Summary of Work and Work Restrictions

Revision1
EditedNov 16, 2026
StatusCurrent
Contents

View changes in this revision   Revision history

Current revision. This is editorial revision 1, the current text of this standard. Read it on the standard's page.

New standard summarizing what the Work is and the restrictions on it: how it is let (single or multiple prime, the Owner's separate contractors and own forces), Owner-furnished items, phasing, the Owner's occupancy during construction, the Contractor's use of the premises, and personnel access at the facility.

1 Scope

NOTE This standard summarizes the Work and states the restrictions under which the Contractor performs it: how the Work is let, what the Owner furnishes or performs itself, how the Work is phased, how the Owner occupies the premises while they are built on, where and when the Contractor is permitted to work, and who is permitted onto the site, on any project and under any Division of the Specifications. (1.1)
NOTE Most of what this standard governs is project-specific and lives in the drawings: the phases on the phasing plan, the limits of work, the staging areas and the access routes on the site utilization plan, and the Owner-furnished items on their schedule. The standard writes the frame once, states what the Contractor owes under each arrangement the drawings can show, and leaves the facts to the documents that carry them, so that the same text serves a new building on a clear site and a treatment plant that stays in service throughout. (1.2)
NOTE The Owner's right to perform work and to award separate contracts, and the Contractor's use of the site, originate in the Agreement and the General Conditions, which are contract instruments, not specifications. This standard carries them into the project manual, where a subcontractor or supplier who reads only its technical section finds them, and it states the working hours, the access rules, and the coordination duties those instruments leave open. (1.3)
1.4 The Contractor shall comply with this standard in addition to any work restriction stated in the Agreement, the General Conditions, or a technical standard.
1.5 Where a requirement of this standard conflicts with the Agreement, the General Conditions, or the Supplementary Conditions, those documents shall govern.
NOTE The following are outside the scope of this standard: (1.6)
  • The Owner's operating constraints, shutdown and outage requests, tie-ins and cutovers, and the role of the Owner's operators during construction, which Maintenance Of Plant OperationsMaintenance of Plant OperationsResolves to the current adopted revision.sync/maintenance-of-plant-operations governs
  • The temporary roads, fencing, gates, field offices, staging facilities, temporary utilities, and site-operation dust and noise controls, which Temporary Facilities And ControlsTemporary Facilities and ControlsResolves to the current adopted revision.sync/temporary-facilities-and-controls governs
  • The receiving, inspection, storage, handling, and protection of an Owner-furnished product once it is furnished, which Product RequirementsProduct RequirementsResolves to the current adopted revision.sync/product-requirements governs
  • The preconstruction conference, the progress meetings, the coordination drawings, and the request-for-information procedure, which Project Management And CoordinationProject Management and CoordinationResolves to the current adopted revision.sync/project-management-and-coordination governs
  • The construction schedule, its updates, and the recovery schedule, which Construction Progress DocumentationConstruction Progress DocumentationResolves to the current adopted revision.sync/construction-progress-documentation governs
  • Phased substantial completion, the partial certificate of occupancy, the punch list, and final payment, which Closeout ProceduresCloseout ProceduresResolves to the current adopted revision.sync/closeout-procedures governs
  • The commencement of the correction period and of the warranties on a portion the Owner places in use, which Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds governs
  • Builder's risk and the other insurance consequences of the Owner's occupancy, which Insurance RequirementsInsurance RequirementsResolves to the current adopted revision.sync/insurance-requirements governs
  • Photography of the facility and the confidentiality of project information, which Document Confidentiality And Ai UseDocument Confidentiality and AI UseResolves to the current adopted revision.sync/document-confidentiality-and-ai-use governs
  • The protection of existing conditions and of installed Work, cutting and patching, and progress cleaning, which Execution RequirementsExecution RequirementsResolves to the current adopted revision.sync/execution-requirements governs
  • The Contractor's safety program, which is the Contractor's means and methods
  • The Agreement, the General Conditions, and the Supplementary Conditions, which are the Owner's contract instruments and govern where this standard conflicts with them

2 Work and Work Restriction Terms

NOTE The following terms are used in this standard with the meanings given here: (2.1)
  • The Work is the construction and the services the Contract Documents require of the Contractor, whether completed or partly completed, including the labor, materials, equipment, and services incorporated in it or furnished for it
  • The premises are the Owner's site and facility, including the buildings, the structures, the grounds, and the access to them, whether or not within the limits of work
  • The limits of work are the parts of the premises within which the Contractor is permitted to carry out construction operations, as shown on the drawings
  • A single prime contract is an arrangement in which one Contractor holds the contract for the whole Work and every other party performing it is a subcontractor or supplier to that Contractor
  • Multiple prime contracts are an arrangement in which the Owner holds two or more contracts for portions of the Work, each with its own prime contractor and none a subcontractor to another
  • A separate contractor is a contractor the Owner engages, under a contract other than this one, to perform work on the premises during the Work, whether or not that work is related to the Work
  • Work by the Owner's own forces is work on the premises the Owner performs with its own employees during the Work
  • An Owner-furnished, Contractor-installed item is a product the Owner purchases and delivers and the Contractor installs, connects, and places in service as part of the Work
  • An Owner-furnished, Owner-installed item is a product the Owner purchases and installs with its own forces or a separate contractor, for which the Work includes the space, the rough-in, the structural support, and the coordination but not the installation
  • A phase is a portion of the Work defined on the phasing plan, with its own sequence, its own milestones, and its own acceptance for occupancy or use
  • Partial occupancy is the Owner's occupancy or use of a completed portion of the Work before substantial completion of the Work as a whole
  • Regular working hours are the hours and days indicated in the datasheet within which the Contractor is permitted to work on the premises without the Owner's specific permission
  • A restricted area is a part of the premises, shown on the drawings or designated by the Owner, which a person enters only with the Owner's escort or the Owner's unescorted-access authorization
  • An authorized person is an individual the Contractor or a lower tier employs or engages who holds the identification and, where required, the access authorization this standard requires for the area the person enters

3 Referenced Standards

3.1 The use of the premises, the working hours, and the access to the facility shall comply with the latest adopted edition of each of the following unless a specific edition is cited or the Contract Documents direct otherwise.
3.2 Where referenced documents conflict, the more stringent requirement shall govern unless the Engineer of Record directs otherwise in writing.
Standard Title
AIA A201 General Conditions of the Contract for Construction
EJCDC C-700 Standard General Conditions of the Construction Contract
ConsensusDocs 200 Standard Agreement and General Conditions Between Owner and Constructor
IBC Chapter 33 Safeguards During Construction
NFPA 241 Standard for Safeguarding Construction, Alteration, and Demolition Operations
NFPA 101 Life Safety Code
ADA Standards Americans with Disabilities Act Standards for Accessible Design
OSHA 29 CFR 1926 Safety and Health Regulations for Construction
AWWA G430 Security Practices for Operation and Management
NOTE The general conditions in common use carry articles on the Owner's right to perform work and to award separate contracts and on the Contractor's use of the site, and they leave the working hours, the access rules, and the project's own phasing to the specifications and the drawings, which is what this standard supplies. The building code's chapter on safeguards during construction and NFPA 241 govern the egress and the fire protection of an occupied building while it is built on, and the local noise ordinance sets the hours in which construction noise is permitted regardless of what the Contract Documents say. (3.3)

4 Submittals

4.1 Work Restriction Submittals

4.1.1 The Contractor shall submit the following, each at the time this standard states for it:
  • The request for permission to work outside regular working hours, within the notice period indicated in the datasheet
  • The request to deviate from the phasing plan, before the deviation
  • The personnel access roster, with the screening submission or certification for each person where screening is indicated, within the lead time indicated in the datasheet
  • The request for an escort into a restricted area, before the entry
  • The receipt for the return of the Owner's keys, access cards, and credentials, at substantial completion
Work Restriction Submittals Requiredcheckbox
☑ Request for work outside regular working hours
☑ Request for a phasing deviation
☑ Personnel access roster with screening submission
☑ Request for a restricted area escort
☑ Receipt for returned keys and credentials
4.1.2 Work restriction submittals shall be transmitted and tracked through the submittal procedure of Submittal And Quality ProceduresSubmittal and Quality ProceduresResolves to the current adopted revision.sync/submittal-and-quality-procedures, except that a request for permission to work outside regular working hours or for an escort may be made by the written notice the Owner designates for it.
NOTE Every item on the list is a request or a record rather than a shop drawing, and each exists so that the permission, the deviation, or the access is in writing before it happens. The hours request is the one made most often, and it is the one a verbal arrangement at the gate turns into a dispute about who agreed to pay the operator's overtime. (4.1.3)

5 Summary of the Work

5.1 Description of the Work

5.1.1 The Work consists of the construction described by the Contract Documents and summarized in the datasheet.
Summary Description of the Worktext
Enter value...
5.1.2 The Work shall be performed on the premises shown on the site plan.
5.1.3 The summary in the datasheet shall not limit the Work, and the Contractor shall perform every part of the Work the Contract Documents require whether or not the summary names it.
NOTE The summary is the one or two sentences a bidder reads first and a subcontractor often reads last: the facility, what is being built, replaced, or expanded, and whether the facility stays in service while it happens. It orients the reader and is deliberately not a specification of anything; the drawings and the technical standards define the Work, and a summary written in enough detail to compete with them becomes a second, drifting description of the same scope. (5.1.4)

5.2 Contracting Arrangement

5.2.1 The Work shall be let under the contracting arrangement indicated in the datasheet.
Contracting Arrangementradio
● Single prime contract for the whole Work
○ Multiple prime contracts, each for a portion of the Work
NOTE Under a single prime contract the Owner holds one contract and one party answers for the schedule, the coordination between trades, and the site, and the Contractor prices that responsibility. Multiple prime contracts are used where the procurement law governing the Owner requires the general, mechanical, electrical, and plumbing work to be let separately, and by an Owner that wants direct contracts with the trades it considers critical, and they move the coordination between the primes to whoever the datasheet names, together with the exposure to a delay claim from one prime caused by another. (5.2.2)
5.2.3 Where multiple prime contracts are indicated, the Work under this Contract shall be the portion the Agreement for this Contract describes, and the remaining portions shall be performed by the other prime contractors.
5.2.4 Where multiple prime contracts are indicated, the prime contractors shall be coordinated by the party indicated in the datasheet.
Coordinating Party Under Multiple Prime Contractsradio
○ The Owner or the Owner's construction manager
○ The prime contractor for the general construction work, designated the coordinating contractor
○ The Engineer
NOTE The Owner or its construction manager coordinating the primes keeps the authority with the party that holds every contract, and it is what a public Owner with a standing construction management staff does, at the cost of the Owner carrying the coordination risk itself. Designating the general construction prime as coordinating contractor puts the schedule and the sequencing in the hands of the contractor with the most work on the site, and it is priced into that contract as a service, with the limit that one prime has no contract with another and directs it only as far as the Contract Documents say. The Engineer coordinating the primes is used on smaller public projects where no construction manager is engaged, and it adds a construction-phase service to the Engineer's agreement that the Owner pays for separately. (5.2.5)
5.2.6 Each prime contractor shall coordinate its portion of the Work with the other prime contractors through the meetings and the coordination drawings of Project Management And CoordinationProject Management and CoordinationResolves to the current adopted revision.sync/project-management-and-coordination, and shall give each other prime contractor the access to the site and to its portion of the Work that the sequence requires.
5.2.7 Each prime contractor shall report to the coordinating party, in writing and before proceeding, a condition in another prime contractor's work on which its own work depends and which it considers unfit to receive its work.
5.2.8 Where the coordinating party is a prime contractor, it shall prepare and maintain the construction schedule for all prime contracts under Construction Progress DocumentationConstruction Progress DocumentationResolves to the current adopted revision.sync/construction-progress-documentation, and each other prime contractor shall furnish its schedule information to it.
5.2.9 Damage one prime contractor causes to the work of another shall be repaired at the cost of the prime contractor that caused it, and the allocation of responsibility for delay between prime contractors shall be as the General Conditions provide.

5.3 The Owner's Separate Contractors

5.3.1 The Owner reserves the right to perform work on the premises with its own forces and to award separate contracts for work on the premises during the Work, as the General Conditions provide.
5.3.2 The separate contracts the Owner anticipates awarding for work on the premises during the Work shall be as described in the datasheet, and where none is described, none is anticipated at the time of bidding.
Owner's Separate Contracts Anticipated During the Worktext
Enter value...
5.3.3 The Contractor shall afford each separate contractor reasonable access to the premises and to the Work, storage space within the limits of work where the Contract Documents designate it, and the opportunity to connect to and build on the Work, and where the parties disagree whether the access or the space afforded is reasonable, the Engineer of Record shall make the initial determination.
5.3.4 The Contractor shall coordinate its schedule with each separate contractor through Project Management And CoordinationProject Management and CoordinationResolves to the current adopted revision.sync/project-management-and-coordination and shall carry each separate contractor's activities that constrain the Work in its schedule under Construction Progress DocumentationConstruction Progress DocumentationResolves to the current adopted revision.sync/construction-progress-documentation.
5.3.5 Before proceeding with Work that depends on a separate contractor's work, the Contractor shall inspect that work and shall report in writing to the Owner any condition that makes it unfit to receive the Work, and proceeding without a report shall constitute acceptance of the condition except for a defect that inspection could not have found.
5.3.6 The Contractor shall not damage, remove, or alter a separate contractor's work, and shall repair at its own cost damage its operations cause to it.
NOTE A separate contractor on a plant site is usually the Owner's system integrator, the Owner's instrument calibration contractor, or a utility making a service connection, and each arrives on a schedule the Contractor does not control. Naming them at bidding lets the Contractor price the coordination and the shared site; a separate contractor that first appears during the Work is a change in the Contractor's conditions, and the time and cost of it are settled under Contract Modification ProceduresContract Modification ProceduresResolves to the current adopted revision.sync/contract-modification-procedures. (5.3.7)

5.4 Work by the Owner's Own Forces

5.4.1 The work the Owner will perform on the premises with its own forces during the Work shall be as described in the datasheet, and where none is described, none is anticipated at the time of bidding.
Work by the Owner's Own Forcestext
Enter value...
5.4.2 The Owner shall give the Contractor not less than seven days' written notice before its own forces begin work within the limits of work, stating the work, its location, and its duration.
5.4.3 The Owner's forces shall observe the Contractor's site access and safety rules while inside the limits of work, and the Contractor shall provide them the access and the coordination it provides a separate contractor under this standard.
NOTE The Owner's operating staff running the facility are not the Owner's own forces for the purpose of this standard; their role during construction, and the Owner's operating constraints on the Work, are governed by Maintenance Of Plant OperationsMaintenance of Plant OperationsResolves to the current adopted revision.sync/maintenance-of-plant-operations. (5.4.4)

5.5 Owner-Furnished Items

5.5.1 The categories of Owner-furnished items on the project shall be as indicated in the datasheet.
Owner-Furnished Item Categories on the Projectcheckbox
☐ Owner-furnished, Contractor-installed items
☐ Owner-furnished, Owner-installed items
5.5.2 The Owner-furnished items shall be as listed on the Owner-furnished items schedule.
NOTE Owner-furnished items appear on a project where the Owner has a standing purchase agreement for a product, such as a controls platform, a meter, a laboratory instrument, or a vehicle, where the Owner wants to hold the manufacturer's relationship after the project, or where a long-lead item was bought before the construction contract was let to protect the schedule. Each one splits the responsibility for the product between the Owner, who buys it, and the Contractor, who builds around it, and the schedule in the drawings is what names the split for each item. (5.5.3)
5.5.4 For each Owner-furnished, Contractor-installed item, the Owner shall arrange and pay for its purchase, shall furnish the Contractor the manufacturer's product data, dimensions, rough-in, and installation instructions in time for coordination, and shall deliver it to the site by the date the Contractor's accepted schedule requires, unless the Owner-furnished items schedule states another delivery point for the item.
5.5.5 For each Owner-furnished, Contractor-installed item, the Work shall include the rough-in, the structural support, the connections, the installation in accordance with the manufacturer's instructions, and the startup and testing the technical standards require for a Contractor-furnished item of the same kind.
5.5.6 The Contractor shall state in its schedule the date by which it requires delivery of each Owner-furnished, Contractor-installed item, and delivery by the Owner after that date shall entitle the Contractor to request a time extension under Contract Modification ProceduresContract Modification ProceduresResolves to the current adopted revision.sync/contract-modification-procedures.
5.5.7 For each Owner-furnished, Owner-installed item, the Work shall include the space, the rough-in, the structural support, and the utility connections the item requires, and the installer of the item shall be afforded access as a separate contractor under this standard.
NOTE The receiving, inspection, storage, handling, and protection of an Owner-furnished item once furnished, and the responsibility for damage to it after delivery, are governed by Product RequirementsProduct RequirementsResolves to the current adopted revision.sync/product-requirements. (5.5.8)

6 Phasing of the Work

6.1 Phases and Sequence

6.1.1 The Work shall be performed in the phasing indicated in the datasheet.
Phasing of the Workradio
○ Single phase, completed and accepted as a whole
○ Multiple phases, each accepted separately
6.1.2 Where multiple phases are indicated, the phases, their order, the Work within each, and the interim milestones shall be as shown on the phasing plan.
6.1.3 A phase shall not be considered complete until the Work in it has been accepted for occupancy or use under the phased closeout of Closeout ProceduresCloseout ProceduresResolves to the current adopted revision.sync/closeout-procedures.
6.1.4 The Contractor shall not begin a phase, or a part of one, out of the order the phasing plan shows without the Owner's written approval of the deviation and of the sequence proposed in its place.
6.1.5 A request to deviate from the phasing plan shall state the deviation, the reason, the effect on each affected phase and on the Owner's occupancy and operations, and the sequence proposed, and the Owner's approval of a deviation shall not change the Contract Time or the Contract Sum unless a modification under Contract Modification ProceduresContract Modification ProceduresResolves to the current adopted revision.sync/contract-modification-procedures says so.
NOTE A phased project on an operating facility is sequenced around what has to keep running: the new unit goes in before the old one comes out, and the second half of a channel is rebuilt after the first half is back in service. The order on the phasing plan is the Owner's and the Engineer's record of that reasoning, and a Contractor who sees a faster sequence proposes it rather than takes it, because the constraint the sequence protects is often not visible from the construction side. (6.1.6)
6.1.7 The interim milestone dates for each phase, and the consequences of missing them, shall be as stated in the Agreement.
NOTE The shutdowns, outages, tie-ins, and cutovers a phase requires are requested and performed under Maintenance Of Plant OperationsMaintenance of Plant OperationsResolves to the current adopted revision.sync/maintenance-of-plant-operations, and the construction schedule that carries the phases is governed by Construction Progress DocumentationConstruction Progress DocumentationResolves to the current adopted revision.sync/construction-progress-documentation. (6.1.8)

7 Owner Occupancy

7.1 Occupancy During Construction

7.1.1 The Owner's occupancy of the premises during the Work shall be as indicated in the datasheet.
Owner Occupancy of the Premises During Constructionradio
○ Unoccupied, the premises vacated for the duration of the Work
○ Partially occupied, with the occupied areas changing by phase
○ Fully occupied and operating throughout the Work
7.1.2 Where the Owner occupies part of the premises, the areas occupied, and the periods of their occupancy where these change by phase, shall be as shown on the phasing plan.
NOTE Unoccupied premises give the Contractor the site, and nearly every restriction in the rest of this standard falls away except the hours the neighbors and the ordinance impose. Partial occupancy is the condition of most renovation and expansion work: the Owner keeps the offices, the laboratory, or the half of the plant that is not being rebuilt, and the Contractor works beside it, with the occupied areas moving as the phases advance. A fully occupied and operating facility is the condition of nearly every water and wastewater plant upgrade, since the plant cannot stop treating, and it puts the Owner's operations, not the Contractor's convenience, first in every scheduling decision on the site. (7.1.3)
7.1.4 The Contractor shall conduct the Work so that the Owner's occupancy of, and operations in, the occupied areas continue without interruption, except for the interruptions the Owner has approved in writing under Maintenance Of Plant OperationsMaintenance of Plant OperationsResolves to the current adopted revision.sync/maintenance-of-plant-operations.
7.1.5 The Owner may use any part of the premises outside the limits of work at any time during the Work.
7.1.6 Work inside an occupied area shall be performed only with the Owner's written permission for the area and the time, requested with the notice this standard requires for work outside regular working hours, unless the phasing plan provides otherwise.

7.2 Partial Occupancy Before Substantial Completion

7.2.1 The Owner's partial occupancy of completed portions of the Work before substantial completion shall be as indicated in the datasheet.
Partial Occupancy of Completed Portions Before Substantial Completionradio
○ Not permitted
○ Permitted for the portions designated in the Contract Documents
○ Permitted for any portion, on the Owner's written notice
NOTE Not permitting partial occupancy keeps one completion date, one certificate, one warranty start, and one insurance transition, and it is the arrangement for a project the Owner cannot use in pieces. Permitting it for designated portions is the phased project: the Owner takes each phase as the phasing plan shows, and the Contractor has priced the occupied-building conditions that follow. Permitting it for any portion on notice gives the Owner the flexibility to move in wherever the Work is finished, at the cost of a Contractor who cannot know at bidding which parts of the site it will lose, and prices that uncertainty. (7.2.2)
7.2.3 The Owner shall give the Contractor written notice of each partial occupancy not less than the period indicated in the datasheet before the occupancy, stating the portion, the date, and the date on which the Owner assumes responsibility for the utilities, the operation, the maintenance, and the security of the portion.
Notice of Partial Occupancyrange
Not less than
days
357142130
7.2.4 Before the Owner occupies a portion, the Contractor and the Owner shall jointly inspect it and shall record in writing its condition and the Work in it that remains incomplete or is to be corrected, and the record shall be the baseline for responsibility for damage after occupancy.
7.2.5 The Contractor shall retain access to an occupied portion, at times the Owner designates, to complete and correct the Work in it.
7.2.6 Where the parties disagree whether the times the Owner designates for access to an occupied portion are sufficient to complete and correct the Work in it, the Engineer of Record shall make the initial determination.
NOTE The partial certificate of occupancy where the authority having jurisdiction requires one, the certificate of substantial completion for the portion, its punch list, and its lien waivers are governed by Closeout ProceduresCloseout ProceduresResolves to the current adopted revision.sync/closeout-procedures; the start of the correction period and the warranties on the portion by Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds; and the insurance consequences of the Owner's occupancy by Insurance RequirementsInsurance RequirementsResolves to the current adopted revision.sync/insurance-requirements. (7.2.7)
NOTE Partial occupancy is where the Owner's and the Contractor's responsibilities overlap for the longest time, and the joint inspection is what keeps that overlap from becoming an argument: a scratched door recorded at occupancy is the Contractor's, and one found a month later is not. The date in the notice does the same work for the utility bill. (7.2.8)

8 Contractor's Use of the Premises

8.1 Limits of Work, Staging, and Access

8.1.1 The Contractor shall confine its construction operations to the limits of work shown on the site utilization plan.
8.1.2 Material storage, staging, the Contractor's field offices, and construction parking shall be confined to the areas designated for them on the site utilization plan.
8.1.3 Construction traffic and deliveries shall enter and leave the premises by the routes and the gates designated on the site utilization plan.
8.1.4 Construction traffic shall not use the Owner's operating entrances, roads, or parking unless the site utilization plan designates them for construction use.
NOTE The site utilization plan in the Contract Documents is the Engineer's and the Owner's statement of what part of the premises the Contractor gets: the limits of work, the areas available for staging and parking, the routes construction traffic takes, and the parts of the facility that stay the Owner's. The Contractor's own site logistics plan under Temporary Facilities And ControlsTemporary Facilities and ControlsResolves to the current adopted revision.sync/temporary-facilities-and-controls lays out its offices, fencing, roads, and utilities inside those limits, and the temporary facilities themselves are governed there, not here. (8.1.5)
8.1.6 Where the drawings show no limits of work, the limits of work shall be the boundary of the Owner's property, less the areas the Owner occupies and the areas this standard or the Owner designates as restricted.
8.1.7 The Contractor shall not use any part of the premises outside the limits of work for construction operations, storage, or parking without the Owner's written permission for the area and the period.
8.1.8 The Contractor shall repair at its own cost damage its operations cause to the Owner's property, roads, paving, landscaping, utilities, and structures outside the limits of work, to the condition they were in before the damage as the record of existing conditions under Execution RequirementsExecution RequirementsResolves to the current adopted revision.sync/execution-requirements establishes it.
8.1.9 The use of the Owner's existing toilets, break rooms, parking, and other facilities by the Contractor's personnel shall be as indicated in the datasheet.
Contractor Personnel Use of the Owner's Existing Facilitiesradio
● Not permitted
○ Permitted for the facilities the Owner designates in writing

8.2 Keeping Occupied Areas and Exits Usable

8.2.1 The Contractor shall keep every road, walk, entrance, exit, fire lane, hydrant, fire department connection, and accessible route serving an occupied area open and usable during every hour the area is occupied, except for a closure the Owner has approved in writing.
8.2.2 Where the Work obstructs or closes a required exit or exit path from an occupied area, the Contractor shall provide and sign a temporary exit or exit path accepted by the authority having jurisdiction before the obstruction, in accordance with IBC Chapter 33, NFPA 241, and NFPA 101.
8.2.3 Where the Work obstructs an accessible route serving an occupied area, the Contractor shall provide a temporary accessible route complying with the ADA Standards for the period of the obstruction.
8.2.4 The Contractor shall not permit dust, debris, water, fumes, odor, or noise from the Work to enter an occupied area beyond the levels the Owner has accepted in writing for the operation, and where the parties disagree whether a condition in an occupied area is caused by the Work, the Engineer of Record shall make the initial determination.
8.2.5 The Contractor shall keep clear the Owner's operating access to every piece of equipment, valve, panel, hydrant, and sampling point the Owner uses during the Work, and shall not block it with material, equipment, or a temporary facility without the Owner's written permission for the period.
NOTE The exits and the fire protection of an occupied building during construction are a code matter before they are a contract one: the building code's chapter on safeguards during construction and NFPA 241 require that the means of egress and the fire protection of the occupied part be maintained, and the fire marshal enforces them on the Contractor directly. The clauses above make the same obligation a contract one so that the Owner can enforce it without waiting for an inspection. The controls that keep dust and noise out of the occupied area are governed by Temporary Facilities And ControlsTemporary Facilities and ControlsResolves to the current adopted revision.sync/temporary-facilities-and-controls; what this standard states is the result the Owner is owed. (8.2.6)

8.3 Working Hours

8.3.1 Regular working hours, stated as the hours of the day, the days of the week, and the Owner's observed holidays on which work is not permitted, shall be as indicated in the datasheet.
Regular Working Hourstext
Enter value...
NOTE Regular working hours are set by the Owner's operations and by the local noise ordinance, not by the construction industry's habits, and no window fits four projects in five. A daytime weekday window on an unoccupied site is the one a bidder assumes without being told; an occupied office building pushes noisy work to evenings and weekends; a plant whose operators are on site around the clock often has no reason to restrict the hours at all except at shift change and during the hours the ordinance protects the neighbors. The ordinance governs regardless of what the datasheet says, and the datasheet states the hours within it that the Owner allows. (8.3.2)
8.3.3 The Contractor shall not work on the premises outside regular working hours without the Owner's written permission, requested in writing not less than the notice period indicated in the datasheet before the work.
Notice for Work Outside Regular Working Hoursrange
Not less than
days
123571014
8.3.4 A request for permission to work outside regular working hours shall state the work, its location, the hours and dates proposed, the number of persons on site, and whether the work is noisy or otherwise disruptive to an occupied area.
8.3.5 The Owner's permission for work outside regular working hours shall not be required for work the phasing plan or the Contract Documents require to be performed outside them, for work the Owner directs in writing to be so performed, or for work necessary to protect life, the Work, or the Owner's property from an immediate danger, and the Contractor shall give the Owner the notice indicated in the datasheet for the first two and notice before the work begins, or within twenty-four hours after it where that is not possible, for the third.
8.3.6 Work outside regular working hours shall remain subject to the property-line noise limit and the hours for high-noise operations under Temporary Facilities And ControlsTemporary Facilities and ControlsResolves to the current adopted revision.sync/temporary-facilities-and-controls and to the local ordinance.
8.3.7 The cost of the Owner's additional staffing, security, inspection, and the Engineer's observation made necessary by work outside regular working hours shall be borne by the party indicated in the datasheet.
Owner's Additional Cost of Work Outside Regular Working Hoursradio
○ The Contractor in every case
○ The Owner in every case
○ The party at whose request or direction the work is performed
NOTE An Owner whose plant is staffed around the clock has an operator on site in any case and bears little additional cost from night work, which is why some Owners carry the cost themselves rather than price it into every bid. An Owner that has to call in an operator, a security guard, or an inspector for a Saturday pour pays overtime it would not otherwise pay, and assigning that cost to the Contractor keeps off-hours requests to the ones the Contractor needs. Assigning it to the party that asked for the work is the arrangement most often reached when the question is negotiated, and it depends on the request record being kept. (8.3.8)
8.3.9 Work the Owner identifies as disruptive to an occupied area, including work producing noise, vibration, odor, or dust that reaches the area, work that interrupts a service to it, and work in or through it, shall be performed only in the windows indicated in the datasheet.
Disruptive Work Windows in Occupied Facilitiesradio
○ No restriction beyond regular working hours
○ Outside the Owner's business hours in the affected area
○ Windows the Owner designates on request
NOTE No restriction beyond the regular hours suits a site where the occupied area is far enough from the Work that nothing reaches it. Working outside the Owner's business hours in the affected area is the rule for an occupied office, a laboratory, or a control room with a day shift, and it moves the disruptive work to evenings and weekends at premium labor rates the bid carries. Windows designated on request suit a facility whose sensitive operations move, such as a laboratory running a certified analysis or a plant in a seasonal demand peak, and they leave the Contractor to request each window and the Owner to answer each request, with the schedule risk that implies. (8.3.10)
8.3.11 Where the parties disagree whether a particular operation is disruptive to an occupied area, the Engineer of Record shall make the initial determination.

9 Personnel Access at the Facility

9.1 Identification and Sign-In

9.1.1 Every person entering the premises on behalf of the Contractor or a lower tier shall carry, while on the premises, the identification indicated in the datasheet.
Personnel Identification on the Premisesradio
○ No requirement beyond the Contractor's own identification
○ Government-issued photo identification carried on the person
○ The Contractor's project identification badge with photograph, in a form the Owner has approved
○ The Owner's identification badge issued to each person
NOTE The identification regime sets how quickly the Owner's staff can tell who belongs on the site. No requirement suits a fenced site the Owner does not occupy. Government identification costs nothing to administer and proves who a person is but not that the person is on the project. A project badge the Contractor issues in an approved form, with a photograph and the employer's name, lets an operator recognize a construction worker at a glance and costs the Contractor a badge printer. The Owner's own badge ties the person to the Owner's access control system and its record, and it costs the Owner the enrollment of every worker and the Contractor the lead time for it, which is why it is the regime of a facility with a security program and of few others. (9.1.2)
9.1.3 Each person entering and leaving the premises on behalf of the Contractor or a lower tier shall be recorded as indicated in the datasheet.
Daily Sign-In Recordradio
○ Not required
○ Kept by the Contractor at its site office and furnished to the Owner on request
○ Made at the Owner's control point on each entry and exit
NOTE A sign-in record is kept for the day the Owner needs to know who was on the site: after an incident, a loss, or a security event. The Contractor's own record at its office is the one most projects keep anyway for the daily report and costs nothing more, and it is as accurate as the Contractor's superintendent makes it. Sign-in at the Owner's control point gives the Owner a record it controls and a count of who is inside at any moment, and it costs every worker a stop at the gate on every entry, which a staffed guard point makes quick and an unstaffed one does not. No record suits an unoccupied site where the Contractor's own daily report under Construction Progress DocumentationConstruction Progress DocumentationResolves to the current adopted revision.sync/construction-progress-documentation is enough. (9.1.4)
9.1.5 Where a badge or screening is indicated, the Contractor shall furnish the Owner, before the first person needs access and whenever it changes, a roster of the persons who will enter the premises on its behalf, stating for each the name, the employer, the trade or role, and the areas and hours of access required.

9.2 Restricted Areas and Escort

9.2.1 The restricted areas of the facility shall be as shown on the site utilization plan and as the Owner designates in writing during the Work.
9.2.2 No person shall enter a restricted area on behalf of the Contractor unless escorted by the Owner's representative or holding the Owner's written unescorted-access authorization for that area.
9.2.3 The Contractor shall request an escort for a restricted area not less than the notice period indicated for work outside regular working hours before the entry, stating the persons, the purpose, and the duration, and the Owner shall furnish the escort at the time agreed.
9.2.4 The Owner may require the Contractor's personnel to be escorted in any area and may change the restricted areas during the Work by written notice, and where a change made after bidding adds cost or time to the Work, the Contractor's remedy shall be under Contract Modification ProceduresContract Modification ProceduresResolves to the current adopted revision.sync/contract-modification-procedures.
NOTE A restricted area on a water or wastewater plant is the control room, the chemical storage and feed area, the electrical rooms, and the reservoir or clearwell hatches: the places where a person with no business there can hurt the public, not only the project. An escort costs the Owner an operator's time for every entry, which is why the restricted areas are drawn narrowly and the rest of the site is open to a badged worker. (9.2.5)

9.3 Background Screening

9.3.1 Before a person is granted unescorted access to the premises on behalf of the Contractor or a lower tier, the person shall have been screened as indicated in the datasheet.
Personnel Background Screeningradio
○ None required
○ The Owner's own screening program, applied to each person before unescorted access
○ A background check by the Contractor under the criteria stated in the Contract Documents, certified to the Owner for each person
NOTE No screening is the condition of most building sites and of a plant site where every worker is escorted. The Owner's own program puts the check, its criteria, and its decision with the Owner, which is what a utility with an existing employee screening program does for consistency, and it costs the Owner the processing and the Contractor the lead time before a new hire can work unescorted. A check the Contractor performs against stated criteria and certifies to the Owner keeps the personal information with the employer and the processing off the Owner's desk, and it leaves the Owner relying on the Contractor's certificate; the criteria, including how far back the check reaches and what disqualifies a person, are stated in the Contract Documents because the law of the jurisdiction on what an employer and an Owner can ask about and act on varies. (9.3.2)
9.3.3 Where screening is indicated, the Contractor shall submit each person for screening, or its certification of the person's screening, not less than the lead time indicated in the datasheet before the person requires unescorted access.
Lead Time for Access Authorizationrange
Not less than
days
35710142130
9.3.4 The cost of screening the Contractor's and the lower tiers' personnel shall be borne by the Contractor unless the Contract Documents state otherwise, and the Owner shall bear the cost of operating its own screening program.
9.3.5 The Owner may deny or withdraw unescorted access to any person on the basis of the screening without stating the reason to the Contractor, and the denial shall not be a basis for a change in the Contract Time or the Contract Sum.
9.3.6 Water, wastewater, and power facilities are critical infrastructure, and the Owner may, by written notice, impose on any part of the facility an identification, screening, escort, or access requirement beyond those indicated in the datasheet where its security program requires it, and where the requirement is imposed after bidding, the cost and time consequences shall be determined under Contract Modification ProceduresContract Modification ProceduresResolves to the current adopted revision.sync/contract-modification-procedures.

9.4 Removal of Persons and Rules of Conduct

9.4.1 The Contractor shall remove from the premises, on the Owner's written request stating the conduct, any person on the premises on its behalf whose conduct the Owner finds unsafe, disruptive to its operations, or in breach of the rules of this standard, and shall remove the person before the end of the shift in which the request is made.
9.4.3 The Contractor shall enforce the following rules of conduct on every person on the premises on its behalf or on behalf of a lower tier:
  • Entry only through the designated gates, and presence only within the limits of work and the areas the person is authorized to enter
  • No firearm, weapon, or explosive on the premises, except where the law of the jurisdiction prevents the Owner from restricting it
  • No alcohol, cannabis, or other impairing substance on the premises, and no person on the premises under the influence of one
  • Smoking, tobacco, and vapor products only in the areas the Owner has designated for them, and nowhere else on the premises
  • No photograph, video, or recording except as Document Confidentiality And Ai UseDocument Confidentiality and AI UseResolves to the current adopted revision.sync/document-confidentiality-and-ai-use and the progress documentation program under Construction Progress DocumentationConstruction Progress DocumentationResolves to the current adopted revision.sync/construction-progress-documentation permit
  • No use of the Owner's tools, equipment, vehicles, materials, utilities, or chemicals, and no operation of the Owner's valves, switches, controls, or process equipment, except under Maintenance Of Plant OperationsMaintenance of Plant OperationsResolves to the current adopted revision.sync/maintenance-of-plant-operations
  • No contact with the Owner's process water, sludge, chemicals, or stored product except as the Work requires and the Owner has approved
  • No animal, no child, and no person not engaged in the Work on the premises
  • Vehicles only on the designated routes, at the speed the Owner posts, and parked only in the designated areas
  • Courteous conduct toward the Owner's staff, the occupants, and the public, and no solicitation on the premises
NOTE The rules are the ones an operating facility already applies to its own staff and its visitors, written down so that they bind the Contractor's workers through the Contractor rather than depending on a sign. The firearm rule is written around the law because several states give a person a right to keep a firearm in a locked vehicle that a property owner cannot override; the Owner restricts what the law lets it restrict. (9.4.4)

9.5 The Owner's Keys and Credentials

9.5.1 The Contractor shall sign for each key, access card, and credential the Owner issues to it, shall hold each in the name of a named individual, and shall not duplicate, lend, or transfer one.
9.5.2 The Contractor shall report a lost or stolen key, access card, or credential to the Owner within twenty-four hours after discovering the loss, and shall bear the cost of the re-keying, re-coring, or re-credentialing the Owner determines the loss requires.
9.5.3 The Contractor shall return every key, access card, and credential to the Owner at substantial completion, or when the person holding it leaves the project, whichever is first, and the Owner's receipt for them shall be a closeout submittal under Closeout ProceduresCloseout ProceduresResolves to the current adopted revision.sync/closeout-procedures.
NOTE A lost master key re-cores a building, and a lost access card is live until someone revokes it. Naming the individual holder is what makes the loss reportable the same day instead of discovered at closeout. Temporary construction cylinders and the keying of the permanent hardware are governed by Door HardwareDoor HardwareResolves to the current adopted revision.sync/door-hardware. (9.5.4)

10 Coordination with the Agreement and Other Standards

10.1 The Contractor shall reconcile the contracting arrangement, the phasing, the occupancy, the working hours, and the access requirements of the Agreement, the General Conditions, the drawings, and each technical standard with this standard, and shall report in writing at the preconstruction conference under Project Management And CoordinationProject Management and CoordinationResolves to the current adopted revision.sync/project-management-and-coordination any conflict between them.
10.2 Where a technical standard and this standard address the same subject, the more stringent requirement shall govern unless the Contract Documents direct otherwise.
10.3 The Contractor shall include the working hours, the disruptive work windows, and the access, identification, screening, and conduct requirements of this standard in each subcontract and purchase order whose scope brings a person onto the premises, and shall remain responsible to the Owner for each lower tier's compliance whether or not the flow-down was made.
NOTE A roofer's crew that arrives at six on a Saturday because its subcontract said nothing about the hours is the Contractor's breach, and a supplier's driver who photographs the clearwell on the way out is the Contractor's disclosure. The flow-down is what gives the Contractor recourse against the lower tier for the breach it is already answerable for. (10.4)

Written and maintained by SynC. Licensed under CC BY 4.0.