Payment Procedures
Revision1
EditedNov 16, 2026
StatusCurrent
Contents
- 1Scope
- 2Payment Terms
- 3Referenced Standards
- 4Submittals
- 4.1Payment Submittals
- 5Schedule of Values
- 5.1Submission and Form
- 5.2Separate Line Items
- 5.3Review for Front-Loading
- 5.4Revisions to the Schedule of Values
- 6Applications for Progress Payment
- 6.1Frequency and Submission
- 6.2Application Form and Content
- 6.3Supporting Documents
- 6.4Engineer's Review and Certification
- 7Stored Materials
- 7.1Materials Eligible for Payment
- 7.2Stored Materials Documentation
- 7.3Title and Risk of Loss
- 8Retainage During Construction
- 8.1Percentage Held on Progress Payments
- 8.2Reduction During Construction
- 9Unit Prices
- 9.1Unit Price Schedule and Application
- 9.2Measurement
- 9.3Variation in Quantity
- 10Allowances
- 10.1Allowance Types and Coverage
- 10.2Allowance Selection and Purchase
- 10.3Allowance Reconciliation
- 11Alternates
- 11.1Alternate Descriptions and Acceptance
- 11.2Coordination of Accepted Alternates
- 12Coordination with the Agreement and Other Standards
View changes in this revision Revision history
Current revision. This is editorial revision 1, the current text of this standard. Read it on the standard's page.
New standard for paying the Contractor as the Work progresses: the schedule of values and its review for front-loading, applications for progress payment and what goes with them, stored materials, retainage during construction, unit price measurement, allowances, and alternates.
1 Scope
NOTE This standard establishes the administrative requirements for the schedule of values, for applications for progress payment and the documents that accompany them, for payment for stored materials, for retainage held during construction, for the measurement and payment of unit price items, for allowances, and for alternates, on any project and under any Division of the Specifications. (1.1)
NOTE The Contract Sum, the payment terms, and the retainage originate in the Agreement and the General Conditions, which are contract instruments between the Owner and the Contractor. This standard carries their requirements into the project manual, where the subcontractors and suppliers who read only the technical sections see the terms on which the Work is paid for, and it states the administrative detail those instruments leave open: the form of the breakdown, the content of the application, the documentation behind a stored material, and the rules by which a quantity is measured. (1.2)
NOTE Several of the values in this standard are set by the procurement law, the retainage law, the prompt-payment law, or the lien law of the jurisdiction of the project, and those laws differ from one state to the next. Where a requirement is set by such a law, the field is left for the Owner to fill and the clause defers to the law, and nothing in this standard is read as modeling the rule of any one jurisdiction. (1.3)
1.4 The Contractor shall comply with this standard in addition to any payment requirement stated in the Agreement, the General Conditions, or a technical standard.
1.5 Where a requirement of this standard conflicts with the Agreement, the General Conditions, or the Supplementary Conditions, those documents shall govern.
1.6 Where a requirement of this standard conflicts with the procurement, retainage, prompt-payment, or lien law governing the Owner, that law shall govern, and the Contractor's obligations under this standard shall be read as reduced only to the extent the law requires.
NOTE The following are outside the scope of this standard: (1.7)
- The pricing of a change in the Work, the cost breakdown and markups on a change, change orders, construction change directives, time extension requests, and claims, which Contract Modification ProceduresContract Modification ProceduresResolves to the current adopted revision.sync/contract-modification-procedures governs
- Final payment, the release of retainage at substantial completion and at final completion, the final lien waivers and affidavits, and the consent of surety to final payment or to a reduction in retainage, which Closeout ProceduresCloseout ProceduresResolves to the current adopted revision.sync/closeout-procedures and Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds govern
- The bid form, the layout and content of the unit price schedule and the schedule of alternates as bid documents, bid security, and the award, which Bidding ProceduresBidding ProceduresResolves to the current adopted revision.sync/bidding-procedures governs
- The construction schedule, its baseline, its updates, and the reconciliation of schedule progress with the application for payment, which Construction Progress DocumentationConstruction Progress DocumentationResolves to the current adopted revision.sync/construction-progress-documentation governs
- Substitutions, comparable products, and the receiving and handling of Owner-furnished products, which Product RequirementsProduct RequirementsResolves to the current adopted revision.sync/product-requirements governs
- The builder's risk, liability, and other insurance the Contractor carries, and the certificates of that insurance, which Insurance RequirementsInsurance RequirementsResolves to the current adopted revision.sync/insurance-requirements governs
- The time within which the Owner pays a certified application, the interest on a late payment, and the Contractor's remedies for nonpayment, which the Agreement and the prompt-payment law governing the Owner set
2 Payment Terms
NOTE The following terms are used in this standard with the meanings given here: (2.1)
- The Engineer is the Engineer of Record or the design professional the Agreement names to administer the Contract and to certify applications for payment
- The schedule of values is the breakdown of the Contract Sum into line items, each with a scheduled value, that is the basis for every progress payment
- An application for payment is the Contractor's periodic request for payment of the value of Work completed and materials stored, prepared on the schedule of values and certified by the Engineer before the Owner pays it
- The payment period is the interval of Work that one application covers, ending on the cutoff date from which the percent complete on each line is measured
- A continuation sheet is the schedule of values carried forward on each application, showing for each line the value completed in earlier periods, the value completed in this period, the materials stored, the total completed and stored, the percent complete, and the balance to finish
- Stored materials are products to be incorporated into the Work that have been delivered and stored, on the site or at an accepted location off the site, before they are installed
- Retainage is the portion of each progress payment the Owner withholds, as a stated percentage of the amount earned, until the point at which the Contract Documents provide for its reduction or release
- Front-loading is a schedule of values in which the early lines carry values above their cost so that the Contractor is paid ahead of the Work, leaving the later lines priced below the cost of finishing them
- A unit price item is a part of the Work paid for at a stated price per unit of measured quantity rather than as part of a lump sum
- A lump sum allowance is an amount included in the Contract Sum for a product or a service that the Owner has not yet selected or that cannot be priced when the bid is made
- A quantity allowance is a unit price multiplied by an estimated quantity, included in the Contract Sum for work whose extent is not known when the bid is made, such as rock excavation or the removal of unsuitable soil
- A contingency allowance is an amount included in the Contract Sum for use at the Owner's sole written direction, for work not otherwise in the Contract Documents
- An alternate is a described change to the base bid, adding to or deducting from the Work and priced separately in the bid, that becomes part of the Contract only when the Owner accepts it
- A lien waiver is a written release by the Contractor, a subcontractor, or a supplier of its right to lien the property or to claim on the payment bond for Work paid for, and it is conditional when it takes effect only on receipt of the payment it names and unconditional when it takes effect on signing
3 Referenced Standards
3.1 The applications for payment and their administration shall comply with the latest adopted edition of each of the following unless a specific edition is cited or the Contract Documents direct otherwise.
3.2 Where referenced documents conflict, the more stringent requirement shall govern unless the Engineer directs otherwise in writing.
| Standard | Title |
|---|---|
| AIA A201 | General Conditions of the Contract for Construction |
| AIA G702 | Application and Certificate for Payment |
| AIA G703 | Continuation Sheet |
| EJCDC C-700 | Standard General Conditions of the Construction Contract |
| EJCDC C-620 | Contractor's Application for Payment |
| ConsensusDocs 200 | Standard Agreement and General Conditions Between Owner and Constructor |
NOTE The general conditions in common use set the payment cycle, the Engineer's review period, the grounds on which a payment is withheld, the passage of title on payment, and the Contractor's duty to pay its subcontractors, and they differ from one publisher to the next in the time each step takes and in the words that describe it. Every state has a prompt-payment statute that fixes the time a public Owner, and in most states a private Owner, has to pay a certified application and the interest owed on a late one, and most states cap the retainage a public Owner withholds, require its reduction or release at a stated point, or both. The lien law of the jurisdiction decides what a lien waiver has to say to be enforceable, and in several states it prescribes the form. (3.3)
4 Submittals
4.1 Payment Submittals
4.1.1 The Contractor shall submit the following, each at the time this standard states for it:
- The schedule of values, within the time indicated in the datasheet after the notice to proceed and before the first application for payment
- Each application for payment, on the indicated form and with the continuation sheet, within the time indicated in the datasheet after the end of the payment period
- The schedule update required by Construction Progress DocumentationConstruction Progress DocumentationResolves to the current adopted revision.sync/construction-progress-documentation, with each application
- Partial lien waivers from the Contractor and its lower tiers, where the datasheet requires them, with each application
- The stored materials documentation this standard requires, with each application that includes stored materials
- The measurement records for unit price work, with each application that includes a unit price item
- The invoices and the record of expenditure against each allowance, with each application that includes an allowance item
Payment Submittals Requiredcheckbox
☑ Schedule of values
☑ Application for payment with continuation sheet
☑ Schedule update with each application
☐ Partial lien waivers with each application
☑ Stored materials documentation
☑ Unit price measurement records
☑ Allowance invoices and expenditure record
4.1.2 Payment submittals shall be transmitted to the Engineer directly, in the number of copies and the medium the Agreement or the preconstruction conference under Project Management And CoordinationProject Management and CoordinationResolves to the current adopted revision.sync/project-management-and-coordination establishes, and shall not be routed through the technical submittal register of Submittal And Quality ProceduresSubmittal and Quality ProceduresResolves to the current adopted revision.sync/submittal-and-quality-procedures.
NOTE An application for payment is a request for money with a review clock on it, not a shop drawing, and routing it through the register that tracks product data delays it behind every submittal ahead of it and loses it from the record the prompt-payment law reads. A direct transmittal, logged by date of receipt, is what starts the Engineer's review period on a date both parties can prove. (4.1.3)
5 Schedule of Values
5.1 Submission and Form
5.1.1 The Contractor shall submit the schedule of values to the Engineer within the time indicated in the datasheet after the notice to proceed, and in every case before the first application for payment.
Schedule of Values Due After Notice to Proceedrange
Not more than
days
7101421304560
NOTE The schedule of values is due before the first application because the first application is prepared on it, and the review of it is the one chance to correct the breakdown before money has moved. The time allowed is set against the size of the Work: a Contractor on a small project writes the schedule in a week from its bid, while a Contractor on a plant with forty specification sections and a dozen major equipment purchases needs subcontract and purchase order values that take a month to settle. A short period produces a schedule with placeholder values that is revised through the first three applications; a long period produces a first application that is late. (5.1.2)
5.1.3 The schedule of values shall be prepared on the same form and with the same columns as the continuation sheet of the application for payment, so that each application carries the schedule forward without transcription.
5.1.4 The schedule of values shall list each line item with its number, its description, and its scheduled value, and the sum of the scheduled values shall equal the Contract Sum, including every alternate the Owner has accepted and every allowance.
5.1.5 The schedule of values shall be broken down to the level indicated in the datasheet.
Schedule of Values Breakdown Levelradio
○ By specification section
○ By specification section within each building, structure, or area
○ By specification section within each phase or milestone
○ By the Owner's cost codes or accounting structure
5.1.7 Each line item shall be broken down further, into labor and material or into subassemblies, where the Engineer requests it in order to verify the percent complete, and a line item whose scheduled value exceeds five percent of the Contract Sum shall be broken down so that no line exceeds that value unless the Engineer accepts the larger line in writing.
5.1.8 The Contractor shall list each unit price item, each allowance, and each accepted alternate as its own line item on the schedule of values, identified as such, and shall not merge any of them into a lump sum line.
5.2 Separate Line Items
5.2.1 Mobilization shall be a separate line item, and its scheduled value shall not exceed the percentage of the Contract Sum indicated in the datasheet.
Mobilization Line Value Caprange
Not more than
% of the Contract Sum
123510
NOTE Mobilization is the one line item whose value is earned before any permanent Work exists, which makes it the first place a schedule of values is front-loaded and the one line Owners cap. The real cost of moving onto a site, setting up the field office, the temporary utilities, and the laydown, and bringing in the first equipment runs from one to three percent of the Contract Sum on a building and higher on a remote site, a marine job, or a plant where a crane and a bypass have to be in place before the first pour. A cap at the real cost pays the Contractor what it spent and nothing more; a cap of zero folds mobilization into the general conditions line and pays it over the duration, which protects an Owner that has been left with a mobilized site and a departed Contractor, at the cost of the Contractor financing the move-in. A cap well above cost is an advance against the Work, which some Owners grant deliberately to a Contractor on a long procurement. (5.2.2)
5.2.4 The Contractor's general conditions costs, including supervision, the field office, temporary facilities under Temporary Facilities And ControlsTemporary Facilities and ControlsResolves to the current adopted revision.sync/temporary-facilities-and-controls, and project management, shall be one or more separate line items whose value is earned in proportion to the time elapsed, and shall not be distributed into the Work line items.
5.2.5 The closeout deliverables shall be separate line items, each priced at not less than the Contractor's cost of producing it, as follows: the record documents, the operation and maintenance manuals under Operation And Maintenance DataOperation and Maintenance DataResolves to the current adopted revision.sync/operation-and-maintenance-data, the demonstration and training under Closeout ProceduresCloseout ProceduresResolves to the current adopted revision.sync/closeout-procedures, and the warranty book under Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds.
5.2.6 No part of the value of a closeout deliverable line item shall be paid before the deliverable has been submitted and accepted under the standard that governs it.
NOTE An operation and maintenance manual that is priced inside the equipment line is paid for when the equipment is set, and at closeout the Contractor is asked to produce, for no further money, a document its subcontractor's supplier has to write. A manual that carries its own value on the schedule of values is produced because the value is unpaid until it arrives. The content of each deliverable is governed by the standard named for it; this standard asks only that each one be a line the Owner can hold. (5.2.7)
5.3 Review for Front-Loading
5.3.1 The Engineer shall review the schedule of values for the reasonableness of the value assigned to each line relative to the cost of that part of the Work, and may require the Contractor to substantiate any value with its subcontract, purchase order, or estimate detail.
5.3.2 Where the Engineer determines that a scheduled value does not reasonably reflect the cost of the Work it covers, the Contractor shall revise the schedule of values as the Engineer directs before the first application for payment is certified.
5.3.3 Where the Contractor and the Engineer disagree whether a scheduled value is reasonable, the Engineer shall make the initial determination, subject to the dispute resolution provisions of the Contract Documents, and the application shall be certified on the Engineer's values pending resolution.
NOTE A front-loaded schedule of values does not change the Contract Sum, and it is not an overpayment in the end, which is why it is tolerated by Contractors and sometimes by Owners as a financing arrangement. Its cost appears when something goes wrong: a Contractor who has been paid for ninety percent of the Work with seventy percent of it built has no reason to finish, a surety completing after a default inherits a balance that will not fund the completion, and an Owner terminating for convenience pays for Work it does not have. The review is cheap, and the place to do it is the first application, which the Contractor needs certified. (5.3.4)
5.3.5 Acceptance of the schedule of values by the Engineer shall not constitute agreement that any scheduled value is the cost of that Work for the purpose of pricing a change under Contract Modification ProceduresContract Modification ProceduresResolves to the current adopted revision.sync/contract-modification-procedures, a termination settlement, or a claim.
5.4 Revisions to the Schedule of Values
5.4.1 Each change order shall be added to the schedule of values as its own line item, in the amount of the change order, on the first application after the change order is executed.
5.4.2 Work performed under a construction change directive before its conversion to a change order shall be carried on the schedule of values as its own line item, in the amount the directive states or, where it states none, in the amount the Engineer determines is due for the Work performed to date, and the line shall be adjusted to the change order amount when the change order is executed.
5.4.3 The Contractor shall not reallocate value between line items after the schedule of values has been accepted except with the Engineer's written acceptance of a revised schedule, submitted with the application on which the revision first takes effect and identifying each line changed and the reason.
NOTE A reallocation is how an early error in the breakdown is corrected, and it is also how a schedule that was accepted as balanced becomes front-loaded one application at a time. Requiring each revision to be identified and accepted keeps the second from hiding inside the first. (5.4.4)
6 Applications for Progress Payment
6.1 Frequency and Submission
6.1.1 The Contractor shall submit applications for payment at the frequency indicated in the datasheet.
Application for Payment Frequencyradio
● Monthly
○ Twice monthly
○ At the milestones stated in the Agreement
NOTE A monthly cycle is the one the general conditions in common use assume and the one every Contractor, subcontractor, supplier, and lender is organized around, and it reaches a project without discussion. A twice-monthly cycle halves the Contractor's financing of the Work in progress and is asked for on a short, intense job with heavy equipment purchases, at the cost of doubling the Engineer's review and the Owner's processing. Payment at milestones replaces the measurement of percent complete with a yes-or-no on a defined deliverable, which suits a procurement-dominated contract, such as the fabrication of a large piece of equipment, and leaves the Contractor financing everything between milestones. (6.1.2)
6.1.3 The payment period shall end on the cutoff date the Engineer and the Contractor establish at the preconstruction conference under Project Management And CoordinationProject Management and CoordinationResolves to the current adopted revision.sync/project-management-and-coordination, and the same cutoff date shall apply to every application unless the Engineer accepts a change in writing.
6.1.4 The Contractor shall submit each application for payment within the time indicated in the datasheet after the end of the payment period it covers.
Application Submission After the Payment Period Endsrange
Not more than
days
13571015
6.1.5 The Contractor shall review a draft of each application with the Engineer, at the site or by the means the Engineer accepts, before the application is submitted, and shall resolve the percent complete claimed on each line at that review.
NOTE The draft review is where the percent complete is walked and argued at the Work rather than by correspondence after the application is in. An application submitted without it is either certified on the Engineer's own reading of progress, which the Contractor then disputes, or returned, which costs a payment cycle. The few days between the cutoff and the submission are what the review takes. (6.1.6)
6.1.7 An application for payment that is incomplete, that is not supported by the documents this standard requires, or that claims a percent complete the Engineer did not agree at the draft review shall be returned to the Contractor, and the review period under the Agreement shall begin again on receipt of the corrected application.
6.2 Application Form and Content
6.2.1 Each application for payment shall be prepared on the form indicated in the datasheet.
Application for Payment Formradio
○ The Owner's application and continuation sheet form bound in the Contract Documents
○ A published application for payment form listed in the Referenced Standards of this standard
○ The Contractor's own form, carrying the content this standard requires, as accepted by the Engineer
NOTE The Owner's form is what a public body or an Owner with a standing capital program requires, because its accounting, its auditor, and its funding reports are built on it, and it is the form the Owner's counsel has read. A published form is the one every Contractor's accounting system already produces and every lender recognizes, it pairs with the general conditions of the same publisher, and it carries that publisher's certification language. A Contractor's own form, accepted by the Engineer, is used on a small private project where no one has a form and the content matters more than the paper. Whichever form is used, the content below is what the Engineer certifies against. (6.2.2)
6.2.3 Each application for payment shall state, for the Contract as a whole, the original Contract Sum, the net change by change orders, the Contract Sum to date, the total completed and stored to date, the retainage held, the total earned less retainage, the previous payments certified, and the current payment due.
6.2.4 Each application for payment shall carry a continuation sheet listing every line of the schedule of values with the value completed in previous periods, the value completed in this period, the value of materials presently stored, the total completed and stored to date, the percent complete, the balance to finish, and the retainage on that line.
6.2.5 Each application for payment shall list each change order and each construction change directive executed under Contract Modification ProceduresContract Modification ProceduresResolves to the current adopted revision.sync/contract-modification-procedures, with its amount and the date it was approved, and shall include no amount for a change that has not been approved in writing.
6.2.6 Each application for payment shall be signed by an officer or authorized representative of the Contractor and shall carry the Contractor's certification that the Work covered by the application has been completed in accordance with the Contract Documents, that every amount previously paid has been applied to discharge the Contractor's obligations for Work covered by earlier applications, and that the current payment is due.
6.2.7 Where the application form, the Agreement, or the law of the jurisdiction requires the application to be notarized, the Contractor shall submit it notarized.
6.3 Supporting Documents
6.3.1 Each application for payment shall be accompanied by the schedule update that Construction Progress DocumentationConstruction Progress DocumentationResolves to the current adopted revision.sync/construction-progress-documentation requires for the period, and the reconciliation of the percent complete claimed with the progress reported on the schedule shall be as that standard provides.
6.3.2 Partial lien waivers with each application for payment shall be as indicated in the datasheet.
Partial Lien Waivers With Progress Applicationsradio
○ Required, covering the payment received for the previous period
○ Not required with progress applications
NOTE A partial waiver with each application gives the Owner, before it pays this month, evidence that last month's payment reached the subcontractors and suppliers who could otherwise lien the property or claim on the payment bond, and it is the arrangement a lender and most private Owners require. It costs the Contractor the collection of a waiver from every lower tier paid in the previous period before the current application is complete, which on a project with a hundred suppliers is a clerical burden that lands on the subcontractors. A public Owner whose property cannot be liened relies on the payment bond under Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds and on the Contractor's certification of payment instead, and omits the waivers until final payment under Closeout ProceduresCloseout ProceduresResolves to the current adopted revision.sync/closeout-procedures. (6.3.3)
6.3.4 Where partial lien waivers are required, each application for payment after the first shall be accompanied by a waiver from the Contractor and from each subcontractor and supplier paid from the previous application, in the amount of the payment received, and the waiver shall be unconditional where the payment has been received or conditional on receipt where it has not.
6.3.5 Where partial lien waivers are required, each waiver shall be on the form the lien law of the jurisdiction prescribes, and where that law prescribes no form, on the form the Owner provides or the Engineer accepts.
NOTE A waiver written on the wrong form is unenforceable in the states that prescribe one, and an unconditional waiver signed before the money arrives releases the lien right for a payment that was never made, which is a loss the subcontractor discovers when the Contractor fails. The two rules together are the whole of what makes a partial waiver worth collecting. (6.3.6)
6.3.7 Each application for payment shall be accompanied by a list of the subcontractors and suppliers paid from the previous application, with the amount paid to each, where the Owner requests it in writing.
6.3.8 Each application that includes stored materials, a unit price item, or an allowance expenditure shall be accompanied by the documentation the article of this standard for that item requires.
6.4 Engineer's Review and Certification
6.4.1 The Engineer shall review each application for payment within the time the Agreement sets and shall certify to the Owner the amount the Engineer determines is due, or shall notify the Contractor and the Owner in writing of the reasons for certifying a lesser amount or withholding certification.
6.4.2 The Engineer may withhold certification, in whole or in part, to the extent necessary to protect the Owner from loss because of defective Work not remedied, a third-party claim filed or reasonable evidence that one will be filed, the Contractor's failure to pay a subcontractor or supplier for Work covered by an earlier payment, reasonable evidence that the Work cannot be completed for the unpaid balance of the Contract Sum, damage to the Owner or a separate contractor, reasonable evidence that the Work will not be completed within the Contract Time and that the unpaid balance will not cover the resulting damages, or the Contractor's failure to furnish a document this standard requires with the application.
6.4.3 Where the Engineer withholds certification of part of an application, the Engineer shall certify the balance, and where the ground for withholding is removed the Engineer shall certify the withheld amount on the next application.
NOTE A withholding is a specific remedy for a specific condition, stated in writing so the Contractor can cure it, and it stops at the amount needed to cover the loss. A withholding that is not explained, or that holds the whole application for a defect on one line, is the kind of action the prompt-payment law treats as a late payment with interest. (6.4.4)
6.4.5 The Owner shall pay the certified amount within the time the Agreement and the prompt-payment law governing the Owner set.
6.4.6 The Contractor shall pay each subcontractor and supplier, out of each payment received, the amount to which it is entitled for its Work covered by that payment, less the retainage the Contractor withholds from it at a percentage not exceeding the retainage the Owner withholds from the Contractor, within the time the Agreement and the prompt-payment law set.
6.4.7 Certification of an application for payment, and payment of it, shall not constitute acceptance of Work that does not conform to the Contract Documents, and shall not waive any right of the Owner under the Contract Documents.
7 Stored Materials
7.1 Materials Eligible for Payment
7.1.1 Materials and equipment to be incorporated into the Work that have been delivered to the site and stored in accordance with the product standard governing them may be included in an application for payment at their invoiced cost, exclusive of the Contractor's overhead and profit, which shall be earned when the material is installed.
7.1.2 Consumables, temporary materials, formwork, shoring, tools, and construction equipment are not stored materials, and shall not be included in an application for payment as such.
7.1.3 Payment for materials stored at a location off the site shall be as indicated in the datasheet.
Payment for Materials Stored Off Siteradio
○ Not permitted
○ Permitted in a bonded warehouse the Owner has accepted
○ Permitted for the major equipment items the Owner designates, in a bonded warehouse the Owner has accepted
NOTE Paying for a material the Owner cannot see is the risk off-site storage carries: the material is in a building the Owner does not control, under insurance the Owner did not buy, and subject to the warehouse operator's and the supplier's own creditors. Not permitting it keeps every paid-for material on the Owner's land and leaves the Contractor financing its procurement until delivery, which on a long lead item is a year of carrying cost priced into the bid. Permitting it in an accepted bonded warehouse lets the Contractor buy early, lets a supplier be paid on fabrication, and costs the Owner the documentation and the inspection this standard requires for every such item. Limiting it to designated major equipment, which is the arrangement most plant Owners use, confines the exposure to the few items, such as the switchgear, the large pumps, and the membrane racks, whose lead time and cost justify it. (7.1.4)
7.1.5 Materials stored on the site shall be stored in the location, and protected in the manner, the governing product standard and Temporary Facilities And ControlsTemporary Facilities and ControlsResolves to the current adopted revision.sync/temporary-facilities-and-controls require, and a material not so stored shall not be eligible for payment.
7.1.6 Stored materials included in an application shall be identified by line item of the schedule of values, and the value of stored materials on a line, together with the value of installed Work on that line, shall not exceed the scheduled value of the line.
7.2 Stored Materials Documentation
7.2.1 Each application that includes stored materials shall be accompanied, for each item, by the supplier's invoice or bill of sale stating the quantity, the unit cost, and the total, a statement of the location where the item is stored and the quantity on hand, and evidence that the item is insured against loss and damage at its full value, under the builder's risk coverage required by Insurance RequirementsInsurance RequirementsResolves to the current adopted revision.sync/insurance-requirements or by separate coverage naming the Owner.
7.2.2 Each application that includes materials stored off the site shall additionally be accompanied, for each item, by a warehouse receipt or a bill of sale transferring title to the Owner on payment, evidence that the item is segregated from other goods and marked as the Owner's property for this project, the consent of the surety where the bond form requires it, and the address of the storage location and the hours at which the Owner and the Engineer have access to it.
7.2.3 The Owner and the Engineer shall have the right to inspect stored materials, on the site at any time and off the site on two business days' notice, and the Contractor shall arrange the access.
7.2.4 The Contractor shall maintain a stored materials log listing, for each item paid for as a stored material, the invoice, the date paid, the storage location, the date installed, and the application on which the value moved from stored to installed, and shall furnish the log with each application that includes stored materials.
NOTE The log is what keeps a material from being paid for twice, once as stored and again as installed, and it is the record that locates the Owner's property when the Contractor defaults. On a project with many stored items it is the only document that reconciles the stored materials column to anything the Owner can count. (7.2.5)
7.3 Title and Risk of Loss
7.3.1 Title to each material paid for as a stored material shall pass to the Owner on payment, free of any lien, security interest, or claim of the supplier, the Contractor, or any other party, and the Contractor shall warrant that title.
7.3.2 Risk of loss of and damage to a material paid for as a stored material shall remain with the Contractor until substantial completion of the Work in which it is incorporated, and the Contractor shall replace, at no cost to the Owner, any such material lost, stolen, or damaged while stored or in transit to the site.
7.3.3 The Contractor shall remain responsible for the storage, protection, insurance, handling, and transport to the site of every stored material, and for the condition of the material when installed, whether or not the Owner has paid for it.
7.3.4 The Contractor shall not remove a material the Owner has paid for from the site or from the accepted storage location except to incorporate it into the Work, without the Owner's written consent.
NOTE Title and risk are separated deliberately. Title in the Owner is what puts the material beyond the reach of the Contractor's creditors and the supplier's reclamation claim if the Contractor fails. Risk in the Contractor is what keeps the Contractor protecting a material it no longer owns, and it is the allocation under which the builder's risk coverage the Contractor carries is the policy that responds to a loss. (7.3.5)
8 Retainage During Construction
8.1 Percentage Held on Progress Payments
8.1.1 The Owner shall withhold from each progress payment, as retainage, the percentage of the amount earned indicated in the datasheet.
Retainage Held on Progress Paymentsrange
%
2.557.510
NOTE Ten percent is the historical figure and the one most private Owners still start from, and it is also the figure that most states have legislated below for public work, with caps of five percent and lower now common and some jurisdictions requiring that withholding stop at a stated point in the Work. The retainage is the Owner's fund for completing and correcting the Work if the Contractor does not, and it is also the subcontractors' money, held by the Owner through the Contractor for the whole duration of a project that the subcontractor finished in its first month. A high percentage protects the Owner and is priced into the bid as the cost of financing it; a low percentage or none relies on the performance bond under Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds for the same protection and reduces the price. On public work the figure is the one the retainage law governing the Owner allows, and the field records it. (8.1.2)
8.1.3 Where the retainage law governing the Owner caps the retainage, requires that it stop being withheld at a stated point, or requires that it be deposited in an interest-bearing escrow, that law shall govern over the values indicated in the datasheet.
8.1.4 Retainage shall be withheld on the value of change order Work at the same percentage as on the original Contract Sum, unless the change order states otherwise.
8.1.5 Retainage on the value of stored materials shall be as indicated in the datasheet.
Retainage on Stored Materialsradio
○ Withheld at the same percentage as on installed Work
○ Not withheld on stored materials
8.1.7 Where the law governing the Owner entitles the Contractor to deposit securities, or to have the retainage held in escrow, in lieu of the Owner's withholding, the Contractor may do so on the terms that law sets, and otherwise a substitute for retainage shall not be accepted unless the Agreement provides for it.
8.2 Reduction During Construction
8.2.1 The reduction of retainage before substantial completion shall be as indicated in the datasheet.
Retainage Reduction Before Substantial Completionradio
○ No reduction before substantial completion
○ Withholding stops at 50 percent completion and the amount held is retained
○ Retainage reduced to half the indicated percentage of the amount earned at 50 percent completion
○ Reduction at the progress point and in the amount the Agreement states
NOTE Holding the full percentage to substantial completion is the simplest arrangement and the one that keeps the Owner's fund at its largest when the Work is most exposed, and it is also the arrangement under which the earliest subcontractors wait longest for their money. Stopping the withholding at the halfway point, so that the amount already held is kept but nothing more is added, is what several retainage statutes require on public work and what many private Owners grant on a Contractor whose progress is satisfactory, and it halves the Contractor's financing cost for the second half of the Work while leaving the fund that was built in the first half intact. Reducing the retainage to half the percentage of the amount earned releases money already held, which the Contractor passes to the subcontractors who have finished, and it leaves the Owner with a smaller fund going into the closeout period when the fund is most used. A reduction on the Agreement's own terms is recorded where the Owner's standing program already sets one. (8.2.2)
8.2.3 A reduction of retainage before substantial completion shall be conditioned on the Engineer's written determination that the Work is progressing in accordance with the schedule and the Contract Documents, that no defective Work remains uncorrected, and that no claim or lien is outstanding, and on the consent of the surety under Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds where the performance bond is in force.
8.2.4 Where the Owner has reduced retainage and the Contractor thereafter falls behind the schedule or leaves defective Work uncorrected, the Owner may resume withholding at the full indicated percentage on subsequent applications until the condition is cured.
8.2.5 The Contractor shall reduce the retainage it withholds from each subcontractor in the same proportion, and within the same time after receipt, as the Owner reduces the retainage withheld from the Contractor, for the subcontractors whose Work is complete and accepted.
8.2.6 The release of retainage at substantial completion and at final payment, and the consent of surety to each, shall be as Closeout ProceduresCloseout ProceduresResolves to the current adopted revision.sync/closeout-procedures and Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds provide.
9 Unit Prices
9.1 Unit Price Schedule and Application
9.1.1 The unit prices for the Work shall be those stated in the unit price schedule of the bid form under Bidding ProceduresBidding ProceduresResolves to the current adopted revision.sync/bidding-procedures and incorporated in the Agreement, and no other unit price shall apply to the Work unless established by change order under Contract Modification ProceduresContract Modification ProceduresResolves to the current adopted revision.sync/contract-modification-procedures.
9.1.2 Each unit price shall include the full cost of the item complete in place, including labor, materials, equipment, tools, transportation, handling, testing, overhead, profit, and every incidental the Contract Documents require for the item, and no separate payment shall be made for any of them.
9.1.3 The estimated quantities stated in the unit price schedule are stated for the comparison of bids, and payment shall be made for the quantity actually furnished and installed, measured as this standard provides, and not for the estimated quantity.
9.1.4 The unit prices shall apply to additions to and deductions from the Work of the same character, performed under the same conditions, as the items they were bid for, and to no other Work.
NOTE A unit price item is paid for by measurement because its quantity is not known until the Work is done: the depth to rock, the extent of unsuitable soil, the length of a pile. The estimated quantity in the bid form is the Engineer's best figure and it is there so that every bidder prices the same job; it is not a promise of the quantity, and the bid is priced knowing that. (9.1.5)
9.2 Measurement
9.2.1 The measurement basis for each unit price item shall be as stated with the item in the unit price schedule, and where the schedule states none, the item shall be measured in place.
9.2.2 Items measured in place shall be measured to the lines, grades, and limits shown on the drawings or established by the Engineer, and no payment shall be made for quantities outside those limits unless the Engineer directed the additional quantity in writing before the Work was performed.
9.2.3 Items measured by weight shall be measured by certified scale tickets from a scale certified by the weights and measures authority of the jurisdiction, with the tare, the gross, and the net weight on each ticket, and the ticket for each load shall be delivered to the Engineer's representative at the point of delivery, or the load shall not be paid for.
9.2.4 Items paid for by the plan quantity shall be paid for at the quantity shown on the drawings or computed from them by the Engineer, without field measurement, and that quantity shall be adjusted only where the Engineer changes the dimensions of the Work in writing.
9.2.5 Items measured by count shall be counted as units complete in place and accepted, and a unit that is installed and later removed or rejected shall not be counted.
NOTE Measurement in place is the method that pays for what is there, and it costs a survey or a tape at each stage, which is why it suits excavation, pipe, and the items whose quantity the Contractor cannot inflate without the Engineer seeing it. Weight with tickets is the method for aggregate, asphalt, riprap, and the materials delivered by the truckload, and it pays for what arrives, so that an unticketed load is the Contractor's. Plan quantity removes the measurement altogether, pays what the drawings show, and is used for the items whose field measurement would cost more than the dispute it prevents, such as the area of a slab or the length of a curb, at the cost of paying the plan figure when the field quantity differs slightly in either direction. Count is for piles, manholes, valves, and the items that are a number of things. (9.2.6)
9.2.7 The Contractor shall give the Engineer not less than two business days' notice before any unit price Work that will be covered or made inaccessible, so that the quantity can be measured before it is, and unit price Work covered without that notice shall be measured at the Engineer's estimate of the quantity or shall be uncovered at the Contractor's cost for measurement.
9.2.8 Measurements shall be taken jointly by the Engineer's representative and the Contractor's representative, recorded on a measurement record signed by both, and the signed record shall be the quantity submitted with the application for payment.
9.2.9 Where the parties disagree on a measured quantity, the Engineer shall make the initial determination, subject to the dispute resolution provisions of the Contract Documents.
9.3 Variation in Quantity
9.3.1 Where the quantity of a unit price item actually performed differs from the estimated quantity in the unit price schedule by more than the percentage indicated in the datasheet, and the variation changes the Contractor's cost per unit of performing the item, either party may request an adjustment of the unit price for the quantity beyond the threshold, and the adjusted price shall be established by change order under Contract Modification ProceduresContract Modification ProceduresResolves to the current adopted revision.sync/contract-modification-procedures.
Quantity Variation Beyond Which a Unit Price Is Adjustedrange
% of the estimated quantity
5101520253050
NOTE A unit price is bid on the estimated quantity: the mobilization of a drill rig, the setup of a dewatering system, and the purchase of a material at a quantity break are spread over the units the bidder expects to install, and a quantity that comes in at a third of the estimate leaves those costs unrecovered while a quantity at three times the estimate recovers them several times over. The threshold is the variation below which both parties accept that the bid price stands. Twenty-five percent is the figure the general conditions in common use and most public works specifications carry, and it is the one a bidder prices around; a lower threshold reopens the price on smaller swings and costs a change order negotiation on more items; a higher one leaves one party carrying a larger loss or windfall before the price is revisited. The adjustment applies in both directions and only to the quantity beyond the threshold, so that the bid price governs the quantity that was within the estimate. (9.3.2)
9.3.3 An adjustment under this article shall apply only to the quantity in excess of, or short of, the threshold quantity, and the bid unit price shall apply to every unit within the threshold.
9.3.4 A request for an adjustment under this article shall be made in writing before the item is complete, or within the time Contract Modification ProceduresContract Modification ProceduresResolves to the current adopted revision.sync/contract-modification-procedures sets for a change proposal after the quantity became known, whichever is earlier.
9.3.5 Where the Agreement provides that the unit prices are not subject to adjustment for variation in quantity, the Agreement shall govern.
9.3.6 Where a unit price item is deleted entirely, or its quantity reduced to zero, the Contractor shall be paid for the units actually performed and for no others, and any claim for the costs of preparing to perform the item shall be made under Contract Modification ProceduresContract Modification ProceduresResolves to the current adopted revision.sync/contract-modification-procedures.
10 Allowances
10.1 Allowance Types and Coverage
10.1.1 The allowances included in the Contract Sum shall be those stated in the Agreement or in the schedule of allowances in the Contract Documents, each identified by number, by type, and by amount.
10.1.2 A lump sum allowance shall cover the cost to the Contractor of the product or service the allowance names, as indicated in the datasheet.
Lump Sum Allowance Coverageradio
○ The cost of the product delivered to the site, including taxes, and nothing else
○ The cost of the product delivered to the site, including taxes, and its installation
NOTE An allowance that covers the product only is the arrangement under which the Contractor bids the installation in the base Contract Sum, where it is priced competitively against known drawings, and the allowance carries only the price of a product the Owner has not chosen, such as the finish hardware, the laboratory casework, or the signage. An allowance that covers the installation as well is used where the installation cannot be priced until the product is known, such as a piece of process equipment whose footing, piping, and electrical connection depend on the make selected, and it moves the installation out of competition and into the reconciliation. The first keeps more of the Work at bid prices; the second avoids a change order for an installation no bidder could have priced. (10.1.3)
10.1.4 The Contractor's overhead and profit on an allowance item shall be as indicated in the datasheet.
Contractor's Overhead and Profit on Allowance Itemsradio
○ Included in the Contract Sum outside the allowance amount
○ Included within the allowance amount
NOTE Overhead and profit carried outside the allowance, in the base Contract Sum, is the arrangement the general conditions in common use assume, and under it the allowance is spent entirely on the item and the Contractor's margin on it was bid competitively; the margin stays fixed when the item costs more or less than the allowance, so neither party is paid for or penalized on the Owner's selection. Overhead and profit inside the allowance treats the allowance as an all-in budget for the item, which is simpler to track and is what an Owner with a fixed line for the item in its own budget asks for, and under it the margin rises and falls with the item cost and the reconciliation carries overhead and profit on the difference. (10.1.5)
10.1.7 A quantity allowance shall be a unit price stated in the Contract Documents multiplied by an estimated quantity, and the unit price shall be applied to the quantity actually performed, measured as this standard provides for unit price items.
10.1.8 A contingency allowance shall be expended only on the Owner's written direction, for work the Owner directs that is not otherwise required by the Contract Documents, and the Contractor shall have no claim to any part of it that the Owner does not direct to be spent.
NOTE A contingency allowance is the Owner's money, held in the Contract Sum so that a small item of added work can be paid for without amending the Contract, and the Contractor's margin on the work it funds is priced as the Contract Documents provide for a change. A Contractor who treats the contingency as part of its price has misread the term, and the clause above is written so that the reading cannot survive. (10.1.9)
10.2 Allowance Selection and Purchase
10.2.1 The Contractor shall notify the Engineer in writing, not less than the lead time of the item plus thirty days before the date the schedule requires it on the site, of the date by which the Owner's selection of each allowance item is needed.
10.2.2 The Contractor shall obtain, at the Engineer's direction, proposals from the suppliers or subcontractors the Engineer designates for each allowance item, and shall submit the proposals to the Engineer with the Contractor's recommendation and the schedule and cost consequences of each.
10.2.3 The Contractor shall purchase each allowance item only on the Engineer's written authorization naming the item, the supplier, and the amount, and shall not be reimbursed from the allowance for a purchase made without it.
10.2.4 Each allowance item shall be submitted, delivered, stored, handled, and installed as the product standard governing it requires, and the allowance shall not relieve the Contractor of any requirement of that standard.
10.2.5 The Contractor shall report in writing, before the purchase, any allowance item whose cost will exceed the allowance, with the reason and the amount, so that the Owner can change the selection before the money is spent.
10.3 Allowance Reconciliation
10.3.1 The Contractor shall include an allowance item in an application for payment only at the amount actually expended against it, supported by the supplier's or subcontractor's invoice, and shall not bill an allowance as a percentage complete.
10.3.2 Where the cost of an allowance item differs from the allowance amount, the Contract Sum shall be adjusted by change order under Contract Modification ProceduresContract Modification ProceduresResolves to the current adopted revision.sync/contract-modification-procedures by the difference between the cost and the allowance, and the adjustment shall carry the Contractor's overhead and profit on the difference where the datasheet places them within the allowance, and shall carry no overhead and profit on the difference where the datasheet places them outside the allowance and in the Contract Sum.
10.3.3 The whole of an allowance that is not expended, and the whole of a contingency allowance the Owner does not direct to be spent, shall be credited to the Owner by change order.
10.3.4 The Contractor shall submit a reconciliation of every allowance, listing for each the allowance amount, the authorizations issued, the invoices paid, and the difference, with the application for payment on which the last allowance item is billed, and in every case before the final application under Closeout ProceduresCloseout ProceduresResolves to the current adopted revision.sync/closeout-procedures.
10.3.5 Where the Owner's selection of an allowance item is made after the date the Contractor's notice stated and the delay affects the critical path, the Contractor's remedy shall be a time extension request under Contract Modification ProceduresContract Modification ProceduresResolves to the current adopted revision.sync/contract-modification-procedures, made within the time that standard sets.
11 Alternates
11.1 Alternate Descriptions and Acceptance
11.1.1 Each alternate shall be identified by number and described in the Contract Documents, and the description shall state the Work of the base bid that the alternate changes, the Work the alternate adds or deletes, and whether the alternate is an addition to or a deduction from the base bid.
11.1.4 The alternates the Owner has accepted shall be those named in the Agreement, and an accepted alternate shall be part of the Work as if it had been in the base bid.
11.1.5 An alternate the Agreement does not name shall have no effect on the Work, and the Contractor shall make no claim on account of an alternate not accepted.
11.1.6 Where the Agreement reserves to the Owner the right to accept an alternate after the Agreement is executed, the Contractor shall hold the bid price for the alternate for the period the Agreement states, and an alternate accepted within that period shall be incorporated by change order under Contract Modification ProceduresContract Modification ProceduresResolves to the current adopted revision.sync/contract-modification-procedures at the bid price and with the adjustment to the Contract Time, if any, stated in the alternate description.
NOTE The schedule of alternates in the bid form, its layout, and the order in which the Owner considers the alternates in determining the lowest bid are governed by Bidding ProceduresBidding ProceduresResolves to the current adopted revision.sync/bidding-procedures. This standard governs what happens to an alternate once the Agreement names it. (11.1.7)
11.2 Coordination of Accepted Alternates
11.2.2 The Contractor shall notify each subcontractor and supplier whose Work is affected by an accepted alternate, in writing, before that party's submittals are prepared.
11.2.3 The product standards of the Contract Documents shall apply to the Work of an accepted alternate as they apply to the base bid Work, and an alternate description that names a product or a system shall be read as invoking the product standard governing it.
11.2.5 Where the Contractor and the Engineer disagree whether an item of Work falls within an accepted alternate or within the base bid, the Engineer shall make the initial determination, subject to the dispute resolution provisions of the Contract Documents.
12 Coordination with the Agreement and Other Standards
12.1 The Contractor shall reconcile the payment requirements of the Agreement, the General Conditions, the Supplementary Conditions, and each technical standard with this standard, and shall report in writing, before the schedule of values is submitted, any conflict between them.
12.2 Where a technical standard and this standard address the same subject, the more stringent requirement shall govern unless the Contract Documents direct otherwise.
12.3 The Contractor shall include in each subcontract and purchase order the payment period, the application cutoff date, the lien waiver, stored materials documentation, and measurement requirements of this standard that apply to the subcontractor's or supplier's scope, and the retainage terms that flow down under this standard.
NOTE A supplier that never saw this standard, because its purchase order incorporated only the technical section for its product, learns of the stored materials documentation when its invoice is refused and of the lien waiver when the next payment is held. Flowing the requirements into the purchase order is what makes them the supplier's obligation and what lets the Contractor assemble a complete application on the cutoff date. (12.4)