SynC · Historical revision
Elevators
Revision6
EditedOct 12, 2026
StatusSuperseded
Contents
- 1Scope
- 2Referenced Standards
- 3Submittals
- 3.1Action Submittals
- 3.2Informational Submittals
- 3.3Closeout Submittals
- 4Quality Assurance
- 4.1Manufacturer and Installer Qualifications
- 4.2Permits, Inspection and Acceptance Authority
- 4.3Component Listing
- 4.4Pre-Installation Conference
- 5Service Basis and Site Conditions
- 5.1Rise, Stops and Car Count
- 5.2Rated Load and Rated Speed
- 5.3Electrical Supply
- 5.4Machine Room and Hoistway Environment
- 6Drive and Machine Arrangement
- 6.1Drive Type
- 6.2Hydraulic Jack and Power Unit
- 6.3Traction Machine and Suspension
- 6.4Regenerative Drive
- 7Controller and Operation
- 7.1Controller and Motor Drive
- 7.2Group Operation and Hall Call Entry
- 7.3Operating Features
- 7.4Remote Monitoring
- 7.5Controller Enclosure
- 8Ride Performance and Leveling
- 8.1Leveling Accuracy
- 8.2Ride Quality
- 9Entrances and Doors
- 9.1Door Opening Type and Size
- 9.2Door Operator and Door Protection
- 9.3Hoistway Entrances
- 9.4Entrance Finishes
- 10Car Enclosure
- 10.1Car Shell and Wall Panels
- 10.2Car Ceiling and Lighting
- 10.3Car Flooring
- 10.4Handrails and Accessories
- 11Signal Fixtures
- 11.1Car Operating Panel
- 11.2Hall Fixtures and Arrival Signals
- 11.3Fixture Faceplates and Finish
- 11.4Emergency Communication
- 12Accessibility
- 13Firefighters' Emergency Operation
- 13.1Phase I Emergency Recall
- 13.2Phase II In-Car Operation
- 13.3Main Line Power Shutdown
- 13.4High-Rise Elevator Designations
- 14Emergency and Standby Power Operation
- 14.1Standby Power Operation
- 14.2Battery-Powered Rescue Operation
- 15Seismic Provisions
- 16Hoistway, Pit and Machine Room
- 16.1Hoistway Construction
- 16.2Pit
- 16.3Machine Room and Control Space
- 17Installation
- 17.1Setting and Alignment
- 17.2Coordination with the Building Work
- 17.3Temporary Use for Construction
- 18Acceptance Testing
- 18.1Acceptance Inspection and Tests
- 18.2Performance Verification
- 19Maintenance During the Warranty Period
- 19.1Maintenance Scope
- 19.2Callback Service
- 20Warranty
- 21Spare Parts and Diagnostic Access
View changes in this revision Revision history
Historical revision. This is editorial revision 6, kept so citations to it stay resolvable. It is not the current text of this standard — see the current revision.
Datasheet constraints: every range, checkbox and listbox field now states its direction
1 Scope
NOTE This standard covers the furnishing, installation, adjustment, testing and acceptance of passenger and service elevators, with their machines, controllers, hoistway equipment, entrances, cars and signal fixtures, and the requirements the building work must satisfy to receive them. (1.1)
NOTE An elevator is a car guided on rails between fixed landings and raised either by a traction machine through ropes or belts balanced by a counterweight, or by a hydraulic jack that lifts the car directly or through ropes. Which of those two families a project uses is a real choice with consequences for the hoistway, the pit, the machine space, the energy use, the speed the car can reach and the rise it can serve, and this standard presents it as a choice rather than settling it. (1.2)
NOTE The sizing decisions are not made here. Rated load, rated speed, car inside dimensions, the number of stops and openings and the number of cars in each group come from the elevator traffic study and the drawings, and the fields that hold them start deferred to those documents. What this standard decides is how the equipment of that size is built, controlled, finished, protected and proven. (1.3)
1.4 Elevator equipment is governed by ASME A17.1/CSA B44 as adopted under Adopted Building CodeAdopted Building CodeParameterEach project supplies its own value.adopted-building-code, and its electrical equipment by ASME A17.5/CSA B44.1 and NFPA 70 Article 620. The requirements of this standard supplement the adopted code and do not relax it.
1.5 Where a datasheet selection in this standard is less stringent than the adopted code requires, the code requirement shall govern.
1.6 The Contractor shall confirm the adopted edition of ASME A17.1/CSA B44 and the elevator jurisdiction's amendments to it in writing with the authority having jurisdiction before preparing layout drawings.
NOTE The following are outside this standard. (1.7)
- Escalators and moving walks, dumbwaiters and material lifts, platform lifts and stairway chairlifts, LU/LA elevators, private residence elevators, Class B and Class C freight elevators, and stage, orchestra and parking lifts, none of which has a SynC standard at this time
- Modernization of existing elevators in place
- The hoistway enclosure as a fire-resistance-rated assembly, see Fire Rated Wall And Floor AssembliesFire-Resistance-Rated AssembliesResolves to the current adopted revision.sync/fire-rated-wall-and-floor-assemblies
- The fire alarm initiating devices and the control relays that command Phase I recall and main line power shutdown, see Fire Alarm SystemsFire Alarm SystemsResolves to the current adopted revision.sync/fire-alarm-systems
- The standby power source, its capacity for elevator load and the transfer scheme, see Emergency And Standby PowerEmergency and Standby Power SystemsResolves to the current adopted revision.sync/emergency-and-standby-power
- The feeder conductors to the elevator disconnecting means, see Conductors And CablesConductors and CablesResolves to the current adopted revision.sync/conductors-and-cables, and the disconnecting means itself, see Enclosed Switches And DisconnectsEnclosed Switches and DisconnectsResolves to the current adopted revision.sync/enclosed-switches-and-disconnects
- The equipment grounding and bonding of the installation, see Grounding And BondingGrounding and Bonding for Electrical SystemsResolves to the current adopted revision.sync/grounding-and-bonding
- Waterproofing of the pit, see Below Grade WaterproofingBelow-Grade WaterproofingResolves to the current adopted revision.sync/below-grade-waterproofing, and a pit pump furnished under the plumbing work, see Sump And Sewage PumpsSump and Sewage PumpsResolves to the current adopted revision.sync/sump-and-sewage-pumps
- Automatic sprinklers in the hoistway, machine room or machinery space, see Wet Pipe Fire Sprinkler SystemsWet-Pipe Fire Sprinkler SystemsResolves to the current adopted revision.sync/wet-pipe-fire-sprinkler-systems
- The code-required signage at hoistway entrances directing occupants to the stairs in a fire, see Signage And Egress MarkingsCode-Required Signage and Egress MarkingsResolves to the current adopted revision.sync/signage-and-egress-markings
NOTE The elevator dictates the dimensions of the hoistway, the depth of the pit, the clearance over the car, the reactions on the structure, the heat released into the machine space and the feeder it draws from, and all of those are built by other trades before the elevator arrives. The approved layout drawings are the one document that reconciles them, which is why the layout submittal gates the hoistway work. (1.8)
2 Referenced Standards
2.1 Equipment, materials and installation shall comply with the latest adopted edition of each of the following unless a specific edition is cited.
2.2 Where referenced standards conflict, the more stringent requirement shall govern unless the Engineer of Record directs otherwise in writing.
| Standard | Title |
|---|---|
| ASME A17.1/CSA B44 | Safety Code for Elevators and Escalators |
| ASME A17.2 | Guide for Inspection of Elevators, Escalators, and Moving Walks |
| ASME A17.3 | Safety Code for Existing Elevators and Escalators |
| ASME A17.5/CSA B44.1 | Elevator and Escalator Electrical Equipment |
| ASME A17.6 | Standard for Elevator Suspension, Compensation, and Governor Systems |
| ASME A17.7/CSA B44.7 | Performance-Based Safety Code for Elevators and Escalators |
| ASME A18.1 | Safety Standard for Platform Lifts and Stairway Chairlifts |
| ICC A117.1 | Accessible and Usable Buildings and Facilities |
| ADA Standards for Accessible Design | Accessibility standards issued under the Americans with Disabilities Act |
| International Building Code | Chapter 30, Elevators and Conveying Systems |
| NFPA 70 | National Electrical Code (Article 620) |
| NFPA 72 | National Fire Alarm and Signaling Code |
| NFPA 13 | Standard for the Installation of Sprinkler Systems |
| NFPA 110 | Standard for Emergency and Standby Power Systems |
| NFPA 80 | Standard for Fire Doors and Other Opening Protectives |
| UL 10B | Fire Tests of Door Assemblies |
| ASCE/SEI 7 | Minimum Design Loads and Associated Criteria for Buildings and Other Structures |
| ISO 18738-1 | Measurement of Ride Quality, Part 1: Lifts (Elevators) |
| ISO 8100-34 | Lifts for the Transport of Persons and Goods, Measurement of Lift Ride Quality |
| ANSI/ASA S1.4 | Electroacoustics, Sound Level Meters |
| ASTM E84 | Standard Test Method for Surface Burning Characteristics of Building Materials |
| ASTM A1008 | Standard Specification for Steel, Sheet, Cold-Rolled, Carbon, Structural |
| ASTM A666 | Standard Specification for Annealed or Cold-Worked Austenitic Stainless Steel Sheet, Strip, Plate, and Flat Bar |
3 Submittals
3.1 Action Submittals
3.1.1 The Contractor shall submit the following for the Engineer's review and return before the hoistway, pit, machine room or structural supports are built and before any elevator equipment is released for fabrication:
- Product data for the machine or power unit, controller, drive, door operator, entrances, car, signal fixtures, safeties, governor and buffers, stating drive type, machine arrangement, rated load and rated speed, and identifying the listing of each electrical component to ASME A17.5/CSA B44.1
- Layout drawings showing each hoistway in plan and section with the car, counterweight or jack, rails and brackets, buffers, pit depth, overhead clearance, running clearances, entrance rough openings and the location of the machine, controller and disconnecting means, dimensioned against the building
- Structural reaction drawings giving the rail bracket reactions and spacing, machine and sheave beam loads, buffer reactions and, for a hydraulic elevator, the jack bearing reaction and the pit floor loading, for the structural engineer's use
- Power confirmation stating the supply voltage, full-load and starting current, demand, the regenerated power returned to the building where a regenerative drive is furnished, and the heat released into the machine room, machinery space and control space
- Elevator traffic study where the datasheet requires one, giving the assumed population and the resulting interval and handling capacity for the cars, loads and speeds indicated on the drawings
- Seismic calculations and anchorage details signed and sealed by a professional engineer, where the seismic provisions of ASME A17.1 apply
- Samples of each car wall, ceiling, flooring, handrail, entrance and fixture faceplate finish, and a fixture engraving and signage schedule
- Firefighters' emergency operation sequence and the point-by-point list of the interface with the fire alarm system
- Standby power operation sequence, including the order in which cars return and the cars that continue to run
- Sample warranty, and the scope and schedule of maintenance proposed for the warranty period
Required Action Submittalscheckbox
☑ Product data with listing identification for each electrical component
☑ Layout drawings with pit, overhead and clearances dimensioned against the building
☑ Structural reaction drawings
☑ Power confirmation with heat release and regenerated power
☐ Elevator traffic study
☐ Seismic calculations and anchorage details
☑ Finish samples and fixture engraving schedule
☑ Firefighters' emergency operation sequence and fire alarm interface point list
☑ Standby power operation sequence
☑ Sample warranty and warranty-period maintenance scope
3.1.2 The Contractor shall not release elevator equipment for fabrication, and the hoistway, pit and machine room shall not be constructed, until the layout drawings and structural reaction drawings have been reviewed and returned without open engineering comments.
3.1.3 The Engineer shall return the layout drawings without review where they are submitted without the structural reaction drawings and the power confirmation, and the Contractor shall bear the cost of the Engineer's review of the resubmittal.
NOTE A layout drawing reviewed without its reactions and its power confirmation is a drawing of a hoistway nobody has confirmed the structure can carry or the feeder can serve, and the three documents change together when the equipment changes. (3.1.4)
3.2 Informational Submittals
3.2.1 The Contractor shall submit the following for information before the pre-installation conference:
- Elevator contractor license and the elevator mechanic licenses or certifications required by the jurisdiction for the mechanics assigned to the project
- Evidence of the installer's authorization by the equipment manufacturer where the datasheet requires it
- Qualification statement listing comparable completed installations with their drive type, rise and completion dates
- Proposed acceptance test plan listing the tests of ASME A17.1 Section 8.10 to be performed, the witnessing arrangements and the test weights to be furnished
- Manufacturer's installation instructions and the Maintenance Control Program documents for the equipment, which the Contractor retains on site for the duration of the installation
Required Informational Submittalscheckbox
☑ Contractor and mechanic licenses and certifications
☐ Manufacturer authorization of the installer
☑ Qualification statement with comparable completed installations
☑ Proposed acceptance test plan
☑ Manufacturer's installation instructions and Maintenance Control Program documents on site
3.3 Closeout Submittals
3.3.1 The Contractor shall submit the following before the elevators are accepted:
- Certificate of operation or its equivalent issued by the authority having jurisdiction for each elevator
- Record of the acceptance inspection and tests witnessed by the authority having jurisdiction, with the governor tripping speeds, safety and buffer test results, rated load and balance test results and, for a hydraulic elevator, the relief pressure and leakage test results
- Record of the firefighters' emergency operation test and the fire alarm interface verification signed by the elevator and fire alarm contractors
- Record of the standby power operation test
- Ride quality and leveling measurements where the datasheet requires them
- Record wiring diagrams for each elevator, as installed, with a straight-line diagram kept in the machine room or control space
- Maintenance Control Program documents required by ASME A17.1 Section 8.6 for the equipment as installed
- Operation and maintenance manual covering normal operation, emergency operations, adjustment, lubrication and troubleshooting
- Keys for the firefighters' and other keyed switches, car and hoistway access keys, and the diagnostic tool, software access and credentials the datasheet requires
- Written warranty documents and the callback contact information for the warranty period
Required Closeout Submittalscheckbox
☑ Certificate of operation for each elevator
☑ Acceptance inspection and test record
☑ Firefighters' emergency operation and fire alarm interface test record
☑ Standby power operation test record
☐ Ride quality and leveling measurements
☑ Record wiring diagrams with straight-line diagram in the machine room
☑ Maintenance Control Program documents
☑ Operation and maintenance manual
☑ Keys, diagnostic tool, software access and credentials
☑ Warranty documents and callback contact information
3.3.2 Firefighters' service keys and the keys to keyed operating switches shall be transmitted to the Owner's designated representative against a signed receipt and shall not be left in the car, the controller or the machine room.
NOTE The Maintenance Control Program documents are the record ASME A17.1 requires to be available on site to the mechanic and the inspector for the life of the equipment, and a set that leaves with the installer leaves the next maintenance provider to reconstruct it. (3.3.3)
4 Quality Assurance
4.1 Manufacturer and Installer Qualifications
4.1.1 The equipment shall be the product of a manufacturer that has produced elevators of the drive type and machine arrangement furnished for not less than the period indicated in the datasheet.
Manufacturer Experience with the Furnished Drive Typerange
Not less than
years
025
Default: 5 years
4.1.2 The relationship between the installer and the equipment manufacturer shall be as indicated in the datasheet.
Installer Relationship to the Manufacturerradio
○ The manufacturer's own installation organization
● An independent elevator contractor authorized by the manufacturer for the equipment furnished
○ Any elevator contractor licensed in the jurisdiction
NOTE A manufacturer's own installation force carries the factory's training and parts channel and ties the installation and the maintenance to one company, which is the arrangement most of the major manufacturers sell. An authorized independent installer gives the Owner a maintenance market after the warranty while keeping the manufacturer's support for the installation. An unrestricted licensed contractor widens bidding and suits non-proprietary equipment whose controller and parts are openly available, and it leaves the Owner to judge whether the installer can obtain support for the controller furnished. (4.1.3)
4.1.4 The installing contractor shall hold the elevator contractor license the jurisdiction requires for the duration of the work.
4.1.5 Mechanics performing the installation shall hold the license or certification the jurisdiction requires for elevator work, and apprentices shall work under the direct supervision of a licensed mechanic.
4.1.6 The installing contractor shall maintain a service office able to reach the site within the callback response time indicated under Maintenance During the Warranty Period.
4.2 Permits, Inspection and Acceptance Authority
NOTE The authority having jurisdiction over elevators is frequently a state or municipal elevator division rather than the building department, and it issues the installation permit, witnesses the acceptance tests and issues the certificate that lets the car carry the public. The work is not complete until that certificate exists. (4.2.1)
4.2.2 The Contractor shall obtain the elevator installation permit before installation begins.
4.2.3 The Contractor shall schedule, arrange and pay for the acceptance inspection and the witnessed acceptance tests by the authority having jurisdiction, including the test weights and instruments.
4.2.4 The Contractor shall obtain the certificate of operation or its equivalent for each elevator before the elevator is placed in service for the Owner's use.
4.2.5 Where the authority having jurisdiction requires a re-inspection because the work failed the acceptance inspection, the Contractor shall bear the cost of the re-inspection.
4.3 Component Listing
4.3.1 Controllers, operating devices, electrical protective devices and the car and hoistway wiring shall be listed and labeled to ASME A17.5/CSA B44.1.
4.3.2 The complete electrical installation of the elevator shall comply with NFPA 70 Article 620.
4.3.3 Hoistway entrance assemblies shall be labeled fire door assemblies tested to UL 10B.
4.3.4 Where the Contractor proposes equipment designed under the performance-based route of ASME A17.7/CSA B44.7, the Contractor shall submit the certification of the Accredited Elevator/Escalator Certification Organization with the product data, and the equipment shall not be ordered until the authority having jurisdiction has accepted that certification in writing.
4.4 Pre-Installation Conference
4.4.1 The Contractor shall convene a pre-installation conference after the layout drawings are returned and before the hoistway walls are closed, attended by the parties indicated in the datasheet.
Required Pre-Installation Conference Attendeescheckbox
☑ Elevator contractor and the mechanic in charge
☑ General contractor
☑ Hoistway and machine room construction trades
☑ Electrical contractor
☑ Fire alarm contractor
☑ Sprinkler contractor
☑ Mechanical contractor
☐ Plumbing contractor
☑ Engineer of Record and the Architect
☐ Elevator consultant
☑ Owner's representative
☐ Authority having jurisdiction
4.4.2 The hoistway dimensions and plumbness tolerance, the rail bracket supports, the entrance rough openings, the pit depth and sump, the machine room temperature range and heat release, the disconnecting means location, the fire alarm interface points and the sprinkler locations shall be reviewed at the conference against the approved layout drawings and recorded in the minutes.
4.4.3 The Contractor shall distribute conference minutes to every attendee and to the Engineer of Record within five business days of the conference.
5 Service Basis and Site Conditions
5.1 Rise, Stops and Car Count
NOTE The number of cars, the landings and the front, rear or side openings each car serves, the floor-to-floor heights and the total rise are the building's traffic answer, settled by the traffic study and the plans before the equipment is chosen. They are read from the drawings here rather than selected, because the same car count cannot be right for two different buildings. (5.1.1)
5.1.2 The number of elevators, the landings and openings served by each, the floor-to-floor heights and the total travel shall be as indicated on the elevator schedule and the building sections.
5.1.3 Where the datasheet requires a traffic study, the Contractor shall submit a study showing the average interval and five-minute handling capacity achieved by the cars, rated loads and rated speeds indicated on the drawings for the population and arrival pattern stated in the study.
Elevator Traffic Studyradio
○ Required, prepared by the Contractor for the cars bid
○ Required, prepared by the Owner's elevator consultant and furnished to the Contractor for information
● Not required
NOTE A traffic study models the peak five minutes of the building's day against the proposed cars and reports how long a passenger waits and what fraction of the population the group can move. In an office, hotel, hospital or residential tower the study is what justifies the car count, and it is normally the Owner's consultant who prepares it before the drawings are issued. The Contractor's study checks that the equipment actually bid delivers what the consultant assumed, and the study is omitted where the building is low and lightly populated and the code and program set the car count without it. (5.1.4)
5.2 Rated Load and Rated Speed
NOTE Rated load and rated speed are set by the traffic study against the rise and the population, and ASME A17.1 ties the maximum inside platform area to the rated load so a car cannot be loaded beyond its rating. A load or speed chosen in a specification without that study is the number most often wrong on opening day, which is why both start deferred to the schedule. (5.2.1)
5.2.2 The rated load of each elevator shall be as indicated in the datasheet.
Rated Loadrange
lb
1500200021002500300035004000450050006000800010000
Per drawings — the elevator schedule (deferred by default)
5.2.3 The rated speed of each elevator shall be as indicated in the datasheet.
Rated Speedrange
fpm
75100125150200250300350400500700800100012001400160018002000
Per drawings — the elevator schedule (deferred by default)
5.2.4 The car inside platform dimensions and the car inside clear height shall be as indicated on the elevator schedule.
5.2.5 The inside net platform area of each car shall not exceed the maximum that ASME A17.1 permits for its rated load.
5.2.6 Where Adopted Building CodeAdopted Building CodeParameterEach project supplies its own value.adopted-building-code requires an elevator to accommodate an ambulance stretcher, the car so designated on the elevator schedule shall provide the stretcher accommodation the code requires and shall be identified with the symbol the code requires at each landing.
5.2.7 The car shall carry the rated load at the rated speed continuously for the duty the traffic study assumes without exceeding the temperature rating of the machine, drive or hydraulic fluid.
5.3 Electrical Supply
5.3.1 The supply voltage at the elevator disconnecting means shall be as indicated in the datasheet.
Supply Voltage and Phaseselect
208 V, 3Φ
240 V, 3Φ
480 V, 3Φ
600 V, 3Φ
208 V, 1Φ
240 V, 1Φ
Per drawings — the electrical one-line diagram (deferred by default)
5.3.2 The elevator equipment shall operate at its rated performance with the supply voltage varying within the range ASME A17.5/CSA B44.1 permits for the rated voltage.
5.3.3 The Contractor shall state the full-load current, the starting current and the demand of each elevator in the power confirmation submittal, and the feeder and disconnecting means shall be sized by the electrical work from those values.
5.3.4 The feeder to each elevator disconnecting means shall be furnished under Conductors And CablesConductors and CablesResolves to the current adopted revision.sync/conductors-and-cables.
5.3.5 The disconnecting means for each elevator, and the separate disconnecting means for the car lighting, receptacle and ventilation circuit that NFPA 70 Article 620 requires, shall be furnished under Enclosed Switches And DisconnectsEnclosed Switches and DisconnectsResolves to the current adopted revision.sync/enclosed-switches-and-disconnects and shall be located as NFPA 70 Article 620 requires.
5.3.6 Where the elevator is equipped with battery-powered rescue operation or a regenerative drive, the Contractor shall furnish the auxiliary contact on the disconnecting means or the controller interlock that NFPA 70 Article 620 requires for that equipment, and shall identify it on the layout drawings.
NOTE A single-phase supply serves only the smallest hydraulic power units, and a 208 V three-phase supply roughly doubles the feeder current a 480 V supply would carry for the same machine, which matters on a long feeder from a distant electrical room. The voltage is a property of the building service and is read from the one-line diagram rather than chosen here. (5.3.7)
5.4 Machine Room and Hoistway Environment
5.4.1 The controller, drive and machine shall operate within the ambient temperature and relative humidity range the manufacturer publishes, and the Contractor shall state that range and the heat released into each machine room, machinery space and control space in the power confirmation submittal.
5.4.2 The means of maintaining the machine room, machinery space and control space within the published range shall be as indicated in the datasheet, provided under the mechanical work.
Machine Room and Control Space Conditioningselect
Ventilation with outdoor air
Dedicated split-system cooling unit
Conditioned air from the building system
Ventilation with a dedicated heater
Per drawings — the mechanical drawings (deferred by default)
5.4.3 Where ventilation alone maintains the space, the mechanical design shall demonstrate that the space stays within the published range with the equipment releasing its stated heat at Site Ambient Temperature MaximumSite Ambient Temperature MaximumParameterEach project supplies its own value.site-ambient-temperature-maximum.
5.4.4 Where a dedicated cooling unit is provided it shall comply with Split System Air ConditionersSplit-System Air Conditioners and Heat PumpsResolves to the current adopted revision.sync/split-system-air-conditioners, and its condensate shall not be routed through the hoistway.
5.4.5 A hoistway in which the controller or machine is located shall be maintained within the same published range as a machine room, and a hoistway that opens to an unconditioned parking level or to the exterior shall be treated as an unconditioned space in the mechanical design.
NOTE A solid-state drive derates and then shuts down on an over-temperature fault, and a hydraulic power unit whose fluid is cold levels poorly until it warms. The cheapest conditioning that holds the published range at the site's design conditions is the right amount, and which means that is depends on the heat the equipment releases and on the climate, both of which the mechanical design reads from the power confirmation. (5.4.6)
6 Drive and Machine Arrangement
6.1 Drive Type
6.1.1 The drive type of each elevator shall be as indicated in the datasheet.
Drive Typeradio
○ Hydraulic
○ Traction
NOTE A hydraulic elevator costs less to buy and to build around for a short rise, needs no overhead machine or counterweight, and places its loads on the pit floor rather than on the hoistway structure. It is limited in speed and in rise, uses more energy per trip because the machine lifts the whole car rather than the imbalance against a counterweight, releases that energy as heat into the fluid, and carries a jack and a reservoir of fluid that can leak. A traction elevator reaches any speed and rise the building needs, rides more smoothly at higher speed, and uses less energy, at a higher first cost and with the machine and counterweight loads carried by the hoistway structure. Where the rise, speed and traffic both families can serve overlap, which is roughly two to six stops at modest speed, the choice turns on first cost, energy, the geotechnical conditions under the pit and the Owner's view of a hydraulic fluid reservoir in the building. (6.1.2)
NOTE The Drive Type field decides the family; the arrangement within the family is decided in the two articles that follow, and the article that does not apply to the drive type selected is read as not applicable. (6.1.3)
6.2 Hydraulic Jack and Power Unit
6.2.1 Requirements in this article apply where a hydraulic drive is selected.
6.2.2 The jack arrangement of a hydraulic elevator shall be as indicated in the datasheet.
Hydraulic Jack Arrangementselect
Holed, direct-acting jack below the car in a drilled hole
Holeless, direct-acting jacks beside the car
Holeless, telescopic jacks beside the car
Roped hydraulic, jack beside the car lifting through ropes
Not applicable to a traction elevator
NOTE A holed jack sits in a cased hole drilled below the pit, serves the longest rise a hydraulic elevator can reach and leaves the hoistway free of jacks beside the car, and it puts a pressurized cylinder in contact with soil and groundwater where a leak is invisible until the fluid is gone. Holeless jacks beside the car avoid drilling and the buried cylinder and limit the rise to the jack length, with a telescopic jack extending that limit at some cost in leveling and ride. A roped hydraulic arrangement lifts the car through ropes from a short jack and reaches a longer rise without drilling, at the cost of the ropes, sheaves and safeties a direct-acting jack does not need. Where rock, contaminated soil or groundwater makes drilling undesirable, the holeless and roped arrangements are the ones that avoid it. (6.2.3)
6.2.4 A holed jack shall be installed in a sealed casing of PVC or HDPE closed at the bottom and extended above the pit floor, with the annular space between the cylinder and the casing filled or sealed so that groundwater cannot contact the cylinder.
6.2.5 Where the bottom of a holed jack is below Seasonal High Groundwater ElevationSeasonal High Groundwater ElevationParameterEach project supplies its own value.seasonal-high-groundwater-elevation, the casing shall be a sealed watertight assembly and the jack shall be fitted with a means of detecting fluid loss from the cylinder that places the elevator out of service.
6.2.6 A holed jack shall be protected against corrosion by a factory-applied coating and by cathodic protection where the geotechnical report identifies corrosive soil.
6.2.7 The hydraulic fluid shall be as indicated in the datasheet.
Hydraulic Fluidradio
● Petroleum-based hydraulic fluid
○ Biodegradable vegetable-based hydraulic fluid
○ Not applicable to a traction elevator
NOTE Petroleum fluid is the fluid the power units, seals and valves are designed around and is the norm. A biodegradable fluid limits the environmental consequence of a leak from a holed jack or a pit spill and is selected where the soil, an aquifer or the Owner's environmental policy makes that consequence a concern, and it costs more, requires the manufacturer's confirmation that the seals and valve are compatible with it, and has a narrower viscosity range across temperature. (6.2.8)
6.2.9 The power unit shall include the pump and motor, the control valve, the reservoir, a muffler and a shutoff valve at the jack, and shall be furnished in the machine room or, for a machine-room-less hydraulic arrangement, in a cabinet at a landing or in the hoistway as ASME A17.1 permits.
6.2.10 The piping between the power unit and the jack shall be steel pipe or hydraulic hose rated for the working pressure, with a pressure relief valve set as ASME A17.1 requires, and buried or concealed piping shall be sleeved so that it can be withdrawn.
6.2.11 A low-fluid, over-temperature or loss-of-pressure condition shall return the car to the lowest landing, open the doors and remove the car from service.
6.2.12 The power unit shall be mounted on isolation pads, and the piping shall be isolated from the building structure so that pump noise is not transmitted to occupied spaces.
6.3 Traction Machine and Suspension
6.3.1 Requirements in this article apply where a traction drive is selected.
6.3.2 The machine room arrangement of a traction elevator shall be as indicated in the datasheet.
Traction Machine Room Arrangementselect
Machine-room-less, machine in the hoistway overhead
Machine-room-less, machine in the pit or beside the hoistway at the lowest landing
Overhead machine room above the hoistway
Basement or adjacent machine room beside the hoistway
Not applicable to a hydraulic elevator
NOTE A machine-room-less arrangement places a compact gearless machine on the rails or a bracket inside the hoistway and the controller in a cabinet at a landing or in a small control space, saving the machine room floor area and the roof penthouse, and it has become the common selection for low- and mid-rise traction. It limits the machine to the sizes that fit the hoistway, requires that the hoistway be conditioned like a machine room, and puts maintenance access on the car top or at a landing cabinet. An overhead machine room accepts any machine size and speed, keeps the machine and controller in one room with floor access, and costs a room and a penthouse. A basement machine room avoids the penthouse at the cost of longer roping, a deflector sheave and the overhead beams it still requires. (6.3.3)
6.3.4 The machine type of a traction elevator shall be as indicated in the datasheet.
Traction Machine Typeradio
○ Gearless permanent-magnet synchronous machine
○ Gearless induction machine
○ Geared machine with worm or helical reduction
○ Not applicable to a hydraulic elevator
NOTE A gearless permanent-magnet machine drives the sheave directly, is the smallest and most efficient machine for its torque, runs at any speed from the lowest to the highest the building needs, and is the machine in nearly every machine-room-less elevator. A gearless induction machine offers the same direct drive at larger sizes and speeds without permanent magnets, at a larger size for the same torque. A geared machine reaches the sheave through a reduction gear, costs less at low speed and modest load, and carries the gear's losses, oil and wear, which is why it has receded to the low-speed machine-room installations where its price advantage survives. (6.3.5)
6.3.6 The roping ratio shall be as indicated in the datasheet.
Roping Ratioradio
○ 1:1
○ 2:1
○ 4:1
○ Not applicable to a hydraulic elevator
Manufacturer's standard (by default)
NOTE A 1:1 roping moves the car at sheave speed and suits a large machine in a machine room, a 2:1 roping halves the rope speed and the machine torque for a given car speed and is what lets a compact machine serve a machine-room-less hoistway, and a 4:1 roping serves the heaviest service cars at low speed. The ratio follows from the machine the manufacturer selects for the load and speed and is left to the manufacturer unless the project has a reason to constrain it. (6.3.7)
6.3.8 The suspension means shall be as indicated in the datasheet.
Suspension Meansradio
○ Steel wire ropes
○ Coated-steel belts
○ Not applicable to a hydraulic elevator
NOTE Steel wire ropes are the suspension every manufacturer offers, are inspected by the methods every elevator mechanic knows, and wear in a way a visual inspection and a diameter gauge can follow. Coated-steel belts run over a smaller sheave, which is what permits the smallest machine-room-less machines, run more quietly and do not need lubrication, and their condition is monitored electrically rather than visually because the steel cords are inside a polyurethane jacket, which ties the Owner to the manufacturer's monitoring and replacement belts. The suspension and its means of monitoring are governed by ASME A17.6 whichever is selected. (6.3.9)
6.3.10 Suspension, compensation and governor systems shall comply with ASME A17.6.
6.3.11 Where coated-steel belts are furnished, the controller shall monitor the condition of the belts continuously and shall remove the elevator from service when the manufacturer's replacement criterion is reached.
6.3.12 Where the rise and speed require it under ASME A17.1, compensation ropes or chains shall be provided, and traveling cables shall be guided so that they cannot contact the counterweight or the car on their travel.
6.3.13 The machine shall be fitted with a brake that holds the car with the rated load and the test overload ASME A17.1 requires, and with the emergency brake or ascending car overspeed and unintended movement protection the code requires for the arrangement furnished.
6.4 Regenerative Drive
6.4.1 Whether the traction drive is regenerative shall be as indicated in the datasheet.
Regenerative Driveradio
○ Regenerative drive returning energy to the building supply
○ Non-regenerative drive dissipating braking energy in resistors
○ Not applicable to a hydraulic elevator
6.4.3 Where a regenerative drive is furnished, the Contractor shall state the regenerated power and the harmonic distortion at the feeder in the power confirmation submittal, and the drive shall cease regenerating and dissipate braking energy internally when the elevator is operating on standby power unless the standby source is confirmed in writing to accept reverse power.
7 Controller and Operation
7.1 Controller and Motor Drive
7.1.1 The controller shall be a microprocessor-based controller executing the operating, signaling, dispatching and emergency functions this standard and ASME A17.1 require, with fault logging that records each fault with its time and the car position.
7.1.2 A traction elevator shall be driven by a closed-loop variable-voltage variable-frequency drive with velocity feedback from the machine, giving controlled acceleration, deceleration and jerk and direct approach to the landing without a leveling creep.
7.1.3 The motor control of a hydraulic power unit shall be as indicated in the datasheet.
Hydraulic Pump Motor Controlradio
● Reduced-voltage starter with an electronic control valve
○ Variable-frequency pump motor drive
○ Not applicable to a traction elevator
NOTE A reduced-voltage starter with an electronic control valve is the conventional hydraulic arrangement and the norm: the pump runs at full speed and the valve meters the flow for acceleration, leveling and descent. A variable-frequency pump drive controls speed at the motor, cuts the starting current that sizes the feeder and the standby source, reduces the heat put into the fluid and improves leveling in cold fluid, and it costs more and adds a drive to the control space that must be kept within its own temperature range. (7.1.4)
7.1.5 The controller shall store its parameters in non-volatile memory and shall restore them without a service tool after a loss of power.
7.1.6 The controller shall provide a means of placing the elevator on inspection operation, hoistway access operation and independent service as ASME A17.1 requires, and the inspection operation shall be available from the car top, the pit and the controller.
7.2 Group Operation and Hall Call Entry
7.2.1 A single car shall operate on selective-collective automatic operation, answering car calls and hall calls in the direction of travel and reversing at the last call.
7.2.2 Cars serving common landings shall operate as a group under a dispatcher that assigns each hall call to the car that minimizes the waiting time of the group, and a car removed from the group for inspection, independent service or a fault shall be removed from dispatching without disturbing the remaining cars.
7.2.3 The number of cars in each group and the landings each car in the group serves shall be as indicated on the elevator schedule.
7.2.4 The method of entering hall calls shall be as indicated in the datasheet.
Hall Call Entry Methodradio
● Conventional up and down hall buttons at each landing
○ Destination entry at every landing
○ Destination entry at the main landing with conventional hall buttons at the other landings
NOTE Conventional hall buttons are what every passenger knows and are the norm; a passenger calls a car and selects the floor inside. Destination entry asks the passenger for the floor at a hall keypad or touchscreen and assigns a car by destination, so passengers bound for the same floors ride together and the group makes fewer stops. In a large group in a busy building it raises handling capacity by a margin a conventional group cannot reach, and it does nothing for a single car or a pair. It changes the lobby fixtures, the car fixtures and the way visitors use the building, it must be made accessible to a passenger who cannot see the display, and it ties the hall fixtures to the manufacturer's dispatcher. Destination entry at the main landing alone captures most of the up-peak benefit where the upper landings have little inter-floor traffic. (7.2.5)
7.2.6 Where destination entry is furnished, the hall terminals shall provide the accessible destination entry, audible confirmation and car identification that ICC A117.1 and the ADA Standards require, and shall indicate the assigned car to the passenger at the terminal and at the car entrance.
7.2.7 Where destination entry is furnished, the group shall revert to conventional operation or to a defined fallback from the car operating panel when the hall terminals fail, and the fallback shall be stated in the product data.
7.3 Operating Features
7.3.1 The operating features furnished on each car shall be as indicated in the datasheet.
Operating Featurescheckbox
☑ Independent service from a keyed switch in the car
☐ Attendant operation
☐ Hospital emergency service with keyed hall switches
☐ Card reader provision for floor lockout under the Owner's access control
☐ Floor lockout by time schedule from the controller
☑ Anti-nuisance car call cancelling on load weighing
☑ Load weighing bypass of hall calls at a set load
☐ Automatic return to a home landing when idle
☐ Sabbath operation
☑ Energy-saving standby that dims car lighting and stops the fan when idle
NOTE Hospital emergency service places a car under the control of a keyed hall switch so that staff can bring it to a floor and hold it, and it is the feature a healthcare occupancy specifies for the stretcher car. Card reader provision means the controller accepts a dry contact or a serial input from the Owner's access control system to lock and unlock floors, with the reader and its wiring furnished under the access control work; floor lockout by time schedule does the same from the controller's own clock without a reader. Attendant operation exists for the building that staffs its elevators, which is rare. (7.3.2)
7.3.3 Where card reader provision is selected, the Contractor shall furnish the reader mounting provision in the car operating panel and the interface terminals at the controller, and the access control contractor shall furnish the reader and its cable in the traveling cable space the Contractor reserves.
7.4 Remote Monitoring
7.4.1 Whether a remote monitoring connection is provided shall be as indicated in the datasheet.
Remote Monitoringradio
○ Provided
○ Not provided
7.4.2 The communication path for remote monitoring shall be as indicated in the datasheet.
Remote Monitoring Communication Pathradio
○ Cellular modem furnished and maintained by the elevator contractor
○ The Owner's network through a connection the Owner provides at the controller
○ Not applicable, remote monitoring not provided
NOTE Remote monitoring reports faults, door cycles and performance to the service organization so that a developing problem is seen before the callback, and it is how a manufacturer's maintenance contract increasingly works. A cellular modem keeps the connection off the Owner's network and leaves its security and its bill with the elevator contractor, and it depends on signal in the machine space. A connection on the Owner's network costs nothing to carry and puts the controller inside the Owner's security perimeter, where the Owner's information security policy governs what the connection may do. (7.4.3)
7.4.4 Where a remote monitoring connection is provided, it shall comply with the cybersecurity provisions of ASME A17.1 and shall not permit remote operation of the car or alteration of safety parameters.
7.4.5 The Contractor shall replace every default and vendor-supplied credential on the controller and the monitoring connection before acceptance testing begins and shall record the accounts created in the closeout documentation.
7.5 Controller Enclosure
7.5.1 The controller enclosure rating shall be as indicated in the datasheet.
Controller Enclosure Ratingselect
NEMA Type 1
NEMA Type 12
NEMA Type 3R
NEMA Type 4
NEMA Type 4X
NOTE A Type 1 enclosure in a dry, conditioned machine room or control space is the norm. Type 12 adds a gasketed door against dust and dripping water for a machine room that doubles as a mechanical room. Type 3R is for a controller cabinet exposed to weather, Type 4 for one that is hosed down, and Type 4X for a corrosive atmosphere such as a parking structure exposed to de-icing salt or a coastal exterior cabinet. The controller's own ventilation and the published temperature range still have to be met inside whichever enclosure is selected. (7.5.2)
7.5.3 A controller cabinet located outdoors or in a space open to the weather shall be rated NEMA Type 3R or better and shall be heated and ventilated to the published range.
7.5.4 A controller cabinet in a parking structure or other location exposed to de-icing salt, washdown or a corrosive atmosphere shall be rated NEMA Type 4X.
8 Ride Performance and Leveling
8.1 Leveling Accuracy
8.1.1 Each car shall stop and re-level automatically at each landing within the leveling accuracy indicated in the datasheet from no load to rated load.
Leveling Accuracyrange
Not more than
in
0.1250.250.3750.5
NOTE ICC A117.1 and the ADA Standards set the outer limit of leveling, and a traction elevator with a closed-loop drive levels well inside it. A value of 1/4 in. is what most specifications ask and most equipment delivers; 1/8 in. is attainable on a gearless machine with direct approach and costs adjustment time, and a hydraulic elevator in cold fluid will hold 3/8 in. more easily than 1/4 in. until the fluid warms. (8.1.2)
8.1.3 The car shall re-level without opening the doors beyond the leveling zone when loading or unloading changes the car position, and shall re-level under rated load after rope stretch or fluid compression.
8.2 Ride Quality
8.2.1 The method of verifying ride quality shall be as indicated in the datasheet.
Ride Quality Verificationradio
○ Measured in the car at acceptance with an instrument conforming to ISO 18738-1
● The manufacturer's published ride quality values accepted without field measurement
8.2.2 Where ride quality is measured, the maximum horizontal vibration in the car at rated speed shall not exceed the value indicated in the datasheet.
Horizontal Vibrationrange
Not more than
milli-g peak-to-peak
810121518202530
8.2.3 Where ride quality is measured, the sound level in the car at rated speed with the fan off shall not exceed the value indicated in the datasheet.
In-Car Sound Level at Rated Speedrange
Not more than
dB(A)
48505255586065
8.2.5 Acceleration and deceleration shall be adjusted so that the car reaches rated speed and stops without perceptible jerk, and the floor-to-floor time between typical adjacent landings stated in the product data shall be achieved at acceptance.
9 Entrances and Doors
9.1 Door Opening Type and Size
9.1.1 The door opening type shall be as indicated in the datasheet.
Door Opening Typeselect
Single-speed side-opening
Two-speed side-opening
Single-speed center-opening
Two-speed center-opening
NOTE A center-opening door clears the opening in half the panel travel of a side-opening door of the same width and so cuts the door time on every stop, which on a busy car is where the trip time goes, and it needs a wider car for the panels to park beside the opening. A side-opening door suits a narrow car and a wide opening and is common on hydraulic and service cars. A two-speed door stacks two panels per side that travel at different speeds and clears a wide opening in a shallow door pocket, at the cost of more hangers, more adjustment and more noise than a single-speed door. (9.1.2)
9.1.3 The clear door opening width shall be as indicated in the datasheet.
Clear Door Opening Widthrange
in
323642485460
Per drawings — the elevator schedule (deferred by default)
9.1.4 The clear door opening height shall be as indicated in the datasheet.
Clear Door Opening Heightrange
in
8496108120
Per drawings — the elevator schedule (deferred by default)
9.1.5 The clear door opening of a car on an accessible route shall be not less than ICC A117.1 and the ADA Standards require.
9.2 Door Operator and Door Protection
9.2.1 Car and hoistway doors shall be power operated by a closed-loop door operator with a variable-frequency or direct-current motor and position feedback that opens and closes the car and hoistway doors together, with the opening, closing and dwell times adjustable at the controller.
9.2.2 The door operator shall limit the kinetic energy and the closing force of the doors to the values ASME A17.1 permits and shall reverse the doors on the detection of a passenger or object in the opening.
9.2.3 The door reopening device shall be as indicated in the datasheet.
Door Reopening Deviceradio
● Infrared multi-beam curtain across the full door height
○ Infrared multi-beam curtain with a mechanical safety edge
○ Three-dimensional infrared detection extending into the landing
NOTE A multi-beam curtain sees a passenger or object anywhere in the plane of the doors without contact and is the device every passenger elevator now carries. Adding a mechanical safety edge keeps a reopening means that works when the curtain is blinded by dust, sunlight at a glass-walled lobby or a fault, and it is the arrangement specified for service cars whose doors meet carts. Three-dimensional detection looks out into the landing and reopens before the passenger reaches the sill, which shortens the dwell a group can run on and protects a slow passenger, and it is more exposed to nuisance reopening from traffic passing the entrance. (9.2.4)
9.2.5 Door nudging shall be provided that, after an adjustable interval during which the reopening device remains obstructed, sounds a buzzer and closes the doors at reduced speed and force as ASME A17.1 permits.
9.2.6 Door dwell times shall be adjustable at the controller and shall meet the minimum dwell that ICC A117.1 and the ADA Standards require at every landing.
9.2.7 The door operator and its reopening device shall be adjusted at acceptance so that the door opening time, closing time and dwell stated in the product data are achieved at every landing.
9.3 Hoistway Entrances
9.3.1 Each hoistway entrance shall be a labeled fire door assembly comprising the frame, the door panels, the sill, the hanger and track, the struts and the fascia and dust cover, furnished and installed by the Contractor.
9.3.2 Hoistway entrance assemblies shall carry the fire protection rating that Adopted Building CodeAdopted Building CodeParameterEach project supplies its own value.adopted-building-code requires for an opening in a shaft enclosure of the rating indicated on the life safety plans.
NOTE The hoistway enclosure itself is a fire-resistance-rated assembly specified under Fire Rated Wall And Floor AssembliesFire-Resistance-Rated AssembliesResolves to the current adopted revision.sync/fire-rated-wall-and-floor-assemblies, and its rating fixes the entrance rating by the code's opening protective table. Neither is a project choice once the building is laid out, so the rating is read from the life safety plans rather than selected here. (9.3.3)
9.3.4 Hoistway door panels shall be flush hollow metal panels of cold-rolled steel sheet to ASTM A1008 of not less than 16 gauge, reinforced at the hangers and sound-deadened, with a sight guard on the leading edge of a side-opening panel.
9.3.5 Entrance frames shall be formed steel of not less than 14 gauge or stainless steel of not less than 14 gauge, with an integral or applied jamb return at each side and a head, and shall be anchored to the hoistway wall at not more than 24 in. on center and grouted or filled as the label requires.
9.3.6 The hoistway door sills shall be as indicated in the datasheet.
Hoistway and Car Sill Materialselect
Extruded aluminum
Extruded nickel silver
Stainless steel
Extruded bronze
NOTE Aluminum sills cost least and wear visibly where a service car's carts cross them. Nickel silver resists that wear and keeps its finish under traffic, and it is the sill most passenger specifications call for at a finished lobby. Stainless steel and bronze are selected to match the entrance and cab finish where those metals are used, and bronze is softer than nickel silver under cart traffic. (9.3.7)
9.3.8 Each hoistway door shall be fitted with an interlock complying with ASME A17.1 that prevents the car from moving away from the landing unless the hoistway door is closed and locked, and that prevents the hoistway door from being opened from the landing unless the car is in the leveling zone.
9.3.9 Each hoistway door shall be provided with a door closer or a self-closing mechanism so that a hoistway door left open at a landing closes itself, and with an emergency unlocking device at the landings ASME A17.1 requires.
9.3.10 The hoistway door at each landing shall carry, where Adopted Building CodeAdopted Building CodeParameterEach project supplies its own value.adopted-building-code requires it, the fire emergency sign directing occupants to the stairs, the sign being furnished under Signage And Egress MarkingsCode-Required Signage and Egress MarkingsResolves to the current adopted revision.sync/signage-and-egress-markings and its location coordinated with the Contractor.
9.4 Entrance Finishes
9.4.1 The finish of the hoistway door panels and entrance frames at each landing shall be as indicated in the datasheet.
Entrance Frame and Door Finishselect
Factory-applied baked enamel
Factory-applied powder coat
Stainless steel, No. 4 satin finish
Stainless steel, No. 8 mirror finish
Stainless steel with a rolled or etched pattern
Satin bronze
Prepared for field finish by others
NOTE Painted or powder-coated entrances cost least, are the norm at service landings and at upper landings of a modest building, and show wear at the sill and strike jamb where carts and passengers touch them. Satin stainless steel is the finish most passenger lobbies carry because it hides fingerprints and wear and needs no refinishing. Mirror stainless shows every mark and is chosen for its appearance where the lobby is attended and cleaned. A patterned stainless hides marks better than either and costs more. Bronze suits a lobby finished in that metal and requires a lacquer or regular maintenance to hold its color. Prepared for field finish leaves a primed frame for the painter where the entrance is meant to disappear into the wall. (9.4.2)
9.4.3 Where the finish differs between landings, the finish at each landing shall be as indicated on the elevator schedule, and the finish selected in the datasheet shall apply at every landing the schedule does not distinguish.
9.4.4 Stainless steel shall be Type 304 to ASTM A666, and the finish grain of adjacent panels and frames shall run in the same direction.
9.4.5 Finished entrances shall be protected with a strippable film or a wrap from installation until final cleaning, and the Contractor shall replace any entrance component whose finish is damaged before acceptance.
10 Car Enclosure
10.1 Car Shell and Wall Panels
10.1.1 The car enclosure shall be a steel shell of cold-rolled sheet to ASTM A1008 of not less than 14 gauge, reinforced and sound-deadened, with a platform, a canopy with an emergency exit as ASME A17.1 requires and a front return and transom carrying the car door and the car operating panel.
10.1.2 The car interior finish materials shall meet the flame spread and smoke developed limits that ASME A17.1 sets for car enclosure materials, tested in accordance with ASTM E84.
10.1.3 The car wall panel finish shall be as indicated in the datasheet.
Car Wall Panel Finishselect
Plastic laminate on a steel or composite backing
Stainless steel, No. 4 satin finish
Stainless steel with a rolled or etched pattern
Factory-applied baked enamel or powder coat
Wood veneer panels on a fire-retardant core
Stone, glass or porcelain panels on a reinforced backing
Removable blank panels prepared for an interior finished by others
NOTE Plastic laminate is the least costly finished wall, is offered in the widest range of patterns, and is cut and scratched by cart and luggage traffic and then replaced panel by panel. Satin stainless steel hides wear and fingerprints and suits a passenger car that sees carts. Patterned stainless hides more and costs more. Painted steel is the service car finish and is repainted rather than replaced. Wood veneer and stone, glass or porcelain are architectural finishes selected for a lobby-grade car; both add weight that counts against the rated load, both require the manufacturer's confirmation of the panel attachment, and stone and glass require a reinforced platform and backing. Removable blank panels hand the car interior to an interior designer or a tenant and leave the Contractor to furnish only the shell, the attachment points and the weight allowance. (10.1.4)
10.1.5 Where wood veneer, stone, glass or porcelain panels are furnished, or where the interior is finished by others, the Contractor shall state the weight allowance for the interior finish in the product data, and the finished interior shall not exceed it.
10.1.6 Wall panels shall be removable from inside the car for replacement without disturbing adjacent panels or the car shell.
10.1.7 Each car shall be furnished with removable protective pads covering the wall panels, with pad hooks or buttons concealed in the panel reveals or the canopy, and the pads shall be used whenever the car carries freight or construction material.
10.2 Car Ceiling and Lighting
10.2.1 The car ceiling type shall be as indicated in the datasheet.
Car Ceiling Typeselect
Suspended island ceiling with downlights
Luminous ceiling with a translucent diffuser
Flush ceiling with recessed downlights
Flush ceiling with perimeter cove lighting
NOTE A suspended island ceiling hangs a finished panel below the canopy with downlights at its edge, hides the canopy and the emergency exit, and is the ceiling most manufacturers offer as standard. A luminous ceiling lights the car evenly through a translucent panel and shows every lamp and every bit of dust above it. Flush ceilings with recessed downlights or cove lighting give the architectural car its appearance and reduce the car's clear height by the depth of the fixtures. (10.2.2)
10.2.3 Car lighting shall be LED, shall be dimmable or switchable to the energy-saving standby where that feature is selected, and shall provide the illuminance at the car controls, the platform and the threshold that ICC A117.1 and the ADA Standards require.
10.2.4 Emergency lighting in the car shall be powered from a battery in the car that illuminates the car and operates the emergency communication for the duration ASME A17.1 requires on loss of normal power, and shall test itself on the schedule the manufacturer publishes.
10.2.5 The car ceiling shall provide an emergency exit complying with ASME A17.1 that is lockable from the car top and does not open from inside the car.
10.3 Car Flooring
10.3.1 The car flooring shall be as indicated in the datasheet.
Car Flooringselect
Resilient sheet or tile flooring furnished by the Contractor
Rubber flooring furnished by the Contractor
Porcelain or stone tile on a reinforced platform furnished by the Contractor
Carpet tile furnished by the Contractor
Recessed platform prepared for a floor finish furnished by others
NOTE Resilient and rubber flooring are the service and ordinary passenger car finishes, take cart traffic, are cleaned with a mop and are replaced as a sheet. Porcelain or stone matches a lobby floor and adds the weight of the tile and its setting bed, which the platform is reinforced to carry and which counts against the rated load. Carpet tile quiets the car and shows wear and stains at the sill first. A recessed platform hands the floor to the flooring trade, so that the car floor matches the lobby exactly, and it requires the recess depth to match the finish and its setting bed to the sill. (10.3.2)
10.3.3 Where the floor finish is furnished by others, the recess depth shall be as indicated on the interior finish schedule, and the finished floor shall be flush with the car sill.
10.3.4 Where a flooring product furnished by the Contractor is of a type covered by Resilient FlooringResilient FlooringResolves to the current adopted revision.sync/resilient-flooring, CarpetCarpetResolves to the current adopted revision.sync/carpet, Ceramic TileCeramic TileResolves to the current adopted revision.sync/ceramic-tile or Natural Stone TileNatural Stone TileResolves to the current adopted revision.sync/natural-stone-tile, the product shall comply with that standard.
10.3.5 The car floor surface shall be firm, stable and slip resistant as ICC A117.1 and the ADA Standards require.
10.4 Handrails and Accessories
10.4.1 The car handrail arrangement shall be as indicated in the datasheet.
Car Handrail Wallsradio
○ Rear wall
○ Both side walls
○ Rear wall and both side walls
○ No handrail
NOTE Neither ICC A117.1 nor the ADA Standards requires a handrail in an elevator car, so the arrangement is a comfort and durability choice. A rear wall handrail steadies a standing passenger and protects the rear panel from carts. Side wall handrails protect the side panels in a service car and cost clear width where the car is narrow. A car finished by others or a car whose walls are protected by pads may omit the handrail. (10.4.2)
10.4.3 Handrails shall be of the same metal and finish as the car fixtures, mounted at the height ICC A117.1 permits for a handrail where one is provided, with returned ends and with the clearance from the wall that lets a hand grip them.
10.4.4 The car accessories furnished shall be as indicated in the datasheet.
Car Accessoriescheckbox
☑ Two-speed ventilation fan in the canopy
☐ Rear wall mirror or mirror panel
☐ Ceiling-mounted camera provision with conduit and power to the canopy
☐ Audio provision with speaker and conduit to the canopy
☑ Hinged or removable car ceiling access for lamp replacement
☐ Threshold light
10.4.5 Where a camera or audio provision is selected, the Contractor shall furnish the traveling cable conductors or the fiber the Owner's system requires, terminated in the controller and at the canopy, and the camera and audio equipment shall be furnished under the Owner's security or audio work.
11 Signal Fixtures
11.1 Car Operating Panel
11.1.1 The number and location of car operating panels shall be as indicated in the datasheet.
Car Operating Panelsradio
● One panel in the front return
○ Two panels, one in each front return
○ One panel at each entrance of a car with front and rear openings
NOTE A single panel is the norm and meets the accessibility standards when its buttons are within the reach range. Two panels put the controls within reach from either side of a wide car and let a crowded car register calls without reaching across passengers. A car with front and rear openings needs a panel at each entrance so that a passenger entering from either side finds the controls at hand. (11.1.2)
11.1.3 Each car operating panel shall contain a floor button for each landing served, a door open and a door close button, an alarm button, the emergency two-way communication control and the keyed switches for independent service, firefighters' Phase II operation and any other keyed function selected, arranged as ICC A117.1 and the ADA Standards require.
11.1.4 Each floor button shall illuminate when a call is registered and extinguish when the call is answered, and shall be identified by a raised character and Braille beside or on the button as ICC A117.1 and the ADA Standards require.
11.1.5 The car operating panel shall include the car position indicator and the capacity, operating and certificate information ASME A17.1 requires, and an engraved or applied legend for each switch.
11.1.6 The pushbutton type shall be as indicated in the datasheet.
Pushbutton Typeradio
● Mechanical pushbutton with an illuminated halo or jewel
○ Vandal-resistant stainless steel pushbutton with an illuminated ring
○ Touch-sensitive button without moving parts
NOTE A mechanical button with a lighted halo is what passengers expect and is the norm. A vandal-resistant button is a solid stainless button with a sealed switch for a transit, parking or correctional setting where buttons are pried and burned. A touch-sensitive button has nothing to wear and nothing to feel, so it relies on the raised characters beside it and on a confirmation tone for the passenger who cannot see it, and it registers a call from a brush of a sleeve. (11.1.7)
11.2 Hall Fixtures and Arrival Signals
11.2.1 Hall call fixtures at each landing shall contain the up and down call buttons the hall call entry method requires, or the destination entry terminal where that method is selected, mounted within the reach range ICC A117.1 and the ADA Standards require, with each button illuminating when a call is registered.
11.2.2 The arrival signal type shall be as indicated in the datasheet.
Arrival Signal Typeradio
○ Hall lanterns at each landing
○ Car-riding lanterns in the car entrance jambs
○ Hall lanterns at the main landing and car-riding lanterns at the other landings
NOTE A hall lantern at each landing announces the arriving car and its direction from the hall wall, where a waiting passenger sees it from anywhere in the lobby, and it costs a fixture, a backbox and wiring at every landing of every car. A car-riding lantern mounts in the car entrance jamb and is visible from the hall only when the doors open, which ICC A117.1 and the ADA Standards permit, and it is the common selection for a single car or a hydraulic pair where the lobby is small. Hall lanterns at the main landing with car-riding lanterns above puts the signal where the crowd is and saves the upper landings. (11.2.3)
11.2.4 Arrival signals shall be visible and audible as ICC A117.1 and the ADA Standards require, with the audible signal sounding once for an up-bound car and twice for a down-bound car or announcing the direction verbally.
11.2.5 The hall position indicators furnished shall be as indicated in the datasheet.
Hall Position Indicatorsradio
● At the main landing
○ At every landing
○ None
NOTE A hall position indicator tells a waiting passenger where the car is and is of most use at the main landing, where the wait is longest and the lobby is busiest; at the upper landings of a small group it is a fixture that mostly tells the passenger the car is somewhere else. The norm is an indicator at the main landing only, and every landing is selected for a hotel or a residential tower where the Owner wants the display. (11.2.6)
11.2.7 The audible car position signal in the car shall be as indicated in the datasheet.
Audible Car Position Signalradio
○ Verbal floor announcement
○ Passing tone at each floor
11.2.8 A car position indicator shall be provided in each car, located and sized as ICC A117.1 and the ADA Standards require, and shall indicate the floor as the car passes or stops at it.
11.3 Fixture Faceplates and Finish
11.3.1 The faceplate finish of the car and hall fixtures shall be as indicated in the datasheet.
Fixture Faceplate Finishselect
Stainless steel, No. 4 satin finish
Stainless steel, No. 8 mirror finish
Satin bronze
Black anodized or powder-coated
NOTE Satin stainless faceplates match the common entrance and car finish and hide fingerprints. Mirror stainless and bronze match a lobby finished in those metals and need the same care. A black faceplate recedes into a dark car interior and shows its scratches. (11.3.2)
11.3.3 Fixture faceplates shall be of not less than 1/8 in. material, mounted with tamper-resistant fasteners or concealed fastening, with engraved or etched legends filled in a contrasting color.
11.3.4 Fixture mounting shall be flush in the car returns and in the hall walls at the main landing, and may be surface applied at other landings where the wall construction does not permit a flush backbox.
11.4 Emergency Communication
11.4.1 Each car shall be provided with two-way emergency communication complying with ASME A17.1 that connects a passenger in the car to the monitoring location indicated in the datasheet, operates on the car emergency power, and provides the visual and text or video means for a passenger who cannot hear or speak that ASME A17.1 requires.
Emergency Communication Monitoring Locationradio
○ An on-site location staffed whenever the building is occupied
○ The elevator contractor's 24-hour monitoring center
○ A third-party 24-hour answering service under contract to the Owner
NOTE An on-site attended location, a security desk or a front desk, answers fastest and knows the building, and it exists only in a building that is staffed whenever anyone might ride the car. The elevator contractor's monitoring center is staffed around the clock, can dispatch a mechanic directly and is bundled with the maintenance contract, and the connection ends when the contract does. A third-party service is the fallback for an unstaffed building that does not want its emergency line tied to its maintenance provider. Whichever answers, the line must be answered by a person, and ASME A17.1 requires that the car be told its call was received. (11.4.2)
11.4.3 The communication path from the controller to the monitoring location, whether a telephone line, a cellular connection or a network connection, shall be furnished under the telecommunications work to a terminal in the machine room or control space the Contractor identifies on the layout drawings, and the Contractor shall furnish the equipment from that terminal to the car.
11.4.4 The emergency communication shall be tested end to end with the monitoring location at acceptance, and the Contractor shall record the number or address the car calls and the location that answered it in the closeout documentation.
12 Accessibility
12.1 Each elevator on an accessible route shall comply with ICC A117.1 Section 407 and the ADA Standards for Accessible Design, and the more stringent of the two shall govern where they differ.
12.2 The car inside dimensions indicated on the elevator schedule shall be not less than ICC A117.1 and the ADA Standards require for the door location of that car.
12.3 The horizontal clearance between the car sill and the hoistway landing sill shall not exceed the limit ICC A117.1 and the ADA Standards set.
12.4 Hall call buttons, car controls, the emergency communication control and the keyed switches a passenger uses shall be within the reach ranges ICC A117.1 and the ADA Standards require.
12.5 Raised and Braille floor designations shall be provided on both jambs of each hoistway entrance, with a tactile star at the main entry level, furnished by the elevator installation or under Signage And Egress MarkingsCode-Required Signage and Egress MarkingsResolves to the current adopted revision.sync/signage-and-egress-markings as that standard's datasheet assigns them; where they are assigned to the elevator installation, they are part of the work of this standard.
12.6 Door reopening, door dwell and hall signal timing shall meet the minimums ICC A117.1 and the ADA Standards require, measured at acceptance.
NOTE The requirements of this section fold the accessibility standards into the car, the entrances and the fixtures already specified rather than describing a separate accessible car. Every passenger elevator in a building subject to the ADA is an accessible elevator unless the code analysis exempts it, and the few dimensions it adds are read from the standards as adopted, not restated here. (12.7)
13 Firefighters' Emergency Operation
13.1 Phase I Emergency Recall
13.1.1 Phase I emergency recall operation complying with ASME A17.1 Section 2.27 shall be provided on every elevator.
13.1.2 Phase I recall shall be initiated by the fire alarm initiating devices at each elevator lobby, in the machine room, machinery space and control space, and at the top of the hoistway where the hoistway is sprinklered, furnished and interfaced under Fire Alarm SystemsFire Alarm SystemsResolves to the current adopted revision.sync/fire-alarm-systems in accordance with NFPA 72, and by the three-position Phase I key switch at the designated level.
13.1.3 The designated level and the alternate level to which cars recall shall be as indicated on the life safety plans.
13.1.4 On recall the cars shall return nonstop to the designated level, or to the alternate level when the initiating device at the designated level has operated, shall open their doors and shall remain out of service with the visual and audible signals ASME A17.1 requires until Phase I is reset or Phase II is taken.
NOTE The fire alarm system commands the recall; the elevator does not read the detectors. Which device triggers which level, which detector drives the shunt trip and how each is annunciated is settled in the fire alarm sequence of operations, and the point list the Contractor submits is the elevator side of that sequence. Every Phase I failure at acceptance traces to the two lists not matching. (13.1.5)
13.1.6 The Contractor shall furnish the terminals at the controller for the recall, alternate level, shunt trip warning and fire alarm supervisory inputs and shall identify each on the layout drawings and in the point list.
13.2 Phase II In-Car Operation
13.2.1 Phase II emergency in-car operation complying with ASME A17.1 Section 2.27 shall be provided on every elevator, with the Phase II key switch, the call cancel button and the firefighters' operating instructions in each car operating panel.
13.2.2 Phase II shall give the firefighter in the car exclusive control of the car, its doors and its destination as ASME A17.1 requires, and the car shall not respond to hall calls or Phase I recall while on Phase II.
13.2.3 Keys for the Phase I and Phase II switches shall be the standardized key the jurisdiction requires, and the key shall be stored at the designated level as the jurisdiction directs.
13.3 Main Line Power Shutdown
13.3.1 Whether the elevator is provided with automatic main line power shutdown on sprinkler activation shall be as indicated in the datasheet.
Main Line Power Shutdown on Sprinkler Activationradio
○ Provided, initiated by heat detection in the sprinklered hoistway, machine room, machinery space or control space
○ Not provided, no sprinklers in the hoistway, machine room, machinery space or control space
Derived — the sprinkler design for the hoistway, machine room, machinery space and control space (by default)
NOTE Where automatic sprinklers are installed in the hoistway, machine room, machinery space or control space, ASME A17.1 requires that power to the elevator be removed before water from those sprinklers reaches energized equipment, and the shutdown is initiated by heat detectors that respond before the sprinkler does, so that the car is recalled and emptied first. Whether the shutdown exists therefore follows from whether those spaces are sprinklered, which the sprinkler design under Wet Pipe Fire Sprinkler SystemsWet-Pipe Fire Sprinkler SystemsResolves to the current adopted revision.sync/wet-pipe-fire-sprinkler-systems and the adopted codes decide, and the field starts derived from that design. (13.3.2)
13.3.3 Where main line power shutdown is provided, the heat detectors and the shunt trip control shall be furnished under Fire Alarm SystemsFire Alarm SystemsResolves to the current adopted revision.sync/fire-alarm-systems, the shunt trip device shall be furnished in the elevator disconnecting means under Enclosed Switches And DisconnectsEnclosed Switches and DisconnectsResolves to the current adopted revision.sync/enclosed-switches-and-disconnects, and the Contractor shall furnish the controller interface that completes the Phase I recall before power is removed.
13.3.4 Where battery-powered rescue operation or a regenerative drive is furnished with main line power shutdown, the shutdown shall also disconnect that equipment as NFPA 70 Article 620 requires.
13.3.5 The main line power shutdown shall be tested at acceptance by operating each initiating heat detector and confirming that the car recalls and the power is removed, with the fire alarm contractor present.
13.4 High-Rise Elevator Designations
13.4.1 The elevators designated as fire service access elevators or as occupant evacuation elevators shall be as indicated in the datasheet.
Code-Required High-Rise Elevator Designationscheckbox
☐ Fire service access elevator
☐ Occupant evacuation elevator with occupant evacuation operation
Per drawings — the life safety plans and the code analysis (deferred by default)
NOTE A fire service access elevator is a car the building code requires in the tallest buildings for firefighter use, with a protected lobby, a protected hoistway and power pathway, a standby power connection and a status panel in the fire command center. An occupant evacuation elevator is a car the code permits to be used by occupants during a fire, with occupant evacuation operation under ASME A17.1 Section 2.27 and the protected lobbies, communication and signage the code adds. Both are consequences of the building's height and occupancy under the adopted code, and the life safety plans identify which cars carry them. (13.4.2)
13.4.3 A car designated a fire service access elevator shall be provided with the status indication, the standby power connection, the water protection of the hoistway and machine space equipment and the lobby communication that Adopted Building CodeAdopted Building CodeParameterEach project supplies its own value.adopted-building-code and ASME A17.1 require for that designation.
13.4.4 A car designated an occupant evacuation elevator shall be provided with occupant evacuation operation complying with ASME A17.1 Section 2.27, with the lobby status displays, the two-way lobby communication and the interface with the fire alarm system that the designation requires.
14 Emergency and Standby Power Operation
14.1 Standby Power Operation
14.1.1 The operation of the elevators on standby power shall be as indicated in the datasheet.
Standby Power Operationradio
○ Automatic sequential return of all cars to the designated landing, then continued operation of selected cars
○ Automatic sequential return of all cars to the designated landing only
○ Automatic sequential return of all cars, then manual selection of the car to operate from a selector switch at the designated landing
○ No standby power connection
Per drawings — the electrical one-line diagram (deferred by default)
14.1.2 The number of cars that operate at one time on standby power shall be as indicated in the datasheet.
Cars Operating Simultaneously on Standby Powerrange
cars
08
Per drawings — the electrical one-line diagram (deferred by default)
NOTE A standby source large enough to start every car at once is rare, so the controller brings the cars down one at a time, opens the doors and then runs whatever the source can carry. Continued operation of selected cars keeps the building served; return only empties the cars and parks them; a selector switch lets the fire department or building staff choose which car runs. Which arrangement a building needs, and how many cars the source can carry, is decided in the standby power system design under Emergency And Standby PowerEmergency and Standby Power SystemsResolves to the current adopted revision.sync/emergency-and-standby-power, which sizes the source for the elevator load and classifies the elevator among the loads it serves, and both fields read that design. (14.1.3)
14.1.4 On transfer to standby power the controller shall return the cars in sequence to the designated landing, hold the cars not selected to run with their doors open, and run the selected cars on normal operation, and on return of normal power shall resume normal operation without manual reset.
14.1.5 The Contractor shall furnish the terminals at the controller for the standby power transfer signal and the pre-transfer signal from the transfer switch, and the automatic transfer switch shall furnish those signals under Emergency And Standby PowerEmergency and Standby Power SystemsResolves to the current adopted revision.sync/emergency-and-standby-power.
14.1.6 Where a regenerative drive is furnished, the controller shall receive the standby power signal before transfer and shall inhibit regeneration while on standby power unless the standby source is confirmed in writing to accept reverse power.
14.1.7 Standby power operation shall be tested at acceptance by transferring the building to the standby source and confirming the return sequence, the cars that continue to run and the return to normal operation.
14.2 Battery-Powered Rescue Operation
14.2.1 Whether battery-powered rescue operation is provided shall be as indicated in the datasheet.
Battery-Powered Rescue Operationradio
○ Provided
○ Not provided
NOTE Battery-powered rescue operation moves a stalled car to the nearest landing and opens the doors on loss of normal power, from a battery in the controller, so that no passenger waits for a mechanic. On a hydraulic elevator it lowers the car on gravity through the valve; on a traction elevator it drives the machine in the direction of the imbalance. It is the ordinary answer where the building has no standby source connected to the elevator, and where the elevator is on standby power it is redundant unless the Owner wants protection against a transfer failure. Where it is furnished, NFPA 70 Article 620 requires that the disconnecting means also disconnect it, which the Electrical Supply article carries. (14.2.2)
14.2.3 Where battery-powered rescue operation is provided, the battery shall be sized to perform the rescue movement at rated load, shall be monitored by the controller, and shall report a low-battery condition to the remote monitoring connection where one is provided and otherwise at the controller.
15 Seismic Provisions
15.1 Whether the elevator seismic requirements of ASME A17.1 Section 8.4 apply shall be as indicated in the datasheet.
Elevator Seismic Requirements of ASME A17.1 Section 8.4radio
○ Apply
○ Do not apply
Derived — Seismic Design CategorySeismic Design CategoryParameterEach project supplies its own value.seismic-design-category (by default)
NOTE ASME A17.1 Section 8.4 applies by the seismic design category of the building under the adopted code, and when it applies it adds counterweight retention, rail bracket spacing and strength, snag guards, a seismic switch and a seismic operating mode to the ordinary anchorage of the equipment. The elevator's seismic requirements are specified here rather than under the general restraint of nonstructural components because the code writes them for the elevator specifically, and the field starts derived from the seismic design category. (15.2)
15.3 Where ASME A17.1 Section 8.4 applies, the guide rails, rail brackets and their fastenings, the counterweight frame and its retention, the machine, controller and power unit anchorage and the snag guards shall be designed for the seismic forces determined under ASME A17.1 Section 8.4 and ASCE/SEI 7 for Seismic Design CategorySeismic Design CategoryParameterEach project supplies its own value.seismic-design-category, by a professional engineer, and installed to the signed and sealed details.
15.4 Where ASME A17.1 Section 8.4 requires it, a seismic switch and, on a traction elevator, a counterweight displacement switch shall be provided that bring the car to a stop at the nearest landing away from the counterweight and place the elevator on seismic operation as ASME A17.1 requires.
15.5 The structural supports for the rail brackets, machine beams and jack reactions under seismic loading shall be designed under the structural work from the reactions in the structural reaction drawings and shall be as indicated on the structural drawings.
16 Hoistway, Pit and Machine Room
16.1 Hoistway Construction
NOTE The hoistway walls, the pit, the machine room and the structural supports are built by other trades to dimensions the elevator sets, and the approved layout drawings are the dimensions they build to. The bid drawings show the hoistway the design assumed; the layout drawings show the hoistway the equipment furnished needs, and where the two differ the layout drawings govern once reviewed. (16.1.1)
16.1.2 The hoistway, pit and overhead shall be constructed to the dimensions, plumbness tolerance and running clearances shown on the approved layout drawings, and the Contractor shall verify them by survey before setting rails.
16.1.3 The hoistway enclosure shall be a fire-resistance-rated shaft enclosure where Adopted Building CodeAdopted Building CodeParameterEach project supplies its own value.adopted-building-code requires one, constructed under Fire Rated Wall And Floor AssembliesFire-Resistance-Rated AssembliesResolves to the current adopted revision.sync/fire-rated-wall-and-floor-assemblies to the rating indicated on the life safety plans.
16.1.4 The supports for the rail brackets at each floor and at the intermediate spacing the layout drawings require, the machine and sheave beams, the buffer and jack reactions and the hoistway divider beams shall be furnished under the structural work to the reactions in the structural reaction drawings and shall be as indicated on the structural drawings.
16.1.5 Only the equipment of the elevator and the sprinklers, detectors, lighting and wiring that serve the hoistway shall be installed in the hoistway, and no piping, duct or wiring foreign to the elevator shall pass through it.
16.1.6 Hoistway venting or pressurization shall be provided where Adopted Building CodeAdopted Building CodeParameterEach project supplies its own value.adopted-building-code requires it for the hoistway, under the mechanical work, with the vent or the fan sized and located as the code requires.
16.1.7 The hoistway shall be provided with permanent lighting and a switch at the pit access and at the machine room or control space as ASME A17.1 requires, furnished under the electrical work.
16.1.8 Where automatic sprinklers are provided in the hoistway, machine room, machinery space or control space, they shall be furnished under Wet Pipe Fire Sprinkler SystemsWet-Pipe Fire Sprinkler SystemsResolves to the current adopted revision.sync/wet-pipe-fire-sprinkler-systems at the locations ASME A17.1 and NFPA 13 permit, and the sprinkler contractor shall coordinate those locations with the Contractor before the hoistway is closed.
16.2 Pit
16.2.1 The pit shall be constructed to the depth shown on the approved layout drawings, with a floor designed for the buffer, rail and jack reactions in the structural reaction drawings.
16.2.2 Where the pit floor is below Seasonal High Groundwater ElevationSeasonal High Groundwater ElevationParameterEach project supplies its own value.seasonal-high-groundwater-elevation, or where the geotechnical report identifies a hydrostatic condition at the pit, the pit shall be waterproofed under Below Grade WaterproofingBelow-Grade WaterproofingResolves to the current adopted revision.sync/below-grade-waterproofing before the elevator equipment is installed.
16.2.3 The means of removing water from the pit shall be as indicated in the datasheet.
Pit Water Removalselect
Sump with a pump and an oil-sensing control, furnished by the Contractor
Sump with a pump and an oil-sensing control, furnished under the plumbing work
Floor drain through an oil interceptor to the building drainage system
Covered sump pit without a pump
NOTE A pit that fills disables the car and corrodes the buffers, the rails and the jack, and ASME A17.1 requires a drain or a sump pump of the capacity the code sets, with a means that keeps hydraulic fluid out of the drainage system. A pump furnished by the Contractor comes with the controls integrated with the elevator; a pump furnished under the plumbing work is maintained with the building's other pumps and complies with Sump And Sewage PumpsSump and Sewage PumpsResolves to the current adopted revision.sync/sump-and-sewage-pumps, with the oil-sensing control this standard still requires. A floor drain through an oil interceptor needs a gravity outlet below the pit floor, which only a shallow pit above a sewer has. A covered sump without a pump keeps the pit dry only where groundwater and washdown cannot reach it and is pumped manually when it does not. (16.2.4)
16.2.5 A pit pump shall be fitted with an oil-sensing control that stops the pump and sounds an alarm when hydraulic fluid is detected, and the pump discharge shall be an indirect connection to the building drainage system.
16.2.6 Where the pit pump is furnished under the plumbing work, it shall comply with Sump And Sewage PumpsSump and Sewage PumpsResolves to the current adopted revision.sync/sump-and-sewage-pumps and shall carry the oil-sensing control this standard requires.
16.2.7 A fixed pit ladder complying with ASME A17.1 shall be furnished by the Contractor at each pit access, and a pit stop switch shall be provided within reach of the ladder at the pit floor and at the pit access.
16.2.8 A pit light and a GFCI-protected receptacle shall be provided in each pit under the electrical work, located as ASME A17.1 and NFPA 70 Article 620 require.
16.2.9 Where the pit is more than one hoistway wide, a guard between the pits and between the counterweight runway and the pit shall be provided as ASME A17.1 requires.
16.3 Machine Room and Control Space
16.3.1 The machine room, machinery space and control space shall be enclosed, lighted, ventilated and conditioned as ASME A17.1 Section 2.7 and the Machine Room and Hoistway Environment article require, with the access, headroom and working clearances the code requires at the controller and the machine.
16.3.2 The machine room and control space door shall be a self-closing, self-locking door openable from inside without a key, with hardware complying with Door HardwareDoor HardwareResolves to the current adopted revision.sync/door-hardware and a sign reading as ASME A17.1 requires.
16.3.3 The machine room and control space shall be provided with lighting, a lighting switch at the door and a GFCI-protected receptacle under the electrical work, as ASME A17.1 and NFPA 70 Article 620 require.
16.3.4 No equipment other than that of the elevator, the sprinklers and detectors that protect the space and the lighting and conditioning that serve it shall be installed in the machine room or control space.
16.3.5 Where a machine-room-less controller is housed in a cabinet at a landing, the cabinet shall provide the working clearance and the lockable access ASME A17.1 requires for a control space and shall be located where the mechanic can see the car or the hoistway door from the controller or has the remote means the code permits.
16.3.6 The controller, machine, rails and car shall be grounded and bonded under Grounding And BondingGrounding and Bonding for Electrical SystemsResolves to the current adopted revision.sync/grounding-and-bonding, with an equipment grounding conductor in the traveling cable to the car as NFPA 70 Article 620 requires.
17 Installation
17.1 Setting and Alignment
17.1.1 Guide rails shall be set plumb and aligned within the manufacturer's tolerance over the full travel, with rail joints dressed so that the guide shoes pass without a perceptible step, and the Contractor shall record the rail alignment survey in the closeout documentation.
17.1.2 The machine, sheaves, power unit and controller shall be set in the locations shown on the approved layout drawings, anchored to the structure as the structural reaction drawings and the seismic details require, and isolated from the structure where the manufacturer requires it to control noise.
17.1.3 Hoistway entrances shall be set plumb and level and aligned with the car entrance so that the doors run freely, the sill gap meets the accessibility limit at every landing and the running clearances meet ASME A17.1.
17.1.4 Traveling cables shall be hung so that they clear the car, the counterweight and the hoistway equipment through the full travel and shall be supported as NFPA 70 Article 620 requires.
17.2 Coordination with the Building Work
17.2.1 Before setting rails the Contractor shall verify that the hoistway, pit, overhead, machine room, structural supports, entrance rough openings, disconnecting means and fire alarm interface points are complete and conform to the approved layout drawings, and shall report any discrepancy to the Engineer in writing before proceeding.
17.2.2 The Contractor shall furnish the sill supports, the entrance anchorage and the inserts or embedded items the hoistway construction must receive before the hoistway walls are closed, and shall install the entrance frames when the wall construction reaches each landing.
17.2.3 The Contractor shall seal the hoistway openings against weather and debris during construction and shall keep the pit free of water and debris from the time the equipment is delivered.
17.3 Temporary Use for Construction
17.3.1 Whether an elevator may be used for construction before acceptance shall be as indicated in the datasheet.
Temporary Use of the Elevator for Constructionradio
○ Permitted after a temporary acceptance by the authority having jurisdiction, with protection and the Contractor's maintenance
○ Not permitted
NOTE A car used to move construction material before acceptance saves the hoist and the stair, and it arrives at acceptance with worn doors, scratched panels and dust in the controller. Where it is permitted, the jurisdiction's temporary acceptance, a protective car liner, a dedicated operator and the Contractor's maintenance through the period are what hold the equipment together, and the car is restored to new condition at the Contractor's cost before final acceptance. Where the schedule does not need it, not permitting it is the simpler protection. (17.3.2)
17.3.3 Where temporary use is permitted, the car shall be fitted with a protective liner over the walls, floor and ceiling and a protective cover over the car operating panel, shall be operated by an operator the Contractor provides, shall be maintained by the Contractor through the period of use, and shall be restored to new condition, with worn door equipment and damaged finishes replaced, before final acceptance.
17.3.4 Where temporary use is permitted, the period of temporary use shall not count toward the warranty or the maintenance period under this standard, both of which begin at final acceptance.
18 Acceptance Testing
18.1 Acceptance Inspection and Tests
18.1.1 The Contractor shall perform the acceptance inspection and tests of ASME A17.1 Section 8.10 on each elevator, using the procedures of ASME A17.2, witnessed by the authority having jurisdiction, before the elevator is placed in service.
18.1.2 The acceptance tests shall include the tests indicated in the datasheet in addition to those ASME A17.1 Section 8.10 requires for the equipment furnished.
Acceptance Tests Witnessed by the Engineercheckbox
☑ Rated load and balance or relief pressure tests
☐ Car and counterweight safety and governor tests
☐ Buffer tests
☐ Terminal stopping device tests
☐ Brake and ascending car overspeed and unintended movement protection tests
☑ Firefighters' Phase I and Phase II operation with the fire alarm contractor
☐ Main line power shutdown with the fire alarm and electrical contractors
☑ Standby power operation with the electrical contractor
☐ Battery-powered rescue operation
☑ Door force, kinetic energy and reopening device tests
☑ Leveling, door timing and floor-to-floor time
☐ Ride quality measurement
☑ Emergency communication end to end
☑ Accessibility dimensions, reach ranges and signal timing
18.1.3 The Contractor shall furnish the test weights, instruments and personnel for the acceptance tests and shall give the Engineer and the Owner not less than ten business days' notice of each witnessed test.
18.1.4 Where a test fails, the Contractor shall correct the deficiency and repeat the test at the Contractor's cost, including the cost of the Engineer's and the authority having jurisdiction's attendance at the repeated test.
NOTE The jurisdiction's inspector witnesses the safety tests the code requires and issues the certificate on them; the Engineer witnesses the tests that prove the elevator does what the project bought, which the code inspector does not check. Door timing, leveling, ride quality, the standby power sequence and the fire alarm interface are where a new installation most often falls short of its submittal, and they are tested with the trades whose work they depend on present. (18.1.5)
18.2 Performance Verification
18.2.1 Leveling accuracy, door opening, closing and dwell times, floor-to-floor time and, where selected, ride quality shall be measured at acceptance and recorded against the values in the datasheet and the product data.
18.2.2 Any car that fails the leveling, sill gap, door timing, reach range or signal timing requirements of the accessibility standards shall be corrected and re-measured before acceptance.
18.2.3 The firefighters' emergency operation test shall operate every interfaced initiating device and confirm the recall level, the alternate level, the Phase II functions and the main line power shutdown where provided, and shall be signed by the elevator and fire alarm contractors.
19 Maintenance During the Warranty Period
19.1 Maintenance Scope
19.1.1 The Contractor shall maintain each elevator for the period indicated in the datasheet, beginning at final acceptance, in accordance with the Maintenance Control Program required by ASME A17.1 Section 8.6 and the manufacturer's maintenance procedures.
Maintenance Period After Acceptancerange
Not less than
months
36121824
19.1.2 Maintenance shall include the systematic examination, cleaning, lubrication, adjustment and repair of the equipment on the intervals the Maintenance Control Program sets, the replacement of parts worn or failed in normal use, and the tests ASME A17.1 Section 8.6 requires during the period.
19.1.3 Maintenance shall be performed by mechanics employed and supervised by the Contractor or the equipment manufacturer and licensed in the jurisdiction, and the mechanic shall record each visit in the on-site maintenance record the Maintenance Control Program requires.
NOTE Twelve months of the installer's maintenance after acceptance is the norm; it covers the period in which the new installation is adjusted to the building's actual traffic and in which the Owner has not yet let a maintenance contract. A period of zero leaves maintenance to the Owner's contract from the first day, which suits an Owner with an existing maintenance provider; longer periods are bought where the Owner wants the installer accountable through the first full year of occupancy after a phased move-in. (19.1.4)
19.2 Callback Service
19.2.1 The callback coverage during the maintenance period shall be as indicated in the datasheet.
Callback Coverageradio
● Normal working hours for all callbacks, with 24-hour response to a passenger entrapment
○ 24-hour response to all callbacks
○ Normal working hours for all callbacks
19.2.2 The Contractor shall respond to a callback within the time indicated in the datasheet from the Owner's call, measured to the mechanic's arrival on site.
Callback Response Timerange
Not more than
hours
124824
NOTE An entrapment is answered around the clock under every arrangement, because a passenger in a stalled car cannot wait for morning. Whether every other callback is answered overnight is what the three coverage options decide, and 24-hour coverage of everything is bought for a hospital, a hotel or a residential tower where a car out of service at night is a service failure. The response time that is reasonable depends on where the Contractor's nearest mechanic sits; one hour is attainable in a city with a resident route mechanic and four hours is what a rural site can hold a contractor to. (19.2.3)
19.2.4 The Contractor shall maintain a callback log recording each call, the time received, the time of arrival, the cause found and the correction made, and shall deliver it to the Owner at the end of the maintenance period.
20 Warranty
20.1 The Contractor shall warrant the elevator equipment and its installation against defects in materials and workmanship for the period indicated in the datasheet, beginning at final acceptance.
Warranty Periodrange
Not less than
years
1235
20.2 The Contractor shall correct a defect reported within the warranty period at no cost to the Owner, including the labor, parts, freight and the re-inspection the authority having jurisdiction requires for the correction.
20.3 A component replaced or repaired under the warranty shall be warranted for the remainder of the original period or for one year from the date of the repair, whichever is longer.
20.4 The warranty shall exclude damage caused by misuse, vandalism, water intrusion into the pit or hoistway from building conditions outside the Contractor's control, operation outside the manufacturer's published environmental range caused by failure of the building conditioning, and alterations made by others, and the Contractor shall document the cause before declining a warranty claim on those grounds.
20.5 Where the Owner and the Contractor disagree whether a failure is a defect or an excluded cause, the Engineer of Record shall make the initial determination.
NOTE A one-year warranty from acceptance is the norm and runs with the maintenance period, so that the installer who maintains the car is also the one who warrants it. A longer warranty is bought where the maintenance period is longer or where the Owner wants the manufacturer bound beyond the first year, and a warranty separated from maintenance invites a dispute over whether a failure was a defect or a maintenance lapse, which the determination clause above exists to settle. (20.6)
21 Spare Parts and Diagnostic Access
NOTE The Owner's ability to maintain the elevator after the warranty depends on three things the Contractor controls at closeout: the parts, the wiring diagrams and the means of reading and adjusting the controller. A controller whose diagnostics need a tool the Owner does not own is maintained only by the company that owns the tool, and the price of that maintenance reflects it. The diagnostic access field is where the Owner decides that question before the contract is let rather than after. (21.1)
21.2 The diagnostic access furnished to the Owner shall be as indicated in the datasheet.
Diagnostic Access Furnished to the Ownerradio
○ Diagnostic tool, software and credentials furnished to the Owner without time limit, with updates through the warranty
○ On-board diagnostics and adjustment accessible at the controller without a separate tool
○ Diagnostic tool loaned to the Owner for the maintenance period and returned
NOTE A tool and software furnished outright, or a controller whose diagnostics live on board, lets any licensed elevator contractor maintain the equipment and is what keeps the Owner's maintenance contract competitive after the warranty. A tool loaned for the maintenance period returns the Owner to the manufacturer's service when the period ends, which is the manufacturers' preferred arrangement and the one that comes with their lowest installation price. Manufacturers differ in what they will furnish, and the selection constrains which equipment can bid. (21.3)
21.4 The Contractor shall deliver to the Owner the items indicated in the datasheet before final acceptance, against a signed inventory.
Spare Parts and Special Tools Furnished to the Ownercheckbox
☑ Record wiring diagrams and straight-line diagram in the machine room or control space
☐ Manufacturer's special tools for the equipment furnished
☐ Door operator and hall fixture spare parts kit
☐ Spare door gibs, rollers and interlock contacts
☐ Spare pushbuttons, lamps and fixture faceplate fasteners
☐ Spare car emergency lighting battery
☑ Recommended spare parts list with part numbers and sources
☑ Hoistway and machine room access keys and fixture keys
21.5 The record wiring diagrams furnished shall reflect the controller as adjusted at acceptance, including every field change, and a straight-line diagram shall be kept in a holder in the machine room or control space as ASME A17.1 requires.
21.6 Where diagnostic credentials are furnished, the Contractor shall record them in a sealed envelope delivered to the Owner's designated representative and shall not retain a credential the Owner has not authorized in writing after the maintenance period ends.