Submittal and Quality Procedures

Rev 2 · Updated Jun 14, 2026 · View history

Build a datasheet from this standard Start a project with this standard already attached — one click, no setup.
Use in a project

1 Scope

NOTE This standard establishes the administrative framework that governs how the Contractor submits information for review and how quality is controlled and verified on the Work. (1.1)
NOTE The submittal and quality requirements stated here apply to the Work of every technical specification section in the project manual unless a technical section states a more specific requirement, in which case the more specific requirement governs. (1.3)
1.4This standard governs the administrative submittal and quality-control regime for the entire project manual.
1.5Each technical specification section shall enumerate the specific submittals it requires; this standard governs only how those submittals are processed, not which items each section demands.
NOTE Statutory special inspections and structural testing mandated by the building code are administered under Special Inspections And Testing and are outside the scope of this standard. (1.6)
NOTE Functional performance testing of integrated building systems is administered under Commissioning and is outside the scope of this standard. (1.7)

2 Referenced Standards

2.1Work performed under this standard shall comply with the latest adopted edition of each of the following unless a specific edition is cited.
2.2Where referenced standards or the contract documents conflict, the more stringent requirement shall govern unless the Architect or Engineer of Record directs otherwise in writing.
NOTE The contract's general conditions are the operative authority for submittal and review obligations; the standards below supplement, but do not supersede, the executed contract. (2.3)
Standard Title
AIA A201-2017 General Conditions of the Contract for Construction (§3.12 submittals; §4.2.7 review)
ASTM E329-21 Specification for Agencies Engaged in Construction Inspection, Testing, or Special Inspection
ASTM D3740-19 Practice for Minimum Requirements for Agencies Engaged in Testing and/or Inspection of Soil and Rock
ISO 9001:2015 Quality Management Systems — Requirements
EM 385-1-1 USACE Safety and Health Requirements Manual (three-phase QC control)
IBC Chapter 17 International Building Code — Special Inspections and Tests (coordination reference)

3 Submittals

NOTE Submittals are the means by which the Contractor demonstrates, in advance of fabrication or installation, that the proposed products and methods conform to the contract documents. (3.1)
NOTE Under AIA A201-2017 §3.12, shop drawings, product data, and samples are not themselves contract documents; they are the Contractor's representation of how the contract will be satisfied, and review of them does not relieve the Contractor of responsibility for conformance. (3.2)
NOTE The Architect's review and approval of a submittal is for general conformance with the design intent only. (3.3)
3.4Approval of a submittal shall not be construed as approval of dimensions, quantities, field measurements, or fabrication means and methods, which remain the Contractor's responsibility.
NOTE Stating the limits of approval expressly in the specification prevents the recurring dispute in which a contractor treats an approval stamp as the Architect's verification of dimensions or quantities it never undertook to check. (3.5)

3.6 Submittal Classification

NOTE Every required submittal shall be classified as either an action submittal or an informational submittal. (3.7)
NOTE The single most common submittal dispute arises from blurring these two categories: a contractor proceeds on an item the Architect merely received for record, or waits for approval the Architect was never obligated to give. The specification must state which class each item falls into. (3.9)
3.10Each submittal shall be transmitted marked with its classification as either an action submittal or an informational submittal.
3.11Action submittals shall not be released to fabrication or installation until returned marked "Approved" or "Approved as Noted."
3.12Select the classification regime that the project manual will enforce.
Submittal classification regimeradio
Action vs. informational, classified per item by specification section
Action vs. informational, classified centrally in the submittal register
Single review track (all submittals treated as action)

3.13 Submittal Types

NOTE The submittal types below cover the deliverables this standard governs; each technical section selects which apply to its Work. (3.14)
NOTE Shop drawings are Contractor-prepared drawings showing fabrication, assembly, connection, and installation detail for a specific element of the Work; they are an action submittal. (3.15)
NOTE Product data are the manufacturer's published technical data, performance characteristics, and installation instructions for a proposed product; they are an action submittal. (3.16)
NOTE Samples are physical specimens of a material, product, or finish submitted to confirm color, texture, pattern, and quality; they are an action submittal where exposed finishes, cladding, or millwork are involved. (3.17)
NOTE Delegated-design submittals are Contractor-furnished, professional-engineer-sealed calculations and drawings for systems the contract documents performance-specify rather than fully detail. (3.18)
NOTE Operation and maintenance (O&M) data are manufacturer manuals and maintenance schedules compiled into the project O&M manual; they are an informational submittal delivered at closeout. (3.19)
3.20Select the submittal types required across the project.
Required submittal typescheckbox
Shop drawings
Product data
Samples (color, finish, material)
Delegated-design (PE-sealed) packages
Operation and maintenance data
Mock-ups

3.21 Action Submittals

  • Shop drawings for each fabricated assembly, showing fabrication, dimensions, connections, and installation detail
  • Product data for each manufactured product, including performance data and installation instructions
  • Samples for each exposed material, finish, and color
  • Delegated-design calculations and drawings, sealed by a professional engineer, for each performance-specified system
  • A submittal schedule coordinated with the construction schedule
Action submittalscheckbox
Shop drawings
Product data
Samples
Delegated-design (PE-sealed) packages
Submittal schedule

3.23 Informational Submittals

3.24The Contractor shall submit the following informational submittals for the record:
  • Qualification statements for the Contractor's QC organization and for any independent testing or inspection agency
  • The contractor quality-control plan
  • Manufacturer's certifications and material test reports where required by a technical section
  • Field test and inspection reports generated during construction
  • Operation and maintenance data and warranties at closeout
Informational submittalscheckbox
QC organization and agency qualifications
Contractor quality-control plan
Manufacturer certifications and test reports
Field test and inspection reports
O&M data and warranties

3.25 Submittal Register and Schedule

NOTE The submittal register is the master log that lists every required submittal by specification section, type, required submission date, and review status; it is the central control document for the entire submittal process. (3.26)
3.28The Contractor shall prepare and maintain a submittal register listing every required submittal by specification section, submittal type, required submission date, and current review status.
3.29The submittal register shall be updated and reissued to the Architect at intervals no longer than the project's regular progress-reporting cycle.
NOTE The submittal schedule embedded in the register sets when each submittal must be received so that review can be completed before the item is needed for fabrication or installation. (3.30)
NOTE A submittal schedule that is not coordinated with the construction schedule is the root of most submittal-driven delay claims: the submittal arrives too late for a full review cycle to close before the installation date, and the resulting compression is then blamed on the reviewer. (3.31)
NOTE Submittal lead time is inherently item-specific: the review-and-fabrication horizon for a stock lamp is nothing like that for a medium-voltage switchgear lineup, so no single figure can govern every product. The governing submission date for each item is the one fixed in the submittal schedule, which accounts for that item's own review cycle and fabrication lead time. The fields below set only the project-wide default minimum that applies to an item until the submittal schedule establishes a longer, item-specific date. (3.32)
3.33Each submittal shall be received no later than the date fixed for that item in the submittal schedule or, where the schedule fixes none, no later than the project-wide default minimum below.
Default minimum submittal lead time — standard itemsrange
weeks
212
Default: 4 weeks
3.34Long-lead fabricated items shall be scheduled in the submittal register for submission far enough ahead to absorb both the review cycle and the fabrication lead time; the default minimum below governs only until that item-specific date is set.
Default minimum submittal lead time — long-lead fabricated itemsrange
weeks
616
Default: 10 weeks

3.35 Review Periods

NOTE AIA A201-2017 §4.2.7 obligates the Architect to review submittals "with reasonable promptness," but that phrase is not a schedulable duration; on any project with a meaningful submittal volume it must be replaced with a stated calendar-day count. (3.36)
NOTE Specifying a definite review period in calendar or business days is the single highest-value clarification in this section: it converts an open-ended contractual standard into a schedulable commitment for both parties and forecloses the chronic RFI traffic that "reasonable promptness" generates. (3.37)
3.38The Architect shall return each initial submittal within the review period stated below, measured from receipt of a complete submittal.
Architect review period — initial submittalrange
business days
520
Default: 10 business days
3.39A resubmittal shall be returned within the resubmittal review period stated below.
Architect review period — resubmittalrange
business days
515
Default: 10 business days
3.40The review period shall not begin until a complete submittal is received; an incomplete submittal shall be returned without review and a new review period begun on resubmission.
NOTE Distinguishing the initial and resubmittal periods, and stating that incomplete submittals do not start the clock, prevents the two most common scheduling arguments at the review stage. (3.41)

3.42 Delegated-Design Submittals

NOTE Delegated design transfers responsibility for engineering a specified system from the design team to a professional engineer retained by the Contractor, typically for performance-specified systems such as cold-formed steel framing, pre-engineered components, and post-installed anchorage. (3.43)
NOTE The boundary between what is delegated and what the Engineer of Record (EOR) designs must be drawn explicitly, because an EOR cannot legally review, approve, or take responsibility for engineering outside the delegated scope, and an ambiguous boundary produces sealed submittals no one can properly act on. (3.44)
3.45The contract documents shall state, for each delegated-design system, the precise scope delegated to the Contractor's engineer and the design criteria the delegated design must satisfy.
3.46Delegated-design submittals shall bear the seal of a professional engineer licensed in the jurisdiction of the project.
3.47The EOR's review of a delegated-design submittal shall be limited to confirming that the delegated design satisfies the stated performance criteria and is compatible with the overall design; it shall not extend to checking the delegated engineer's calculations.
3.48Delegated-design calculations shall be retained by the Contractor for no less than the duration of the project warranty period.
3.49Select how the delegated-design boundary is documented.
Delegated-design scope documentationradio
Performance criteria stated in each technical section
Consolidated delegated-design criteria schedule in the project manual
Performance criteria shown on the structural drawings

4 Quality Assurance

NOTE Quality assurance comprises the contractor quality-control (QC) plan and the independent testing and inspection program; together they verify, during construction, that the Work conforms before it is concealed or accepted. (4.1)
NOTE This standard's quality regime is distinct from the building code's special-inspection program. Where the IBC Chapter 17 program applies, the Statement of Special Inspections, the special inspector's qualifications, and the structural reporting chain are administered under Special Inspections And Testing, and the agency engaged for code special inspections is not interchangeable with the agency engaged for general quality testing unless the contract expressly authorizes one agency to perform both. (4.2)
4.3Independent testing and inspection performed under this standard shall be coordinated with, but shall not substitute for, the IBC Chapter 17 special-inspection program administered under Special Inspections And Testing.
NOTE Using a single agency for both general quality testing and statutory special inspection without express contract authorization creates code-compliance exposure, because the two roles carry different qualification, independence, and reporting obligations. (4.4)

4.5 Contractor Quality-Control Plan

NOTE The contractor QC plan is the Contractor's written description of how it will organize, execute, and document control of quality on the Work, including the personnel responsible, the inspection procedures, and the records to be kept. (4.6)
NOTE On federal and public projects the plan is mandatory and is typically structured on the USACE three-phase control model: a preparatory phase before each definable feature of work, an initial phase at the start of that work, and a follow-up phase of continuing checks. On VA and large healthcare projects the plan is often required to be ISO 9001-aligned. (4.7)
NOTE A QC requirement with no stated consequence for non-submission or non-compliance is unenforceable; the specification must tie the plan to a hold on the affected Work so the requirement has effect. (4.8)
4.9The Contractor shall submit a written quality-control plan describing the QC organization, the personnel responsible and their authority, the control procedures for each definable feature of work, and the quality records to be maintained.
4.10The QC plan shall be submitted no later than the deadline below in advance of the first quality-control-required activity.
QC plan submission deadline before first QC activityrange
calendar days
730
Default: 15 calendar days
4.11Work on a definable feature shall not begin until the QC plan covering that feature has been accepted.
4.12Select the QC plan format the project requires.
Contractor QC plan formatradio
Project-specific QC plan (commercial standard)
USACE three-phase model (preparatory / initial / follow-up)
ISO 9001:2015-aligned QC plan
4.13Select the phased-control model the QC plan shall follow.
QC control phasingradio
Three-phase (preparatory, initial, follow-up)
Two-phase (initial, follow-up)
Inspection-and-test-plan only

4.14 Independent Testing and Inspection Agencies

NOTE Independent testing and inspection agencies provide the third-party verification — material sampling, laboratory testing, and field inspection — that the Contractor's own QC cannot impartially provide. (4.15)
NOTE Their competence is established by accreditation rather than assertion: ASTM E329-21 sets the personnel, equipment, and quality-system requirements for construction testing and inspection agencies, and ASTM D3740-19 does the same for soil and rock testing laboratories. Accreditation programs such as AASHTO (AAP), CCRL, AMRL, and IAS provide the independent confirmation that an agency meets those requirements. (4.16)
NOTE Whether the testing agency is engaged and paid by the Owner or by the Contractor must be stated, because an unstated arrangement leads contractors either to assume they bear no testing cost or to retain an unqualified low-bid laboratory. (4.17)
4.18Each independent testing and inspection agency shall meet the qualification requirements of ASTM E329-21, and each soil and rock testing laboratory shall meet ASTM D3740-19.
4.19Each agency shall hold current accreditation from a recognized program (AASHTO AAP, CCRL, AMRL, or IAS) for the test methods it will perform on the project.
4.20The Contractor shall submit the qualifications and accreditation of each proposed agency for acceptance before that agency performs any work.
4.21Each agency shall distribute test and inspection reports to the Owner, Architect, and Contractor within the reporting interval stated below after each test or inspection.
Test and inspection report distribution intervalrange
business days
110
Default: 3 business days
4.22Select how the independent testing and inspection agency is engaged.
Testing and inspection agency engagementradio
Owner-engaged and Owner-paid
Contractor-engaged and Contractor-paid
Hybrid (Owner engages structural/special; Contractor engages general)

4.23 Pre-Installation Meetings

NOTE A pre-installation meeting convenes the parties responsible for a definable feature of work before it begins, to confirm that submittals are approved, conditions are ready, and the installation sequence is understood. (4.24)
NOTE Holding the meeting before work starts, rather than diagnosing problems after, is the cheapest quality control available on most assemblies, particularly those with multiple trades or critical interfaces. (4.25)
4.26The Contractor shall convene a pre-installation meeting before beginning each definable feature of work designated in the contract documents.
4.27Each pre-installation meeting shall confirm that the governing submittals are approved, that substrate and environmental conditions are ready, and that the installation sequence and trade interfaces are agreed.
4.28Select which assemblies require a documented pre-installation meeting.
Pre-installation meeting required forcheckbox
Exterior cladding and curtain wall
Roofing and waterproofing
Below-grade and water-resistive assemblies
Fireproofing and firestopping
Flooring and exposed finishes
MEP equipment connections

4.29 Field Mock-Ups

NOTE A field mock-up is a full-scale, in-place prototype of a critical assembly, built and reviewed before production work begins, so that workmanship, appearance, and performance can be approved against a physical benchmark rather than a drawing. (4.30)
NOTE Mock-ups are standard on curtain wall, precast, masonry, and storefront scopes, and the approved mock-up becomes the standard of acceptance for the balance of that work — see also Architectural Precast Concrete and Cast Stone. (4.31)
NOTE A mock-up loses its value the moment it is demolished, so the specification must state a retention period; otherwise the Contractor removes the mock-up to recover materials and the quality benchmark for the rest of the work disappears. (4.32)
4.33The Contractor shall construct a field mock-up of each assembly designated for mock-up before beginning production work on that assembly.
4.34Each mock-up shall be reviewed and approved before production work proceeds, and the approved mock-up shall be the standard of acceptance for that assembly.
4.35The mock-up shall be retained in place until the retention milestone below, and shall not be removed earlier without the Owner's written authorization.
Mock-up retention milestoneradio
Until Substantial Completion
Until the related assembly is complete and accepted
Until Final Completion
4.36Select the minimum mock-up size for wall and cladding assemblies.
Minimum mock-up sizeradio
4 ft × 4 ft (wall assembly minimum)
8 ft × 8 ft (one full bay, exterior cladding)
Full-height single bay
4.37State whether the approved mock-up may be incorporated into the permanent Work.
Mock-up dispositionradio
Mock-up may be incorporated into the Work if undamaged and approved
Mock-up shall be removed and not incorporated

5 Non-Conforming Work

NOTE Non-conforming work is any portion of the Work that does not comply with the contract documents, whether discovered by the Contractor's QC, an independent agency, or the design team. (5.1)
NOTE A defined non-conformance process — prompt written notice, a documented disposition decision, and a record of the resolution — keeps defects from being quietly concealed and gives the Owner a basis to choose among repair, replacement, or acceptance with a price adjustment. (5.2)
5.3The Contractor shall give written notice of non-conforming work to the Owner and Architect within the notice period below after discovery.
Non-conforming work notice period after discoveryrange
business days
15
Default: 3 business days
5.4A disposition decision for each non-conformance shall be issued within the disposition period below after notice.
Non-conforming work disposition period after noticerange
business days
515
Default: 10 business days
5.5Non-conforming work shall not be concealed before its disposition is decided.
5.6The Contractor shall maintain a non-conformance log recording each non-conformance, its disposition, and the corrective action taken.
5.7Select the dispositions available for non-conforming work.
Available non-conforming work dispositionscheckbox
Repair in place with EOR/Architect acceptance
Remove and replace
Accept as-is with negotiated price reduction

6 Quality Documentation at Closeout

NOTE At closeout the submittal and quality records are assembled into the permanent project record that the Owner relies on to operate, maintain, and warrant the building. (6.1)
NOTE This standard governs only the submittal and quality records — the closed submittal register, test and inspection reports, the non-conformance log, and QC records. Assembly of the full O&M manual and record drawings is a separate Division 01 closeout function handled outside this standard. (6.2)
6.3The Contractor shall submit, at closeout, the closed submittal register showing the final status of every submittal.
6.4The Contractor shall submit the complete set of independent test and inspection reports and the non-conformance log with all dispositions resolved.
6.5The Contractor shall submit the operation and maintenance data and manufacturer warranties for the installed products.
6.6Select the quality records required at submittal closeout.
Closeout quality recordscheckbox
Closed submittal register
Independent test and inspection reports
Non-conformance log with resolved dispositions
QC plan records and phase checklists
O&M data and manufacturer warranties

Edit this page

SynC Standards are reference material provided for informational purposes only and as a guide. They are not engineering, architectural, or legal advice and are not a substitute for the judgment of a licensed design professional. It is the responsibility of the user to determine the applicability of any standard to a specific project and to verify all requirements against the governing codes, manufacturer data, and project conditions. SynC does not render professional services and forms no professional relationship by publishing this content. Provided "as is," without warranty of any kind, including fitness for a particular purpose. See our Terms of Use for the complete terms.

This standard is published by SynC and licensed under Creative Commons Attribution-ShareAlike 4.0. You may share and adapt it, including commercially, provided you give credit, link to the license, indicate any changes, and license your adaptations under the same terms. Keep the attribution and notice below with any copy — it includes the warranty disclaimer the license requires you to retain.

Attribution & reuse notice — keep this with any copy:
"Submittal and Quality Procedures." SynC Standards. Licensed under CC BY-SA 4.0 (https://creativecommons.org/licenses/by-sa/4.0/). Source: https://synergyinconstruction.com/wiki/sync/submittal-and-quality-procedures — reference material only; not professional engineering advice and provided without warranty. Verify against governing codes and have a licensed professional review before use.