SynC · SynC Standards
Maintenance of Plant Operations
Contents
- 1Scope
- 2Maintenance of Plant Operations Terms
- 3Referenced Standards
- 4Submittals
- 4.1Plan Submittals
- 4.2Shutdown and Tie-In Submittals
- 5Operating Constraints
- 5.1Facilities That Remain in Service
- 5.2Permits and Service Levels
- 5.3Flows, Loads and Capacity During Construction
- 5.4Plant Utilities
- 5.5Constraints Table and Sequence Drawings
- 6Maintenance of Plant Operations Plan
- 6.1Plan Content
- 6.2Submittal and Review
- 6.3Plan Updates
- 7Shutdown and Outage Requests
- 7.1Request and Notice
- 7.2Request Content
- 7.3Owner's Review and Response
- 7.4Permitted Times and Seasons
- 7.5Duration and Overrun
- 7.6Cancellation and Postponement
- 7.7Readiness Check
- 7.8Unplanned Shutdowns
- 8Tie-Ins and Cutovers
- 8.1Pre-Tie-In Meeting
- 8.2Verification of the Existing Condition
- 8.3Hot Taps and Line Stops
- 8.4Operation of Existing Valves and Equipment
- 8.5Isolation, Lockout and Tagout
- 8.6Cutover Sequence and Temporary Control
- 8.7Return to Service
- 9Temporary Facilities That Maintain Operations
- 9.1Requirement and Performance Basis
- 9.2Standby Provisions
- 9.3Removal
- 10Placing New Facilities in Service
- 10.1Authorization
- 10.2Record and Operation
- 11Compliance During Construction
- 11.1Notice of a Compliance Threat
- 11.2Monitoring During a Shutdown
- 11.3Responsibility for Exceedances
- 11.4Reporting to the Regulator
- 12Coordination with the Owner's Operations Staff
- 12.1Points of Contact
- 12.2Operations Log
- 12.3Control Room and SCADA Access
- 12.4Training on Temporary Arrangements
- 13Coordination with the Agreement and Other Standards
Download
Build a datasheet from this standard
Start a project with this standard already attached — one click, no setup.
Use in a project
1 Scope
NOTE This standard establishes the administrative requirements for maintaining the operation of an existing plant or facility, and its compliance with the permits and service levels that govern it, while the Work is constructed within it, connected to it, or carried out beside it, on any project and under any Division of the Specifications. (1.1)
NOTE A treatment plant under expansion treats every day of the construction period, a pump station under rehabilitation pumps through it, and a hospital or a data center under renovation serves its patients or its tenants through it. The Work is built around an operating facility whose permit, whose customers, and whose operators do not pause for it. This standard states what the Owner needs kept running, how the Contractor asks for the interruptions the Work cannot avoid, who operates what while the two overlap, and who answers when the plant falls out of compliance. (1.2)
NOTE The Owner's operating constraints and the Contractor's plan for working within them are the two documents this standard turns on. The constraints are project-specific and belong on the drawings; the plan is the Contractor's and belongs in its submittals. This standard states the categories of constraint, the content of the plan, and the procedures that connect them, and it does not invent a constraint list for a plant it has not seen. (1.3)
1.4 The Contractor shall comply with this standard in addition to any maintenance of operations requirement stated in the Agreement, the General Conditions, a technical standard, or on the drawings.
1.5 Where a requirement of this standard conflicts with the Agreement, the General Conditions, or the Supplementary Conditions, those documents shall govern.
1.6 Where a technical standard states a requirement for a shutdown, a tie-in, or the operation of existing equipment within its own scope, this standard shall govern the request, notice, review, readiness, and return-to-service procedure for that shutdown or tie-in unless the technical standard states a more stringent requirement.
NOTE The following are outside the scope of this standard: (1.7)
- The temporary pumping system that carries a sewer flow, a plant process stream, or a pump station flow around the Work, with its design basis, equipment, piping, monitoring, sealed plan, test run, and spill responsibility, which Temporary Bypass PumpingTemporary Bypass PumpingResolves to the current adopted revision.sync/temporary-bypass-pumping governs
- Temporary power, lighting, water, heat, ventilation, enclosures, field offices, fencing, and the other temporary facilities and controls of the site, which Temporary Facilities And ControlsTemporary Facilities and ControlsResolves to the current adopted revision.sync/temporary-facilities-and-controls governs
- The phasing of the Work and the sequence of construction as a scope statement, Owner occupancy, the Contractor's use of the premises, working hours, and personnel access and screening at the facility, which Summary Of Work And Work RestrictionsSummary of Work and Work RestrictionsResolves to the current adopted revision.sync/summary-of-work-and-work-restrictions governs
- The construction schedule, its format, its updates, and the recovery schedule, which Construction Progress DocumentationConstruction Progress DocumentationResolves to the current adopted revision.sync/construction-progress-documentation governs
- The cost and time consequences of a change in the Work, including the adjustment that follows an Owner-cancelled or Owner-postponed shutdown once this standard has stated who bears it, which Contract Modification ProceduresContract Modification ProceduresResolves to the current adopted revision.sync/contract-modification-procedures governs
- The startup, the field performance test, the early-use decision, and the restoration after early use of process equipment, which Common Work Results ProcessCommon Work Results for Process EquipmentResolves to the current adopted revision.sync/common-work-results-process governs, and the commissioning of the new building systems, which CommissioningTotal Building CommissioningResolves to the current adopted revision.sync/commissioning governs
- The control narratives, the software configuration, the loop checks, and the acceptance tests of the control system, including the migration of an existing control platform, which Control Systems IntegrationControl Systems Integration and TestingResolves to the current adopted revision.sync/control-systems-integration governs
- Planned electrical outages in an existing building, their notice, their timing, and their log, which Common Work Results ElectricalCommon Work Results for ElectricalResolves to the current adopted revision.sync/common-work-results-electrical governs, and the removal and relocation of existing electrical work, which Electrical Demolition And RelocationSelective Electrical DemolitionResolves to the current adopted revision.sync/electrical-demolition-and-relocation governs
- Site security during construction, which Temporary Facilities And ControlsTemporary Facilities and ControlsResolves to the current adopted revision.sync/temporary-facilities-and-controls and Summary Of Work And Work RestrictionsSummary of Work and Work RestrictionsResolves to the current adopted revision.sync/summary-of-work-and-work-restrictions govern
- The Contractor's safety program, its hazard analyses, and its procedures for confined spaces and energized work, which are means and methods
2 Maintenance of Plant Operations Terms
NOTE The following terms are used in this standard with the meanings given here: (2.1)
- The plant is the existing water treatment plant, wastewater treatment plant, pump station, industrial process facility, or other facility within or beside which the Work is performed and whose operation is maintained under this standard
- The Owner's operations staff are the employees and the contract operators who run the plant under the Owner's permits and who hold the Owner's authority over its process, its equipment, and its control system
- The operations representative is the individual the Owner designates to receive shutdown requests, authorize shutdowns and tie-ins, and speak for the operations staff under this standard
- The constraints table is the schedule on the drawings that lists, for each process, unit, flow path, and utility of the plant, whether it remains in service, the minimum capacity or performance it maintains, the longest shutdown it tolerates, and the conditions under which a shutdown is permitted
- A shutdown is any interruption, isolation, de-energization, draining, or reduction below the constraints table of a process, unit, flow path, or utility of the plant that the Work requires, however brief
- An outage is a shutdown of an electrical, instrumentation, control, communication, or other utility service to the plant
- A tie-in is the connection of new work to an existing pipe, channel, structure, conduit, circuit, or control system, including the cutting, the hot tap, the line stop, and the connection itself
- A cutover is the transfer of a process, a flow, a load, or a control function from an existing facility to a new or temporary one, or back
- The maintenance of plant operations plan is the Contractor's written plan, with its drawings and schedule, for performing the Work within the constraints table
- A readiness check is the joint inspection, before a shutdown begins, that confirms the materials, the prefabrication, the crews, the temporary facilities, and the standby provisions the shutdown depends on are in place
- A compliance threat is any condition arising from the Work that could cause the plant to exceed a permit limit, bypass a treatment unit, discharge or overflow untreated or partially treated water or wastewater, fail a drinking water standard, or fall below a service level the constraints table states
- A return to service is the restoration of a process, unit, flow path, or utility to the Owner's operation after a shutdown, confirmed by the operations representative
3 Referenced Standards
3.1 The maintenance of plant operations shall comply with the latest adopted edition of each of the following unless a specific edition is cited or the Contract Documents direct otherwise.
3.2 Where referenced documents conflict, the more stringent requirement shall govern unless the Engineer of Record directs otherwise in writing.
| Standard | Title |
|---|---|
| 40 CFR Part 122 | EPA Administered Permit Programs, the National Pollutant Discharge Elimination System (Section 122.41, conditions applicable to all permits) |
| 40 CFR Part 141 | National Primary Drinking Water Regulations |
| 40 CFR Part 403 | General Pretreatment Regulations for Existing and New Sources of Pollution |
| 29 CFR 1910.147 | The Control of Hazardous Energy (Lockout/Tagout) |
| AWWA C651 | Disinfecting Water Mains |
| AWWA C652 | Disinfection of Water-Storage Facilities |
| AWWA C653 | Disinfection of Water Treatment Plants |
| AIA A201 | General Conditions of the Contract for Construction |
| EJCDC C-700 | Standard General Conditions of the Construction Contract |
| ConsensusDocs 200 | Standard Agreement and General Conditions Between Owner and Constructor |
NOTE The discharge permit of a wastewater plant and the operating permit of a water plant are issued to the Owner, in most states by a state agency administering a delegated federal program under its own rules, and the permit conditions on bypass, upset, and reporting are the Owner's conditions. The Contractor holds none of them, which is why this standard places the notice on the Contractor and the reporting on the Owner, and why the permit, rather than any value in this standard, is the performance the plant has to keep. The general conditions in common use settle the Contractor's responsibility for the Owner's existing property and for its own operations, and this standard states the administrative detail they leave open. (3.3)
4 Submittals
4.1 Plan Submittals
4.1.1 The Contractor shall submit the following before any work that affects the operation of the plant and within the time the Maintenance of Plant Operations Plan section of this standard states:
- The maintenance of plant operations plan, with the content the Plan Content article requires
- The shutdown schedule, listing every shutdown the plan requires, keyed to the constraints table and to the construction schedule under Construction Progress DocumentationConstruction Progress DocumentationResolves to the current adopted revision.sync/construction-progress-documentation
- Drawings of each temporary facility the plan depends on, showing its location, its connections to the existing plant, its capacity, and its source of power
- The contingency measures for each shutdown, stating what the Contractor does if the shutdown overruns, if a temporary facility fails, or if the Owner postpones it
- Each update of the plan, marked to show the change from the accepted plan
Plan Submittals Requiredcheckbox
☑ Maintenance of plant operations plan
☑ Shutdown schedule
☑ Temporary facility drawings
☑ Contingency measures for each shutdown
☑ Marked plan updates
4.1.2 Plan submittals shall be transmitted and tracked through the submittal procedure of Submittal And Quality ProceduresSubmittal and Quality ProceduresResolves to the current adopted revision.sync/submittal-and-quality-procedures and shall be classified as action submittals.
4.1.3 The temporary pumping plan, where the plan depends on temporary pumping, shall be submitted under Temporary Bypass PumpingTemporary Bypass PumpingResolves to the current adopted revision.sync/temporary-bypass-pumping and shall be referenced in the maintenance of plant operations plan by its submittal number.
4.2 Shutdown and Tie-In Submittals
4.2.1 The Contractor shall submit the following for each shutdown and each tie-in, each at the time the Shutdown and Outage Requests and the Tie-Ins and Cutovers sections of this standard state for it:
- The written shutdown request, with the content the Request Content article requires
- The readiness checklist, signed by the Contractor's superintendent and the operations representative at the readiness check
- The minutes of the pre-tie-in meeting
- The record of the existing condition verified before the tie-in, including the result of each isolation valve test
- The return-to-service record, signed by the operations representative
- The entries the Contractor made in the operations log during the shutdown
Shutdown and Tie-In Submittals Requiredcheckbox
☑ Written shutdown request
☑ Signed readiness checklist
☑ Pre-tie-in meeting minutes
☑ Existing condition verification record
☑ Signed return-to-service record
☑ Operations log entries
4.2.2 Shutdown and tie-in submittals shall be classified as informational submittals, except the shutdown request, which shall be answered by the operations representative under the Owner's Review and Response article and not by the Engineer's submittal review.
NOTE The shutdown request is answered by the people who run the plant, on the plant's calendar, and routing it through the Engineer's submittal log adds a review cycle to a document the Engineer does not decide. The readiness checklist and the return-to-service record are signed on the day, by the two people who were there, and are filed afterward so that the record of what was isolated and what was restored exists when a question about it arrives. (4.2.3)
5 Operating Constraints
5.1 Facilities That Remain in Service
5.1.1 The processes, units, flow paths, utilities, and buildings of the plant that remain in service throughout the Work, and those that may be taken out of service and under what conditions, shall be as indicated on the maintenance of plant operations constraints table.
5.1.2 The Contractor shall maintain the operation of every facility the constraints table lists as remaining in service, at not less than the capacity or performance the table states, except during a shutdown approved under this standard.
5.1.3 The Contractor shall perform the Work in the order indicated on the sequence of construction drawings where the drawings state a sequence, and shall not take a facility out of service before the facility that replaces it, permanently or temporarily, is in service and accepted under this standard.
NOTE The constraints are written by the Engineer with the Owner's operations staff, before bid, because they are the Owner's knowledge of its own plant: which clarifier can be drained in winter, which pump the plant cannot lose on a wet day, which header has no isolation valve that holds. A constraint discovered after award is a change in the Work, and a constraint stated in the bid documents is a condition the Contractor priced. The table is the one place the Contractor, the Engineer, and the operators read the same list. (5.1.4)
5.1.5 Where the Contractor and the Owner disagree whether a facility is within a constraint the table states, the Engineer of Record shall make the initial determination, subject to the dispute resolution provisions of the Contract Documents.
5.2 Permits and Service Levels
5.2.1 The performance the plant maintains during the Work shall be governed by the permits and service levels indicated in the datasheet, and the limits, conditions, and reporting obligations of each shall be the performance basis for every shutdown, tie-in, and temporary facility under this standard.
Permits and Service Levels Governing Plant Performance During Constructioncheckbox
☐ NPDES or state discharge permit
☐ Drinking water operating permit or approval
☐ Industrial pretreatment permit or discharge authorization
☐ Air permit
☐ Biosolids or residuals management permit
☐ Owner-stated service level without a regulatory permit
5.2.2 The Owner shall furnish the Contractor, before the maintenance of plant operations plan is prepared, the permit limits, the sampling points, the monitoring frequencies, and the bypass, upset, and reporting conditions of each permit indicated in the datasheet that the Work can affect, and the service level of any facility that has no permit.
NOTE A permit is a performance the plant is measured against at a sampling point on a schedule, and the Contractor cannot plan a shutdown around a limit it has not seen. A wastewater plant is measured at its outfall under a discharge permit, a water plant at its entry point and in its distribution system under its operating approval, an industrial plant at its connection to the sewer under a pretreatment authorization, and a plant with a digester or a dryer at its stack under an air permit. A hospital, a data center, or a campus central plant has no regulator at the pipe and is held instead to the service level its Owner states, which is written into the constraints table in the same terms as a permit limit so that the Contractor plans against a number rather than a sentiment. (5.2.3)
5.2.4 The Contractor shall not rely on any provision of a permit that excuses an exceedance or a bypass, and the Owner alone shall decide whether to invoke such a provision.
5.3 Flows, Loads and Capacity During Construction
5.3.1 The flows, loads, and demands the plant shall carry during each shutdown, including the wet-weather flow, the peak-hour demand, and the firm capacity with the largest unit out of service, shall be as indicated on the constraints table for that shutdown.
5.3.2 Where a shutdown reduces the capacity of a process below the flow the constraints table states for the season in which the shutdown is scheduled, the Contractor shall provide temporary facilities under this standard, or temporary pumping under Temporary Bypass PumpingTemporary Bypass PumpingResolves to the current adopted revision.sync/temporary-bypass-pumping, that restore the stated capacity for the duration of the shutdown.
NOTE The flow a shutdown has to carry is the flow of the day it happens, not the annual average, and a plant that treats twice its average flow on a wet day loses a clarifier on that day with consequences it does not have on a dry one. The constraints table states the flow by season, and the Contractor schedules the shutdown against the season or provides the capacity to meet it. (5.3.3)
5.4 Plant Utilities
5.4.1 An interruption of the plant's electrical service, plant water, non-potable water, instrument air, chemical supply, fuel, communications, or control network that the Work requires is an outage under this standard and shall be requested, approved, and returned to service as this standard requires for a shutdown.
5.4.2 Where an outage of the plant's electrical service is also a planned outage under Common Work Results ElectricalCommon Work Results for ElectricalResolves to the current adopted revision.sync/common-work-results-electrical, the request under this standard shall satisfy the content and the log that standard requires, and the longer of the two notice periods shall govern.
NOTE A plant loses its process when it loses its utilities as surely as when it loses a basin, and the utilities are the interruptions the trades treat as routine: the electrician who opens a breaker to land a feeder opens the breaker that runs the blower. Treating every utility interruption as an outage under one procedure is what puts the blower in front of the operations representative before the breaker is opened. (5.4.3)
5.5 Constraints Table and Sequence Drawings
NOTE The constraints table and the sequence of construction drawings are the Owner's statement of what the Work has to live with, and the maintenance of plant operations plan is the Contractor's statement of how it will. The two are read together, and the Contractor's plan proposes the shutdowns, the temporary facilities, and the order of the Work within the table's limits, which is a different thing from the table proposing the Contractor's means. (5.5.1)
5.5.2 Where the sequence of construction drawings show a sequence, the Contractor may propose a different sequence in the maintenance of plant operations plan, and shall not perform the Work in the proposed sequence until the Engineer of Record has accepted it in writing with the concurrence of the operations representative.
5.5.3 A sequence proposed by the Contractor shall satisfy every constraint the table states, and acceptance of the proposed sequence shall not relieve the Contractor of any constraint.
6 Maintenance of Plant Operations Plan
6.1 Plan Content
6.1.1 The Contractor shall prepare a maintenance of plant operations plan that states, for each shutdown the Work requires, the facility shut down, the date and the hour it begins and ends, the work performed during it, the flows and loads the plant carries during it, the temporary facilities and the temporary pumping it depends on and their capacity, the crews and the equipment assigned to it, the contingency measures if it overruns or a temporary facility fails, and the sequence that restores the facility to service.
6.1.2 The plan shall include drawings of each temporary connection to the existing plant, showing the point of connection, the pipe, duct, conduit, or cable, the valves and the isolation, the supports, and the route, and shall identify every existing valve, gate, breaker, and switch the shutdown depends on.
6.1.3 The plan shall state, for each shutdown, the person on the Contractor's staff who directs it and the person on the Owner's operations staff whose concurrence the Contractor has obtained for the date and the duration.
6.1.4 The plan shall identify each shutdown during which new equipment is placed in service to maintain operations under the Placing New Facilities in Service section of this standard, and the acceptance under Common Work Results ProcessCommon Work Results for Process EquipmentResolves to the current adopted revision.sync/common-work-results-process that the equipment has to complete first.
NOTE A plan that lists the shutdowns and nothing else is a schedule. The plan is the contingency column: what the Contractor does at hour ten of an eight-hour shutdown, what it does when the temporary pump trips at two in the morning, and what it does when the valve that was supposed to hold does not. Those are the decisions that are made badly under pressure and well on paper, and the plan is where they are made. (6.1.5)
6.2 Submittal and Review
6.2.1 The Contractor shall submit the maintenance of plant operations plan not less than the number of days indicated in the datasheet before the first work that affects the operation of the plant, and shall not begin that work until the Engineer of Record has accepted the plan in writing with the concurrence of the operations representative.
Plan Submittal Before the First Work Affecting Operationsrange
Not less than
days
142130456090
NOTE Thirty days is the period under which the operators can read the plan, walk the plant against it, and return it with the shutdown dates adjusted to their own calendar, and it is what most projects use without discussion. A shorter period suits a small plant with a single shutdown and a short construction period, where a month of waiting is a month of the contract. A longer period suits a large plant with many shutdowns, where the plan is a document of some size and the operators review it between the other demands of running the plant. (6.2.2)
6.2.3 The Engineer of Record's acceptance of the plan shall be an acceptance that the plan satisfies the constraints table and this standard, and shall not relieve the Contractor of responsibility for the means, the methods, the adequacy of the temporary facilities, or the outcome of any shutdown.
6.2.4 Where the Engineer of Record or the operations representative returns the plan with comments, the Contractor shall revise and resubmit it within fourteen days after its return, and the period for the Owner's review of the resubmittal shall be the same as for the first submittal unless the operations representative agrees to a shorter one.
6.2.5 The Contractor shall not perform any shutdown, tie-in, or cutover that the accepted plan does not include until the plan has been updated to include it and the update has been accepted.
6.3 Plan Updates
6.3.1 The Contractor shall update the maintenance of plant operations plan whenever a shutdown is added, removed, or rescheduled by more than seven days, whenever a temporary facility the plan depends on changes, and whenever the construction schedule is revised under Construction Progress DocumentationConstruction Progress DocumentationResolves to the current adopted revision.sync/construction-progress-documentation in a way that moves a shutdown.
6.3.2 Each update shall be submitted as a complete plan marked to show every change from the last accepted version, and the Contractor shall not perform a changed shutdown until the update has been accepted.
6.3.3 An update shall not be required for a change in the date of a shutdown within the window the operations representative approved for it, provided the Contractor gives the notice the Shutdown and Outage Requests section requires for the new date.
NOTE A plan accepted in the first month and never touched is wrong by the sixth, because the schedule has moved and the shutdowns have moved with it, and the operators who concurred with the plan in March are surprised by the shutdown in September. Tying the update to the schedule revision keeps the two documents saying the same thing. (6.3.4)
7 Shutdown and Outage Requests
7.1 Request and Notice
7.1.1 The Contractor shall request each shutdown in writing from the operations representative not less than the number of days indicated in the datasheet before the shutdown begins, whether or not the shutdown appears in the accepted plan.
Written Shutdown Request Noticerange
Not less than
days
357101421304560
NOTE The notice period is set against what the Owner has to do before the plant can lose the facility. A small plant with one operator on shift needs a week to arrange the second person a shutdown requires. A large plant needs two or three weeks to fill a clearwell, draw down a digester, notify a downstream utility, or reschedule a sampling event, and a shutdown of a facility the regulator wants told about in advance needs whatever the permit says plus the Owner's own time to write the notice. A short period suits a plant that has decided every shutdown in the plan already and treats the request as confirmation; a long period suits a plant whose operators treat each request as a decision. (7.1.2)
7.1.3 The Contractor shall give the operations representative a second notice, confirming the date, the hour, and the duration, not less than one working day before the shutdown begins, and the shutdown shall not begin without it.
7.1.4 A request for a shutdown of a fire protection, emergency power, or life safety system of the plant shall additionally be given to the Authority Having Jurisdiction and to the Owner's insurer where either requires notice, and the interim measures they require shall be in place before the shutdown begins.
7.1.5 Where a shutdown affects a downstream utility, a wholesale customer, a receiving sewer, or a public water system other than the Owner's, the Owner shall give the notice that party requires, and the Contractor's request shall allow the time for it.
7.2 Request Content
7.2.1 Each shutdown request shall state the facility to be shut down, the valves, gates, breakers, and switches to be operated and by whom, the date and the hour the shutdown begins, the duration, the work to be performed, the flows and loads the plant carries during it and the temporary facilities that carry them, the crews and the equipment assigned, the standby provisions, the contingency measures, the sequence of return to service, and the names of the Contractor's person in charge and the operations staff member the Contractor has coordinated with.
7.2.2 Each request shall reference the shutdown's entry in the accepted plan, or shall state that the shutdown is not in the plan and shall be accompanied by the plan update that adds it.
7.2.3 Each request shall state whether the shutdown places new equipment in service to maintain operations and, where it does, shall attach the acceptance under Common Work Results ProcessCommon Work Results for Process EquipmentResolves to the current adopted revision.sync/common-work-results-process that permits it.
NOTE The request is the shutdown written down in enough detail that the operations representative can refuse it for a reason. A request that says the Contractor wants the east header on Tuesday tells the operator nothing about whether the plant can afford it; a request that says which three valves close, that the west header carries the flow, that a temporary pump of a stated capacity stands by, and that the header is back by four o'clock is a request the operator can approve or correct. (7.2.4)
7.3 Owner's Review and Response
7.3.1 The operations representative shall approve, approve with conditions, or refuse each shutdown request in writing within the number of days indicated in the datasheet after receiving it, and a request not answered within that period shall be deemed refused for the requested date.
Owner's Response to a Shutdown Requestrange
Not more than
days
12357101421
NOTE A response time is the Owner's commitment, and it is the one obligation in this standard that runs the other way. A short response suits a plant with a full-time operations representative who reads the request the day it arrives; a long response suits a small utility whose superintendent runs three plants and a distribution system. The response is deemed a refusal rather than an approval when it is missed, because a shutdown nobody approved is a shutdown nobody prepared the plant for, and the Contractor's remedy for a late response is the schedule and cost provision of Contract Modification ProceduresContract Modification ProceduresResolves to the current adopted revision.sync/contract-modification-procedures, not the shutdown itself. (7.3.2)
7.3.3 A refusal shall state the operating reason for it and the earliest date on which the operations representative expects the shutdown can be approved.
7.3.4 An approval with conditions shall state each condition, and the Contractor shall satisfy each condition before the readiness check or shall withdraw the request.
7.3.5 No shutdown shall begin until the operations representative has approved the request in writing and the readiness check has been completed under this standard.
7.4 Permitted Times and Seasons
7.4.1 Shutdowns shall be performed at the times of day indicated in the datasheet unless the operations representative approves a different time for a particular shutdown in writing.
Permitted Shutdown Hoursradio
○ During the plant's normal working hours
○ Outside the plant's normal working hours only
○ During the low-flow or low-demand hours the constraints table states
○ At the time the operations representative approves for each shutdown, with no standing rule
NOTE A shutdown during working hours is performed with the full operations staff on site and on straight time for the Contractor, and it suits a plant whose process tolerates the loss of the facility at daytime flow. A shutdown outside working hours puts the Contractor on overtime and the Owner on call-out pay, and it suits a facility whose daytime occupants or daytime flow cannot stand the interruption. A shutdown in the low-flow hours of a wastewater plant, which are the small hours of the morning, or the low-demand hours of a water plant, is the time the plant can best afford to lose capacity, and it is the time the fewest people are awake to deal with what goes wrong. No standing rule puts every shutdown before the operations representative on its own facts, which is the position of a plant with a continuous process that cannot generalize. (7.4.2)
7.4.3 Shutdowns of the processes the constraints table designates shall not be scheduled during the seasons indicated in the datasheet, with the dates of each season as indicated on the constraints table.
Seasonal Shutdown Restrictionscheckbox
☐ Wet-weather season for flow-dependent processes
☐ Peak-demand season for water production and storage
☐ Permit-defined seasonal limit period
☐ Freezing season for exposed temporary piping and outdoor process units
☐ Owner-designated event periods
7.4.4 Where a seasonal restriction is indicated, the operations representative may approve a shutdown within the restricted season for a particular facility in writing, and the approval shall state the conditions under which the shutdown proceeds.
NOTE The seasons are the ones that change what a shutdown costs the plant. A wastewater plant that loses a clarifier in the wet season loses it on the day the flow doubles. A water plant that loses a filter in August loses it on the day demand peaks. A plant with seasonal nutrient or disinfection limits is held to a tighter number for part of the year, and a shutdown that nudges the effluent in the loose season violates the permit in the tight one. Exposed temporary piping freezes, and an Owner's own event, a tourist season, a harvest, a semester, is a season to the facility it serves. Leaving a restriction unchecked permits shutdowns year-round for that reason, which is correct for a plant the reason does not touch. (7.4.5)
7.5 Duration and Overrun
7.5.1 The duration of each shutdown shall not exceed the longest shutdown the constraints table states for that facility, and the Contractor shall plan each shutdown with a margin for the work that takes longer than planned.
7.5.2 Where a shutdown cannot be completed within the approved duration, the Contractor shall notify the operations representative not later than the midpoint of the approved duration that an overrun is likely, shall restore the facility to service at the end of the approved duration by the contingency measures the plan states, and shall reschedule the remaining work under a new request, unless the operations representative extends the approval in writing at the time.
7.5.3 The Contractor shall bear the cost of restoring a facility at the end of an approved duration and of rescheduling the remaining work, including the cost of a second mobilization and of any temporary facility held in place for it, except where the overrun was caused by a condition the Owner is responsible for under the Verification of the Existing Condition article or by an act of the Owner.
NOTE The midpoint notice is what turns an overrun from a surprise into a decision. At the midpoint the operations representative still has half the duration to extend it, to start a standby pump, to call a second operator, or to insist on restoration, and after it the plant is at the mercy of a crew that is already late. A contingency that puts the old facility back costs the Contractor a lost shutdown; a contingency that leaves the plant without the facility past its tolerance costs the Owner its permit. (7.5.4)
7.5.5 A shutdown that the constraints table limits to a stated duration shall be planned so that the facility can be returned to service at any point within the duration, with the materials and the crews needed to close up on hand from the moment the shutdown begins.
7.6 Cancellation and Postponement
7.6.1 The operations representative may cancel or postpone an approved shutdown at any time before it begins, and may suspend one in progress, for an operating reason including a storm event, a high-flow or high-demand condition, a permit condition, an equipment failure elsewhere in the plant, a loss of utility service, or a regulatory inspection, and the Contractor shall restore the facility and stand down on the operations representative's instruction.
7.6.2 The operations representative shall state the operating reason for a cancellation, postponement, or suspension in writing within one working day after giving it, and shall offer the earliest date on which the shutdown can be rescheduled.
7.6.3 The cost of the Contractor's labor, equipment, temporary facilities, and standby provisions idled or demobilized by an Owner-ordered cancellation, postponement, or suspension shall be borne as indicated in the datasheet, and the adjustment of the Contract Sum and the Contract Times, where one is due, shall be made under Contract Modification ProceduresContract Modification ProceduresResolves to the current adopted revision.sync/contract-modification-procedures.
Cost of an Owner-Ordered Cancellation or Postponementradio
○ Borne by the Contractor as a condition of working in an operating plant
○ Borne by the Owner for a cancellation or postponement ordered after the readiness check, and by the Contractor before it
○ Borne by the Owner as a change in the Work
NOTE The allocation sets who carries the weather. Placing it on the Contractor prices every shutdown with a contingency for the one that is cancelled, and the plant can cancel freely; a Contractor that has been cancelled three times for the same header will price the fourth bid on that plant accordingly. Placing it on the Owner after the readiness check recognizes that the readiness check is the moment the Contractor has staged its crews and its equipment at the Owner's request, and before it the Contractor has committed little that the postponement wastes. Placing it on the Owner as a change makes every cancellation a cost event, which an Owner with a reliable plant and a dry climate can afford and an Owner on a river that floods cannot. A cancellation caused by the Contractor's own failure to be ready is the Contractor's under every option. (7.6.4)
7.6.5 A cancellation, postponement, or suspension ordered because the Contractor failed a condition of the approval or the readiness check shall be at the Contractor's cost under every allocation indicated in the datasheet.
7.6.6 A suspension of a shutdown in progress shall be followed by the restoration the contingency measures of the plan state, and the Contractor shall not resume the shutdown without the operations representative's written instruction.
7.7 Readiness Check
7.7.1 The Contractor and the operations representative shall jointly perform a readiness check not less than the number of hours indicated in the datasheet before each shutdown begins, and the Contractor shall not begin the shutdown until the readiness checklist has been signed by both.
Readiness Check Before a Shutdownrange
Not less than
hours
48244872120168
NOTE A check a few hours before a short shutdown confirms that the crew and the fittings that were there yesterday are still there, and it suits a tie-in that takes a morning. A check a day or two before a long shutdown leaves time to get the missing coupling, to re-test the valve that did not hold, and to cancel before the plant has drawn down a tank for nothing, and it suits a shutdown the plant has spent a week preparing for. A week suits a shutdown that depends on a temporary facility whose test run has to be witnessed before the plant will rely on it. (7.7.2)
7.7.3 The readiness check shall confirm that every material, fitting, valve, gasket, bolt, and spool the shutdown requires is on site, inspected, and staged at the point of use; that every assembly that can be prefabricated has been; that the crews, the supervision, and the relief crews the plan assigns are confirmed for the date; that each temporary facility and each temporary pumping system has completed its test run and is in service or ready to start; that the standby provisions are on site; that every existing valve, gate, breaker, and switch the shutdown depends on has been located, identified, and verified under the Tie-Ins and Cutovers section; and that the operations staff who operate during the shutdown have been briefed.
7.7.4 A shutdown that fails any item of the readiness check shall not begin, and the Contractor shall correct the item and request a new readiness check, or shall withdraw the request and reschedule.
7.8 Unplanned Shutdowns
7.8.1 A shutdown of a facility the constraints table lists as remaining in service that occurs without an approved request, whether caused by the Contractor's work, by a failure of a temporary facility, or by damage to the existing plant, is a compliance threat under this standard, and the Contractor shall give the notice the Compliance During Construction section requires and shall restore the facility, or provide a temporary facility that maintains its service, at once and at its own cost.
7.8.2 Where the Contractor's work damages an existing pipe, conduit, cable, structure, or item of equipment of the plant, the Contractor shall repair it, or replace it where the operations representative determines it cannot be repaired to its condition before the damage, at no cost to the Owner, and shall maintain the service it carried by temporary means until the repair is complete.
NOTE An unplanned shutdown is the one the plant did not prepare for, and it is the one that produces the exceedance. The obligations after it are the same as after a planned one, with the request replaced by the notice and the readiness check replaced by whatever can be done in the time there is, and the Contractor who caused it restores the service before it argues about the cause. (7.8.4)
8 Tie-Ins and Cutovers
8.1 Pre-Tie-In Meeting
8.1.1 The Contractor shall convene a pre-tie-in meeting for each tie-in and each cutover not less than the number of days indicated in the datasheet before it, attended by the Contractor's superintendent and the foreman who directs the work, each subcontractor whose work the tie-in involves, the operations representative and the operators who are on shift for it, the Engineer of Record's representative, and, where new equipment or a control function enters service, the manufacturer's representative and the control system integrator.
Pre-Tie-In Meeting Lead Timerange
Not less than
days
2357101421
8.1.2 The meeting shall walk the tie-in step by step in the order it will be performed, shall identify every valve, gate, breaker, and switch to be operated and the person who operates it, shall confirm the isolation and the lockout sequence, shall confirm the flows and loads during the tie-in and the temporary facilities that carry them, shall review the contingency measures and the point at which each is invoked, shall review the return-to-service sequence and the person who authorizes it, and shall review the compliance threats the tie-in presents and the notice each requires.
8.1.3 The Contractor shall record the meeting in minutes that list each step, the person responsible for it, and each decision made, and shall distribute the minutes to every attendee within two working days after the meeting and before the readiness check.
8.1.4 Several tie-ins may be covered in one meeting where they are performed within one shutdown or within one week, provided each is walked separately.
NOTE The meeting is where the operator says the valve on the drawing was abandoned in place in 1994 and the one that actually isolates the header is in a vault across the road. It is the cheapest hour on the project. A short lead suits a routine tie-in on a plant the crew has worked in for months; a long lead suits the first tie-in, a tie-in that places new equipment in service, or one that needs a part ordered after the walk. (8.1.5)
8.2 Verification of the Existing Condition
8.2.1 Before each tie-in, and before the shutdown request for it is submitted, the Contractor shall expose and verify the existing pipe, channel, structure, conduit, or circuit at the point of connection, including its location, its elevation, its outside diameter or dimensions, its material, its wall thickness or condition where the connection method depends on it, its joint type, its coating and lining, and the clearance available for the connection.
8.2.2 The Contractor shall exercise and test, in the presence of the operations representative, each existing isolation valve and gate the tie-in depends on, by closing it under the operations representative's direction and confirming that it holds against the pressure or the level it will see during the shutdown, and shall record the result of each test in the existing condition verification record.
8.2.3 Where an existing isolation valve or gate does not hold, or cannot be operated, the Contractor shall notify the operations representative and the Engineer of Record in writing within one working day after the test, before the shutdown request is submitted, and the tie-in shall not proceed until the means of isolating around the valve has been agreed in writing.
8.2.4 The cost of the means of isolating around an existing isolation valve or gate that does not hold, including a line stop, an inflatable or mechanical plug, a freeze plug, a temporary bulkhead, or the replacement of the valve, shall be borne as indicated in the datasheet.
Cost of Isolating Around an Existing Valve That Does Not Holdradio
○ Borne by the Owner, where the Contractor tested the valve and reported the result before the shutdown request
○ Borne by the Contractor as a risk of working in the existing plant
NOTE An existing valve that does not hold is the condition that turns an eight-hour tie-in into a thirty-hour one, with the plant on a temporary pump the whole time, and it is the single most common cause of a shutdown overrun. The test before the request finds it while there is time to plan around it. Placing the cost on the Owner where the valve was tested and reported treats the valve as what it is, a part of the Owner's plant in a condition the bid documents did not disclose, and it is the allocation under which the Contractor has every reason to test early and report honestly. Placing the cost on the Contractor prices a line stop into every tie-in on the project whether or not one is needed, and it suits an Owner that knows its valves are in poor condition and would rather pay for the risk in the bid than in change orders. Under either allocation, a valve the Contractor did not test before the shutdown is the Contractor's problem when it does not hold. (8.2.5)
8.2.6 Where the Contractor failed to test an existing isolation valve before the shutdown and the valve does not hold during it, the cost of isolating around it and of the overrun shall be borne by the Contractor under every allocation indicated in the datasheet.
8.2.7 A condition at the point of connection that differs from the Contract Documents, other than an isolation valve that does not hold, shall be reported as a differing site condition under Contract Modification ProceduresContract Modification ProceduresResolves to the current adopted revision.sync/contract-modification-procedures, and the Contractor shall not proceed with the connection until the Engineer of Record has directed how.
8.2.8 The existing condition verification record shall be signed by the Contractor's superintendent and the operations representative and shall be submitted before the shutdown request for the tie-in.
8.3 Hot Taps and Line Stops
8.3.1 A connection to an existing pipe under pressure or in service by hot tap, and an isolation of an existing pipe by line stop or by an inserted plug, shall be performed by a firm that has performed that operation on pipe of the same material and pressure class on not fewer than five previous projects, named in the maintenance of plant operations plan with its project record.
8.3.2 The tapping sleeve, saddle, or line stop fitting shall be installed and pressure tested against the existing pipe, at the test pressure the governing piping standard states for the pipe, before the pipe wall is cut, in the presence of the operations representative, and the coupon or the plug shall be recovered and shown to the operations representative before the connection is placed in service.
8.3.3 A hot tap or a line stop on an existing pipe is a shutdown under this standard for the purpose of the request, the readiness check, and the return to service, whether or not the pipe is taken out of service for it.
NOTE The hot tap exists so that the plant does not lose the header, and the line stop exists so that a valve that does not hold does not stop the project, and both put a cutting tool through the wall of a pipe the plant is depending on. The fitting tested before the cut, and the coupon in hand afterward, are the two checks that keep a connection without a shutdown from becoming a shutdown without a plan. (8.3.4)
8.4 Operation of Existing Valves and Equipment
8.4.1 The operation of existing valves, gates, breakers, switches, pumps, and other equipment of the plant during shutdowns, tie-ins, and cutovers shall be as indicated in the datasheet.
Operation of Existing Valves and Equipmentradio
○ The Owner's operations staff operate every existing valve, gate, breaker, switch, and item of equipment, on the Contractor's request and in the Contractor's presence
○ The Contractor operates existing isolation valves and gates the operations representative has released to it in writing for the shutdown, and the Owner's operations staff operate every breaker, switch, pump, and item of process equipment
○ The Contractor operates every existing valve, gate, breaker, switch, and item of equipment under the operations representative's written authorization for each shutdown
NOTE The operators know the plant, know which valve sticks a quarter turn from closed and which breaker trips the wrong bus, and they hold the Owner's permit, so an operation they perform is an operation the Owner has decided to make. The Contractor's crew is on site at two in the morning when the operator is at home, and a shutdown that waits for a call-out for every valve is a long shutdown. Having the operators operate everything is the position of a plant whose operators are on site around the clock and whose Owner wants every operation of its plant made by its own staff, and it costs the Contractor the time spent waiting for them. Releasing the isolation valves to the Contractor and keeping the equipment with the operators splits the plant along the line most Owners draw: a valve on a header the Contractor is about to cut is the Contractor's problem either way, while a pump, a breaker, or a chemical feed is the process, and the process is the Owner's. Having the Contractor operate everything under written authorization suits a small plant or a pump station with no operator on site, and it puts the Contractor behind every operation it makes. (8.4.2)
8.4.3 Where the Contractor operates an existing valve, gate, breaker, or switch, the Contractor shall operate it only as the written authorization or release for that shutdown identifies it, only in the sequence the pre-tie-in meeting minutes state, and only with the operations representative notified before and after each operation.
8.4.4 The Contractor shall be responsible for damage to the plant and for any compliance threat caused by its operation of an existing valve, gate, breaker, switch, or item of equipment, including an operation it was not authorized to make.
8.4.5 The Owner shall be responsible for the consequence of an operation its operations staff perform at the Contractor's request where the Contractor's request correctly identified the device and the operation, and the Contractor shall be responsible where it did not.
8.4.6 Under no allocation shall the Contractor operate an existing chemical feed system, a disinfection system, a process control setpoint, or a SCADA command, each of which shall be operated by the Owner's operations staff only.
8.5 Isolation, Lockout and Tagout
8.5.1 Each existing item of equipment and each existing energy source on which or near which the Contractor works shall be isolated and locked out under the Owner's control of hazardous energy program by the Owner's authorized employee, and the Contractor's personnel shall apply their own locks and tags to the isolation before working on it and shall remove them only when their own work is complete.
8.5.2 The Contractor shall furnish its own lockout and tagout program for the temporary facilities, the temporary pumping, and the new work it controls, shall coordinate it with the Owner's program before the first shutdown, and shall inform the operations representative of each isolation it applies to the Owner's plant.
8.5.3 The Owner and the Contractor shall each inform the other of the restrictions and the procedures of its own program before the first shutdown, as 29 CFR 1910.147 requires of a host employer and an outside employer, and the record of that exchange shall be kept in the project file.
NOTE A valve closed and tagged by an operator and a breaker locked by an electrician are the two halves of one isolation, and a cutover in which the operator removed the tag because the Contractor's crew had gone to lunch is the one that fills the excavation. Two programs with two sets of locks on one isolation point, each removed only by the one who applied it, is the arrangement the regulation contemplates and the one that keeps the plant and the crew apart until both are ready. (8.5.4)
8.5.5 No isolation of the Owner's plant shall be removed, and no facility returned to service, until every Contractor lock and tag on it has been removed by the person who applied it or under the Contractor's documented procedure for a lock whose owner is absent, and the operations representative has confirmed the removal.
8.6 Cutover Sequence and Temporary Control
8.6.1 Each cutover shall be performed in the sequence the pre-tie-in meeting minutes state, and a departure from the sequence shall be agreed by the Contractor's person in charge and the operations representative at the time and recorded in the operations log.
8.6.2 Where a cutover transfers a control function, an interlock, an alarm, or an instrument signal from the existing control system to a new or temporary one, the Contractor shall provide, through the control system integrator under Control Systems IntegrationControl Systems Integration and TestingResolves to the current adopted revision.sync/control-systems-integration, a temporary means of monitoring and controlling the affected process that the Owner's operations staff can operate from the control room or from a location the operations representative accepts, for the duration of the cutover.
8.6.3 The temporary control arrangement for each cutover shall be demonstrated to the operations staff before the cutover begins, and the operations representative shall confirm in writing that the staff can operate the process through it.
8.6.4 The Contractor shall not disconnect an existing instrument, interlock, or alarm that the constraints table lists as remaining in service until the temporary or permanent replacement for it has been demonstrated to the operations representative and accepted.
NOTE The transfer of a plant from one control platform to another, and the acceptance tests of the new platform, are the integrator's scope and are specified where that scope lives. What this standard adds is the operator's seat during the hours in between: a plant whose flow meter is being re-terminated is a plant whose operator cannot see the flow, and the temporary indication, a local readout, a portable logger, or a temporary point on the old system, is what lets the operator run the plant blind in one place rather than everywhere. (8.6.5)
8.6.6 Where a cutover places a new facility in service, the cutover shall additionally comply with the Placing New Facilities in Service section of this standard.
8.7 Return to Service
8.7.1 Before a facility is returned to service after a shutdown, the Contractor shall complete the connection, shall remove every temporary blind, plug, bulkhead, jumper, and test connection, shall restore every support, shall inspect the connection for leakage under the operating pressure or level in the presence of the operations representative, and shall remove its locks and tags under the Isolation, Lockout and Tagout article.
8.7.2 A potable water facility returned to service after a tie-in shall first be flushed, disinfected, and sampled as AWWA C651, C652, or C653 requires for the facility, and shall not be returned to service until the samples meet the bacteriological requirements of the Owner's operating permit, unless the Owner's permit or the state regulator permits a different procedure for the connection.
8.7.3 The Contractor shall return each facility to service in the sequence the plan states, filling, venting, and pressurizing at the rate the operations representative directs, and shall not open an isolation to the operating plant until the operations representative has authorized it.
8.7.4 The return to service shall be confirmed by the operations representative on the return-to-service record, which shall state the time the facility was restored, the operations performed, any condition observed, and any temporary arrangement that remains in place.
8.7.5 The Contractor shall remain on site with the crew and the equipment that performed the tie-in until the operations representative has confirmed the return to service and the facility has operated under the plant's normal conditions for the period the operations representative states at the pre-tie-in meeting, and shall correct, at no cost to the Owner, any leak or defect in the connection found during that period.
NOTE A tie-in is not finished when the last bolt is tight. It is finished when the header has been filled slowly enough not to hammer the old pipe, the air is out, the pressure is on, the joint has been looked at under pressure, and the operator has signed the record. The crew that leaves at the bolt is the crew that is called back at midnight for a weeping flange, by which time the shutdown that could have covered the repair is over. (8.7.6)
9 Temporary Facilities That Maintain Operations
9.1 Requirement and Performance Basis
9.1.1 Where a shutdown, a tie-in, or the sequence of the Work removes from service a facility the constraints table lists as remaining in service, or reduces a process below the capacity the table states, the Contractor shall provide a temporary facility that maintains the service for the duration.
9.1.2 Each temporary facility shall carry the flows, loads, and demands the constraints table states for the season of the shutdown, shall meet the permit limits and the service level that govern the facility it replaces, and shall be in service and demonstrated to the operations representative before the facility it replaces is taken out of service.
9.1.3 The temporary pumping system that carries a flow around the Work shall be provided under Temporary Bypass PumpingTemporary Bypass PumpingResolves to the current adopted revision.sync/temporary-bypass-pumping, and temporary power, water, heat, and the other temporary facilities of the site shall be provided under Temporary Facilities And ControlsTemporary Facilities and ControlsResolves to the current adopted revision.sync/temporary-facilities-and-controls.
9.1.4 Temporary piping, channels, chemical feed, disinfection, aeration, instrumentation, and other temporary process facilities that are not temporary pumping and are not site facilities shall be provided under this standard, in materials suited to the fluid and the pressure they carry, with isolation at each connection to the existing plant, and with the monitoring the Owner's permit requires at the point the temporary facility affects.
9.1.5 A temporary chemical feed or disinfection facility shall be operated by the Owner's operations staff, with the Contractor furnishing, installing, maintaining, and removing it, unless the operations representative agrees in writing to a different arrangement for a particular shutdown.
NOTE The temporary facility is the plant for as long as the shutdown lasts, and it is held to the permit for that long. A temporary chlorine feed that cannot hold a residual, a temporary pump that cannot pass the wet-weather flow, and a temporary channel that short-circuits a basin each fail the permit as surely as the facility they replaced would have, and the demonstration before the shutdown is the proof that they will not. (9.1.6)
9.2 Standby Provisions
9.2.1 The Contractor shall have on site, from the readiness check until the return to service of each shutdown, the standby provisions indicated in the datasheet in addition to the standby temporary pumping Temporary Bypass PumpingTemporary Bypass PumpingResolves to the current adopted revision.sync/temporary-bypass-pumping requires.
Standby Provisions During a Shutdowncheckbox
☐ Standby power source for each temporary facility that depends on electrical power
☐ Spare pipe, fittings, couplings, gaskets, and bolts for each tie-in connection
☐ Relief crew where the shutdown exceeds one shift
☐ Manufacturer's representative on site where new equipment enters service
☐ Standby means of isolation for each existing valve the shutdown depends on
NOTE Standby provisions are the things that keep a problem during a shutdown from becoming an overrun. A spare set of fittings and gaskets costs a few hundred dollars and saves the shutdown when a flange face turns out to be the wrong drilling. A standby power source matters where the temporary facility is on a generator and the generator is the single point of failure. A relief crew is what keeps a thirty-hour tie-in from being finished by people who have been awake for all of it. A standby means of isolation, a line stop machine or an inflatable plug staged at the excavation, is the fallback for a valve that held during the test and does not hold on the day. Each is left unchecked where the shutdown does not present the risk it answers. (9.2.2)
9.3 Removal
9.3.1 The Contractor shall remove each temporary facility after the permanent facility it covered has been returned to service and accepted, shall restore the point of connection to the existing plant to its condition before the temporary connection, and shall not leave a temporary connection, a blind flange on an open tee, or a capped stub on the existing plant without the operations representative's written acceptance of it as a permanent condition.
9.3.2 A temporary facility that is to remain in service after substantial completion of the Work, at the Owner's request, shall be transferred to the Owner under a written record stating its condition, its remaining rental or ownership terms, and the date the Contractor's responsibility for it ends.
10 Placing New Facilities in Service
10.1 Authorization
10.1.1 No new or modified process unit, pipe, channel, structure, equipment, electrical facility, or control function shall be connected to the operating plant, or placed in service in it, until the operations representative has authorized it in writing for the date and the facility, whether the new facility is placed in service permanently or to maintain operations during a shutdown.
10.1.2 Before requesting the operations representative's authorization, the Contractor shall have completed for the new facility the testing, cleaning, disinfection, and acceptance the governing technical standard requires before service, and, for process equipment, the installation inspection, certificate of proper installation, and startup that Common Work Results ProcessCommon Work Results for Process EquipmentResolves to the current adopted revision.sync/common-work-results-process requires before early use.
NOTE The decision whether permanent process equipment may be operated before substantial completion to maintain plant operations is made in Common Work Results ProcessCommon Work Results for Process EquipmentResolves to the current adopted revision.sync/common-work-results-process, and the warranty, the run log, and the restoration that early use carries are stated there. This standard adds the procedure that the operating plant imposes on the day the new equipment is connected to it: the operations representative's authorization, because the new pump will be pumping the Owner's water under the Owner's permit, and the record of when it began. (10.1.3)
10.1.4 The Contractor's request for authorization shall identify the facility, the acceptance it has completed, the date and the hour it is to be placed in service, the connection to the existing plant that places it there, the person who starts it, the operating mode it starts in, and the monitoring the operations staff perform while it runs.
10.2 Record and Operation
10.2.1 The operations representative's authorization and the time the new facility was placed in service shall be recorded in the operations log and on the return-to-service record for the shutdown that placed it in service, and the record shall state whether the facility is in service permanently or to maintain operations.
10.2.2 A new facility placed in service to maintain operations shall be operated by the Owner's operations staff, under the manufacturer's instructions and the control narrative the control system integrator has demonstrated, with the Contractor maintaining it under Common Work Results ProcessCommon Work Results for Process EquipmentResolves to the current adopted revision.sync/common-work-results-process until substantial completion of the system it belongs to.
10.2.3 Placing a new facility in service under this standard shall not constitute substantial completion of that facility, acceptance of Work that does not conform to the Contract Documents, or the start of any warranty, each of which is governed by Closeout ProceduresCloseout ProceduresResolves to the current adopted revision.sync/closeout-procedures and Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds.
11 Compliance During Construction
11.1 Notice of a Compliance Threat
11.1.1 The Contractor shall notify the operations representative immediately, by the fastest means available and in person or by telephone rather than by message alone, on discovering any compliance threat arising from the Work, including a leak, a spill, a loss of a temporary facility, a failure of a temporary pump, an unplanned shutdown, an overrun that approaches the tolerance the constraints table states, and any condition that could cause a bypass, an overflow, or an exceedance.
11.1.2 The Contractor shall follow the immediate notice with a written notice within the number of hours indicated in the datasheet after the discovery, stating the condition, the time it was discovered, its cause so far as known, the facilities affected, the action the Contractor has taken, and the action it proposes.
Written Notice of a Compliance Threat After Discoveryrange
Not more than
hours
1248122448
NOTE The spoken notice is what lets the operator act, and the written notice is what lets the Owner report. A discharge permit requires the permittee to report a bypass or an upset that endangers health or the environment within twenty-four hours of learning of it and in writing within five days, and the Owner cannot write that report without the Contractor's account of what happened, which is why twenty-four hours is the written notice most projects set. A shorter period suits a facility whose own reporting clock is shorter or whose Owner wants the written account the same shift; a longer period gives the Contractor time to find the cause before writing it down, at the cost of the Owner writing its report from the telephone call. (11.1.3)
11.1.4 Discovery by a subcontractor or a lower tier shall be discovery by the Contractor for the purpose of the notice, and the Contractor shall require each of them to report to it on discovery.
11.1.5 The Contractor shall take, at once and without waiting for direction, the action the plan's contingency measures state for the condition, and shall take any further action the operations representative directs to protect the plant, the public, and the receiving water.
11.2 Monitoring During a Shutdown
11.2.1 The Owner's compliance sampling and monitoring shall continue throughout every shutdown, and the Contractor shall maintain the operations staff's access to every sampling point, flow meter, and analyzer the Owner's permit requires, or shall provide, with the operations representative's written acceptance, a temporary sampling point or measurement that the Owner has confirmed its permit allows.
11.2.2 Where a temporary facility changes the flow path so that a permit sampling point no longer represents the discharge or the finished water, the Contractor shall identify the change in the shutdown request, and the Owner shall decide, before approving the request, how the permit monitoring is kept during the shutdown.
11.2.3 The Contractor shall notify the operations representative before any work that could affect a flow meter, an analyzer, or a sampler the Owner uses for permit reporting, including work that interrupts its power, its sample line, or its signal, and shall not proceed until the operations representative has arranged the alternate measurement the permit requires.
NOTE A permit is enforced at a sampling point, and a plant that stops sampling because the Contractor's temporary piping bypassed the sampler has a reporting violation whether or not the effluent was clean. The sampler, the flow meter, and the analyzer are the instruments the regulator reads, and they are the ones a crew notices least. (11.2.4)
11.3 Responsibility for Exceedances
11.3.1 The Contractor's responsibility for a permit exceedance, a bypass, an overflow, a drinking water standard violation, or a failure to meet a service level during the Work shall be as indicated in the datasheet.
Contractor's Responsibility for Exceedances During Constructionradio
○ For an exceedance caused by the Contractor's work or by its failure to follow the accepted plan
○ For an exceedance caused by the Contractor's failure to follow the accepted plan, with an exceedance that occurs while the Contractor followed the plan borne by the Owner
○ For every exceedance that occurs during a Contractor-requested shutdown, however caused
NOTE The three allocations draw the line in different places between the Contractor's conduct and the plant's behavior. Holding the Contractor to exceedances its work caused, whether or not it followed the plan, puts on the Contractor the consequence of its own acts and leaves with the Owner the exceedance that would have happened anyway, and it suits a project where the plant's baseline compliance is sound and the cause of an exceedance can be found. Holding the Contractor only to its departures from the plan treats the accepted plan as the Owner's acceptance of the risk inside it, and it suits a project where the Owner and the Engineer wrote the constraints with care and the Contractor is being asked to execute rather than to judge; it leaves the Owner with the exceedance caused by work performed exactly as planned. Holding the Contractor to everything that happens during its shutdown is the simplest to administer and the most expensive to bid, since it prices the plant's own fragility into every shutdown, and it suits an Owner on a plant with a thin margin and a regulator with a long memory. Under each allocation the fine, the remediation, and the cost of the Owner's response are what the Contractor bears, and the Owner's compliance history is what it does not. (11.3.2)
11.3.3 Where the Contractor is responsible for an exceedance under the allocation indicated in the datasheet, the Contractor shall bear the civil penalty, the stipulated penalty, the remediation, the cleanup, the sampling and monitoring the regulator requires in response, the cost of the Owner's operations staff and consultants in responding, and the cost of public notification the regulator requires, and the Owner may recover them by deducting them from sums due the Contractor or by claim.
11.3.4 Where the Contractor and the Owner disagree whether an exceedance was caused by the Contractor's work or by its departure from the plan, the Engineer of Record shall make the initial determination from the operations log, the plant's monitoring record, and the Contractor's notice, subject to the dispute resolution provisions of the Contract Documents.
11.3.5 Responsibility for a spill or a discharge from a temporary pumping system shall additionally be as Temporary Bypass PumpingTemporary Bypass PumpingResolves to the current adopted revision.sync/temporary-bypass-pumping states, and where the two standards differ the more stringent requirement shall govern.
11.3.6 The Contractor's responsibility under this article shall be in addition to its responsibility for damage to the Owner's property and to third parties under the Agreement and the General Conditions, and nothing in this article shall limit the insurance the Contractor carries.
11.4 Reporting to the Regulator
11.4.1 Every report, notice, and notification to a regulator, a health department, a downstream utility, or the public concerning the plant's compliance shall be made by the Owner, as the permittee, and the Contractor shall not communicate with a regulator concerning the plant's compliance except at the Owner's written request or as the law requires of the Contractor directly.
11.4.2 The Contractor shall furnish the Owner, within the time the Owner's permit allows for the report and in any case within the written notice period indicated in the datasheet, every fact the Owner needs for the report, including the time, the duration, the volume, the cause, and the corrective action, and shall furnish any further information the Owner requests for the report within one working day after the request.
11.4.3 The Contractor shall cooperate with any inspection, sampling, or inquiry the regulator makes concerning a condition arising from the Work, and shall give the operations representative notice at once of any contact from a regulator concerning the plant.
NOTE The permit is the Owner's, the reporting duty is the Owner's, and the regulator's relationship is with the Owner, which has to answer to the same inspector after the Contractor has gone. A Contractor who calls the regulator directly, however well meant, reports a plant it does not run under a permit it has not read. What the Contractor owes is the facts, fast and complete, and the Owner's report is only as good as they are. (11.4.4)
11.4.5 The Contractor's own obligations under the law for a spill or a release from its own operations, equipment, or materials, including the notifications that law requires of the party responsible for the release, are not reduced by this article, and the Contractor shall give the operations representative a copy of any such notification at the time it is made.
12 Coordination with the Owner's Operations Staff
12.1 Points of Contact
12.1.1 The Owner shall designate the operations representative and an alternate in writing at or before the preconstruction conference under Project Management And CoordinationProject Management and CoordinationResolves to the current adopted revision.sync/project-management-and-coordination, with the telephone numbers at which each can be reached at any hour, and shall notify the Contractor in writing of any change within one working day.
12.1.2 The Contractor shall designate in writing, at the same time, the person who directs each shutdown and an alternate, with the telephone numbers at which each can be reached at any hour, and shall ensure that one of them is on site throughout every shutdown.
12.1.3 The Contractor shall attend the plant's operations meeting, or a coordination meeting with the operations staff, at the interval the operations representative sets and not less often than monthly while any work that affects the operation of the plant is in progress, and shall present at each meeting the shutdowns scheduled for the following period.
NOTE The person on the Contractor's side who directs the shutdown and the person on the Owner's side who can authorize an operation are the two people a shutdown cannot run without, and a shutdown in which either is reached through a voicemail is a shutdown that stops while someone drives in. The names and the numbers are exchanged before the first shutdown, for every hour of the day, because the shutdown is at two in the morning. (12.1.4)
12.2 Operations Log
12.2.1 The Contractor shall record in the plant's operations log, or in a shutdown log the operations representative designates and keeps with it, the time of each notice it gives, each operation of an existing valve, gate, breaker, or switch it makes or requests, the start and the end of each shutdown, each temporary facility placed in and removed from service, each departure from the planned sequence, each compliance threat and the action taken, and the time of each return to service.
12.2.2 Each entry shall be made at the time of the event by the Contractor's person in charge, shall be initialed by the operator on shift, and shall be copied to the Contractor's submittal under the Shutdown and Tie-In Submittals article within two working days after the shutdown.
NOTE The operations log is the plant's own record, kept by the shift, and it is the document a regulator reads first after an exceedance and a lawyer reads first after a claim. An entry written at the time, in the plant's log, by the person who did the thing, is evidence; a reconstruction a week later is a story. (12.2.3)
12.3 Control Room and SCADA Access
12.3.1 The Contractor's personnel shall not enter the control room, an operator workstation area, an electrical room containing the plant's operating switchgear, or a chemical feed area except with the operations representative's permission for a stated purpose and accompanied as the operations representative directs.
12.3.2 The Contractor's personnel shall not operate a SCADA workstation, change a setpoint, acknowledge an alarm, or issue a command through the plant's control system, and every such action during a cutover shall be performed by the Owner's operations staff at the Contractor's request.
12.3.3 During a cutover the control system integrator shall have the access to the control system that Control Systems IntegrationControl Systems Integration and TestingResolves to the current adopted revision.sync/control-systems-integration grants for the configuration work, under the operations representative's supervision, and the integrator's configuration access shall not extend to operating the plant.
12.3.4 The Contractor shall coordinate with the operations representative, before each cutover, the alarms the cutover will raise, the points that will read falsely or not at all while the cutover is in progress, and the time each will be restored, so that the operations staff can distinguish a cutover condition from a plant condition.
NOTE An operator who sees forty alarms at once because a cutover re-terminated a marshalling cabinet cannot see the one alarm that is real. The list of what will alarm and when it will stop is what lets the operator run the plant through the noise, and it is a coordination item, not a configuration one, which is why it is here rather than in the integration standard. (12.3.5)
12.4 Training on Temporary Arrangements
12.4.1 Before each temporary facility is relied on, and before each cutover that changes how the operations staff monitor or control a process, the Contractor shall brief the operators on every shift who will operate during the arrangement on its operation, its alarms, its limits, its failure modes, the contingency measures, and the person to call, and shall leave at the operator's station a one-page written description of the arrangement with the names and the numbers.
12.4.2 Where a temporary arrangement remains in place for longer than one week, the Contractor shall repeat the briefing for any operator who did not attend it before that operator's first shift under the arrangement, on the operations representative's notice of the operator's name.
12.4.3 The training this article requires is a briefing on a temporary arrangement and is distinct from the training on the permanent systems that Common Work Results ProcessCommon Work Results for Process EquipmentResolves to the current adopted revision.sync/common-work-results-process, Closeout ProceduresCloseout ProceduresResolves to the current adopted revision.sync/closeout-procedures, and the technical standards require before substantial completion.
NOTE The temporary pump has a different float switch, the temporary chlorine feed has a different pump stroke, and the temporary channel has a gate the plant never had, and the operator on the night shift who was off the day it was installed is the one who meets it alone. A page at the station, with a number on it, is the difference between a call and a bypass. (12.4.4)
13 Coordination with the Agreement and Other Standards
13.1 The Contractor shall reconcile the maintenance of operations requirements of the Agreement, the General Conditions, the Supplementary Conditions, the constraints table, the sequence of construction drawings, and each technical standard with this standard, and shall report in writing, before the maintenance of plant operations plan is submitted, any conflict between them.
13.2 Where a technical standard and this standard address the same shutdown, tie-in, or operation of existing equipment, the more stringent requirement shall govern unless the Contract Documents direct otherwise.
13.3 The Contractor shall include in each subcontract and purchase order whose scope involves a shutdown, a tie-in, a cutover, a temporary facility, or work on or near the operating plant the request, notice, readiness check, operation of existing equipment, lockout, return to service, and compliance notice requirements of this standard that apply to that scope.
NOTE A subcontractor whose subcontract carried only the piping section learns that the header cannot be cut on a Tuesday from the operator standing in front of it, which is the wrong moment. The constraints and the procedures reach the trade that performs the tie-in only if the Contractor puts them in the subcontract. (13.4)
This standard is written and maintained by SynC and licensed under Creative Commons Attribution 4.0. You may share and adapt it, including commercially, provided you credit SynC Standards, link to the license, and indicate any changes. Each standard is drafted from cited sources under published authoring rules, reviewed before adoption, and corrected in the open. Keep the attribution and notice below with any copy; it carries the warranty notice the license asks you to retain.
"Maintenance of Plant Operations," SynC Standards, revision 1. Licensed under CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Source: https://synergyinconstruction.com/standards/general/maintenance-of-plant-operations. Reference material only; not professional engineering advice and provided without warranty. Verify against governing codes and have a licensed professional review before use.