Common Work Results for Electrical

Written and maintained by SynC.

Rev5
IssuedOct 19, 2026
LicenseCC BY 4.0
Contents

Revision history

Build a datasheet from this standard Start a project with this standard already attached — one click, no setup.
Use in a project

1 Scope

NOTE This standard is the umbrella for the electrical discipline. It states once the code basis and the administrative and execution provisions that every electrical standard on the project inherits, so that the equipment, wiring, lighting, communications, and electronic safety and security standards can confine themselves to their own products and procedures. (1.1)
1.2 The requirements of this standard apply to every item of electrical work on the project, including communications and electronic safety and security work and work on systems above 1000 V, whether or not the standard governing that work restates them.
1.3 Where a standard governing a particular item of electrical work states a requirement on a matter this standard also addresses, the more specific standard shall govern that item unless the Engineer of Record directs otherwise in writing.
NOTE This standard carries no product requirements. The products and procedures below are governed by their own standards, and nothing here restates them. (1.4)
  • Building wire and cable, splices, and terminations: Conductors And CablesConductors and CablesResolves to the current adopted revision.sync/conductors-and-cables; feeder and service conductors: Distribution Feeder CablesService and Feeder ConductorsResolves to the current adopted revision.sync/distribution-feeder-cables; shielded cable above 1000 V: Medium Voltage CablesMedium-Voltage CablesResolves to the current adopted revision.sync/medium-voltage-cables; control and instrumentation cable: Instrumentation And Control CableInstrumentation and Control CableResolves to the current adopted revision.sync/instrumentation-and-control-cable
  • Conduit, tubing, boxes, fittings, surface raceways, and their supports: Raceways And ConduitRaceways and ConduitResolves to the current adopted revision.sync/raceways-and-conduit; wireways and auxiliary gutters: Wireways And Auxiliary GuttersWireways and Auxiliary GuttersResolves to the current adopted revision.sync/wireways-and-auxiliary-gutters; cable tray: Cable TrayCable Tray SystemsResolves to the current adopted revision.sync/cable-tray; concrete-encased duct banks: Underground DuctbankUnderground Electrical Duct BanksResolves to the current adopted revision.sync/underground-ductbank; busway: BuswayBuswayResolves to the current adopted revision.sync/busway
  • The grounding electrode system, bonding, and equipment grounding conductors: Grounding And BondingGrounding and Bonding for Electrical SystemsResolves to the current adopted revision.sync/grounding-and-bonding
  • Conductor color coding, wire markers, cable tags, raceway markers, and box cover marking: Electrical IdentificationWiring System IdentificationResolves to the current adopted revision.sync/electrical-identification; equipment nameplates, circuit directories, warning signs, and the arc-flash label as a product: Equipment LabelingElectrical Equipment LabelsResolves to the current adopted revision.sync/equipment-labeling
  • The short-circuit study, the protective device coordination study, and the arc-flash study: Short Circuit StudyShort-Circuit StudyResolves to the current adopted revision.sync/short-circuit-study, Protective Coordination StudyProtective Device Coordination StudyResolves to the current adopted revision.sync/protective-coordination-study, and Arc Flash StudyArc-Flash StudyResolves to the current adopted revision.sync/arc-flash-study
  • The field acceptance test program, its tester, its criteria, and its report: Electrical Acceptance TestingElectrical Acceptance TestingResolves to the current adopted revision.sync/electrical-acceptance-testing
  • Through-penetration firestop systems: FirestoppingFirestoppingResolves to the current adopted revision.sync/firestopping; wall and ceiling access doors: Access Doors And PanelsAccess Doors and PanelsResolves to the current adopted revision.sync/access-doors-and-panels; housekeeping pads: Concrete PadsConcrete Equipment PadsResolves to the current adopted revision.sync/concrete-pads; post-installed anchors: Post Installed AnchorsPost-Installed Concrete and Masonry AnchorsResolves to the current adopted revision.sync/post-installed-anchors
  • Seismic restraint design, bracing, anchorage design, and special seismic certification: Vibration Isolation And Seismic RestraintVibration Isolation and Seismic RestraintResolves to the current adopted revision.sync/vibration-isolation-and-seismic-restraint
  • Dedicated electrical rooms, their clearances, ventilation, and egress: Electrical RoomsElectrical RoomsResolves to the current adopted revision.sync/electrical-rooms
  • The installation inside a hazardous (classified) location: Electrical Hazardous LocationsElectrical Installations in Hazardous (Classified) LocationsResolves to the current adopted revision.sync/electrical-hazardous-locations
  • The service from the utility point of delivery through the service disconnecting means: Electrical Service EntranceElectrical Service EntranceResolves to the current adopted revision.sync/electrical-service-entrance
  • Motors: Electric MotorsCommon Motor Requirements for Electrical EquipmentResolves to the current adopted revision.sync/electric-motors; individually enclosed starters: Combination Motor StartersCombination and Manual Motor StartersResolves to the current adopted revision.sync/combination-motor-starters; motor control centers: Motor Control CentersMotor Control CentersResolves to the current adopted revision.sync/motor-control-centers; variable frequency drives: Low Voltage Variable Frequency DrivesLow-Voltage Variable Frequency DrivesResolves to the current adopted revision.sync/low-voltage-variable-frequency-drives and HVAC Variable Frequency DrivesHVAC Variable Frequency DrivesResolves to the current adopted revision.sync/hvac-variable-frequency-drives; enclosed switches and disconnects: Enclosed Switches And DisconnectsEnclosed Switches and DisconnectsResolves to the current adopted revision.sync/enclosed-switches-and-disconnects; panelboards: PanelboardsPanelboardsResolves to the current adopted revision.sync/panelboards; industrial control panels: Industrial Control PanelsIndustrial Control PanelsResolves to the current adopted revision.sync/industrial-control-panels
  • Removal, abandonment, and relocation of existing electrical systems: Electrical Demolition And RelocationSelective Electrical DemolitionResolves to the current adopted revision.sync/electrical-demolition-and-relocation; temporary construction power and lighting: Temporary Facilities And ControlsTemporary Facilities and ControlsResolves to the current adopted revision.sync/temporary-facilities-and-controls
  • The facility's written electrical safety program, its energized work permits, and its lockout and tagout procedures: Electrical Safety ProgramElectrical Safety ProgramResolves to the current adopted revision.sync/electrical-safety-program
  • The submittal register and review workflow: Submittal And Quality ProceduresSubmittal and Quality ProceduresResolves to the current adopted revision.sync/submittal-and-quality-procedures; operation and maintenance manual content and format: Operation And Maintenance DataOperation and Maintenance DataResolves to the current adopted revision.sync/operation-and-maintenance-data; substantial completion, punch list, and final completion: Closeout ProceduresCloseout ProceduresResolves to the current adopted revision.sync/closeout-procedures; warranty and bond administration: Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds; commissioning and functional performance testing: CommissioningTotal Building CommissioningResolves to the current adopted revision.sync/commissioning
  • Mechanical, plumbing, and process common work: Common Work Results MechanicalCommon Work Results for MechanicalResolves to the current adopted revision.sync/common-work-results-mechanical, Common Work Results PlumbingCommon Work Results for PlumbingResolves to the current adopted revision.sync/common-work-results-plumbing, and Common Work Results ProcessCommon Work Results for Process EquipmentResolves to the current adopted revision.sync/common-work-results-process

2 Referenced Standards

2.1 Equipment, materials, and installation shall comply with the latest adopted edition of each of the following unless a specific edition is cited.
2.2 Where the Contract Documents, the adopted codes, and a referenced standard differ on the same matter, the most stringent requirement shall govern unless the Engineer of Record directs otherwise in writing.
Standard Title
NFPA 70 National Electrical Code (Articles 110, 300, 430, 500 through 516, and 695)
NFPA 70E Standard for Electrical Safety in the Workplace
29 CFR 1926 Subpart K Safety and Health Regulations for Construction, Electrical
NEMA 250 Enclosures for Electrical Equipment (1000 Volts Maximum)
UL 50 Enclosures for Electrical Equipment, Non-Environmental Considerations
UL 50E Enclosures for Electrical Equipment, Environmental Considerations
IBC International Building Code (Section 714, Penetrations; Chapter 17, Special Inspections and Tests)
ASCE/SEI 7 Minimum Design Loads and Associated Criteria for Buildings and Other Structures (Chapter 13)

3 Governing Code and Authority

3.1 Electrical work shall comply with Adopted Electrical CodeAdopted Electrical CodeParameterEach project supplies its own value.adopted-electrical-code, including the amendments the Authority Having Jurisdiction has enacted to it.
3.2 The fire-resistance, seismic, and structural provisions of Adopted Building CodeAdopted Building CodeParameterEach project supplies its own value.adopted-building-code that bear on electrical penetrations, supports, and anchorage shall apply to the electrical work.
NOTE Where an electrical standard cites an article of NFPA 70, the citation refers to that article as it reads in the edition adopted under Adopted Electrical CodeAdopted Electrical CodeParameterEach project supplies its own value.adopted-electrical-code, and the number is given for the reader's convenience rather than as a pin to a particular edition. (3.3)
3.4 Before requesting the first rough-in inspection, the Contractor shall confirm the adopted electrical code edition and amendments with the Authority Having Jurisdiction.
3.5 The Contractor shall notify the Engineer of Record in writing of any adopted amendment that conflicts with the Contract Documents within seven days of identifying it.
3.6 Work affected by a reported amendment conflict shall not proceed until the Engineer of Record has responded in writing.
3.7 Unless the Contract Documents assign the duty to another party, the Contractor shall obtain the electrical permits, pay the associated fees, and arrange every inspection the Authority Having Jurisdiction requires.
3.8 The Contractor shall deliver the signed inspection records and the final electrical approval to the Owner with the closeout submittals.
NOTE Many jurisdictions adopt NFPA 70 one or two cycles behind the current publication, several enforce a state electrical code built on it, and nearly all enact amendments. The electrical code is a fact about the project, answered once, and every electrical standard reads the same answer; the design was prepared against that edition, and a newer edition is not a substitute for it. (3.9)

4 Submittals

4.1 Submittal Procedures

4.1.1 Each submittal made under an electrical standard shall identify the equipment tag or system it covers, the governing standard, and the datasheet values of that standard on which the selection depends.
4.1.2 Product data shall be marked to show the model, ratings, options, and accessories proposed, with inapplicable options struck through.
4.1.3 Where a submittal proposes a departure from the Contract Documents, the departure shall be identified in the transmittal, and a submittal that is silent on a departure shall not be construed as having disclosed it.
4.1.4 Delegated-design submittals shall bear the seal of a professional engineer licensed in the project jurisdiction.
4.1.5 The submittal register, the review timeline, and the action classification of each submittal shall follow Submittal And Quality ProceduresSubmittal and Quality ProceduresResolves to the current adopted revision.sync/submittal-and-quality-procedures.

4.2 Action Submittals

  • Electrical coordination drawings for each area in which they are required under the Trade Coordination section of this standard
  • Sleeve and penetration layout drawings locating every sleeve, block-out, slab stub-up, and roof or exterior wall penetration for electrical work, with the sleeve size and the listed firestop system at each rated assembly
  • Access door location schedule identifying each concealed junction box, pull box, or device that requires service and the access provided to it
  • Delegated-design submittals, including seismic restraint and anchorage design, where the Contract Documents delegate design
  • Outage plan for work in an existing building, listing each planned outage, the systems and areas affected, and its proposed date and duration
Required Action Submittalscheckbox
☑ Electrical coordination drawings
☑ Sleeve and penetration layout drawings
☑ Access door location schedule
☑ Delegated-design submittals
☐ Outage plan

4.3 Informational Submittals

4.3.1 The Contractor shall submit the following for the record:
  • Written confirmation of the adopted electrical code edition and amendments obtained from the Authority Having Jurisdiction
  • Copies of electrical permits and signed inspection records as they are issued
  • Outage requests and the outage log where work is performed in an existing building
  • Installer qualification statement naming the licensed electrical contractor and the supervising electricians
Required Informational Submittalscheckbox
☑ Adopted electrical code and amendment confirmation
☑ Permits and inspection records
☐ Outage requests and log
☑ Installer qualification statement

4.4 Closeout Submittals

4.4.1 The Contractor shall submit the following before substantial completion:
  • Record drawings showing the installed routing of feeders, underground and in-slab raceways, and cable tray, the installed location of every item of equipment, junction box, and pull box, the circuit numbers as installed, and every deviation from the Contract Drawings
  • Operation and maintenance manuals for each electrical system and each item of distribution equipment, prepared and delivered under Operation And Maintenance DataOperation and Maintenance DataResolves to the current adopted revision.sync/operation-and-maintenance-data and indexed by equipment tag
  • The compiled acceptance test report prepared under Electrical Acceptance TestingElectrical Acceptance TestingResolves to the current adopted revision.sync/electrical-acceptance-testing
  • Warranty documentation for each item of equipment, listing the warranty start date, the term, and the party responsible for warranty service
  • Spare parts and spare fuse receipt signed by the Owner's representative
  • Demonstration and training records naming the personnel trained, the dates, and the systems covered
Required Closeout Submittalscheckbox
☑ Record drawings
☑ Operation and maintenance manuals
☑ Compiled acceptance test report
☑ Warranty documentation
☑ Spare parts receipt
☑ Demonstration and training records
4.4.2 Record drawings shall be delivered in the format indicated in the datasheet.
Record Drawing Formatselect
Marked-up prints of the Contract Drawings
Revised CAD drawing files
Revised building information model
NOTE Marked-up prints cost the least to produce and record what the field crew actually saw, and they live on paper and resist searching. Revised CAD files put the record in the Owner's drafting standard at the price of a redrafting step in which field marks are reinterpreted. A revised model carries the most information and feeds facility management software directly, and it is realistic where the project was coordinated in a model to begin with. (4.4.3)
4.4.4 The Contractor shall keep a set of prints at the site marked up as the work is installed, and the record drawings shall be prepared from that set.

5 Quality Assurance

5.1 Installer Qualifications

5.1.1 Electrical work shall be performed by a contractor licensed for electrical work in the project jurisdiction.
5.1.2 Each crew performing electrical work shall be supervised at the site by an electrician licensed in the project jurisdiction, and where the jurisdiction licenses individual electricians, each electrician shall hold the license the jurisdiction requires for the work performed.
NOTE The additional qualifications a particular system requires of its installers, such as the fire alarm, structured cabling, and medium-voltage cable splicing certifications, are stated by the standards governing those systems. (5.1.3)

5.2 Listing and Labeling

5.2.1 Every product installed under an electrical standard shall be listed and labeled by a Nationally Recognized Testing Laboratory for the use and for the environment in which it is installed, under the product standard its governing standard names, and where that standard names none, under the UL standard applicable to the product.
5.2.2 Equipment for which no listing category exists, and equipment modified in the field in a way that affects its listing, shall be field-evaluated and labeled by a Nationally Recognized Testing Laboratory before it is energized.
NOTE An equipment listing is what the inspector and the Engineer of Record rely on in place of evaluating each product's electrical and fire safety themselves, and NFPA 70 110.3(B) makes the listing instructions part of the installation requirements. A field modification that alters the wiring, the overcurrent devices, or the enclosure voids the listing, and the field evaluation label restores the basis the Authority Having Jurisdiction accepts. (5.2.3)

5.3 Electrical Safety During Construction

5.3.1 Work on or near conductors or circuit parts that are or may become energized shall be performed by qualified persons in accordance with NFPA 70E and 29 CFR 1926 Subpart K.
5.3.2 New electrical work shall be installed, connected, and tested with the circuit de-energized and locked out, and energized work shall be performed only under a written energized electrical work permit issued under the Contractor's electrical safety program or, where the Owner's program under Electrical Safety ProgramElectrical Safety ProgramResolves to the current adopted revision.sync/electrical-safety-program governs the site, under that program.
5.3.3 No item of electrical equipment shall be energized until the acceptance tests its governing standard requires have been completed under Electrical Acceptance TestingElectrical Acceptance TestingResolves to the current adopted revision.sync/electrical-acceptance-testing, the Authority Having Jurisdiction has inspected the installation, and the Engineer of Record has released it for energization in writing.
NOTE Construction power, lighting, and the protection of temporary circuits are governed by Temporary Facilities And ControlsTemporary Facilities and ControlsResolves to the current adopted revision.sync/temporary-facilities-and-controls. (5.3.4)

6 Enclosure Types by Location

6.1 Every enclosure furnished under an electrical standard shall be rated under NEMA 250 and listed under UL 50 and UL 50E for the environment of its installed location, and the enclosure type for the normal location of each product shall be as selected under the standard governing that product.
6.2 An enclosure installed outdoors shall be Type 3R or higher.
6.3 An enclosure installed where it is exposed to hose-directed water, wash-down, or dripping or splashing liquid shall be Type 4 or Type 4X.
6.4 An enclosure installed where it is exposed to salt air, chlorine, chemical vapor, or another corrosive agent, indoors or outdoors, shall be Type 4X.
6.5 An enclosure installed where the atmosphere carries non-hazardous dust, lint, fibers, or oil mist shall be Type 12, Type 4, or Type 4X.
6.6 An enclosure installed within a location classified under NFPA 70 Articles 500 through 516 shall be Type 7 in a Class I location and Type 9 in a Class II location, unless the equipment inside it is protected by another technique that the installation under Electrical Hazardous LocationsElectrical Installations in Hazardous (Classified) LocationsResolves to the current adopted revision.sync/electrical-hazardous-locations permits for that equipment.
6.7 A location the Contract Documents or Adopted Electrical CodeAdopted Electrical CodeParameterEach project supplies its own value.adopted-electrical-code designate as damp, wet, corrosive, or classified shall receive enclosures for that location whether or not the standard governing the equipment restates it.
6.8 Where the location of an item of equipment demands a higher enclosure type than the datasheet of its governing standard selects, the higher type shall be furnished at that location.
NOTE Type 1 keeps fingers off live parts in a dry, conditioned interior and does nothing else. Type 12 is gasketed against dust and dripping oil and does not resist a hose. Type 3R sheds rain and sleet outdoors and admits a hose stream, condensation, and wind-driven dust. Type 4 resists the hose, and Type 4X resists the hose and the atmosphere, in stainless steel where it will be struck and in a non-metallic material where chlorides would pit the steel. Type 7 contains an internal explosion of a Class I gas, and Type 9 excludes a Class II dust and limits its own surface temperature; the device inside either has to be listed for the location along with the box. Each product standard asks the enclosure question once for the location its product normally occupies, and these clauses raise the answer wherever the location is worse. (6.9)

7 Trade Coordination

7.1 Coordination Drawings

7.1.1 Where composite coordination drawings are prepared under Common Work Results MechanicalCommon Work Results for MechanicalResolves to the current adopted revision.sync/common-work-results-mechanical, the electrical trade shall add its work to them in every area they cover, within the response period that standard sets, and shall not prepare separate drawings for those areas.
7.1.2 Where no composite coordination drawings are prepared, the Contractor shall prepare electrical coordination drawings for each electrical room, each shaft, each ceiling plenum and corridor in which feeders, busway, or cable tray are routed, and each other area in which electrical equipment or raceway shares space with structure, ductwork, piping, or ceiling systems, before any work in that area is fabricated or installed.
7.1.3 Electrical coordination drawings shall show, at true size, the electrical equipment with the working space and dedicated space NFPA 70 110.26 requires for it, conduit of 2 in. trade size and larger, cable tray, busway, wireways, luminaires, and the work of the other trades indicated in the datasheet.
Work of Other Trades Shown on Electrical Coordination Drawingscheckbox
☑ Structure, including beams, joists, and slab depressions
☑ Ductwork and its insulation
☑ Mechanical piping and its insulation
☑ Plumbing piping
☑ Fire sprinkler piping
☑ Ceiling systems and ceiling-mounted devices
☑ Telecommunications pathways and cable tray
☐ Process equipment and process piping
7.1.4 Conflicts the trades cannot resolve among themselves shall be referred to the Engineer of Record in writing, with the proposed resolutions, before work in the affected area proceeds.
7.1.5 Work installed in an area before the coordination drawings for that area are accepted shall be relocated at the Contractor's cost where it conflicts with the accepted drawings.
NOTE Conduit is the most flexible element in a ceiling and is routed last under the space priority rule the mechanical umbrella sets, which is why a separate electrical coordination process is wasted effort where a composite one exists. The elements the electrical trade cannot move are the equipment and its working space, the busway, and the cable tray, and those are what the coordination drawing exists to protect. (7.1.6)

7.2 Information to Other Trades

7.2.1 The Contractor shall furnish to the concrete and masonry trades the locations and sizes of every sleeve, block-out, slab stub-up, and housekeeping pad for electrical work before the formwork is closed or the masonry is laid.
7.2.2 The Contractor shall furnish to the structural trade the operating weights and the support and anchorage reactions of electrical equipment hung from or set on the structure before that structure is fabricated or placed.
7.2.3 The Contractor shall furnish to the mechanical trade the heat rejection of the electrical equipment in each electrical room and closet before the ventilation or cooling for that room is fabricated.
7.2.4 Where the approved equipment differs from the scheduled basis in any dimension, weight, heat rejection, or connection another trade relies on, the Contractor shall issue the change to that trade in writing within five working days of the approval.

8 Equipment Access and Working Space

8.1 Every item of electrical equipment likely to require examination, adjustment, servicing, or maintenance while energized shall be installed with the working space, the headroom, and the entrance to that space that NFPA 70 110.26 requires for its voltage and condition, wherever it is installed.
8.2 The dedicated equipment space NFPA 70 110.26(E) requires above and below switchboards, switchgear, panelboards, and motor control centers shall be kept clear of ductwork, piping, and other foreign systems, and the Contractor shall report to the Engineer of Record in writing any foreign system shown or installed in that space before installing the equipment.
8.3 Junction boxes, pull boxes, splices, and devices that require access shall be installed so they can be reached without removing other work or ceiling construction other than a lay-in ceiling panel or an access door furnished under Access Doors And PanelsAccess Doors and PanelsResolves to the current adopted revision.sync/access-doors-and-panels.
8.4 Equipment that cannot be installed with the required working space at the location shown shall be reported to the Engineer of Record in writing before it is installed.
8.5 Equipment installed without the working space NFPA 70 110.26 requires shall not be energized until the space is provided or the Engineer of Record has accepted the condition in writing.
NOTE The design of dedicated electrical rooms, including their clearances, headroom, ventilation, and egress, is governed by Electrical RoomsElectrical RoomsResolves to the current adopted revision.sync/electrical-rooms; this section applies to electrical equipment wherever else it is installed, including mechanical rooms, corridors, ceiling spaces, and the outdoors. (8.6)

9 Serving Equipment Furnished Under Other Standards

9.1 Each item of utilization equipment furnished under a mechanical, plumbing, fire suppression, process, cathodic protection, or other non-electrical standard shall be served by the electrical trade with the branch circuit or feeder, the disconnecting means, and the branch-circuit overcurrent protection that NFPA 70 and the equipment schedule require for it, as shown on the electrical one-line diagram and the equipment and motor schedules.
9.2 The components of that service shall be furnished under the standards that govern them:
  • The conductors, under Conductors And CablesConductors and CablesResolves to the current adopted revision.sync/conductors-and-cables or, for feeders, Distribution Feeder CablesService and Feeder ConductorsResolves to the current adopted revision.sync/distribution-feeder-cables
  • The raceway, boxes, and rough-in, under Raceways And ConduitRaceways and ConduitResolves to the current adopted revision.sync/raceways-and-conduit
  • The overcurrent device, under PanelboardsPanelboardsResolves to the current adopted revision.sync/panelboards, Low Voltage SwitchboardsLow Voltage SwitchboardsResolves to the current adopted revision.sync/low-voltage-switchboards, Low Voltage SwitchgearLow Voltage SwitchgearResolves to the current adopted revision.sync/low-voltage-switchgear, or Motor Control CentersMotor Control CentersResolves to the current adopted revision.sync/motor-control-centers, whichever assembly holds it
  • The disconnecting means, under Enclosed Switches And DisconnectsEnclosed Switches and DisconnectsResolves to the current adopted revision.sync/enclosed-switches-and-disconnects or, where a starter is the disconnect, Combination Motor StartersCombination and Manual Motor StartersResolves to the current adopted revision.sync/combination-motor-starters
  • The equipment grounding and bonding, under Grounding And BondingGrounding and Bonding for Electrical SystemsResolves to the current adopted revision.sync/grounding-and-bonding
9.3 A disconnecting means within sight of each motor, electric actuator, rectifier, or other item of utilization equipment shall be furnished where NFPA 70 Article 430 or the article governing that equipment requires one, unless the equipment is furnished with a factory-mounted disconnect that its listing and NFPA 70 accept as the disconnecting means.
9.4 Overcurrent protection on the supply to a fire pump controller shall comply with NFPA 70 Article 695 in addition to the standard governing the device.
9.5 Before ordering the overcurrent device, the disconnecting means, and the conductors serving an item of equipment furnished under another standard, the electrical trade shall take that equipment's voltage, phase, full-load current, minimum circuit ampacity, and maximum overcurrent protection from the reviewed submittal for the equipment rather than from the schedule.
9.6 Where a value taken from the reviewed submittal differs from the value shown on the schedules, the electrical trade shall report the difference to the Engineer of Record in writing before ordering, and the circuit shall not be installed until the Engineer of Record has responded.
9.7 Control and network wiring to such equipment shall be installed by the party the umbrella standard of the equipment's discipline or the Contract Documents assign, using the wiring methods of NFPA 70, with the cable under Instrumentation And Control CableInstrumentation and Control CableResolves to the current adopted revision.sync/instrumentation-and-control-cable and the control system under Control Systems IntegrationControl Systems Integration and TestingResolves to the current adopted revision.sync/control-systems-integration or Building Automation SystemBuilding Automation SystemResolves to the current adopted revision.sync/building-automation-system as the equipment's discipline requires.
NOTE Equipment is bought from a schedule and circuits are sized from the same schedule, and the two diverge the moment a substitute unit arrives with a larger motor or a different control transformer. The mechanical and process umbrellas require the equipment trade to reconcile the approved unit against the circuit shown; this clause puts the same check on the electrical side, so that a breaker is corrected while it is still a line item instead of a change order. (9.8)

10 Sleeves, Penetrations, and Firestopping

10.1 A sleeve shall be provided at every point a conduit, cable, or busway passes through a concrete or masonry wall, floor, roof, or foundation, set before the concrete is placed or the masonry is laid wherever the construction sequence allows.
10.2 Sleeves through foundation walls, below-grade walls, and floors subject to wetting shall be galvanized steel pipe.
10.3 Sleeves elsewhere shall be galvanized steel pipe, galvanized sheet steel, or a cast-in sleeve device, and at a rated assembly the sleeve shall be one the listed firestop system includes.
10.4 Sleeves through floors in electrical rooms, mechanical rooms, and other locations subject to standing water or wash-down shall project not less than 2 in. above the finished floor.
10.5 The annular space at a penetration through a foundation wall, a below-grade wall, or a slab on grade shall be sealed watertight with a modular mechanical sleeve seal or a cast-in sleeve with a waterstop collar, rated for not less than the hydrostatic head at the penetration.
10.6 The annular space at a non-rated penetration in a dry location shall be packed and sealed with sealant at each face.
10.7 Penetrations of fire-resistance-rated and smoke-resistant assemblies by electrical work shall be firestopped under FirestoppingFirestoppingResolves to the current adopted revision.sync/firestopping with a system listed for the assembly, the penetrant, the sleeve, and the annular dimension at that condition.
10.8 Sleeve size and annular dimension at each rated penetration shall be set to match a listed firestop system before the sleeve is installed.
10.9 Penetrations of the roof and of exterior walls by electrical work shall be flashed and sealed under the standards governing those assemblies, and the electrical trade shall furnish the sleeve, pipe portal, or flashing sleeve the flashing detail requires.
NOTE A firestop system is listed for a specific annulus around a specific penetrant, and a sleeve cut to fit the conduit bundle with no room for the fill is the most common reason an electrical penetration fails inspection. Setting the sleeve to a listing before it is cast is what makes the firestop installable later. (10.10)

11 Supports and Seismic Restraint

11.1 Electrical equipment, raceways, cable tray, and busway shall be supported from the building structure under the standard governing each, and shall not be supported from ductwork, piping, ceiling suspension systems, or other trades' work.
11.2 Floor-mounted electrical equipment shall be set on concrete housekeeping pads furnished under Concrete PadsConcrete Equipment PadsResolves to the current adopted revision.sync/concrete-pads where its governing standard or the Contract Documents require a pad, and shall be anchored to the pad or the structure with the anchors its governing standard or the seismic restraint design requires.
11.3 Seismic restraint of electrical equipment, raceways, cable tray, and busway shall be provided under Vibration Isolation And Seismic RestraintVibration Isolation and Seismic RestraintResolves to the current adopted revision.sync/vibration-isolation-and-seismic-restraint wherever ASCE/SEI 7 Chapter 13 requires it for Seismic Design CategorySeismic Design CategoryParameterEach project supplies its own value.seismic-design-category.
NOTE This standard sets no restraint detail of its own. It names the threshold once so that no electrical standard can be read as exempt from it, and it leaves the exemptions, the design responsibility, the bracing, and the certification to the restraint standard, which carries them in full. (11.4)

12 Electrical Work in Existing Buildings

12.1 Maintaining Service and Outages

12.1.1 Electrical service to the occupied areas of an existing building, and to the systems the Owner keeps in operation during construction, shall be maintained throughout the work except during outages scheduled under this article.
12.1.2 Each planned outage shall be requested in writing, stating the systems and areas affected, the proposed start time, and the duration, not less than the number of days indicated in the datasheet before the outage.
Advance Notice of Planned Outagesrange
Not less than
days
123571014
12.1.3 Planned outages shall be scheduled on the basis indicated in the datasheet.
Planned Outage Timingradio
○ During normal working hours, with notice
○ Outside normal working hours only
○ At the time the Owner approves for each outage, with no standing rule
NOTE A short notice period and daytime outages suit a building that is unoccupied or whose occupants can tolerate an interruption, and they keep the work on straight time. Outages outside working hours protect an occupied office, school, or clinic and are paid for in overtime and in a crew that works at night; a hospital, a data center, or a plant on continuous process tolerates neither rule and reviews each outage on its own, which is the position with no standing rule. Two weeks of notice gives an Owner time to warn tenants and reschedule operations, and one or two days is enough where the Owner's own staff are the only people affected. (12.1.4)
12.1.5 An outage shall not begin until the Owner has approved the request in writing.
12.1.6 Where an outage cannot be completed within the approved duration, the Contractor shall restore service at the end of that duration and reschedule the remaining work, unless the Owner extends the approval at the time.
12.1.7 An outage of a fire alarm, emergency, or standby system shall be reported in advance to the Authority Having Jurisdiction and to the Owner's insurer where either requires notice, and the interim measures they require shall be in place before the outage begins.
12.1.8 The Contractor shall keep a log of each outage stating the systems affected, the start and end times, and the work performed, and shall submit it with the informational submittals.
12.1.9 Existing circuits, equipment, and raceways to be removed, abandoned, or relocated shall be handled under Electrical Demolition And RelocationSelective Electrical DemolitionResolves to the current adopted revision.sync/electrical-demolition-and-relocation.

12.2 Cutting and Patching

12.2.1 Cutting, coring, and drilling for electrical work shall be performed so as not to impair the strength, weather resistance, or fire resistance of the construction cut.
12.2.2 Before coring or drilling an existing concrete slab or wall, the Contractor shall locate the embedded reinforcement, conduit, and post-tensioning tendons with a scanning instrument and shall mark the core location clear of them.
12.2.3 A post-tensioning tendon shall not be cut, nicked, or drilled under any circumstances.
12.2.4 Structural members shall not be cut, notched, or cored except where shown on the structural drawings or approved in writing by the structural Engineer of Record.
12.2.5 Openings cut through rated assemblies shall be firestopped as required under the Sleeves, Penetrations, and Firestopping section of this standard.
12.2.6 Surfaces disturbed by electrical work shall be patched to match the adjacent undisturbed construction in material, thickness, texture, and finish.
12.2.7 Where the parties disagree whether a patch matches the adjacent construction, the Architect shall make the determination.

13 Protection and Cleaning

13.1 Electrical equipment and materials shall be stored off the ground, under cover, in a dry space protected from condensation, construction traffic, and physical damage.
13.2 Switchgear, switchboards, motor control centers, transformers, and drives stored or installed in a space that is not yet conditioned shall have their space heaters energized from a temporary circuit, or shall be kept dry by a desiccant or a temporary heat source where no heaters are furnished.
13.3 Equipment installed before the building is weather-tight shall be protected from moisture, dust, paint overspray, and physical damage until the space it occupies is enclosed and conditioned.
13.4 Open ends of raceways, and the openings of enclosures whose covers are off, shall be capped or covered whenever work on them is not in progress.
13.5 Before energization, the interior of each enclosure shall be cleaned of construction debris, dust, and moisture by vacuum, and shipping braces, blocks, and packing shall be removed.
13.6 Compressed air shall not be used to clean the interior of an enclosure containing bus, insulators, or electronic devices.
13.7 Factory finishes damaged during construction shall be touched up with the manufacturer's finish before substantial completion.
13.8 Where the Engineer of Record determines that touch-up does not restore a damaged factory finish, the component shall be refinished or replaced at the Contractor's cost.
NOTE Blowing an enclosure out with compressed air drives conductive dust into bus joints, relays, and trip units and leaves it there, which is why vacuum cleaning is required. Gear stored in a damp building without its heaters energized condenses moisture on its insulators, and the first evidence of it is an insulation resistance reading that fails acceptance. (13.9)

14 Demonstration and Training

14.1 Before substantial completion, the Contractor shall demonstrate the operation of each electrical distribution system, each emergency and standby system, and each lighting, communications, and electronic safety and security system to the Owner's operating and maintenance personnel, and shall train those personnel in its normal operation, its maintenance, and its response to an alarm or a fault.
14.2 The total duration of demonstration and training furnished under this section shall be not less than the number of hours indicated in the datasheet, in addition to any training a governing equipment or system standard requires for its own product.
Demonstration and Training Durationrange
Not less than
hours
248162440
14.3 Training shall be conducted after the operation and maintenance manuals have been delivered, using those manuals as the text, by persons who installed the system or by the manufacturer's representative for the equipment covered.
14.4 Each session shall be recorded on a training record stating the date, the system covered, the instructor, and the personnel trained, and the records shall be submitted with the closeout submittals.
NOTE A small building with a few panelboards and a lighting control system is covered in an hour or two, and a plant with switchgear, generators, transfer switches, and a power monitoring system can need days; the hours are set by what the Owner's staff will be expected to operate without calling the Contractor back. The hours stated here carry the systems whose standards state none, and a system standard that states its own hours adds to them. (14.5)

15 Warranty

15.1 The Contractor shall warrant the electrical work against defects in materials and workmanship for the period indicated in the datasheet, measured from the date of substantial completion.
Workmanship Warranty Periodrange
Not less than
years
1235
15.2 During the warranty period the Contractor shall repair or replace defective work at no cost to the Owner.
15.3 The Contractor shall repair other work damaged by a warranted defect or by its correction at no cost to the Owner.
15.4 Work repaired or replaced under warranty shall be warranted for a fresh full term from the date of the repair or for the remainder of the original term, whichever is longer.
15.5 Manufacturer warranties on equipment and components shall be assigned to the Owner and shall run from the date of substantial completion.
15.6 Where a manufacturer's warranty runs from startup or shipment rather than from substantial completion, the Contractor shall warrant the equipment on the manufacturer's terms for the interval between the two dates.
NOTE The warranty term and coverage particular to a product are stated by the standard governing that product, and the notice, response, correction, and claim procedure for every warranty is administered under Warranties And BondsWarranties and BondsResolves to the current adopted revision.sync/warranties-and-bonds. (15.7)
NOTE A one-year warranty from substantial completion is the term the industry's standard general conditions carry, and most projects adopt it without discussion. Longer terms are bought by institutional owners who keep their buildings for decades, at a premium that rises with the term, because the contractor is pricing equipment failures it does not control. (15.8)

SynC Standards are reference material provided for informational purposes only and as a guide. They are not engineering, architectural, or legal advice and are not a substitute for the judgment of a licensed design professional. It is the responsibility of the user to determine the applicability of any standard to a specific project and to verify all requirements against the governing codes, manufacturer data, and project conditions. SynC does not render professional services and forms no professional relationship by publishing this content. Provided "as is," without warranty of any kind, including fitness for a particular purpose. See our Terms of Use for the complete terms. Moderation log.

This standard is written and maintained by SynC and licensed under Creative Commons Attribution 4.0. You may share and adapt it, including commercially, provided you credit SynC Standards, link to the license, and indicate any changes. Each standard is drafted from cited sources under published authoring rules, reviewed before adoption, and corrected in the open. Keep the attribution and notice below with any copy; it carries the warranty notice the license asks you to retain.

Attribution and reuse notice. Keep this with any copy:
"Common Work Results for Electrical," SynC Standards, revision 5. Licensed under CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Source: https://synergyinconstruction.com/standards/general/common-work-results-electrical. Reference material only; not professional engineering advice and provided without warranty. Verify against governing codes and have a licensed professional review before use.