SynC · SynC Standards
Electrical Acceptance Testing
Contents
- 1Scope
- 2Referenced Standards
- 3Submittals
- 3.1Action Submittals
- 3.2Informational Submittals
- 3.3Closeout Submittals
- 4Quality Assurance
- 4.1Testing Organization
- 4.2Technician Certification
- 4.3Test Instruments
- 4.4Electrical Safety During Testing
- 5Acceptance Test Program
- 5.1Equipment Within the Program
- 5.2Optional Tests Added to the Program
- 5.3Test Plan and Sequence
- 5.4Hold Points and Energization Release
- 5.5Coordination with Commissioning
- 6Acceptance Criteria
- 6.1Governing Source of a Criterion
- 6.2Insulation Resistance
- 6.3Bolted Connections and Contact Resistance
- 6.4Protective Device Settings
- 7Circuit Breaker and Trip Unit Testing
- 7.1Electronic Trip Unit Test Method
- 7.2Molded-Case Circuit Breaker Test Extent
- 7.3Power and Medium-Voltage Circuit Breaker Operation
- 8Protective Relay Testing
- 8.1Relay Test Scope
- 9Transformer Test Criteria
- 10Switchgear Bus and Cable Dielectric Tests
- 11Instrument Transformers and Metering
- 12Transfer Switches, Generators, Drives, and Stored-Energy Systems
- 13Infrared Survey
- 14Test Report
- 14.1Report Content
- 14.2Report Format and Delivery
- 14.3Deficiencies and Retesting
- 15Testing Services Warranty
Download
Build a datasheet from this standard
Start a project with this standard already attached — one click, no setup.
Use in a project
1 Scope
NOTE This standard governs the field acceptance test program for new electrical power distribution equipment rated 1000 V and below through 38 kV: the testing organization and its technicians, the instruments, the equipment and tests within the program, the sequence and the hold points, the acceptance criteria, the resolution of deficiencies, and the test report. (1.1)
NOTE Factory and production tests prove that the equipment left the factory in good order. They say nothing about damage in transit, errors in field assembly, contamination during construction, a bolted connection left loose, a shipping brace left in, or a trip unit set to values other than the study recommends. Acceptance testing is the independent check between a finished installation and the moment it is placed in service, and most of its tests cannot be performed, or cannot be performed safely, once the equipment is energized. (1.2)
NOTE The equipment standards and this standard divide the work in one way throughout the corpus. The equipment standard for a transformer, a switchboard, a motor control center, or a transfer switch names the field tests that equipment receives, in a checkbox its project selects from. This standard governs who performs those tests, what instruments and safety practices they use, the criteria a result is judged against, what happens when a result fails, and the report that records it all. A test an equipment standard requires is performed under this standard; a criterion this standard states applies to every equipment standard's test of that kind. (1.3)
NOTE The following are governed elsewhere and are outside this standard: (1.4)
- the short-circuit, coordination, and arc-flash studies, under Short Circuit StudyShort-Circuit StudyResolves to the current adopted revision.sync/short-circuit-study, Protective Coordination StudyProtective Device Coordination StudyResolves to the current adopted revision.sync/protective-coordination-study, and Arc Flash StudyArc-Flash StudyResolves to the current adopted revision.sync/arc-flash-study; the tests under this standard verify that the installed settings match those studies and do not perform them
- factory tests, witnessed or certified, under the equipment standard for each product
- the construction, ratings, and field test lists of the equipment itself, under Low Voltage SwitchgearLow Voltage SwitchgearResolves to the current adopted revision.sync/low-voltage-switchgear, Medium Voltage SwitchgearMedium Voltage SwitchgearResolves to the current adopted revision.sync/medium-voltage-switchgear, Metal Enclosed Interrupter SwitchgearMetal-Enclosed Interrupter SwitchgearResolves to the current adopted revision.sync/metal-enclosed-interrupter-switchgear, Generator Paralleling SwitchgearGenerator Paralleling SwitchgearResolves to the current adopted revision.sync/generator-paralleling-switchgear, Medium Voltage Bus DuctMedium-Voltage Metal-Enclosed BusResolves to the current adopted revision.sync/medium-voltage-bus-duct, Medium Voltage DrivesMedium-Voltage Variable Frequency DrivesResolves to the current adopted revision.sync/medium-voltage-drives, Low Voltage SwitchboardsLow Voltage SwitchboardsResolves to the current adopted revision.sync/low-voltage-switchboards, PanelboardsPanelboardsResolves to the current adopted revision.sync/panelboards, Motor Control CentersMotor Control CentersResolves to the current adopted revision.sync/motor-control-centers, Combination Motor StartersCombination and Manual Motor StartersResolves to the current adopted revision.sync/combination-motor-starters, Medium Voltage TransformersMedium-Voltage Distribution TransformersResolves to the current adopted revision.sync/medium-voltage-transformers, Low Voltage Dry Type TransformersLow-Voltage Dry-Type TransformersResolves to the current adopted revision.sync/low-voltage-dry-type-transformers, Secondary Unit SubstationsSecondary Unit SubstationsResolves to the current adopted revision.sync/secondary-unit-substations, Automatic Transfer SwitchesAutomatic Transfer SwitchesResolves to the current adopted revision.sync/automatic-transfer-switches, GeneratorsEngine GeneratorsResolves to the current adopted revision.sync/generators, and the other equipment standards named in this standard
- commissioning process management, functional performance testing, and systems integration testing, under CommissioningTotal Building CommissioningResolves to the current adopted revision.sync/commissioning
- the facility's written electrical safety program, its energized work permits, and its lockout procedures, under Electrical Safety ProgramElectrical Safety ProgramResolves to the current adopted revision.sync/electrical-safety-program
- the withstand test method, voltage, and duration for shielded medium-voltage cable, under Medium Voltage CablesMedium-Voltage CablesResolves to the current adopted revision.sync/medium-voltage-cables
- the grounding electrode resistance test method and target value on systems rated 1000 V and below, under Grounding And BondingGrounding and Bonding for Electrical SystemsResolves to the current adopted revision.sync/grounding-and-bonding
- the insulation resistance test of low-voltage building wire, under Conductors And CablesConductors and CablesResolves to the current adopted revision.sync/conductors-and-cables, and of motor windings, under Electric MotorsCommon Motor Requirements for Electrical EquipmentResolves to the current adopted revision.sync/electric-motors
- battery and uninterruptible power supply acceptance, under DC Battery SystemsDC Battery SystemsResolves to the current adopted revision.sync/dc-battery-systems and Uninterruptible Power Supply SystemsUninterruptible Power Supply SystemsResolves to the current adopted revision.sync/uninterruptible-power-supply-systems
- photovoltaic system commissioning, under Photovoltaic SystemsPhotovoltaic SystemsResolves to the current adopted revision.sync/photovoltaic-systems
- the labels and nameplates the visual inspection verifies, under Equipment LabelingElectrical Equipment LabelsResolves to the current adopted revision.sync/equipment-labeling
- maintenance testing of equipment in service, which ANSI/NETA MTS governs and which this standard's criteria do not apply to
1.5 Acceptance testing under this standard shall be performed on new equipment, on existing equipment modified or relocated under the project, and on existing equipment that the project reconnects to a new source.
2 Referenced Standards
2.1 Field testing shall comply with the latest adopted edition of each of the following unless a specific edition is cited.
2.2 Where the contract documents, the equipment manufacturer's published instructions, the Authority Having Jurisdiction, or two referenced standards impose conflicting requirements, the more stringent requirement shall govern unless the Engineer of Record directs otherwise in writing.
| Standard | Title |
|---|---|
| ANSI/NETA ATS | Standard for Acceptance Testing Specifications for Electrical Power Equipment and Systems |
| ANSI/NETA ETT | Standard for Certification of Electrical Testing Technicians |
| NFPA 70 | National Electrical Code (Articles 110, 230, 240, and 250) |
| NFPA 70B | Standard for Electrical Equipment Maintenance |
| NFPA 70E | Standard for Electrical Safety in the Workplace |
| IEEE 43 | Recommended Practice for Testing Insulation Resistance of Electric Machinery |
| IEEE 81 | Guide for Measuring Earth Resistivity, Ground Impedance, and Earth Surface Potentials of a Grounding System |
| IEEE C57.12.90 | Standard Test Code for Liquid-Immersed Distribution, Power, and Regulating Transformers |
| IEEE C57.12.91 | Standard Test Code for Dry-Type Distribution and Power Transformers |
| IEEE C57.13 | Standard Requirements for Instrument Transformers |
| IEEE C37.20.1 | Standard for Metal-Enclosed Low-Voltage Power Circuit Breaker Switchgear |
| IEEE C37.20.2 | Standard for Metal-Clad Switchgear |
3 Submittals
3.1 Action Submittals
3.1.1 The Contractor shall submit the following for review before any field test is performed:
- the testing organization's qualification statement, giving its accreditation, its independence from the installing contractor and the equipment suppliers, and its experience with equipment of each class within the program
- the certification record of every technician assigned to the project, giving the ANSI/NETA ETT level or the equivalent qualification of each, and naming the crew lead for each mobilization
- the test plan, listing every item of equipment within the program by its designation on the one-line diagram, the tests each item receives under its equipment standard and under this standard, the test method and the acceptance criterion for each test, the instrument to be used, and the planned test date
- a sample field data sheet for each equipment class, showing every value to be recorded
- the test instrument list, giving the manufacturer, model, serial number, calibration date, and calibration due date of each instrument
- the testing organization's electrical safety procedures for the work, referencing the arc-flash labels produced under Arc Flash StudyArc-Flash StudyResolves to the current adopted revision.sync/arc-flash-study and the lockout procedures of Electrical Safety ProgramElectrical Safety ProgramResolves to the current adopted revision.sync/electrical-safety-program
Action Submittalscheckbox
☑ Testing organization qualification statement
☑ Technician certification records and crew lead assignments
☑ Test plan by equipment designation
☑ Sample field data sheets by equipment class
☑ Test instrument list with calibration dates
☑ Electrical safety procedures for the testing work
3.1.2 No field test shall be performed before the test plan covering it has been reviewed and returned.
NOTE The test plan is the document that settles scope disputes before they start. Equipment that is not on it tends not to be tested, and a panelboard, a transfer switch, or a drive left off the plan is energized without a test and discovered only when the report is indexed against the one-line diagram. (3.1.3)
3.2 Informational Submittals
3.2.1 The Contractor shall submit the following as the work proceeds:
- the reviewed short-circuit, coordination, and arc-flash studies, furnished to the testing organization as reference documents before any protective device is tested
- the completed field data sheets for each item of equipment, submitted before that item is released for energization
- a deficiency notice for every result outside its acceptance criterion, submitted within one working day of the test
- the calibration certificate of every instrument used, traceable to the National Institute of Standards and Technology
Informational Submittalscheckbox
☑ Reviewed studies furnished to the testing organization
☑ Field data sheets before energization of each item
☑ Deficiency notices within one working day
☑ Instrument calibration certificates
3.2.2 The testing organization shall not verify a protective device setting against values transcribed in the field, against a settings sheet furnished by the installing contractor, or against the equipment manufacturer's shipping settings; the reviewed coordination study is the only reference for a setting.
3.3 Closeout Submittals
3.3.1 The Contractor shall submit the following before the equipment within the program is accepted:
- the compiled test report described under Test Report, covering every item of equipment within the program
- the deficiency log, listing every result outside its acceptance criterion, the correction made, the retest result, and the date each was closed
- the record of every protective device setting as left in service, cross-referenced to the coordination study
- the infrared survey report for each survey the datasheet requires, with the thermographic image of every finding
- the written energization release for each item of equipment, signed by the release authority named in the datasheet
Closeout Submittalscheckbox
☑ Compiled test report
☑ Deficiency log
☑ As-left protective device settings record
☐ Infrared survey reports
☑ Energization release records
4 Quality Assurance
4.1 Testing Organization
4.1.1 Acceptance testing shall be performed by the testing organization indicated in the datasheet.
Testing Organizationselect
Independent testing firm holding NETA accreditation
Independent testing firm without NETA accreditation
Equipment manufacturer's field service organization
Installing contractor's own technicians
Owner's in-house testing group
NOTE An independent firm has no stake in whether the installation passes, and NETA accreditation adds a published audit of the firm's technician certification, its instrument calibration program, and its procedures, which is what an Owner's insurer or an Authority Having Jurisdiction asks for when the report is questioned; an independent firm without accreditation offers the same independence on the firm's own representation of its program; the manufacturer's field service organization knows its own product and its trip units best and is already on site where the equipment standard requires a start-up visit, and its report carries the maker's name rather than a third party's; the installing contractor's technicians cost least and work on the installer's schedule, with the report reading as self-certification; an Owner's in-house group is the arrangement of a utility, a campus, or an industrial owner that maintains its own testing staff and instruments. The program this standard describes is written around ANSI/NETA ATS, which assumes an independent tester, and that is the arrangement most projects that invoke this standard specify. (4.1.2)
4.1.3 Where an equipment standard selects a different testing organization for a particular class of equipment, that selection shall govern for that equipment, and the test plan shall identify which organization tests each item.
4.1.4 An independent testing firm shall be one that is not the installing contractor, not a subsidiary or affiliate of the installing contractor, and not a manufacturer or supplier of equipment within the program, and whose compensation does not depend on the outcome of the tests.
4.1.5 Where a testing organization other than an independent firm holding NETA accreditation is selected, it shall maintain an instrument calibration program and a technician qualification record meeting the requirements of this standard, and shall describe both in the qualification statement.
4.1.6 The testing organization shall have performed acceptance testing on equipment of each class within the program, at the voltage class furnished, on not fewer than three completed projects, and shall name them in the qualification statement.
4.2 Technician Certification
4.2.1 Every test crew shall be led by a technician holding a current certification at the ANSI/NETA ETT level indicated in the datasheet, or at a level of the manufacturer's or Owner's qualification program that the qualification statement demonstrates to be equivalent.
Crew Lead Minimum Certification Levelselect
ANSI/NETA ETT Level II
ANSI/NETA ETT Level III
ANSI/NETA ETT Level IV
NOTE ANSI/NETA ETT defines four levels. A Level II technician performs tests under supervision; a Level III technician performs and evaluates the full range of acceptance tests and directs lower-level technicians, which is the level ANSI/NETA ATS itself requires of a crew lead and the level most projects adopt without discussion; a Level IV technician plans programs and resolves anomalous results, which a project asks for where the program includes medium-voltage relaying, differential schemes, or a transfer scheme whose test the crew lead has to design on site. Level II as a crew lead is the arrangement a small program of low-voltage equipment is sometimes let under, with evaluation of the results reserved to a senior technician off site. (4.2.2)
4.2.3 Every technician who performs a test on equipment rated above 1000 V shall hold a current certification at ANSI/NETA ETT Level II or higher, or the equivalent under the qualification program named in the qualification statement.
4.2.4 Every technician who performs or evaluates a test shall be a qualified person under NFPA 70E for the equipment and voltage class tested.
4.3 Test Instruments
4.3.1 Every instrument used to produce a recorded value shall be calibrated at the interval the instrument manufacturer recommends and not less often than once every twelve months, and its calibration shall be traceable to the National Institute of Standards and Technology.
4.3.2 Every instrument shall carry a dated calibration label, and its serial number and calibration date shall be recorded on every field data sheet it produced a value for.
4.3.3 An instrument that has been dropped, overloaded, or exposed to a fault during the work shall be withdrawn from the program until it has been recalibrated, and every value it produced since its last verified reading shall be retaken.
NOTE The acceptance criteria of this standard are tight tolerances on absolute measurements. A micro-ohmmeter reading 20% high fails a sound bus joint; a test set reading 5% low passes a relay that trips late. The instrument is the only thing standing between a number that looks authoritative and a number that is right, which is why the calibration record is part of the report. (4.3.4)
4.4 Electrical Safety During Testing
4.4.1 Every test shall be performed with the equipment under test in an electrically safe work condition established in accordance with NFPA 70E and the lockout procedures of Electrical Safety ProgramElectrical Safety ProgramResolves to the current adopted revision.sync/electrical-safety-program, except for a test that by its nature is performed with the equipment energized, which shall be performed under an energized electrical work permit issued under that program.
4.4.2 Before a test lead is applied, the testing organization shall verify the absence of voltage on every conductor within reach of the work, and shall apply temporary protective grounds to medium-voltage conductors in accordance with NFPA 70E.
4.4.3 After every high-voltage test, the tested conductors and windings shall be grounded through a discharge resistor and then solidly grounded for not less than four times the duration of the test, or for the period the instrument manufacturer requires, whichever is longer, before any person touches them.
4.4.4 Where the arc-flash labels required under Arc Flash StudyArc-Flash StudyResolves to the current adopted revision.sync/arc-flash-study are not yet installed on equipment to be tested energized, the testing organization shall work to the incident energy the study reports for that equipment, and where no study value is available, shall not perform the energized test.
5 Acceptance Test Program
5.1 Equipment Within the Program
5.1.1 The equipment classes within the acceptance test program shall be as indicated in the datasheet, and every item of equipment of a selected class on the project shall be within the program.
Equipment Classes Within the Programcheckbox
☐ Liquid-immersed transformers
☐ Dry-type transformers rated above 1000 V
☐ Dry-type transformers rated 1000 V and below
☐ Medium-voltage switchgear
☐ Metal-enclosed interrupter switchgear
☐ Low-voltage switchgear
☐ Low-voltage switchboards
☐ Panelboards
☐ Motor control centers and enclosed motor controllers
☐ Enclosed switches and busway
☐ Metal-enclosed bus above 600 V
☐ Medium-voltage circuit breakers
☐ Low-voltage power circuit breakers and insulated-case circuit breakers
☐ Molded-case circuit breakers
☐ Protective relays
☐ Instrument transformers
☐ Metering and power monitoring
☐ Medium-voltage cables
☐ Low-voltage feeder conductors
☐ Grounding electrode systems
☐ Automatic transfer switches
☐ Engine-generator sets
☐ Variable frequency drives
☐ Electric motors
☐ Stationary batteries and uninterruptible power supplies
☐ Surge protective devices
☐ Power factor correction capacitors
NOTE The equipment classes are selected here so that the testing organization can price and plan the whole program from one document, and so that a class left out is left out on purpose. The classes present on a project are read from the one-line diagram; which of them are tested is the project's decision, and the equipment that is tested in nearly every program is the service and distribution equipment, the transformers, the medium-voltage cable, the protective devices and their relays, and the grounding electrode system, with panelboards, molded-case breakers, and motors the classes most often tested on a sample or excluded. (5.1.2)
5.1.3 Each item of equipment within the program shall receive the field acceptance tests its equipment standard requires, and where the equipment standard carries no field test list, the tests ANSI/NETA ATS specifies as required for that equipment class.
5.1.4 Where an equipment standard states a criterion for one of its tests, that criterion shall apply to that equipment, and the criteria of this standard shall apply to every test for which the equipment standard states none.
5.1.5 The test plan shall identify every item of equipment present on the project of a class not selected, and shall record it as excluded from the program.
5.2 Optional Tests Added to the Program
5.2.1 The tests ANSI/NETA ATS designates as optional shall be performed where an equipment standard requires them or where indicated in the datasheet.
Optional Tests Added to the Programcheckbox
☐ Dielectric withstand of medium-voltage switchgear bus
☐ Dielectric withstand of low-voltage switchgear and switchboard bus
☐ Partial discharge survey of medium-voltage switchgear and cable terminations
☐ Insulation power factor of dry-type transformer windings
☐ Excitation current of liquid-immersed transformer windings
☐ Core-to-ground insulation resistance of transformers with an accessible core ground
☐ Sweep frequency response analysis of transformers 5 MVA and larger
☐ Contact timing and travel analysis of low-voltage power circuit breakers
☐ Excitation and burden tests of current transformers
☐ Watts-loss test of surge arresters
NOTE An optional test is one whose result adds information the required tests do not give, at a cost in time and in instruments. A dielectric withstand test of a switchgear bus finds a crack in an insulator or a foreign object left on the bus that an insulation resistance test reads through, at the cost of a high-voltage set on site and a stress the bus sees once; a partial discharge survey finds a void or a contaminated termination before it tracks, and matters where the equipment is medium-voltage and the terminations were made in the field; insulation power factor on a dry-type winding grades contamination that resistance alone does not; excitation current, core ground, and sweep frequency response detect a shorted turn, an unintended core ground, and winding movement in shipment, and are the tests a large or critical transformer receives; timing and travel on a low-voltage power breaker finds a slow mechanism before it fails to clear; excitation and burden tests confirm a current transformer will saturate where its relay expects it to; a watts-loss test finds a degraded arrester block. (5.2.2)
5.3 Test Plan and Sequence
5.3.1 Tests shall be performed in the order of the test plan, with the visual and mechanical inspection of each item of equipment completed before any electrical test is applied to it.
5.3.2 The mobilization basis of the program shall be as indicated in the datasheet.
Mobilization Basisradio
○ Single mobilization after all equipment within the program is installed
○ Phased mobilizations following the energization sequence
NOTE A single mobilization tests everything in one visit at the lowest cost per test and holds every energization until the last item is installed; phased mobilizations follow the construction sequence so that a service, a substation, or a wing is tested and energized while the rest is still being installed, at the cost of repeated mobilizations and a test plan that tracks which items have been released. (5.3.3)
5.3.4 Where phased mobilizations are selected, the Contractor shall furnish the testing organization a written energization sequence before the first mobilization, and shall give not less than five working days' notice of each item of equipment ready for test.
5.3.5 The Contractor shall furnish the testing organization access to every item of equipment within the program, with covers removed and reinstalled by the installing contractor, temporary power for the test instruments, and the operation of any equipment the test requires, at no cost to the testing organization.
5.3.6 The Contractor shall confirm before each mobilization that the equipment to be tested is installed and anchored, that every conductor to be tested is terminated, that shipping braces and packing have been removed, and that the equipment is clean and dry, and a mobilization that finds the equipment not ready shall be charged to the Contractor.
5.3.7 Equipment installed in a space that will be closed in by ceilings, walls, or finishes shall be tested before that space is closed.
5.4 Hold Points and Energization Release
5.4.1 No item of equipment within the program shall be energized before the field data sheets covering it have been reviewed and the energization release for it has been issued in writing by the release authority indicated in the datasheet.
Energization Release Authorityselect
Engineer of Record
Commissioning authority
Owner's representative
NOTE The Engineer of Record is the author of the studies the tests verify against and the party most projects have review the field data before energization; a commissioning authority holds the release where the project runs a commissioning program under CommissioningTotal Building CommissioningResolves to the current adopted revision.sync/commissioning and the Owner wants one party to control every system release; an Owner's representative holds it where the Owner maintains its own electrical staff and the review is performed in house. (5.4.2)
5.4.3 No item of equipment shall be energized before the items upstream of it on the one-line diagram, through the service or the generator that supplies it, have been released.
5.4.4 Where ground-fault protection of equipment is furnished, the performance test NFPA 70 230.95(C) requires shall be completed and its written record delivered before the equipment it protects is energized.
5.4.5 Where arc energy reduction is furnished under NFPA 70 240.87 or 240.67, the performance test those sections require shall be completed and its record delivered before the device is energized.
5.4.6 The testing organization shall be present at the initial energization of each service and of each medium-voltage bus within the program.
NOTE A hold point that is not contractual is not enforced. Without a written release tied to the field data, a system is energized the day the utility is available and the de-energized tests that remain are deferred, then waived. The release record in the closeout submittals is what proves each item was tested before it was placed in service. (5.4.7)
5.5 Coordination with Commissioning
5.5.1 Acceptance testing of each item of equipment shall be completed and the equipment released for energization before that equipment is turned over to functional performance testing under CommissioningTotal Building CommissioningResolves to the current adopted revision.sync/commissioning.
5.5.2 Where a commissioning program is in effect, the test plan shall identify which verifications are performed under this standard and which under the commissioning plan, so that no verification is assumed by each program to be performed by the other.
NOTE Acceptance testing proves the equipment is electrically sound and set as the studies direct; functional performance testing proves the energized system does what the sequence of operations says. The two are sequential, and a transfer switch timing test, a generator load test, or a ground-fault performance test belongs to whichever program the test plan assigns it to, as long as it belongs to exactly one. (5.5.3)
6 Acceptance Criteria
6.1 Governing Source of a Criterion
6.1.1 Where the equipment manufacturer publishes a value for a test and ANSI/NETA ATS states one in its tables, the governing criterion shall be as indicated in the datasheet.
Governing Criterion Where Both Sources Publish a Valueradio
● Manufacturer's published value
○ ANSI/NETA ATS table value
○ The more stringent of the two
NOTE The manufacturer's published value is the one the equipment was designed and factory-tested to, and the ANSI/NETA ATS tables state their values for use where the manufacturer publishes none, so a project that cites ATS and says nothing else is already under this order; the ATS table value as the governing criterion gives one published number for every make on the project, which is what a reviewer comparing results across equipment wants, at the cost of failing a product whose maker allows more; the more stringent of the two gives the tightest acceptance and the most retests. (6.1.2)
6.1.3 Where the governing source publishes no value for a test, the other source shall apply, and where neither publishes one, the testing organization shall propose a criterion with the test plan and the Engineer of Record shall set it before the test is performed.
6.1.4 Where the test plan proposes a criterion and the Engineer of Record has not set one before the test is performed, the proposed criterion shall apply to that test.
6.1.5 A result that falls outside the governing criterion is a deficiency, and a result that falls within the criterion but is inconsistent with the results of like equipment on the project by more than the criterion's own tolerance shall be reported to the Engineer of Record with the test data.
6.2 Insulation Resistance
6.2.1 Insulation resistance shall be measured with a direct-current test set at the voltage ANSI/NETA ATS Table 100.1 assigns to the rated voltage of the equipment, unless the manufacturer publishes a lower test voltage for the equipment, in which case the manufacturer's voltage shall apply.
6.2.2 Every insulation resistance reading shall be a one-minute reading, corrected to 20 °C using the temperature conversion factors ANSI/NETA ATS publishes for the insulation type, and the reading, the test voltage, the winding or conductor temperature, and the corrected value shall be recorded.
6.2.3 A corrected one-minute reading below the minimum ANSI/NETA ATS Table 100.1 states for the equipment voltage class, or below the manufacturer's published minimum where that governs, is a deficiency.
NOTE Insulation resistance readings are compared to a minimum, and the minimum is set by the test voltage, so a test at a voltage below the one the table assigns yields a number that cannot be judged against the table. The temperature correction matters because resistance halves for roughly every 10 °C of winding temperature, and a transformer tested warm from a dry-out reads a fraction of what the same winding reads at 20 °C. (6.2.4)
6.2.5 A ten-minute polarization index shall be taken on every transformer winding rated above 1000 V and on every transformer whose one-minute reading is below twice the applicable minimum, and a polarization index below 1.0 shall be investigated before the transformer is energized.
6.2.6 Insulation resistance of rotating machine windings within the program shall be judged against IEEE 43 for the insulation class, including the polarization index minimum IEEE 43 states for that class.
6.2.7 Where solid-state or electronic components are connected to a circuit under test, they shall be disconnected or shorted out before the test voltage is applied, and the test plan shall identify each such component and the measure taken.
6.3 Bolted Connections and Contact Resistance
6.3.1 Every bolted electrical connection within the program shall be verified by the method indicated in the datasheet.
Bolted Connection Verification Methodradio
● Calibrated torque wrench to the manufacturer's published values
○ Low-resistance ohmmeter across each connection
○ Thermographic survey under load
NOTE ANSI/NETA ATS admits three ways to prove a bolted joint. A torque check with a calibrated wrench, to the manufacturer's value or to the ANSI/NETA ATS bolt-torque table where the manufacturer publishes none, is the method most programs use, because it is done at the same time as the visual inspection with no instrument beyond the wrench; a low-resistance reading across each joint measures the joint rather than the bolt and finds a contaminated or mis-seated contact surface that is torqued correctly, at the cost of a micro-ohmmeter reading per joint; a thermographic survey proves the joint under load after energization, finds the joint that carries current badly for whatever reason, and leaves nothing checked before the equipment is energized. (6.3.2)
6.3.3 Where the torque method is selected, each verified bolt shall be witness-marked, and a joint found below the published torque shall be loosened, its contact surfaces inspected and cleaned, and the joint retorqued, not simply tightened to value.
6.3.4 Where the low-resistance method is selected, the measurement shall be made with a micro-ohmmeter applying not less than 10 A direct current, and a reading that deviates from the reading of a similar connection, or from the lowest reading among the poles of the same device, by more than 50% of the lowest value is a deficiency.
6.3.5 Where the thermographic method is selected, the survey shall be performed in accordance with the Infrared Survey article of this standard, and the equipment shall not be considered accepted until the survey has been completed and every finding corrected.
6.3.6 The contact resistance of every circuit breaker pole, every switch blade, and every transfer switch pole within the program shall be measured with a micro-ohmmeter applying not less than 10 A direct current, and a reading that exceeds the manufacturer's published maximum, or that deviates from the lowest reading among the poles of the same device by more than 50% of the lowest value where the manufacturer publishes none, is a deficiency.
NOTE Contact resistance is the most sensitive indicator of a connection that will fail under load. A loose bolt, an oxidized contact face, a conductor not fully seated in its lug, and a vacuum interrupter with a damaged contact all read as elevated resistance long before they heat visibly, and a pole that reads half again what its neighbors read on the same breaker is the one that will overheat at full load. (6.3.7)
6.4 Protective Device Settings
6.4.1 Every adjustable trip unit, protective relay, ground-fault relay, and motor overload relay within the program shall be verified to be set to the values the reviewed study under Protective Coordination StudyProtective Device Coordination StudyResolves to the current adopted revision.sync/protective-coordination-study recommends, and the as-found and as-left settings shall be recorded on the field data sheet.
6.4.2 Protective device settings shall be applied by the party indicated in the datasheet, and the testing organization shall verify every setting regardless of who applied it.
Protective Device Settings Applied Byselect
The testing organization
The installing contractor
The equipment manufacturer's field service organization
NOTE The testing organization applying the settings puts the party with the test set and the study in hand at the trip unit, and makes the setting and its verification one visit; the installing contractor applying them is the lowest-cost arrangement, with the risk that a setting is transcribed from the wrong document and the verification visit becomes a correction visit; the manufacturer's field service organization applies them where the equipment standard requires a start-up visit and the trip units need the maker's software to program, as with a networked trip unit or a transfer scheme, and the testing organization then verifies what the manufacturer left. (6.4.3)
6.4.4 A device found set to a value other than the study recommends shall be reset to the study value, and where the device cannot be set to the study value, the discrepancy shall be reported to the Engineer of Record before the device is placed in service.
6.4.5 A device that cannot be set to the study value shall not be left at a value the testing organization selects, and the Engineer of Record shall direct the setting to apply.
6.4.6 No protective device within the program shall be energized with its trip unit or relay at the manufacturer's shipping settings.
NOTE A relay that tests perfectly against the wrong settings is a coordination failure waiting for its first fault. The study is the only authority for a setting, which is why the reviewed study is an informational submittal to the testing organization and why the as-left settings record in the closeout submittals is cross-referenced to it line by line. (6.4.7)
7 Circuit Breaker and Trip Unit Testing
7.1 Electronic Trip Unit Test Method
7.1.1 Every electronic trip unit within the program shall be tested at not less than one point on each of its long-time, short-time, instantaneous, and ground-fault functions furnished, by the method indicated in the datasheet, and the measured pickup and operating time at each point shall be within the manufacturer's published tolerance for the function.
Electronic Trip Unit Test Methodradio
○ Primary current injection
○ Secondary injection through the trip unit test port
○ Secondary injection with a primary injection check of each current sensor
NOTE Primary current injection passes test current through the breaker poles and proves the current sensors, the wiring between them and the trip unit, the trip unit, and the mechanism as one path, and needs a high-current test set, a de-energized bus, and time per breaker that grows with the frame size; secondary injection feeds a signal into the trip unit's test port and proves the trip unit's logic and settings and the trip actuator, in minutes per breaker with a portable kit, and proves nothing about the sensors or the wiring to them; secondary injection with a primary injection check of each sensor proves the trip unit by the fast method and the sensor path by one primary injection at a single point per pole, which is the arrangement that catches a swapped sensor lead or a sensor of the wrong ratio without the full primary injection of every function. (7.1.2)
7.1.3 Where ground-fault protection of equipment is furnished, its performance test shall be by primary current injection through the sensing elements regardless of the method selected for the other functions, in accordance with NFPA 70 230.95(C), and the test shall confirm that the device opens at the pickup and within the delay the study recommends.
7.1.4 Every thermal-magnetic trip unit tested under this standard shall be tested by primary current injection, because its trip elements carry the load current directly and no secondary path exists.
7.2 Molded-Case Circuit Breaker Test Extent
7.2.1 The extent to which molded-case circuit breakers within the program receive a trip test shall be as indicated in the datasheet, and every molded-case breaker within the program shall receive a visual and mechanical inspection, a contact resistance measurement, and an insulation resistance test whether or not it receives a trip test.
Molded-Case Circuit Breaker Trip Test Extentselect
Every molded-case circuit breaker in the program
Every breaker with an electronic or adjustable trip unit
Every breaker at or above the frame size threshold
A sample of each frame size and trip unit type
Visual and mechanical inspection with no trip test
NOTE Trip testing every molded-case breaker proves every device at the cost of a primary injection per breaker, which on a project with hundreds of branch breakers is the largest single item in the testing bid; limiting the trip test to electronic and adjustable trip units tests the devices whose settings can be wrong and leaves the fixed thermal-magnetic devices, which have no settings to verify, to inspection; a frame size threshold tests the feeder and main devices whose failure to clear would be consequential and leaves the small branch devices untested; a sample of each frame size and type proves the product family rather than each device, and expands to the whole family where a sample fails; inspection alone is the program a project adopts where the molded-case breakers are small, factory-tested, and protected by a tested device upstream. (7.2.2)
7.2.3 Where the frame size threshold extent is selected, the threshold shall be as indicated in the datasheet.
Molded-Case Breaker Trip Test Frame Size Thresholdrange
A
10015022525040060080010001200
7.2.4 Where the sample extent is selected, the sample shall be not less than one breaker in ten of each frame size and trip unit type and not fewer than one, selected by the testing organization, and where any sampled breaker fails its trip test, every breaker of that frame size and trip unit type on the project shall be tested.
7.2.5 A molded-case breaker trip test shall verify the long-time element at 300% of its rating and the instantaneous element at its setting, and the measured values shall be within the manufacturer's published tolerance for the device, or within the tolerances ANSI/NETA ATS states for molded-case breakers where the manufacturer publishes none.
7.2.6 A molded-case breaker that fails a trip test shall be replaced, not adjusted or repaired, and the replacement shall be tested.
7.3 Power and Medium-Voltage Circuit Breaker Operation
7.3.1 Every low-voltage power circuit breaker, insulated-case circuit breaker, and medium-voltage circuit breaker within the program shall be operated through one open and close cycle by its manual means and, where furnished, by its electrical control from the control station and from every remote close and trip contact, and every drawout breaker shall be racked through every position with every interlock and shutter verified to operate.
7.3.2 Every medium-voltage circuit breaker within the program shall receive a contact timing test, and the measured opening time, closing time, and pole spread shall be within the manufacturer's published tolerance, with a pole spread exceeding the manufacturer's tolerance, or exceeding one-half cycle where the manufacturer publishes none, recorded as a deficiency.
7.3.3 Every vacuum circuit breaker within the program shall receive a vacuum interrupter integrity test at the voltage and by the method the manufacturer publishes, and an interrupter that fails shall be replaced before the breaker is placed in service.
NOTE A breaker that carries normal current correctly and opens slowly is a breaker that clears a fault late, and the timing test is the only acceptance test that sees the mechanism rather than the contacts. On a medium-voltage breaker it is a required test; on a low-voltage power breaker it is the optional test selected under this standard where the breaker is the main of a selectively coordinated system. (7.3.4)
8 Protective Relay Testing
8.1 Relay Test Scope
8.1.1 Every protective relay within the program shall be tested to the scope indicated in the datasheet, by a relay test set that injects current and voltage into the relay with the relay in service wiring and the breaker in the test position.
Protective Relay Test Scopeselect
Functional trip check from each relay output to its breaker
Setting verification by secondary injection at the applied settings
Full characteristic verification by secondary injection at multiple points on each element
NOTE A functional trip check proves that the relay's output contact trips its breaker and nothing more, and is the scope of a project whose relays were bench-tested and settings-verified off site; setting verification injects each element at its applied pickup and at one or two multiples of it, proves that the relay picks up and times out where the study says, and is the scope ANSI/NETA ATS requires and the one most projects adopt; full characteristic verification injects enough points on each element to plot its curve against the published characteristic, proves the relay rather than its settings, and is the scope a utility or an industrial owner specifies for a differential, a distance, or a generator protection relay whose misoperation would be costly. (8.1.2)
8.1.3 Where setting verification is selected, each overcurrent element shall be verified at its pickup and at two multiples of pickup, the measured pickup shall be within 5% of the setting, and the measured operating time at each multiple shall be within 5% of the time the published characteristic gives for the applied setting, or within the manufacturer's published tolerance where it is wider.
8.1.4 Where full characteristic verification is selected, each element shall be verified at not fewer than four points spanning its characteristic, and the test plan shall list the points.
8.1.5 Every relay test shall conclude with a functional trip from each relay output through the trip circuit to the breaker it controls, with the breaker operated, and with every target, alarm contact, and communications point verified.
8.1.6 Every current transformer circuit serving a relay within the program shall be verified for ratio, polarity, and continuity through the relay, and every voltage transformer circuit for ratio, polarity, and phase, before the relay is placed in service.
8.1.7 An electromechanical relay within the program shall also receive a mechanical inspection of its disc, contacts, and taps, and a microprocessor relay shall have its settings file read from the relay after testing and attached to the field data sheet.
9 Transformer Test Criteria
9.1 Every transformer within the program shall receive the field tests its equipment standard requires, judged against the criteria of this article where the equipment standard states none.
9.2 The measured turns ratio at each tap position tested shall be within 0.5% of the nameplate ratio, with the ratio taken at every tap where the equipment standard requires it and at the connected tap as a minimum.
9.3 The measured direct-current winding resistance of each phase shall be within 1% of the other phases of the same winding, and within 1% of the factory value corrected to the same temperature where the factory test report is available.
9.4 The corrected insulation power factor of a liquid-immersed transformer winding at 20 °C shall not exceed the manufacturer's published value, or the ANSI/NETA ATS maximum for the insulation system where the manufacturer publishes none, and a value exceeding 1.0% shall be investigated before the transformer is energized whether or not it exceeds the governing criterion.
9.5 The insulating liquid of every liquid-immersed transformer within the program shall be sampled after filling and before energization, and the sample tested to the criteria the equipment standard states, under Medium Voltage TransformersMedium-Voltage Distribution TransformersResolves to the current adopted revision.sync/medium-voltage-transformers for a unit within that standard's scope.
9.6 The phase relationship and the polarity of every transformer within the program shall be verified against the nameplate and the one-line diagram before the secondary is connected to a bus that another source can also supply.
NOTE Transformer acceptance testing confirms three things: that the windings are electrically continuous and connected as the nameplate says, which the turns ratio, the winding resistance, and the phase relationship prove; that the insulation is dry and clean, which the insulation resistance and the power factor prove; and that the unit was not damaged in shipment, which the sum of those tests and the liquid sample prove. The test methods are those of IEEE C57.12.90 for a liquid-immersed unit and IEEE C57.12.91 for a dry-type unit, applied in the field with portable instruments. (9.7)
10 Switchgear Bus and Cable Dielectric Tests
10.1 Where a dielectric withstand test of a switchgear or switchboard bus is required under the Optional Tests article, it shall be performed with the breakers withdrawn and the instrument and control circuits isolated, at a direct-current or power-frequency voltage not exceeding 75% of the factory withstand voltage the equipment standard assigns to the assembly under IEEE C37.20.1 or IEEE C37.20.2, held for one minute per phase to ground with the other phases grounded.
10.2 A bus that fails a dielectric withstand test shall not be retested until the cause has been found and corrected, and the retest shall be at the same voltage.
10.3 The withstand test of shielded medium-voltage cable shall be performed by the method, at the voltage, and for the duration Medium Voltage CablesMedium-Voltage CablesResolves to the current adopted revision.sync/medium-voltage-cables requires, and this standard shall govern the testing organization, the instrument, the safety practice, the report, and the energization release for that test.
10.4 The insulation resistance test of low-voltage feeder conductors within the program shall be at the voltage Conductors And CablesConductors and CablesResolves to the current adopted revision.sync/conductors-and-cables requires, judged against the minimum of this standard's Insulation Resistance article.
10.5 The resistance to earth of a grounding electrode system serving equipment rated 1000 V and below shall be measured by the method and judged against the value Grounding And BondingGrounding and Bonding for Electrical SystemsResolves to the current adopted revision.sync/grounding-and-bonding requires, and the resistance to earth of a ground grid serving equipment rated above 1000 V shall be measured by the fall-of-potential method of IEEE 81 and shall not exceed the value indicated on the grounding plan.
NOTE A dielectric withstand test stresses the bus insulation at a voltage above operating voltage and below the factory test voltage, so that a sound bus is not damaged and a cracked insulator, a foreign object, or an insufficient clearance left by field assembly breaks down under test rather than in service. The 75% ceiling exists because the factory test has already been applied once and insulation is not meant to see that voltage twice. (10.6)
11 Instrument Transformers and Metering
11.1 Every current transformer within the program shall be verified for ratio by voltage or current method and for polarity, and its secondary circuit shall be verified for continuity through every device it serves and for the grounding of the secondary at one point only, before the circuit is placed in service.
11.2 Every voltage transformer within the program shall be verified for ratio, polarity, and secondary fusing, and its secondary circuit for the grounding of the secondary at one point only.
11.3 The insulation resistance of every instrument transformer within the program shall be measured winding-to-winding and winding-to-ground at the test voltage ANSI/NETA ATS assigns to the winding, and judged against the Insulation Resistance article of this standard.
11.4 Every meter and power monitor within the program shall be verified to read the correct phase, magnitude, and direction of current and voltage against the instrument transformer circuits that serve it, and the meter configuration shall be recorded on the field data sheet; the meter's accuracy class and its monitoring system are governed by Electrical Power MonitoringElectrical Power Monitoring and MeteringResolves to the current adopted revision.sync/electrical-power-monitoring.
NOTE A current transformer with reversed polarity or a swapped secondary lead makes every relay and meter downstream of it wrong while every one of them tests perfectly on secondary injection, which is why the instrument transformer circuit is verified end to end before the relay test is counted. (11.5)
12 Transfer Switches, Generators, Drives, and Stored-Energy Systems
12.1 Every automatic transfer switch within the program shall receive the field acceptance tests Automatic Transfer SwitchesAutomatic Transfer SwitchesResolves to the current adopted revision.sync/automatic-transfer-switches requires, with the transfer and retransfer timing recorded against the limits that standard derives, and the whole-system acceptance of the emergency or standby system it serves shall be as Emergency And Standby PowerEmergency and Standby Power SystemsResolves to the current adopted revision.sync/emergency-and-standby-power requires.
12.2 Every engine-generator set within the program shall receive the field acceptance tests and the load test GeneratorsEngine GeneratorsResolves to the current adopted revision.sync/generators requires, with the alternator insulation resistance judged against IEEE 43.
12.3 Every variable frequency drive within the program shall receive the field acceptance tests Low Voltage Variable Frequency DrivesLow-Voltage Variable Frequency DrivesResolves to the current adopted revision.sync/low-voltage-variable-frequency-drives or HVAC Variable Frequency DrivesHVAC Variable Frequency DrivesResolves to the current adopted revision.sync/hvac-variable-frequency-drives requires for the drive furnished, with the drive's power circuit insulation resistance measured with the drive's power electronics disconnected.
12.4 Every stationary battery and uninterruptible power supply within the program shall receive the acceptance tests DC Battery SystemsDC Battery SystemsResolves to the current adopted revision.sync/dc-battery-systems or Uninterruptible Power Supply SystemsUninterruptible Power Supply SystemsResolves to the current adopted revision.sync/uninterruptible-power-supply-systems requires, performed by the testing organization under this standard where the test plan assigns them to it.
12.5 Every surge protective device within the program shall be verified for the integrity of its connection, the length of its leads, and the operation of its status indication, and every power factor correction capacitor for its insulation resistance, its discharge resistor operation, and its capacitance against nameplate.
NOTE These classes carry their own test lists in their own standards because their functional tests, the transfer sequence, the load test, the drive start, and the battery discharge, are tests of what the equipment does rather than of its insulation and connections. This standard adds the tester, the instruments, the criteria for the electrical tests among them, and the report. (12.6)
13 Infrared Survey
13.1 The infrared survey of the equipment within the program shall be as indicated in the datasheet.
Infrared Survey of the Program Scopeselect
Not included in the program
One survey within 90 days of energization
Two surveys, within 90 days of energization and at eleven months
NOTE An infrared survey finds the connection that passed its torque check and heats under load anyway, and it is the only acceptance test performed on energized equipment under load; one survey within 90 days finds the connection that was wrong from the start; a second survey near the end of the first year finds the termination that loosened through the first full cycle of seasonal load and files the warranty claim before the warranty ends, at the cost of a second visit under load; a program that omits the survey relies on the de-energized tests and on the Owner's maintenance program under NFPA 70B to find a heating joint. (13.2)
13.3 Where an equipment standard requires an infrared inspection of a particular assembly, that inspection shall be performed under the method of this article whether or not a program-wide survey is selected.
Infrared Survey Loadrange
Not less than
%
102030405060
NOTE A joint heats in proportion to the square of the current through it, so a survey at light load sees a fraction of the rise the same joint shows at full load; 40% of rated load is the minimum ANSI/NETA ATS states and the level most programs survey at, a lower value is accepted where the facility cannot be loaded further before the survey window closes, and a higher value is specified where the Owner can apply load banks or the facility reaches full load early. (13.5)
13.6 The survey shall be performed with a thermal imaging camera resolving 0.1 °C at 30 °C, with every energized connection, bus joint, device terminal, and cable termination within the program scanned with covers removed where the equipment is listed for the covers to be removed energized, and otherwise through infrared windows or with the covers in place and the limitation recorded.
13.7 Every connection showing a temperature rise of more than 10 °C above a comparable connection under the same load, or of more than 40 °C above ambient, shall be reported as a deficiency, corrected, and rescanned under load, and every finding shall be classified by the temperature-rise bands ANSI/NETA ATS Table 100.18 states.
13.8 The survey report shall include the thermographic image and the visible-light image of every finding, the load at the time of the scan, the ambient temperature, the camera and its calibration date, and the location of each finding by equipment designation and connection.
14 Test Report
14.1 Report Content
14.1.1 The testing organization shall compile a test report covering every item of equipment within the program, and the report shall include for each item the equipment designation from the one-line diagram, the nameplate data, each test performed, the instrument used with its serial number and calibration date, the as-found and as-left values, the governing criterion applied, the pass or fail determination, the technician who performed the test, and the date.
14.1.2 The report shall include the as-left setting of every protective device cross-referenced to the coordination study, the deficiency log, and the field data sheets as recorded in the field.
14.1.3 The report shall be indexed against the test plan and against the one-line diagram so that every item of equipment on the project appears in the index as tested, excluded, or not yet tested.
14.1.4 The report shall be signed by the crew lead and by a principal of the testing organization, and shall state that the tests were performed in accordance with the test plan and this standard and that the recorded values are the values measured.
NOTE The test report is the permanent record of the as-installed condition of the electrical system and the baseline every later maintenance test is judged against under NFPA 70B. A report that records pass and fail without the measured values is not a baseline, and a report that cannot be indexed against the one-line diagram cannot show what was never tested. (14.1.5)
14.2 Report Format and Delivery
14.2.1 The report shall be delivered in the formats indicated in the datasheet.
Test Report Formatcheckbox
☑ Searchable electronic PDF with the field data sheets
☐ Signed hard copies
☐ Native instrument data files and relay settings files
☐ Thermographic images with each infrared survey finding
14.2.2 The report shall be delivered to the recipients indicated in the datasheet.
Test Report Recipientscheckbox
☑ Owner
☑ Engineer of Record
☐ Authority Having Jurisdiction
☐ Commissioning authority
☐ Serving utility
14.2.3 The compiled report shall be delivered within the number of days after the last test of the program indicated in the datasheet.
Compiled Report Delivery After the Last Testrange
Not more than
days
71421304560
NOTE A short delivery period gets the baseline into the Owner's hands while the testing crew is still available to answer questions and before the warranty clock has run far, at the cost of a report compiled under schedule pressure; a longer period lets the testing organization compile, check, and index a large program's data, and leaves the Owner operating for that period on the field data sheets alone. (14.2.4)
14.2.5 The compiled report shall be delivered before the certificate of substantial completion is issued, whatever delivery period the datasheet selects.
14.3 Deficiencies and Retesting
14.3.1 A result outside its governing criterion is a deficiency, and the equipment it was measured on shall not be energized until the deficiency has been corrected and the test repeated with a passing result.
14.3.2 The testing organization shall report every deficiency to the Contractor and to the Engineer of Record within one working day of the test, with the measured value, the criterion applied, and the instrument used.
14.3.3 The Contractor shall correct every deficiency, and where the Contractor and the testing organization disagree whether a result is a deficiency, the Engineer of Record shall make the determination.
14.3.4 The Engineer of Record shall determine whether a deficient item is to be repaired or replaced, and where an item is repaired, the repair shall be made by the equipment manufacturer or under its written instructions.
14.3.5 The cost of correcting a deficiency, of every repeated test, and of every additional mobilization the correction requires shall be borne by the Contractor, and a deficiency found to result from a defect in the equipment as furnished shall be corrected by the manufacturer under the equipment standard's warranty at no cost to the Owner.
14.3.6 Every deficiency, its correction, its retest result, and its closing date shall be entered in the deficiency log, and no item of equipment shall be released for energization with an open deficiency against it or against any item upstream of it.
15 Testing Services Warranty
15.1 The testing organization shall warrant that every test was performed in accordance with the test plan and this standard, that every recorded value is the value measured by the instrument identified, and that the instruments were calibrated as this standard requires on the dates recorded.
15.2 Acceptance testing shall not extend, reduce, or alter the manufacturer's warranty on any item of equipment, and a defect revealed by a test shall be corrected under the equipment or installation warranty that covers it.
15.3 Where a test performed under this standard is later shown to have been performed with an uncalibrated instrument, at a voltage other than the one this standard assigns, or against a criterion other than the governing one, the testing organization shall repeat the test at no cost to the Owner, and where the equipment has since been energized, shall perform it at the next outage the Owner makes available.
This standard is written and maintained by SynC and licensed under Creative Commons Attribution 4.0. You may share and adapt it, including commercially, provided you credit SynC Standards, link to the license, and indicate any changes. Each standard is drafted from cited sources under published authoring rules, reviewed before adoption, and corrected in the open. Keep the attribution and notice below with any copy; it carries the warranty notice the license asks you to retain.
"Electrical Acceptance Testing," SynC Standards, revision 5. Licensed under CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Source: https://synergyinconstruction.com/standards/general/electrical-acceptance-testing. Reference material only; not professional engineering advice and provided without warranty. Verify against governing codes and have a licensed professional review before use.