Underground Fire Service Mains

Read revision 3

Revision 3 · Oct 12, 2026 +1 −1

P1 batch 3: knife gate valves, water storage tanks, water wells, cathodic protection and instrumentation cable now owned; bare-text mentions re-pointed to the new standards
Showing changes from Rev 2 to Rev 3 in Underground Fire Service Mains.
---
title: Underground Fire Service Mains
…68 unchanged lines
- Thrust restraint calculations and details, identifying the restraint method at each bend, tee, cross, reducer, valve, hydrant lateral, and dead end, including restrained-joint length calculations or thrust block bearing areas
- Material certifications for the pipe, fittings, and gaskets, confirming compliance with the referenced AWWA standards
−- Corrosion protection details, including polyethylene encasement or cathodic protection where required by the soil resistivity evaluation
+- Corrosion protection details, including polyethylene encasement or cathodic protection (see [[sync/cathodic-protection]]) where required by the soil resistivity evaluation
```datasheet
…512 unchanged lines
## Because the main is buried, a warranty repair entails excavation and site restoration in addition to the pipe repair, and the Contractor's warranty shall extend to the full cost of restoring the disturbed surface. {note}