Submittal and Quality Procedures

Revision 2 · SynC Standards Team — Specifier, SynC (SynC Platform Team / Platform Standards) ✓ Official · Jun 14, 2026 +6 −8

Remove in-body license/authorship footer; reframe submittal lead-time as project-wide default minimum
Showing changes from Rev 1 to Rev 2 in Submittal and Quality Procedures.
---
title: Submittal and Quality Procedures
186 unchanged lines
## A submittal schedule that is not coordinated with the construction schedule is the root of most submittal-driven delay claims: the submittal arrives too late for a full review cycle to close before the installation date, and the resulting compression is then blamed on the reviewer. {note}
## Each submittal shall be received no later than the lead time below in advance of the date the related material or fabrication is required.
+## Submittal lead time is inherently item-specific: the review-and-fabrication horizon for a stock lamp is nothing like that for a medium-voltage switchgear lineup, so no single figure can govern every product. The governing submission date for each item is the one fixed in the submittal schedule, which accounts for that item's own review cycle and fabrication lead time. The fields below set only the project-wide default minimum that applies to an item until the submittal schedule establishes a longer, item-specific date. {note}
+## Each submittal shall be received no later than the date fixed for that item in the submittal schedule or, where the schedule fixes none, no later than the project-wide default minimum below.
+
```datasheet
label: Submittal lead time before required installation (standard items)
+label: Default minimum submittal lead time — standard items
type: range
unit: weeks
4 unchanged lines
```
## Long-lead fabricated items shall be scheduled for submission far enough ahead to absorb both the review cycle and the fabrication lead time.
+## Long-lead fabricated items shall be scheduled in the submittal register for submission far enough ahead to absorb both the review cycle and the fabrication lead time; the default minimum below governs only until that item-specific date is set.
```datasheet
label: Submittal lead time before required installation (long-lead fabricated items)
+label: Default minimum submittal lead time — long-lead fabricated items
type: range
unit: weeks
314 unchanged lines
- O&M data and manufacturer warranties
```
## --- {note}
## This standard was independently authored by the SynC Standards Team from public consensus standards, building codes, and public government guide specifications. It is licensed under CC BY-SA 4.0. {note}