wet long after the surface is dry, one at the edge reads the unheated ground, and one under a snow pile reads a storm that ended a week ago. The location is a design decision because the sensor is the only thing the controller knows about the pavement. (8.1.5)
8.2 Setpoints and Sequence
8.2.1 The controller shall start the system when the sensor reports moisture and the pavement or air temperature is at or below the activation temperature indicated in the datasheet, and the activation temperature shall be adjustable at the controller.
Activation Temperaturerange
°F
3245
Default: 38 °F
8.2.2 The controller shall continue heating after the sensor reports the surface dry or the precipitation ended for the after-run period indicated in the datasheet, and the period shall be adjustable at the controller.
After-Run Periodrange
min
15306090120180240
NOTE An activation temperature a few degrees above freezing starts the system while the surface is still above the freeze point so that the first snow lands on a warm pavement, and 38°F is the setting controllers are shipped with and the one nearly every project keeps. The after-run has no norm because it depends on the surface: a sloped drive that drains dries in minutes, and a flat plaza with a sensor at its high point holds meltwater in its low corners for an hour after the sensor reads dry, and that water is the ice the system was built to prevent. (8.2.3)
8.2.4 The idle mode of each system shall be as indicated in the datasheet.
Idle Moderadio
○ No idle mode, cold start on each call
○ Idle at a pavement temperature setpoint
○ Idle at a pavement temperature setpoint with outdoor temperature reset
NOTE A system that starts cold heats the whole mass of the pavement from the outdoor temperature before the surface reaches the melting point, which on a thick slab in deep cold takes hours, during which the snow accumulates; it uses no energy between storms. Idling holds the pavement at a setpoint near freezing between storms so that melting begins within minutes of the call, at an idle energy use that over a season can exceed the energy used for melting. Outdoor reset lowers the idle setpoint as the outdoor temperature rises so that the pavement is held only as warm as the next storm needs, which recovers part of that idle energy. Class III surfaces are usually idled because the response time is the point of the class; Class I surfaces usually are not. No mode is the norm across projects. (8.2.5)
8.2.6 Where an idle mode is selected, the idle pavement temperature setpoint shall be as indicated in the datasheet and shall be adjustable at the controller.
Idle Pavement Temperature Setpointrange
°F
2038
8.2.7 Where an idle mode is selected, the controller shall hold the idle setpoint by cycling the heating circuits or by resetting the supply temperature of a hydronic system, and shall not idle a hydronic system by stopping the circulating pump while the plant remains on.
8.2.8 The controller shall stop heating when the pavement sensor reads a high limit adjustable between 40°F and 60°F, and shall restart when the reading falls below the limit, so that the pavement is not heated beyond the melting condition during a storm.
8.2.9 The controller shall be furnished with the features indicated in the datasheet.
Controller Featurescheckbox
☑ Manual override with a timed run
☐ Remote start input from the building automation system
☑ Status and alarm contacts to the building automation system
☐ Networked interface to the building automation system
☐ Ground-fault trip alarm contact
☑ Sensor failure alarm with fail-safe operation
☐ Run-time and energy logging
8.2.10 Where a sensor failure alarm is selected, the controller shall respond to a failed sensor by the fail-safe operation indicated in the datasheet.
Sensor Failure Responseradio
○ Run on the remaining sensor or the air temperature alone
○ Stop and alarm
8.2.11 The points the controller exposes to the building automation system shall be integrated under Building Automation SystemBuilding Automation SystemResolves to the current adopted revision.sync/building-automation-system, and the controller shall be furnished with the interface that standard selects for the project.
8.2.12 For a hydronic system, the controller shall interlock with the plant under BoilersBoilersResolves to the current adopted revision.sync/boilers and HVAC PumpsHVAC PumpsResolves to the current adopted revision.sync/hvac-pumps so that the circulating pump runs whenever heat is called and the plant delivers the design supply temperature on a call from the snow melt controller.
8.3 Control Panel Enclosure
8.3.1 The controller enclosure shall be rated under NEMA 250 as indicated in the datasheet.
Controller Enclosure Ratingselect
NEMA Type 1
NEMA Type 3R
NEMA Type 4
NEMA Type 4X
NEMA Type 12
NOTE The controller of a hydronic system usually sits in the mechanical room beside the plant, and the controller of an electric system is as often mounted outdoors near the junction boxes as it is in the electrical room, so no rating is the norm across projects. Type 1 is the indoor dry-location enclosure; Type 3R sheds rain and is the outdoor minimum; Type 4 resists hose-directed water for a location that is washed down; Type 4X adds corrosion resistance for a location exposed to deicing salt spray; Type 12 excludes dust and dripping oil in an industrial interior. (8.3.2)
8.3.3 Controllers and ground-fault protection equipment installed outdoors shall be rated NEMA Type 3R or better.
8.3.4 Controllers installed where deicing salt spray or a washdown reaches them shall be rated NEMA Type 4X.
9 Pavement Assembly and Embedment
9.1 Insulation Beneath the Heated Pavement
9.1.1 Insulation beneath the heated pavement shall have the thermal resistance indicated in the datasheet.
Insulation Thermal Resistance Beneath the Pavementrange
Not less than
h·ft²·°F/Btu
57.5101520
9.1.3 Where insulation is selected, the insulation board shall be polystyrene conforming to ASTM C578 of the type indicated in the datasheet.
Insulation Board Typeselect
ASTM C578 Type X, 15 psi
ASTM C578 Type IV, 25 psi
ASTM C578 Type VI, 40 psi
ASTM C578 Type VII, 60 psi
ASTM C578 Type V, 100 psi
Derived — the design loading of the pavement section on the civil paving plans (by default)
9.1.4 Edge insulation at the heated pavement shall be as indicated in the datasheet.
Edge Insulationradio
○ None
○ Vertical board of the same type and thermal resistance as the insulation beneath the pavement, at every edge not abutting a heated area
NOTE An exposed pavement edge, a curb, or a building wall draws heat sideways out of the heated panel and shows as a strip along the edge that melts last. Edge insulation stops that where the edge abuts unheated ground or an unheated slab, and it is omitted where the edge abuts another heated area or where the layout places the first tube or cable run close enough to the edge to carry the loss. (9.1.5)
9.1.6 Insulation shall be placed on the prepared base, with the joints between boards butted tight, and the embedded elements shall be secured above it on the reinforcement, the rails, or the mesh and not pinned through it.
9.2 Embedment Depth and Attachment
9.2.1 The depth of hydronic tubing below the finished surface, measured to the top of the tube, shall be as indicated in the datasheet.
Hydronic Tubing Depth Below the Finished Surfacerange
in
1.54
9.2.2 The depth of electric heating elements below the finished surface, measured to the top of the element, shall be as indicated in the datasheet, and shall be not less than the cover the element's listing requires for the pavement material.
Electric Heating Element Depth Below the Finished Surfacerange
in
1.54
NOTE Depth trades response against protection. An element close to the surface heats the surface quickly at a low supply temperature or watt density and sits within reach of a contraction joint saw cut and of the surface loads; an element set deeper is protected by the pavement above it and heats the surface slowly, through more mass, at a higher output. The depth is also what the installer has to hold during placement, and a depth the reinforcement does not naturally give is a depth that needs chairs or rails to hold. Neither value has a norm across projects. (9.2.3)
9.2.4 Embedded elements shall be secured to the reinforcement, to manufacturer-supplied rails or tracks, or to a carrier mesh at intervals not exceeding the manufacturer's published spacing and not exceeding 3 ft on straight runs and 1 ft at bends, so that the element holds its position and depth through placement.
9.2.5 Where tubing or cable is secured to reinforcement, the ties shall be of a material and form that does not cut or abrade the element, and wire ties shall be twisted away from the element.
9.2.6 The pavement contractor shall hold the depth below the finished surface by the method agreed at the pre-placement conference, and shall not raise or lower the element to suit the screed.
9.2.7 The embedded elements shall be laid out so that no contraction joint is sawn over a tube or a cable, and the joint plan under Concrete PavingConcrete Paving, Curbs, and SidewalksResolves to the current adopted revision.sync/concrete-paving shall be reconciled with the circuit layout on the shop drawings before layout begins.
9.2.8 Where a tube crosses a pavement expansion or isolation joint, the tube shall pass through a sleeve of a length not less than 12 in centered on the joint, and the tube shall be dropped below the joint depth so that the saw cut of an adjacent contraction joint cannot reach it.
9.2.9 Where tubing or cold leads pass from the pavement into the building, the penetration shall be sleeved, and where it passes through a rated assembly it shall be firestopped under FirestoppingFirestoppingResolves to the current adopted revision.sync/firestopping.
9.2.10 Where the pavement is unit pavers, the embedded elements shall be placed in the concrete base beneath the setting bed or in the setting bed itself as the element's listing or the tubing manufacturer's instructions permit, and the pavers shall be set without impact over the elements.
9.2.11 Where the pavement is asphalt, the asphalt shall be placed at a temperature not exceeding the rating of the element's listing, the elements shall be covered by hand-placed material before the paver or roller runs over them, and no vibratory compaction shall be used over the elements until the lift above them is in place.
10 Testing
10.1 Hydronic Tubing Pressure Test
10.1.1 Each hydronic circuit shall be pressure tested from the manifold before the pavement is placed, and the test pressure shall be held through the placement and until the pavement has been finished and is no longer being worked.
10.1.2 The pressure test shall be made with the medium indicated in the datasheet.
Pressure Test Mediumradio
○ Compressed air or nitrogen
○ Water
○ Glycol solution at the selected concentration
NOTE Air or nitrogen is the usual medium on a snow melt circuit because the test is made outdoors, often in freezing weather, and a water-filled circuit that is left under test overnight freezes and bursts the tube the test was meant to prove; air shows a leak as a pressure drop and shows its location poorly. Water shows a leak where it is and reads a pressure drop with less sensitivity to temperature, and it suits a test made in warm weather on a circuit that will be drained or charged immediately after. Testing with the glycol solution proves the circuit and charges it in one operation, and it puts the fluid in the tube before the pavement is placed, where a tube damaged during placement spills it into the base. No medium is the norm across projects. (10.1.3)
10.1.4 The test pressure shall be not less than the value indicated in the datasheet and not less than 1.5 times the system working pressure.
Tubing Test Pressurerange
Not less than
psig
4050607580100125150
10.1.5 The test pressure shall be held with no pressure drop, after allowance for temperature change, for not less than the period indicated in the datasheet before the pavement is placed.
Tubing Test Hold Period Before Placementrange
Not less than
h
1248244872
10.1.6 A gauge readable from outside the pavement shall remain on each manifold throughout placement, and the pressure shall be read and recorded before placement begins, at intervals not exceeding one hour during placement, and after finishing is complete.
10.1.7 Where the pressure falls during placement, placement over the affected circuit shall stop until the leak is located and the circuit is replaced or the Engineer of Record directs otherwise in writing, and the cost of the delay and the replacement shall be borne by the Contractor.
10.1.8 The test record for each circuit shall state the medium, the pressure, the ambient temperature, the start and end times, and each reading taken during placement, and shall be signed by the installer and by the pavement contractor.
10.2 Electric Insulation Resistance Test
10.2.1 Each electric heating circuit shall be tested for insulation resistance between the heating conductors and the sheath or braid, and for element resistance between the conductors, on receipt, after the element is secured and before the pavement is placed, after the pavement is placed, and before the circuit is energized.
10.2.2 The insulation resistance test voltage shall be as indicated in the datasheet, and shall not exceed the voltage the element manufacturer permits.
Insulation Resistance Test Voltagerange
V DC
50010002500
10.2.3 The insulation resistance of each circuit at each test shall be not less than the value indicated in the datasheet or the element manufacturer's published minimum, whichever is greater.
Insulation Resistancerange
Not less than
MΩ
151020501005001000
10.2.4 The element resistance of each circuit shall be within the tolerance the manufacturer publishes of the design value, and shall not change between successive tests by more than that tolerance.
NOTE A reading that falls between the test before placement and the test after it is the signature of a cable damaged by the pavement work, and the stage at which it fell is what tells the Contractor where to look. The test before energizing catches the moisture that entered a connection during the weeks the circuit sat waiting for the pavement to cure. The 20 MΩ default is the minimum IEEE 515.1 sets for a commercial heat tracing circuit, and a manufacturer's higher published minimum governs where one is stated. (10.2.5)
10.2.6 A circuit whose insulation resistance or element resistance fails at the test before placement shall be replaced before placement, and a circuit that fails at a later test shall be reported to the Engineer of Record, who shall determine whether the circuit is repaired through the pavement, replaced, or abandoned and replaced by an adjacent circuit, with the cost borne by the Contractor.
10.2.7 The test record for each circuit shall state the test voltage, the readings at each stage, the ambient conditions, and the instrument used, and shall be signed by the electrician.
10.3 Functional Test
10.3.1 After the pavement has cured and before the first heating season, the Contractor shall operate each system through a complete cycle, by simulating the sensor conditions at the controller, and shall demonstrate that each circuit flows or draws its rated current, that the activation, after-run, idle, and high limit functions operate at their setpoints, that the manual override runs the system for its timed period, and that the alarm and status contacts report to the building automation system.
10.3.2 For a hydronic system, the flow in each circuit shall be read at the manifold and balanced to the circuit schedule, and the supply and return temperatures shall be recorded with the system at the design supply temperature.
10.3.3 For an electric system, the current of each heating circuit shall be measured at the controller and recorded against the rated current, and the ground-fault protection shall be tripped by its test function and reset.
10.3.4 The functional test shall be witnessed by the Engineer of Record or the commissioning authority where one is engaged, and the record shall be delivered with the closeout submittals.
10.3.5 Functional performance testing of the system under the commissioning plan, where the project is commissioned, shall be performed under CommissioningTotal Building CommissioningResolves to the current adopted revision.sync/commissioning after the functional test of this standard is complete.
11 Installation
11.1 Placement Sequence
11.1.1 The embedded elements shall be laid out on the prepared base or on the insulation, secured, tested, photographed, and released by the Engineer of Record before the pavement is placed, and the pavement contractor shall not begin placement over a heated area until that release is given.
11.1.2 Placement over the embedded elements shall be from outside the heated area or from boards or mats that spread the load, and no wheeled equipment, chute, or pump hose shall rest on the elements.
11.1.3 Concrete shall be consolidated over the elements by means that do not contact them, and internal vibrators shall not be inserted at an element.
11.1.4 An element damaged during placement shall be exposed, replaced for its full circuit length or repaired by the manufacturer's listed method where the listing permits an embedded repair, retested, and recorded on the record drawings, and the pavement over it shall be replaced to match the adjacent work at the Contractor's cost.
NOTE The elements are the only part of the pavement that is finished before the pavement is started, and every trade that follows works over them. Naming the release as a hold point and the pavement contractor as the party who does not start without it is what keeps the pour from being the first time the two trades talk. (11.1.5)
11.2 Record Drawings
11.2.1 Before the pavement is placed, the Contractor shall measure the location of every circuit, manifold, junction box, splice, and sensor from fixed site features, and shall record the depth below the finished surface, and those measurements shall be the basis of the record drawings.
11.2.2 The record drawings shall be delivered as a dimensioned plan of each heated area at a scale that shows the individual runs, and a reduced copy shall be mounted in a frame at the controller.
12 Delivery, Storage, and Handling
12.1 Tubing, heating cable, and mats shall be delivered in the manufacturer's packaging, stored off the ground and out of direct sunlight, and protected from crushing, abrasion, and the heat of other site work until they are laid out.
12.2 Tubing shall not be exposed to sunlight for longer than the manufacturer's published limit before it is covered by the pavement, and tubing that has exceeded the limit shall not be installed.
12.3 Heating cable and mats shall be tested for insulation resistance on receipt, and an element that fails the test on receipt shall be rejected and returned.
12.4 Glycol shall be stored in sealed containers protected from freezing and contamination until it is charged under Hydronic Cleaning And FlushingHydronic System Cleaning and FlushingResolves to the current adopted revision.sync/hydronic-cleaning-and-flushing.
13 Warranty
13.1 The Contractor shall warrant the embedded elements and their connections against leakage, open circuit, and loss of insulation resistance, and the controller and sensors against failure to operate as specified, for the period indicated in the datasheet, measured from the date of substantial completion.
Snow Melt System Warranty Periodrange
Not less than
years
1235102025
13.2 Where the contract General Conditions specify a longer warranty period than the datasheet, the longer period shall govern.
13.3 A failure of an embedded element within the warranty period shall be corrected by the Contractor at no cost to the Owner, including locating the failure, removing and replacing the pavement over it to match the adjacent work, the glycol lost, and the restoration of any finish, planting, or site feature disturbed to reach it.
13.4 Where the parties disagree whether a failure arose from the element, its installation, or from later work by others in the pavement, the Engineer of Record shall make the initial determination, and the record drawings shall be the evidence of where the elements were.
NOTE The unassigned cost in a snow melt warranty is the pavement. The tube or the cable is a few dollars a foot, and the slab over it is what a warranty argument is about, which is why the pavement is named here and why the record drawings are named as the evidence. (13.5)
14 Spare Parts
14.1 The Contractor shall furnish the spare parts indicated in the datasheet, delivered to the Owner with the closeout submittals.
Spare Parts Furnishedcheckbox
☑ One pavement-mounted sensor of each type installed
☐ One aerial sensor of each type installed
☐ One ground-fault protection module of each type installed
☐ Glycol concentrate for one makeup of the loop
☐ One power connection kit and one end seal of each type installed
NOTE A pavement sensor is the part that fails first, by physical damage from a plow blade or by water entry at its lead, and it fails during a storm. A spare on the shelf is what lets the Owner's staff restore the system the same day instead of waiting for a part in the week the pavement is iced. (14.2)
This standard is written and maintained by SynC and licensed under Creative Commons Attribution 4.0. You may share and adapt it, including commercially, provided you credit SynC Standards, link to the license, and indicate any changes. Each standard is drafted from cited sources under published authoring rules, reviewed before adoption, and corrected in the open. Keep the attribution and notice below with any copy; it carries the warranty notice the license asks you to retain.
"Snow Melt Systems," SynC Standards, revision 3. Licensed under CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Source: https://synergyinconstruction.com/standards/general/snow-melt-systems. Reference material only; not professional engineering advice and provided without warranty. Verify against governing codes and have a licensed professional review before use.