SynC · SynC Standards
Closeout Procedures
Contents
- 1Scope
- 2Closeout Terms
- 3Referenced Standards
- 4Submittals
- 4.1Closeout Submittals
- 4.2Final Payment Submittals
- 5Closeout Sequence
- 5.1Order of Closeout
- 6Substantial Completion
- 6.1Readiness for the Substantial Completion Inspection
- 6.2The Engineer's Inspection
- 6.3The Certificate and Its Date
- 7Phased Closeout and Designated Portions
- 7.1Separate Certificates for Designated Portions
- 7.2Retainage and Lien Waivers on a Portion
- 8Punch List
- 8.1Preparation of the Punch List
- 8.2Completion of the Punch List
- 9Final Cleaning
- 9.1Cleaning Level and Scope
- 9.2Indoor Air Quality Before Occupancy
- 10Record Documents
- 10.1Record Documents During the Work
- 10.2Record Document Delivery
- 11Spare Parts and Spare Materials Delivery
- 11.1Delivery Procedure
- 12Demonstration and Training
- 12.1Training Plan and Notice
- 12.2Delivery of Training
- 12.3Training Records and Recording
- 13Permits, Occupancy, and Operating Approvals
- 13.1Closing of Permits
- 13.2Certificate of Occupancy
- 13.3Operating Approvals for Regulated Facilities
- 14Closeout Package
- 14.1Assembly and Delivery
- 15Final Completion and Final Inspection
- 15.1Request for the Final Inspection
- 15.2The Final Inspection and Final Completion
- 16Final Payment and Release of Retainage
- 16.1Release of Retainage at Substantial Completion
- 16.2Final Application for Payment
- 16.3Affidavits, Final Lien Waivers, and Consent of Surety
- 17Coordination with the Agreement and Other Standards
Download
Build a datasheet from this standard
Start a project with this standard already attached — one click, no setup.
Use in a project
1 Scope
NOTE This standard establishes the administrative procedure by which the Work, or a designated portion of it, is inspected, certified substantially complete, finished, cleaned, documented, handed to the Owner's operators, inspected again, and paid for in full, on any project and under any Division of the Specifications. (1.1)
NOTE Closeout is the controlled transfer of a finished, documented, and operable facility from the Contractor to the Owner. Its purpose is to fix the date from which the Contract Documents measure everything that follows, to see that every item of Work is complete and corrected, and to put into the Owner's hands the records it needs to operate, maintain, and protect what it has paid for. The same procedure serves a building the Owner occupies, a pump station the Owner starts, and a pipeline the Owner puts into service, and the readiness test in this standard is written so that it applies to each of them. (1.2)
NOTE The substantial completion inspection, the certificate, final payment, and the release of retainage originate in the Agreement and the General Conditions, which are contract instruments. This standard carries their requirements into the project manual, where the subcontractors and suppliers who read only the technical sections see what closes the Contract, and it states the readiness conditions, the lists, the deliverables, the periods, and the sequence those instruments leave open. (1.4)
1.5 The Contractor shall comply with this standard in addition to any closeout requirement stated in the Agreement, the General Conditions, or a technical standard.
1.6 Where a requirement of this standard conflicts with the Agreement, the General Conditions, or the Supplementary Conditions, those documents shall govern.
1.7 Where a requirement of this standard conflicts with the lien law, the retainage law, the prompt-payment law, or the building code of the jurisdiction of the project, that law shall govern, and the Contractor's obligations under this standard shall be read as reduced only to the extent the law requires.
NOTE The following are outside the scope of this standard: (1.8)
- Applications for progress payment, the retainage held on them and its reduction before substantial completion, partial lien waivers, stored materials, unit prices, allowances, and alternates, which Payment ProceduresPayment ProceduresResolves to the current adopted revision.sync/payment-procedures governs
- The correction period and its length, the form, execution, and claim procedure of warranties, the content of the warranty book, the bonds, and the form and content of the consent of surety, which Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds governs
- The content, organization, copy count, and medium of the operation and maintenance package, which Operation And Maintenance DataOperation and Maintenance DataResolves to the current adopted revision.sync/operation-and-maintenance-data governs
- The commissioning process, the functional performance and integrated systems tests, the issues log, the seasonal and deferred tests, the systems manual, and the verification that training was delivered and understood, which CommissioningTotal Building CommissioningResolves to the current adopted revision.sync/commissioning governs
- The startup and the field performance tests each system receives, which its equipment standard and the discipline umbrellas such as Common Work Results ProcessCommon Work Results for Process EquipmentResolves to the current adopted revision.sync/common-work-results-process state
- The construction schedule, the daily reports, the progress photographs, and the survey and layout records kept during the Work, which Construction Progress DocumentationConstruction Progress DocumentationResolves to the current adopted revision.sync/construction-progress-documentation governs
- The submittal register and the transmittal and review workflow, which Submittal And Quality ProceduresSubmittal and Quality ProceduresResolves to the current adopted revision.sync/submittal-and-quality-procedures governs, and testing, inspection, quality control during construction, and the disposition of nonconforming Work, which Quality RequirementsQuality RequirementsResolves to the current adopted revision.sync/quality-requirements governs
- The protection of installed Work until substantial completion and the progress cleaning during the Work, which Execution RequirementsExecution RequirementsResolves to the current adopted revision.sync/execution-requirements governs
- The phasing plan, the decision whether the Owner may occupy a completed portion before substantial completion, the notice of that occupancy, the joint inspection that records the portion's condition, and the return of the Owner's keys and credentials, which Summary Of Work And Work RestrictionsSummary of Work and Work RestrictionsResolves to the current adopted revision.sync/summary-of-work-and-work-restrictions governs
- The builder's risk insurance, the date on which the Owner's property insurance takes over the Work, and the insurance that continues after final completion, which Insurance RequirementsInsurance RequirementsResolves to the current adopted revision.sync/insurance-requirements governs
- Placing a new facility in service in an operating plant to maintain operations, which Maintenance Of Plant OperationsMaintenance of Plant OperationsResolves to the current adopted revision.sync/maintenance-of-plant-operations governs
- The items and quantities of spare parts, spare materials, and special tools, which each product standard states for its product, and the spare parts basis for process equipment, which Common Work Results ProcessCommon Work Results for Process EquipmentResolves to the current adopted revision.sync/common-work-results-process governs
- The removal of temporary facilities and the restoration of the areas they occupied, which Temporary Facilities And ControlsTemporary Facilities and ControlsResolves to the current adopted revision.sync/temporary-facilities-and-controls governs
- The content of the certificate of return or destruction of confidential documents, which Document Confidentiality And Ai UseDocument Confidentiality and AI UseResolves to the current adopted revision.sync/document-confidentiality-and-ai-use governs
- The Contract Times, the required date of substantial completion, the liquidated damages, the time within which the Owner pays a certified final application, and the interest on a late payment, which the Agreement and the prompt-payment law governing the Owner set
2 Closeout Terms
NOTE The following terms are used in this standard with the meanings given here: (2.1)
- The Engineer is the Engineer of Record or the design professional the Agreement names to administer the Contract, to inspect the Work for completion, and to certify payment
- Substantial completion is the stage at which the Work, or a designated portion of it, is complete in accordance with the Contract Documents to the point that the Owner can occupy it, use it, or place it in service for the purpose the Contract Documents intend, with only the items on the punch list remaining
- The certificate of substantial completion is the document the General Conditions prescribe, prepared by the Engineer, on which the date of substantial completion is stated, the punch list is attached, and the responsibilities of the Owner and the Contractor between that date and final completion are fixed
- A designated portion is a part of the Work the Contract Documents identify for separate substantial completion, whether as a phase on the phasing plan or as a portion the Owner elects to occupy or use, and it is certified, listed, and paid for as this standard provides for the Work as a whole
- The punch list is the list, attached to the certificate of substantial completion, of the items of Work observed to be incomplete or not in accordance with the Contract Documents, which the Contractor completes or corrects within the period this standard sets
- Final completion is the stage at which every item on the punch list has been completed and accepted, every closeout deliverable has been received and accepted, and the Work is complete in accordance with the Contract Documents, so that the Contractor is entitled to final payment
- Record documents are the set of drawings, specifications, addenda, modifications, submittals, and responses on which the Contractor records, as the Work proceeds, every departure of the constructed Work from the Contract Documents, and the record drawings prepared from that set
- The closeout package is the indexed collection of every closeout deliverable this standard and the standards it names require, assembled by the Contractor and delivered to the Owner before the final inspection
- Spare materials, also called attic stock, are the surplus quantities of installed finish materials a product standard requires to be delivered to the Owner for future repair, and spare parts are the replacement parts a product standard requires to be delivered with an item of equipment
- An operating approval is the authorization of the regulatory agency that permits a water, wastewater, or other regulated facility to be placed in permanent service, as distinct from the building permit and the certificate of occupancy
3 Referenced Standards
3.1 The closeout of the Contract and its administration shall comply with the latest adopted edition of each of the following unless a specific edition is cited or the Contract Documents direct otherwise.
3.2 Where referenced documents conflict, the more stringent requirement shall govern unless the Engineer directs otherwise in writing.
| Standard | Title |
|---|---|
| AIA A201 | General Conditions of the Contract for Construction |
| AIA G704 | Certificate of Substantial Completion |
| AIA G706 | Contractor's Affidavit of Payment of Debts and Claims |
| AIA G706A | Contractor's Affidavit of Release of Liens |
| AIA G707 | Consent of Surety to Final Payment |
| EJCDC C-700 | Standard General Conditions of the Construction Contract |
| EJCDC C-625 | Certificate of Substantial Completion |
| ConsensusDocs 200 | Standard Agreement and General Conditions Between Owner and Constructor |
| IBC Section 111 | Certificate of Occupancy |
| ASTM E1971 | Standard Guide for Stewardship for the Cleaning of Commercial and Institutional Buildings |
NOTE The general conditions in common use each carry a procedure for substantial completion, the punch list, final inspection, and final payment, and each publishes the certificate and affidavit forms that go with its procedure. The forms in the table are examples of those document families and are not the instrument: the certificate of substantial completion on a project is the one the General Conditions on that project prescribe, and a published form is used only where those General Conditions call for it or the Owner accepts it. The lien law of the jurisdiction decides what a final lien waiver has to say, and in several states prescribes its form, the retainage law of a public Owner decides when retainage is released, and the building code decides when a building may be occupied. (3.3)
4 Submittals
4.1 Closeout Submittals
4.1.1 The Contractor shall submit the following, each at the point in the closeout sequence this standard states for it, and shall assemble them into the closeout package:
- The request for the substantial completion inspection, with the Contractor's preliminary list of items remaining to be completed or corrected
- The record documents, in the form and at the milestone this standard requires
- The spare parts, spare materials, and special tools inventory, with the Owner's signed receipt for each delivery
- The training plan and schedule, and after delivery the agenda, the attendance record, and the recording where required, for each training session
- The certificate of occupancy or the operating approval, and the final inspection record for every permit the Contractor or a lower tier held
- The operation and maintenance package under Operation And Maintenance DataOperation and Maintenance DataResolves to the current adopted revision.sync/operation-and-maintenance-data, with the warranty book under Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds bound into it
- The commissioning closeout submittals that CommissioningTotal Building CommissioningResolves to the current adopted revision.sync/commissioning lists, carried into the package
- The progress documentation retained under Construction Progress DocumentationConstruction Progress DocumentationResolves to the current adopted revision.sync/construction-progress-documentation
- The closed request for information log, the record of transmittals, and the export of the project platform under Project Management And CoordinationProject Management and CoordinationResolves to the current adopted revision.sync/project-management-and-coordination
- The Owner's receipt for the keys, access cards, and credentials returned under Summary Of Work And Work RestrictionsSummary of Work and Work RestrictionsResolves to the current adopted revision.sync/summary-of-work-and-work-restrictions
- The certificate of return or destruction of confidential documents under Document Confidentiality And Ai UseDocument Confidentiality and AI UseResolves to the current adopted revision.sync/document-confidentiality-and-ai-use, where that standard applies
- The request for the final inspection, with the Contractor's statement that every item on the punch list is complete
Closeout Submittals Requiredcheckbox
☑ Request for substantial completion inspection with preliminary list
☑ Record documents
☑ Spare parts and materials inventory with signed receipts
☑ Training plan, agendas, attendance records, and recordings
☑ Certificate of occupancy or operating approval and closed permits
☑ Operation and maintenance package with warranty book
☑ Commissioning closeout submittals
☑ Progress documentation
☑ Request for information log, transmittal record, and platform export
☑ Receipt for returned keys and credentials
☐ Certificate of return or destruction of confidential documents
☑ Request for final inspection with completion statement
4.1.2 Closeout submittals shall be transmitted and tracked through the submittal procedure of Submittal And Quality ProceduresSubmittal and Quality ProceduresResolves to the current adopted revision.sync/submittal-and-quality-procedures, except that the request for an inspection shall be made by written notice to the Engineer, with a copy to the Owner, so that the inspection period runs from a date both parties can prove.
4.2 Final Payment Submittals
4.2.1 The Contractor shall submit the following with the final application for payment, and no final payment shall be certified until each has been received and accepted:
- The final application for payment, on the form and with the continuation sheet the progress applications used under Payment ProceduresPayment ProceduresResolves to the current adopted revision.sync/payment-procedures, stating the Contract Sum as finally adjusted
- The Contractor's affidavit that every payroll, every bill for materials and equipment, and every other debt connected with the Work for which the Owner or its property could be held responsible has been paid or otherwise satisfied
- The final lien waivers from the Contractor and from each subcontractor and supplier of every tier that furnished labor, material, or equipment to the Work, on the condition this standard indicates
- The Contractor's affidavit of release of liens, listing every waiver furnished and every claim not released
- The consent of surety to final payment under Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds, where a performance bond is in force
- The maintenance bond under Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds, where one is required
- The evidence of continuing insurance that Insurance RequirementsInsurance RequirementsResolves to the current adopted revision.sync/insurance-requirements requires at final completion
- The final reconciliation of every allowance and the final measurement record of every unit price item under Payment ProceduresPayment ProceduresResolves to the current adopted revision.sync/payment-procedures
- The final change order adjusting the Contract Sum and the Contract Time under Contract Modification ProceduresContract Modification ProceduresResolves to the current adopted revision.sync/contract-modification-procedures, where any adjustment remains open
Final Payment Submittals Requiredcheckbox
☑ Final application for payment with adjusted Contract Sum
☑ Affidavit of payment of debts and claims
☑ Final lien waivers from every tier
☑ Affidavit of release of liens
☐ Consent of surety to final payment
☐ Maintenance bond
☑ Evidence of continuing insurance
☑ Allowance reconciliation and final unit price measurement
☐ Final change order
4.2.2 Final payment submittals shall be transmitted to the Engineer directly, in the manner Payment ProceduresPayment ProceduresResolves to the current adopted revision.sync/payment-procedures provides for an application for payment, and shall not be routed through the technical submittal register.
5 Closeout Sequence
5.1 Order of Closeout
5.1.1 The Contractor shall carry out the closeout of the Work, and of each designated portion, in the following order, and shall not request a step before the steps that precede it are complete:
- Startup and the field tests of every system under its own standard, and the functional performance tests under CommissioningTotal Building CommissioningResolves to the current adopted revision.sync/commissioning other than the seasonal and deferred tests
- Final cleaning, the delivery of spare parts and spare materials, and the training the datasheet requires before substantial completion
- The final inspections for the permits, and the certificate of occupancy or the operating approval where the datasheet requires it before substantial completion
- The Contractor's pre-inspection and the preliminary list, and the request for the substantial completion inspection
- The Engineer's inspection and the certificate of substantial completion, which fixes the date and attaches the punch list
- The release of retainage at substantial completion, as the datasheet provides
- The completion of the punch list within its period, the delivery of the record documents and the closeout package, and the delivery of the operation and maintenance package by the time this standard sets
- The request for the final inspection, the Engineer's final inspection, and the certification of final completion
- The final application for payment with its affidavits, waivers, and consent, and the release of the remaining retainage
NOTE Closeout is a dependency chain and not a checklist worked in any order. The certificate cannot issue until the Owner can use what it is certifying, and nothing the certificate starts, the correction period, the insurance transfer, or the punch list period, can be relied on until the certificate exists. The sequence is written down so that a Contractor who wants a certificate in June knows in March what has to be finished first, and so that no step is skipped on the argument that a later one covered it. (5.1.2)
5.1.3 The operation and maintenance package under Operation And Maintenance DataOperation and Maintenance DataResolves to the current adopted revision.sync/operation-and-maintenance-data, with the warranty book under Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds bound into it, shall be delivered in its final, corrected form within the number of days after the date of substantial completion indicated in the datasheet.
Operation and Maintenance Package Delivery After Substantial Completionrange
Not more than
days
101430456090
NOTE Delivery on the date of substantial completion gives the Owner's operators the manuals the day they take over, and it is achievable only where the preliminary submittal was reviewed well before the inspection and the corrections were small. A period of ten to thirty days after substantial completion allows the corrections from the preliminary review and the as-left setpoints from the last functional performance test to be incorporated, and it is the period most projects use, with the Owner operating on the reviewed preliminary package in the interval. A longer period suits a plant whose seasonal or operational tests continue after substantial completion and whose manuals carry their results, at the cost of operators running the facility for months on a draft. The preliminary submittal before substantial completion, and the content of the package, are governed by Operation And Maintenance DataOperation and Maintenance DataResolves to the current adopted revision.sync/operation-and-maintenance-data, and the time stated here is the one the warranty book delivered under Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds is also held to. (5.1.4)
5.1.5 After substantial completion, the Contractor shall complete and correct the Work at the times the Owner designates so that the Owner's occupancy and operation are not interrupted, and the Owner shall afford the Contractor the access the punch list work requires.
5.1.6 The removal of the temporary facilities under Temporary Facilities And ControlsTemporary Facilities and ControlsResolves to the current adopted revision.sync/temporary-facilities-and-controls shall be sequenced so that every temporary facility the Owner's operation or the punch list work still depends on remains in service until the Owner has released it in writing or final completion, whichever is first.
6 Substantial Completion
6.1 Readiness for the Substantial Completion Inspection
6.1.1 The Work, or a designated portion of it, shall be considered ready for the substantial completion inspection when it is complete in accordance with the Contract Documents to the point that the Owner can occupy it, use it, or place it in service for the purpose the Contract Documents intend, with only items that do not prevent that occupancy, use, or service remaining, and when each condition indicated in the datasheet has been satisfied.
Conditions Required Before the Substantial Completion Inspectioncheckbox
☑ Every system the Contract Documents require to be started and tested has been started and has passed the tests its standard requires
☐ Functional performance testing under the commissioning process is complete except for the seasonal and deferred tests
☑ The certificate of occupancy or the operating approval is in hand or is being issued concurrently
☑ Permanent power, water, and the other permanent utilities are connected and in service
☑ The Contractor's pre-inspection has been made and its preliminary list submitted
☑ Final cleaning is complete
☑ The operation and maintenance package has been submitted at least in its preliminary form
☐ Training has been delivered on every system the Owner will operate from the date of substantial completion
☐ Spare parts, spare materials, and special tools have been delivered and receipted
NOTE A percentage complete is not a test of readiness, because a plant that is ninety-nine percent built with its disinfection system untested cannot be placed in service and a building at ninety-five percent with its elevator inspected and its kitchen unfinished can be occupied. The test is whether the Owner can use the thing for what it was built for, and the conditions in the datasheet are the evidence of that: the systems run and have passed their tests, the authority that controls occupancy or operation has signed, the utilities are on, and the Contractor has looked for itself. The conditions not selected by default are selected on a project that holds the certificate until its operators are trained, its spares are on the shelf, or its commissioning tests are signed, each of which protects the Owner on the day it takes over and each of which can delay a certificate past the date the Agreement requires if the Owner's own staff are not available. (6.1.2)
6.1.3 The Contractor shall make its own pre-inspection of the Work, or of the designated portion, with each subcontractor responsible for Work in it, before requesting the substantial completion inspection, and shall complete or correct every item the pre-inspection finds that can be completed or corrected before the request.
6.1.4 The Contractor shall submit with the request for inspection a preliminary list of every item of Work remaining to be completed or corrected, each identified by location and by the party responsible for it, and the Contractor's statement of the date by which each will be complete.
6.1.5 Omission of an item from the Contractor's preliminary list, or from the punch list the Engineer prepares, shall not relieve the Contractor of the obligation to complete the Work in accordance with the Contract Documents.
NOTE The Contractor's own walk is the one inspection no one else can do for it, and the preliminary list is what proves it happened. A request for inspection made without one produces a list the Engineer writes alone, which is longer than the list a Contractor writes for itself, and a second inspection that the Contractor pays for. (6.1.6)
6.2 The Engineer's Inspection
6.2.1 The Engineer shall inspect the Work, or the designated portion, within the number of days after receiving the Contractor's request for an inspection indicated in the datasheet, with the Contractor and the Owner's representative present, and the same period shall apply to the substantial completion inspection, to each re-inspection of punch list items, and to the final inspection.
Engineer's Inspection After the Contractor's Requestrange
Not more than
days
357101421
NOTE The inspection period is the Engineer's, and it is set against the size of the Work and the distance the Engineer travels: a small project close to the Engineer's office is walked within a few days, and a plant with a dozen structures and three disciplines takes a week to inspect and a crew to do it. A short period gets the certificate issued close to the day the Work was ready and keeps the Contractor from carrying a finished project it is not yet paid for; a long period gives the Engineer time to schedule every discipline for one visit, and it moves every date the certificate fixes by the same amount. (6.2.2)
6.2.3 Where the Engineer's inspection finds the Work substantially complete, the Engineer shall prepare the certificate of substantial completion the General Conditions prescribe and shall deliver it to the Owner and the Contractor for their signatures.
6.2.4 Where the Engineer's inspection finds the Work not substantially complete, the Engineer shall notify the Contractor in writing, within the inspection period, of the reasons and of the items that prevent substantial completion, and the Contractor shall complete or correct them and shall request another inspection.
6.2.5 The Engineer's cost of each inspection or re-inspection under this standard, after the first, that the Contractor requested before the Work, the portion, or the items it reported complete were in fact ready shall be borne by the Contractor and may be deducted from sums due it, unless the Agreement provides otherwise.
6.2.6 Where the Contractor and the Engineer disagree whether the Work, or a designated portion, is substantially complete, the Engineer shall make the initial determination, subject to the dispute resolution provisions of the Contract Documents.
6.3 The Certificate and Its Date
6.3.1 The certificate of substantial completion shall state the date of substantial completion, shall attach the punch list, shall state the period within which the Contractor is to complete the punch list, and shall fix the responsibilities of the Owner and the Contractor for the security, the maintenance, the heat, the utilities, the operation, and the damage to the Work between the date of substantial completion and final completion.
6.3.2 The certificate of substantial completion shall state the date on which responsibility for insuring the Work passes from the builder's risk insurance to the Owner's property insurance under Insurance RequirementsInsurance RequirementsResolves to the current adopted revision.sync/insurance-requirements, and that date shall be the date of substantial completion unless the certificate states another.
6.3.3 The date of substantial completion shall be the date the Engineer states on the certificate of substantial completion, and it shall be the date from which the correction period and every warranty required by the Contract Documents commence under Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds, the date from which the punch list completion period under this standard runs, and the date of substantial completion for every other purpose of the Contract Documents.
6.3.4 The date the Engineer states shall be the date on which the Engineer's inspection found the Work substantially complete, or the later date on which the last condition the datasheet requires was satisfied, and not the date on which the certificate was signed.
6.3.5 The Owner and the Contractor shall sign the certificate of substantial completion to accept the responsibilities it assigns them, and the Owner's occupancy, use, or operation of the Work under the certificate shall begin on the date it states.
NOTE A certificate dated when it was signed, rather than when the Work was ready, moves every clock in the Contract by the time the signatures took, and on a certificate that circulates for a month that is a month of the Contractor's correction period and a month of liquidated damages argued over. Stating the date the Work was found ready is what makes the certificate a record rather than a negotiation, and tying every warranty to that one date is what keeps each subcontractor from claiming a different start for its own. (6.3.6)
6.3.7 The Owner's occupancy or use of the Work or of any portion before the certificate for it is issued, including the placing of a new facility in service under Maintenance Of Plant OperationsMaintenance of Plant OperationsResolves to the current adopted revision.sync/maintenance-of-plant-operations to maintain the operation of an existing plant, shall not constitute substantial completion of it, acceptance of Work that does not conform to the Contract Documents, or the start of any warranty.
6.3.8 The Contractor's responsibility for the protection of the Work under Execution RequirementsExecution RequirementsResolves to the current adopted revision.sync/execution-requirements shall end, for the Work or for the portion the certificate covers, on the date of substantial completion the certificate states, except for the protection the punch list work and the Contractor's own operations after that date require.
7 Phased Closeout and Designated Portions
7.1 Separate Certificates for Designated Portions
7.1.1 Where the phasing plan under Summary Of Work And Work RestrictionsSummary of Work and Work RestrictionsResolves to the current adopted revision.sync/summary-of-work-and-work-restrictions designates phases for separate acceptance, or where the Owner occupies or uses a completed portion of the Work before substantial completion of the whole under that standard, the Engineer shall issue a separate certificate of substantial completion for each phase or portion, and each certificate shall state its own date, attach its own punch list, and fix the responsibilities this standard requires for the portion it covers.
7.1.2 A phase or portion shall be accepted for occupancy or use only by the certificate of substantial completion for it, and the Contractor's and the Owner's responsibilities for the portion shall transfer on the date that certificate states.
7.1.3 The Contractor shall request the inspection of each designated portion as this standard provides for the Work, and the readiness conditions in the datasheet shall apply to the portion and to the systems that serve it.
7.1.4 Where the authority having jurisdiction requires a certificate of occupancy for a building, a partial certificate of occupancy for the portion shall be obtained before the Owner occupies it, as this standard provides for the certificate of occupancy.
NOTE Each phase of an operating plant is a facility the Owner starts running while the Contractor builds the next one, and the certificate for the phase is what records the day the Owner took it over. Without a certificate for each portion, the correction period on the first clarifier runs from the day the whole plant was finished two years later, the Owner is insuring something it does not yet own, and no one can say whether the pump that failed in the interval was the Contractor's to fix. The correction period and the warranties on each portion commence on the date of its certificate under Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds. (7.1.5)
7.2 Retainage and Lien Waivers on a Portion
7.2.1 The retainage held on the Work in a designated portion shall be treated, on the certificate of substantial completion for the portion, as indicated in the datasheet.
Retainage Release on Substantial Completion of a Portionradio
○ Released for the portion as this standard provides at substantial completion, in proportion to the scheduled value of the Work in the portion
○ Held until substantial completion of the Work as a whole
NOTE Releasing the retainage on a portion when its certificate issues pays the subcontractors whose Work is in that portion when it is accepted, which on a phased plant may be years before the last phase, and it requires a schedule of values broken down by phase under Payment ProceduresPayment ProceduresResolves to the current adopted revision.sync/payment-procedures so that the amount earned in the portion can be identified. Holding it to the end keeps the Owner's whole fund in place until the last phase is accepted, and it is the arrangement where the phases are short, the schedule of values is not broken down by phase, or the retainage law requires a single release. (7.2.2)
7.2.3 Where retainage is released for a portion, the Contractor shall furnish the final lien waivers for the Work in the portion, on the condition and in the form this standard requires for final waivers, and the consent of surety to the partial release under Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds where the performance bond is in force.
NOTE A phase occupied for months without lien waivers for the Work in it leaves the Owner holding a facility it is operating and a lien exposure it cannot measure, and the waivers for the portion close that exposure as each phase is taken over. (7.2.4)
8 Punch List
8.1 Preparation of the Punch List
8.1.1 The punch list shall be prepared by the party indicated in the datasheet, from the Engineer's inspection and the Contractor's preliminary list, and shall be attached to the certificate of substantial completion.
Punch List Authorradio
○ The Engineer, from its inspection and the Contractor's preliminary list
○ The Contractor, with the Engineer verifying and supplementing the list on its inspection
○ The Engineer, the Contractor, and the Owner's representative together on one walkthrough
NOTE A list the Engineer writes is the list the general conditions in common use contemplate, and it carries the Engineer's authority to say what is not in accordance with the Contract Documents, at the cost of items the Contractor considers complete and argues about. A list the Contractor writes and the Engineer verifies is shorter, is ready sooner, and relies on the Contractor to find its own deficiencies, which the Engineer's supplement corrects where it does not. A joint walkthrough produces one list that all three parties watched being written, at the cost of three schedules to coordinate, and it is the arrangement where the Owner's operators know the facility better than either of the others and will be the ones who find what was missed. (8.1.2)
8.1.3 Each item on the punch list shall identify the location of the Work by room, area, structure, or drawing reference, the deficiency or the incomplete Work specifically enough that its completion can be verified without further description, and the party responsible for it.
8.1.4 The punch list shall be recorded in the medium indicated in the datasheet.
Punch List Record Mediumradio
○ A written list keyed to the room, area, structure, or drawing location of each item
○ Entries on the project platform, each with its location and a photograph of the condition
NOTE A written list is the record every party can read without a license, and it is enough on a project whose list runs to a few pages. Entries on the project platform under Project Management And CoordinationProject Management and CoordinationResolves to the current adopted revision.sync/project-management-and-coordination carry a photograph of every condition, a status every party sees at once, and a record of who closed each item and when, at the cost of every item being entered one at a time on a tablet in the field, and they are the medium of a project whose list runs to hundreds of items across many structures. (8.1.5)
8.1.6 The Engineer may add to the punch list, in writing, an item of incomplete or nonconforming Work observed after the certificate of substantial completion and before the final inspection, and the Contractor shall complete or correct it within the punch list completion period or within fourteen days after the addition, whichever is later.
8.1.7 The punch list shall be closed at final completion, and a defect in the Work discovered after the punch list has been closed shall be a claim under the correction period and the warranties administered under Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds, and not a punch list item.
NOTE A punch list that can be added to without end never reaches final completion, and one that is closed the day it is issued leaves the Owner no remedy for the deficiency found the next morning other than a warranty claim on a Contractor still on the site. Closing the list at final completion, with additions in writing until then, is the line between the two: everything found while the Contractor is finishing goes on the list, and everything found after is handled under the correction period, where the procedure for it already exists. (8.1.8)
8.2 Completion of the Punch List
8.2.1 The Contractor shall complete or correct every item on the punch list within the number of days after the date of substantial completion indicated in the datasheet.
Punch List Completion Period After Substantial Completionrange
Not more than
days
142130456090120
NOTE The period is set against the size of the list and the Owner's tolerance for sharing the facility with the Contractor after it has moved in. Thirty days is the period most building projects state and most lists can be finished in, and it keeps the Contractor's crews on the site while they are still mobilized; a longer period suits a plant whose punch items wait on a shutdown the Owner has to schedule, or a list that includes a long-lead replacement, and it costs the Owner the Contractor's presence for that long. A period shorter than the lead time of the longest item on the list is one the Contractor will miss, and the time within which the Work is finally complete, where the Agreement states one, is a Contract Time that this period cannot extend. (8.2.2)
8.2.3 The Contractor shall notify the Engineer in writing when every item on the punch list is complete, listing each item and the date it was completed, and shall request a re-inspection.
8.2.4 The Engineer shall re-inspect the items within the inspection period and shall accept each item in writing or return it as not complete with the reason, and the Contractor shall correct each returned item and request a further re-inspection.
8.2.5 Where the Contractor and the Engineer disagree whether a punch list item has been completed or corrected, the Engineer shall make the initial determination, subject to the dispute resolution provisions of the Contract Documents.
8.2.6 Where the Contractor does not complete the punch list within the period, the Owner may, after seven days' written notice, complete or correct the remaining items by others, and the cost, including the Engineer's services made necessary by it, shall be borne by the Contractor and deducted from the retainage held or from other sums due, and the Owner's remedies under the General Conditions shall not be limited by this clause.
9 Final Cleaning
9.1 Cleaning Level and Scope
9.1.1 The Contractor shall perform final cleaning of the Work, or of the designated portion, and of every area of the premises its operations used, before the substantial completion inspection, to the level indicated in the datasheet.
Final Cleaning Levelradio
○ Construction clean, with the Owner's own staff performing the finish cleaning
○ Occupancy clean, with every exposed surface cleaned as this article describes
○ Occupancy clean, with a terminal clean of the areas the Contract Documents designate
NOTE Construction clean removes the Contractor's debris, dust, labels, and protection and leaves the finish cleaning to an Owner that has a cleaning staff or a cleaning contract already in place, which is the arrangement on an occupied facility the Owner cleans anyway and on a plant whose structures are not finished spaces. Occupancy clean delivers every surface in the condition a new facility is accepted in, and it is what an Owner moving into a new building expects and prices into the Contract. A terminal clean of designated areas is the protocol a hospital's infection control, a laboratory, a cleanroom, or a food facility requires before the area is used, performed after every other trade has left it and documented, and it is specified for those areas on top of the occupancy clean of the rest. (9.1.2)
9.1.3 Final cleaning at every level shall include the removal of every temporary protection, temporary label, marking, and covering, every manufacturer's label not required to remain, and all construction debris and waste from the Work and from the areas the Contractor used.
9.1.4 Where occupancy clean is indicated, final cleaning shall additionally include cleaning every exposed interior and exterior surface, including glass, glazing, frames, and hardware, to a condition free of dust, dirt, stains, film, fingerprints, and residue, cleaning every floor as the floor's product standard requires for its initial cleaning, removing spatter and residue from every finished surface, and cleaning the equipment, piping, ductwork, light fixtures, lamps, and lenses that are exposed to view.
9.1.5 Final cleaning shall include replacing the filters of every air-handling unit and air-moving device that operated during construction, cleaning the strainers of every piping system that operated during construction, and removing the construction debris, sediment, and foreign material from every tank, channel, wet well, manhole, vault, and sump before it is placed in service.
9.1.6 Final cleaning shall include cleaning the paved surfaces, walks, and drives the Contractor's operations soiled, removing waste and surplus material from the site, flushing the drainage structures the Contractor's operations loaded with sediment, and leaving the grounds within the limits of work free of debris.
9.1.7 Where a terminal clean is indicated, the Contractor shall perform it in the designated areas after every other trade has completed its Work in them, to the protocol the Owner's infection control, cleanroom certification, or food safety program requires, by personnel trained in that protocol, and shall document the cleaning and any surface testing the protocol requires in the closeout package.
9.1.8 The Contractor shall use only the cleaning materials and methods the manufacturer of each surface permits, and shall bear the cost of restoring a surface its cleaning damages.
9.1.9 Final cleaning shall be performed to the standard of care ASTM E1971 describes, and where the Contractor and the Owner disagree whether a surface or an area has been cleaned as this standard requires, the Engineer shall make the initial determination.
NOTE ASTM E1971 describes how cleaning is done and to what level of care; it does not state a pass or fail criterion, which is why the determination of a disputed surface is given to the Engineer rather than to the guide. Progress cleaning during the Work, which keeps the site safe and the installed Work protected, is governed by Execution RequirementsExecution RequirementsResolves to the current adopted revision.sync/execution-requirements and does not substitute for the final cleaning here. (9.1.10)
9.2 Indoor Air Quality Before Occupancy
9.2.1 Where the Work includes an occupied building, the indoor air quality procedure before occupancy shall be as indicated in the datasheet.
Indoor Air Quality Flush-Out or Testing Before Occupancyradio
○ Not required
○ A flush-out of the building with outdoor air before occupancy, for the duration and at the ventilation rate the Contract Documents state
○ Air testing of the occupied spaces before occupancy, against the contaminant limits the Contract Documents state
NOTE No procedure suits a building whose finishes have low emissions or whose occupancy is not sensitive to them, and it is what most projects without a certification program do. A flush-out runs the ventilation system on outdoor air for a stated volume or duration after the finishes are in and before occupancy, which is the procedure the green building certification programs accept, and it costs the schedule the days of the flush-out and the Contractor the energy and the filters it consumes. Air testing samples the finished spaces for the contaminants the Contract Documents name and permits occupancy on the results, which takes days rather than weeks and is the alternative where the schedule cannot carry a flush-out, at the cost of a retest and a flush-out of any space that fails. The duration, the rate, the contaminants, and the limits are stated by the certification program or the Owner's requirement the Contract Documents invoke. (9.2.2)
9.2.3 Where a flush-out or air testing is indicated, the Contractor shall perform it after final cleaning and after every finish that emits is installed, shall deliver the record of the procedure and its results to the Engineer before the Owner occupies the spaces it covers, and shall include the record in the closeout package.
10 Record Documents
10.1 Record Documents During the Work
10.1.1 The Contractor shall keep at the site, from the start of the Work until the record documents are delivered, one complete set of the Contract Drawings, the Specifications, the addenda, the modifications, the reviewed submittals, and the responses to requests for information, reserved for the record and not used for construction, on which it records every departure of the constructed Work from the Contract Documents as the Work proceeds.
10.1.2 The Contractor shall record on the record documents, in a color that distinguishes the record from the print and as each element is built, every change in location, dimension, elevation, routing, size, or material from the Contract Documents, every concealed condition, every element of Work that differs from the drawings because of a field condition, every product furnished under an accepted substitution or comparable product, each change order and construction change directive by its number, and each response to a request for information that affected what was built, identified by the request number under Project Management And CoordinationProject Management and CoordinationResolves to the current adopted revision.sync/project-management-and-coordination.
10.1.3 The Contractor shall record on the record documents the as-placed horizontal location and the invert or top elevation of every buried pipe, conduit, duct bank, structure, valve, and other element that will be concealed, from the survey and layout records kept under Construction Progress DocumentationConstruction Progress DocumentationResolves to the current adopted revision.sync/construction-progress-documentation, before the element is covered.
10.1.4 The Contractor shall make the record documents available to the Engineer for review at each progress meeting under Project Management And CoordinationProject Management and CoordinationResolves to the current adopted revision.sync/project-management-and-coordination, and where the Engineer finds them not current shall bring them current before the next application for payment.
NOTE A record set marked as the Work proceeds is the only accurate one. A set marked at closeout from memory, from the superintendent's phone, and from the shop drawings is a guess, and the guess is discovered when the Owner's crew digs for a valve that is not where the drawing says. Reviewing the markups at the progress meetings, when the trench is still open, is what keeps the record honest. (10.1.5)
10.2 Record Document Delivery
10.2.1 The Contractor shall deliver the marked-up record documents to the Engineer at the milestone indicated in the datasheet, together with the Contractor's certification that they record every departure of the constructed Work from the Contract Documents known to it.
Record Document Delivery Milestoneradio
○ With the request for the substantial completion inspection
○ With the request for the final inspection
NOTE Delivery with the request for the substantial completion inspection puts the record in the Owner's hands on the day it takes over, which is when the operators start looking for the valve, and it is the milestone to choose on a plant or a pipeline the Owner operates from that date, at the cost of a record that does not yet show the punch list corrections and has to be supplemented. Delivery with the request for the final inspection produces one record that shows the Work as finally completed, which is the milestone the general conditions in common use contemplate, and it leaves the Owner operating for the punch list period on the Contractor's site set. Whichever milestone is indicated, the marked-up set is the Contractor's record, and the final record drawings prepared from it follow by the time this article sets. (10.2.2)
10.2.3 The final record drawings shall be prepared by the party indicated in the datasheet, from the Contractor's marked-up record documents.
Party Preparing the Final Record Drawingsradio
○ The Contractor, from its own record markups
○ The Engineer, from the Contractor's record markups, under the Owner's agreement with the Engineer
NOTE The Contractor preparing the final drawings keeps the knowledge of what was built with the party that built it, and it costs the Contractor a drafter, the Engineer's drawing files, and a release for their use, which the Engineer sets on its own terms. The Engineer preparing them from the Contractor's markups produces drawings in the Engineer's own standard, consistent with the Engineer's other drawings of the facility, and it is the arrangement a public Owner with a standing agreement for record drawings uses, at the cost of a service in the Owner's agreement with the Engineer and a drawing whose accuracy rests on the markups the Contractor certified. (10.2.4)
10.2.5 Whichever party prepares them, the final record drawings shall carry a statement that they were prepared from the Contractor's record of the constructed Work, with the date of that record, and shall not be represented as the Engineer's design drawings.
10.2.6 Where the Contractor prepares the final record drawings, the Engineer shall furnish the Contractor the drawing files for that purpose on the terms of use the Engineer states, and the Contractor's use of the files shall be limited to the preparation of the record drawings.
10.2.7 The final record drawings shall be delivered in the formats indicated in the datasheet.
Final Record Drawing Formatcheckbox
☑ Searchable PDF scans of the marked-up record prints
☐ CAD files, revised from the Engineer's design files to the record condition
☐ The building information model revised to the record condition
☐ GIS data of the buried utilities and structures in the Owner's coordinate system
NOTE The scanned markups are the record itself and the one format every project delivers, because they are the Contractor's own hand and cannot be mistaken for a design drawing. Revised CAD files give the Owner drawings it can edit for the next project, at the cost of the drafting and of the Engineer's files being released and reworked. A revised model is asked for by an Owner that manages the facility from its model, and it costs the modeling of every change the markups show. GIS data of the buried utilities is what a utility Owner loads into the system its crews locate from, and it costs the survey in the Owner's coordinates under Construction Progress DocumentationConstruction Progress DocumentationResolves to the current adopted revision.sync/construction-progress-documentation and the attribution of each element in the Owner's schema, which the Contract Documents state. (10.2.8)
10.2.9 Where the Contractor prepares the final record drawings, it shall deliver them within the number of days after the Engineer's acceptance of the marked-up record documents indicated in the datasheet.
Final Record Drawing Delivery After Acceptance of the Record Markupsrange
Not more than
days
1430456090
NOTE Thirty days is enough to scan a set of markups and index it, and a longer period is set only where revised CAD files, a model, or GIS data are indicated, because each of those is drafting rather than scanning and a plant's drawing set runs to hundreds of sheets. The period runs from the Engineer's acceptance of the markups so that the Contractor is not drafting from a record the Engineer has sent back. (10.2.10)
10.2.11 The Contractor shall deliver with the record drawings the record specifications, marked to show the product furnished under each section, each accepted substitution and comparable product, and each addendum and modification incorporated, and the record product data, consisting of the reviewed submittals for each product as furnished.
10.2.12 The record documents shall include the closed request for information log and the record of transmittals delivered under Project Management And CoordinationProject Management and CoordinationResolves to the current adopted revision.sync/project-management-and-coordination, and the shop drawings, product data, and samples record that Submittal And Quality ProceduresSubmittal and Quality ProceduresResolves to the current adopted revision.sync/submittal-and-quality-procedures maintains.
10.2.13 Where a technical standard lists the record content for its system, that content is the system's part of the record documents, and it shall be assembled and delivered in the form and at the milestone this article requires.
11 Spare Parts and Spare Materials Delivery
11.1 Delivery Procedure
11.1.1 The Contractor shall deliver to the Owner the spare parts, spare materials, special tools, and other surplus items each product standard requires, in the items and quantities that standard states, by the procedure in this article.
NOTE Each product standard states what is delivered with its product and how much: the filters, the belts, the seals, the ceiling tile, the flooring, the paint. What every one of those deliveries has in common is where it goes, how it is packaged and labeled, who signs for it, and when it arrives, and this article states that once so that the product standards state only the items and the quantities. (11.1.2)
11.1.3 Spare parts, spare materials, and special tools shall be delivered to the location indicated in the datasheet.
Spare Parts and Materials Delivery Locationradio
○ A storage room within the Work that the Owner designates in writing
○ The Owner's existing storeroom, warehouse, or maintenance shop on or near the site
○ An address off the site the Owner states in writing, shipped at the Contractor's cost
NOTE A room within the Work is where the material is nearest to where it will be used, and it is the location on a new facility that has one; it depends on the room being finished and lockable before the delivery. The Owner's existing storeroom puts the parts on the shelf with the Owner's other stock under its own inventory control, which is where a utility with a maintenance shop wants them, and it is available from the first day of the Work. An address off the site is the arrangement for an Owner whose stores are central and whose facility has no staff, and it costs the Contractor the shipping and the Owner the step of matching the shipment to the receipt. (11.1.4)
11.1.5 Spare parts and spare materials shall be delivered in the manufacturer's original, unopened packaging, and where a quantity is less than a full package, in a sealed container the manufacturer supplies or the Contractor labels as this article requires.
11.1.6 Each package shall be labeled, on the outside and in a form that survives storage, with the name of the product, the manufacturer and the manufacturer's part or product number, the equipment number or tag of the equipment it serves or the color, finish, pattern, and lot of the material and the rooms or areas in which the matching material is installed, the quantity in the package, and the specification section under which it was furnished.
11.1.7 The Contractor shall store spare parts and spare materials, from their arrival on the site until the Owner's receipt, in a conditioned and secure space in which they are protected from moisture, temperature, dust, and damage as the product standard for the material requires, and shall replace at its own cost any item damaged before the Owner's receipt.
11.1.8 The Contractor shall replace, before delivery to the Owner, any spare part or spare material consumed during startup, testing, demonstration, or the correction of punch list items, so that the Owner receives the full quantity the product standard requires.
11.1.9 The Contractor shall obtain the Owner's signed receipt for each delivery, itemizing every package by the label information this article requires, and the signed receipts shall be the Contractor's evidence that the delivery was made.
11.1.10 Spare parts, spare materials, and special tools for the Work, or for a designated portion, shall be delivered before the substantial completion inspection of the Work or of the portion containing the product they serve, and not before the Owner has designated the location and is ready to receive them.
11.1.11 The Contractor shall include in the closeout package an inventory of every spare part, spare material, and special tool delivered, listing the product, the quantity, the location delivered to, the date, and the receipt that covers it.
NOTE A box of ceiling tile with no label is a box of tile the Owner cannot match to a room, and a pump seal delivered to a trailer that was demobilized the next week is a seal no one can find. The label, the receipt, and the inventory are the three records that make a delivery a delivery, and the receipt is the one that ends the argument about whether it happened. (11.1.12)
12 Demonstration and Training
12.1 Training Plan and Notice
12.1.1 The Contractor shall deliver training to the Owner's operating and maintenance staff on each system and item of equipment for which a product standard requires training, and on every system within the commissioning scope under CommissioningTotal Building CommissioningResolves to the current adopted revision.sync/commissioning.
12.1.2 The Contractor shall submit a training plan to the Engineer not less than the number of days before the first training session indicated in the datasheet, listing each system and item of equipment on which training will be delivered, the sessions proposed for it, the instructor and the instructor's qualification for each, the duration and the agenda of each session, the materials to be used, the group of the Owner's staff each session is for, and the proposed dates.
Training Plan Submission Before the First Sessionrange
Not less than
days
1421304560
NOTE The plan is what the commissioning authority reviews against the Owner's requirements under CommissioningTotal Building CommissioningResolves to the current adopted revision.sync/commissioning and what the Owner uses to decide who attends, and both take time: a plan submitted two weeks before the first session suits a building with a handful of systems and an Owner with a facilities staff already on the payroll, and a plan submitted a month or two ahead suits a plant with thirty pieces of equipment, operators on three shifts, and a manufacturer's representative who has to be booked for each. (12.1.3)
12.1.4 The Contractor shall give the Owner and the Engineer written notice of each training session not less than the number of days before the session indicated in the datasheet, stating the system, the date, the time, the location, the duration, and the instructor.
Notice Before Each Training Sessionrange
Not less than
days
57101421
NOTE The notice is what lets the Owner pull an operator off a shift and the commissioning authority attend the sessions it has to witness, and a session the Owner's staff could not attend is a session that has to be given again. A week's notice is enough for an Owner with staff on the site; two or three weeks is needed where the attendees travel from the Owner's other facilities or where the Owner's shift schedule is set a month ahead. (12.1.5)
12.1.6 The Owner shall designate the attendees for each session and shall make them available on the date the notice states, and where the Owner postpones a session after the notice period has run, the session shall be rescheduled and the cost of the instructor's return shall be the Owner's, determined under Contract Modification ProceduresContract Modification ProceduresResolves to the current adopted revision.sync/contract-modification-procedures.
12.2 Delivery of Training
12.2.1 Each training session shall be delivered by the manufacturer's representative where the product standard requires the manufacturer's field services for training, and otherwise by the manufacturer's representative or the installer of the system, and in every case by a person who is familiar with the system as installed on the project and competent to teach its operation and maintenance.
12.2.2 Training shall be delivered at the site, on the installed equipment, after the system has been started and has passed the tests its standard requires, and shall use the operation and maintenance manual for the system, reviewed under Operation And Maintenance DataOperation and Maintenance DataResolves to the current adopted revision.sync/operation-and-maintenance-data, as its reference material.
12.2.3 Each training session shall cover the startup of the system, its normal operation in each control mode, its shutdown, its emergency and manual operation, its alarms and protective devices and the response to each, the lockout and isolation of its energy sources, the routine maintenance in its maintenance schedule, and the troubleshooting its manual describes, and where the Owner's operating staff and maintenance staff are separate groups, the operation and the maintenance content shall be delivered as separate sessions to the group that performs each.
12.2.4 The duration of training on each system shall be as the product standard governing it states, and where the product standard states none, shall be as the training plan proposes and the Engineer accepts as sufficient to cover the content this article requires.
12.2.5 Training on every system shall be complete by the milestone indicated in the datasheet.
Training Completion Milestoneradio
● Before the substantial completion inspection of the Work or of the portion containing the system
○ Before final completion
○ Within the period after substantial completion the Owner designates so that its operating staff are in place
NOTE Training before substantial completion puts a trained operator at the controls on the day the Owner takes over, which is what a plant the Owner starts running that day needs and what most projects require, and it depends on the Owner's staff being hired by then. Training before final completion gives the Contractor the punch list period to schedule the sessions around the Owner's move-in, at the cost of the Owner operating untrained for that period. A period the Owner designates after substantial completion is the arrangement for a new facility whose operators are hired after the building is finished, and it keeps the instructor's obligation open until the Owner names the date, which the Contractor prices. (12.2.6)
12.2.7 A session delivered without the notice this standard requires, without the reviewed operation and maintenance manual, on a system that has not been started and tested, or by a person not qualified under this article shall be delivered again at the Contractor's cost.
12.3 Training Records and Recording
12.3.1 The Contractor shall record each training session on an attendance sheet signed by the instructor and by each attendee, stating the system, the date, the duration, and the agenda as delivered, and shall deliver the agenda and the attendance sheet for every session in the closeout package, with a copy retained in the operation and maintenance package under Operation And Maintenance DataOperation and Maintenance DataResolves to the current adopted revision.sync/operation-and-maintenance-data.
12.3.2 Training sessions shall be recorded as indicated in the datasheet.
Training Session Recordingradio
○ Not recorded
○ Recorded on video by the Contractor, with the recordings delivered in the closeout package
○ Recorded by the Owner with its own equipment, with the Contractor's consent given by this clause
NOTE A recording lets the Owner train the operator hired two years after the Contractor left on the system as it was taught the first time, and it is asked for on a facility whose operators turn over, on a plant with few of them, and on any system whose manufacturer's representative will not come back for free. The Contractor recording it delivers a product the Owner can file with the manuals, at the cost of a camera operator and the editing of each session into a usable file; the Owner recording it costs the Contractor nothing and relies on the Owner to do it. No recording suits a facility with a stable staff and a manual good enough to train from. (12.3.3)
12.3.4 Where the Contractor records the sessions, each recording shall be delivered in a format the Owner can play without a license, labeled with the system, the date, and the instructor, and indexed in the closeout package.
13 Permits, Occupancy, and Operating Approvals
13.1 Closing of Permits
13.1.1 The Contractor shall schedule and pass the final inspection for every permit it or a lower tier holds, including the building, electrical, plumbing, mechanical, fire alarm, fire suppression, elevator, and other trade permits, and shall deliver the final inspection record or the closed permit for each to the Owner in the closeout package.
NOTE Each trade pulls its own permit, and no one drives the final inspection on a permit whose work is finished, so permits are left open for years after a facility is in use, until the Owner's next project finds them. Naming the Contractor as the party that closes every permit, and making the closed permit a closeout deliverable, is what gets them closed. (13.1.2)
13.2 Certificate of Occupancy
13.2.1 Where Adopted Building CodeAdopted Building CodeParameterEach project supplies its own value.adopted-building-code requires a certificate of occupancy before a building or a portion of it is occupied, the certificate shall be obtained by the party indicated in the datasheet before the Owner occupies it.
Party Obtaining the Certificate of Occupancyradio
○ The Contractor, as the holder of the building permit
○ The Owner, as the holder of the building permit, on the inspections and documents the Contractor furnishes
NOTE The party that holds the building permit is the party the building official issues the certificate to, and the datasheet records which that is. A Contractor that pulled the permit obtains the certificate as part of closing it, and it carries the cost of every inspection and correction the official requires. An Owner that pulled the permit, which a public Owner building on its own land often does, obtains the certificate itself, and the Contractor's obligation is to pass the inspections, to furnish the test reports, the commissioning report, and the other documents the official requires, and to correct what the official finds, so that the Owner's application is not held up by the Work. (13.2.2)
13.2.3 Where a certificate of completion, rather than a certificate of occupancy, is the document the authority having jurisdiction issues for a structure that is not occupied, the same party shall obtain it on the same terms.
13.2.4 The Contractor shall furnish, before the certificate of occupancy is requested, every test report, inspection record, certification, and commissioning document the authority having jurisdiction requires for its issuance, including the preliminary commissioning report and the integrated test report under CommissioningTotal Building CommissioningResolves to the current adopted revision.sync/commissioning where the authority requires them, and shall correct at its own cost every condition the authority identifies as preventing issuance.
13.2.5 A temporary certificate of occupancy, where the authority issues one, shall not satisfy a readiness condition or a closeout deliverable that calls for the certificate of occupancy, and the Contractor shall obtain the final certificate before final completion.
13.2.6 The Contractor shall deliver the certificate of occupancy, or the certificate of completion, to the Owner in the closeout package, and where the Owner obtained it, the Owner shall furnish the Contractor a copy for the package.
NOTE A certificate the Contractor obtained and did not deliver leaves the Owner unable to prove lawful occupancy to its insurer or its lender, and the obligation is the transmittal, not the issuance. A temporary certificate is issued on conditions and expires, and a facility occupied on one for years is a facility whose permit was never closed. (13.2.7)
13.3 Operating Approvals for Regulated Facilities
13.3.1 Where a regulatory agency's approval is required before a water, wastewater, or other regulated facility, or a portion of one, may be placed in permanent service, the Owner shall apply for the approval as the permittee, and the Contractor shall furnish every test result, disinfection and bacteriological record, pressure and leakage test record, certification, record drawing, and inspection the approval requires, within the time the Owner's application needs, and shall correct at its own cost every condition the agency identifies as preventing approval.
13.3.2 The operating approval for a facility, or for a portion of one, shall be in hand before the certificate of substantial completion for it is issued where the datasheet under Readiness for the Substantial Completion Inspection requires it, and in every case before the Owner places the facility in permanent service.
NOTE The approval to operate a water or wastewater facility belongs to the Owner that holds the operating permit, and the agency issues it to the Owner on the evidence the Contractor produces: the disinfection of the main, the test of the tank, the record drawing of the pipe. The Contractor cannot apply for it and the Owner cannot produce the evidence, which is why the obligation is split as it is, and why a facility whose approval has not arrived is not substantially complete where the Owner has said so in the datasheet. Placing a new facility in service to keep an existing plant running, before the approval or the certificate, is governed by Maintenance Of Plant OperationsMaintenance of Plant OperationsResolves to the current adopted revision.sync/maintenance-of-plant-operations and does not constitute substantial completion. (13.3.3)
14 Closeout Package
14.1 Assembly and Delivery
14.1.1 The Contractor shall assemble every closeout deliverable this standard and the standards it names require into one closeout package, indexed so that each deliverable can be located by the standard that required it and by the system or the subject it covers, and shall deliver the package to the Engineer before requesting the final inspection.
14.1.2 The closeout package shall be delivered in the medium, the format, and the number of copies Operation And Maintenance DataOperation and Maintenance DataResolves to the current adopted revision.sync/operation-and-maintenance-data requires for the operation and maintenance package, so that the Owner holds one set of closeout records in one form.
14.1.3 The Contractor shall carry into the closeout package the closeout submittals that CommissioningTotal Building CommissioningResolves to the current adopted revision.sync/commissioning requires of the commissioning authority, the warranty book that Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds requires, the progress documentation that Construction Progress DocumentationConstruction Progress DocumentationResolves to the current adopted revision.sync/construction-progress-documentation requires, the platform export, the request for information log, and the transmittal record that Project Management And CoordinationProject Management and CoordinationResolves to the current adopted revision.sync/project-management-and-coordination requires, and the certificate of return or destruction that Document Confidentiality And Ai UseDocument Confidentiality and AI UseResolves to the current adopted revision.sync/document-confidentiality-and-ai-use requires, and each of them shall be a condition of final completion whether or not the standard that requires it says so.
NOTE Every one of the standards named above produces a record that the Owner's operators will look for in one place, and each of them hands the record to this package. The index is what makes the package findable, and the condition on final completion is what makes it complete: a deliverable that is not a condition of the last payment is a deliverable that arrives after it, or never. (14.1.4)
14.1.5 The Engineer shall review the closeout package for completeness against the index and against the submittal lists of this standard and of the standards it names, and shall return in writing, within the inspection period, a list of every deliverable missing or not accepted, and the Contractor shall furnish or correct each before requesting the final inspection.
14.1.6 The Contractor shall deliver with the closeout package a written statement that every closeout deliverable has been submitted, listing each by the standard that required it and the date it was delivered.
15 Final Completion and Final Inspection
15.1 Request for the Final Inspection
15.1.1 The Contractor shall request the final inspection in writing only after every item on the punch list has been completed and accepted, the closeout package has been delivered and the Engineer's completeness review returned without a missing item, the final record documents have been delivered, the training required before final completion has been delivered, every permit has been closed and the certificate of occupancy or the operating approval delivered, and the temporary facilities have been removed under Temporary Facilities And ControlsTemporary Facilities and ControlsResolves to the current adopted revision.sync/temporary-facilities-and-controls except those the Owner has asked to remain.
15.1.2 The request for the final inspection shall be accompanied by the Contractor's statement that the Work is complete in accordance with the Contract Documents and by the list of punch list items with the date each was accepted.
15.2 The Final Inspection and Final Completion
15.2.1 The Engineer shall make the final inspection within the inspection period after receiving the request, with the Contractor and the Owner's representative present.
15.2.2 Where the final inspection finds the Work complete in accordance with the Contract Documents and every closeout deliverable received and accepted, the Engineer shall certify final completion by the final certificate for payment the General Conditions prescribe, and the date of final completion shall be the date the Engineer states on that certificate.
15.2.3 Where the final inspection finds the Work not complete, the Engineer shall notify the Contractor in writing, within the inspection period, of each item that prevents final completion, and the Contractor shall complete or correct each item and shall request another final inspection.
15.2.4 Final completion shall not release the Contractor from the correction period and the warranties under Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds, from the seasonal and deferred tests and the warranty-period review under CommissioningTotal Building CommissioningResolves to the current adopted revision.sync/commissioning, from the obligations that Document Confidentiality And Ai UseDocument Confidentiality and AI UseResolves to the current adopted revision.sync/document-confidentiality-and-ai-use states survive final payment, or from any other obligation the Contract Documents state survives completion.
NOTE Final completion is the day the Contractor's work on the site ends, and it is written so that it is not the day its obligations end. The correction period runs for a year or more past it, the seasonal test waits for the season, and the confidentiality of the documents it holds does not expire; each of those is governed by the standard that states it, and this clause is what keeps the final certificate from being read as a release of them. (15.2.5)
16 Final Payment and Release of Retainage
16.1 Release of Retainage at Substantial Completion
16.1.1 On the issuance of the certificate of substantial completion for the Work, the retainage held on the Work under Payment ProceduresPayment ProceduresResolves to the current adopted revision.sync/payment-procedures shall be treated as indicated in the datasheet.
Retainage Release at Substantial Completionradio
○ Released, less the amount held for incomplete and uncorrected items and for outstanding claims
○ Reduced to the percentage of the Contract Sum the Agreement states, with the balance held to final payment
○ Held in full to final payment
NOTE Releasing the retainage at substantial completion, less what the punch list and any claim are worth, pays the Contractor and its subcontractors for the Work the Owner is now using and leaves the Owner holding a fund sized to what remains, which is the arrangement the general conditions in common use contemplate and the one most retainage statutes require of a public Owner at that point. Reducing it to a stated percentage of the Contract Sum keeps a larger fund through the punch list period than the list is worth, which an Owner uses where the list is long or the Contractor's performance has been poor, and the percentage is a financial term the Agreement states. Holding it in full to final payment is the simplest arrangement and the one that keeps the Owner's whole fund in place until the last deliverable is in, at the cost of every subcontractor waiting for the last one. The percentage, where one applies, is stated in the Agreement and not in this standard, because it is a term between the parties on which this standard takes no side. (16.1.2)
16.1.3 Where retainage is released at substantial completion, the Owner shall hold from it, for each item on the punch list, the multiple of the Engineer's estimate of the cost of completing or correcting the item indicated in the datasheet, and shall release the amount held for each item on its acceptance.
Retainage Held Against Each Incomplete Item at Substantial Completionrange
times the Engineer's estimated cost
11.522.53
16.1.5 The release of retainage at substantial completion shall be conditioned on the consent of surety to the reduction in or partial release of retainage under Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds where the performance bond is in force, and on the final lien waivers for the Work covered by the release where the datasheet requires final waivers to be unconditional.
16.1.6 Where the retainage law governing the Owner requires the release of retainage at substantial completion or at another point, caps the amount held after it, or requires that it be released within a stated time after a request, that law shall govern over the values indicated in the datasheet.
16.1.7 The Contractor shall release to each subcontractor and supplier whose Work is complete and accepted the retainage it withholds from that party, in the same proportion and within the same time after receipt as the Owner releases retainage to the Contractor.
16.2 Final Application for Payment
16.2.1 The Contractor shall submit the final application for payment after the Engineer has certified final completion, on the form and with the continuation sheet the progress applications used under Payment ProceduresPayment ProceduresResolves to the current adopted revision.sync/payment-procedures, stating the Contract Sum as finally adjusted by every change order, the total previously paid, the retainage held, and the balance due, which shall include the release of every amount retained.
16.2.2 The final application for payment shall be accompanied by each of the final payment submittals this standard requires, and the Engineer shall not certify it, and the Owner shall not pay it, until each has been received and accepted.
16.2.3 The Engineer shall review the final application within the time the Agreement sets for an application for payment and shall certify the amount due or shall notify the Contractor and the Owner in writing of the reasons for certifying a lesser amount, and the Owner shall pay the certified amount within the time the Agreement and the prompt-payment law governing the Owner set.
16.2.4 The Owner may withhold from final payment the scheduled value of any closeout deliverable priced as a separate line item under Payment ProceduresPayment ProceduresResolves to the current adopted revision.sync/payment-procedures that has not been received and accepted, and the amount the Engineer estimates as the cost of any Work not complete or not corrected, and shall release each amount when the deliverable is accepted or the Work is complete.
16.2.5 The holdback at final payment for the seasonal and deferred tests under CommissioningTotal Building CommissioningResolves to the current adopted revision.sync/commissioning whose condition has not yet occurred, and for the correction of what they find, shall be as indicated in the datasheet.
Holdback at Final Payment for Open Seasonal and Deferred Testsradio
○ No holdback, the Contractor's obligation surviving final payment on its undertaking and the performance bond
○ The Engineer's estimate of the cost of the open tests and of correcting what they find, held until each test is complete
NOTE No holdback closes the Contract on the day the Work is done and relies on the Contractor's written undertaking and the performance bond, which remains in force through the correction period under Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds, to bring the Contractor back for the heating test in January, and it is the arrangement where the Contractor is local and the bond is adequate. A holdback keeps money on the table until the last test is run, which is the arrangement a public Owner uses where its experience is that a paid Contractor does not return, and it costs the Contractor and its subcontractors the interval to the season and the Owner the administration of one more release. The obligation to perform the tests survives final payment under either arrangement. (16.2.6)
16.2.7 The Contract Sum as finally adjusted shall account for every change order, every unit price item at its measured quantity, every allowance at its reconciled amount, and every credit due the Owner, each under the standard that governs it, and no claim for an adjustment not made before the final application shall be included in it except as the General Conditions permit.
16.2.8 The effect of the Owner's final payment, and of the Contractor's acceptance of it, on the claims of either party shall be as the General Conditions provide, and nothing in this standard shall enlarge or reduce it.
16.3 Affidavits, Final Lien Waivers, and Consent of Surety
16.3.1 The Contractor's affidavit of payment of debts and claims shall be executed by an officer or authorized representative of the Contractor, shall be notarized where the Agreement or the law of the jurisdiction requires it, and shall list every debt connected with the Work that has not been paid and the reason.
16.3.2 The final lien waivers shall be furnished on the condition indicated in the datasheet.
Final Lien Waiver Conditionradio
○ Conditional on receipt of the final payment, with unconditional waivers delivered after payment
○ Unconditional, delivered with the final application for payment
NOTE A conditional final waiver releases the lien right the moment the final payment arrives and not before, which is the waiver a subcontractor can sign without giving up a claim for money it has not received, and it is the arrangement the lien law of most states contemplates and several prescribe a form for; it costs the Owner a second collection, of the unconditional waivers after it has paid. An unconditional waiver delivered before payment gives the Owner a clean title before it releases the last dollar, which a lender financing the project often requires, and it asks every subcontractor and supplier to release a lien right on the Contractor's promise to pay, which the subcontractors resist and the lien law of some states does not enforce. (16.3.3)
16.3.4 Where conditional final waivers are indicated, the Contractor shall deliver the unconditional final waiver from itself and from each subcontractor and supplier within fourteen days after it receives the final payment, and the Owner may withhold any later payment, release, or return of security until they are received.
16.3.5 Each final lien waiver shall be on the form the lien law of the jurisdiction prescribes, and where that law prescribes no form, on the form the Owner provides or the Engineer accepts, and shall state the amount of the final payment it is conditioned on or the amount through which it releases.
16.3.6 Where the Owner's property cannot be liened, the final waivers shall be releases, in the same form, of every claim against the payment bond under Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds and against the Contract funds for the Work covered.
16.3.7 Where a subcontractor or supplier refuses to furnish a final waiver, or a lien or a claim remains unreleased when the final application is made, the Contractor shall furnish the Owner a bond, in the amount the Owner determines is sufficient, indemnifying the Owner against the lien or the claim, and shall pay the Owner every cost, including attorney's fees, the Owner incurs in discharging a lien the Contractor should have satisfied.
16.3.8 The Contractor's affidavit of release of liens shall list every final waiver furnished, by the party and the amount, and every lien, claim, or waiver outstanding, and shall be executed and notarized as the affidavit of payment of debts and claims is.
16.3.9 Where a performance bond is in force, the consent of surety to final payment, in the form and with the content Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds requires, shall be furnished with the final application for payment, and no final payment shall be made without it.
NOTE A waiver on the wrong form is unenforceable in the states that prescribe one, a conditional waiver filed as unconditional releases nothing, and a final payment made without the surety's consent hands the surety a defense the day the Owner needs the bond. The three documents in this article are collected at the one moment the Contractor still has money at stake, and each is checked for the defect that would make it worthless later. (16.3.10)
17 Coordination with the Agreement and Other Standards
17.1 The Contractor shall reconcile the closeout requirements of the Agreement, the General Conditions, the Supplementary Conditions, and each technical standard with this standard, and shall report in writing, not later than the submission of the training plan, any conflict between them.
17.2 Where a technical standard and this standard address the same subject, the more stringent requirement shall govern unless the Contract Documents direct otherwise.
17.3 The Contractor shall include in each subcontract and purchase order the record document, spare parts delivery, training, punch list, final cleaning, final lien waiver, and affidavit requirements of this standard that apply to the subcontractor's or supplier's scope, and the retainage release terms that flow down under this standard.
NOTE A subcontractor that finished its Work in the first month learns at closeout that the lien waiver it is asked for is on a form it has never seen, that the spare parts it delivered to the Contractor's trailer were never receipted, and that the record markups it was supposed to keep were never asked for. Flowing the requirements into the subcontract is what makes each of them the subcontractor's obligation from the start, and what lets the Contractor assemble a complete package when the Owner asks for it. (17.4)
This standard is written and maintained by SynC and licensed under Creative Commons Attribution 4.0. You may share and adapt it, including commercially, provided you credit SynC Standards, link to the license, and indicate any changes. Each standard is drafted from cited sources under published authoring rules, reviewed before adoption, and corrected in the open. Keep the attribution and notice below with any copy; it carries the warranty notice the license asks you to retain.
"Closeout Procedures," SynC Standards, revision 5. Licensed under CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Source: https://synergyinconstruction.com/standards/general/closeout-procedures. Reference material only; not professional engineering advice and provided without warranty. Verify against governing codes and have a licensed professional review before use.