SynC · SynC Standards

Water Supply Wells

Rev1
IssuedOct 12, 2026
Contents

Revision history

Build a datasheet from this standard Start a project with this standard already attached — one click, no setup.
Use in a project

1 Scope

NOTE This standard governs the construction of a drilled water supply well, from the well construction permit and the mobilization of the drilling rig through the casing, the annular seal, the screen, the filter pack, the development, the plumbness and alignment survey, the test pumping, the water quality sampling, the disinfection, and the wellhead completion, and it ends at the well record that states what was built and what the well produces. (1.1)
NOTE The standard is written for a well that is a public water supply source or the raw, process, or service water supply of a treatment plant or an industrial facility; it applies to a private domestic or irrigation well where the drawings assign it, because the state well construction code holds a private well to the same casing, seal, and setback rules and differs only in the approvals that follow. (1.2)
NOTE This standard is read with Common Work Results ProcessCommon Work Results for Process EquipmentResolves to the current adopted revision.sync/common-work-results-process, which carries the submittal register, the factory and witnessed test policy, the manufacturer's field services, the nameplate basis, the spare parts policy, the anchorage basis, and the vibration and noise limits for the equipment on the project; those obligations apply to the well and are not restated here. (1.3)
NOTE This standard ends where Vertical Turbine PumpsVertical Turbine PumpsResolves to the current adopted revision.sync/vertical-turbine-pumps begins. The permanent pump, whether a deep-well line-shaft turbine or a submersible well pump, with its motor, column, discharge head, cable, column check valve, and the pitless unit or discharge tee where the pump manufacturer furnishes it, and the pump field test, are that standard's. The temporary test pump used for the test pumping is within this standard, because it is removed when the test is complete and is never the pump the well is operated with. (1.4)
NOTE The depth, the diameter, the target aquifer, the anticipated yield, and the test pumping rate are the hydrogeologist's design and live on the well plan and section and in the well design memorandum; this standard carries no norm for any of them. The screen slot and the filter pack gradation are designed from the formation samples after the pilot hole is drilled, and that design is a hold point before the screen is ordered rather than a value this standard asserts. (1.6)
NOTE The following are outside this standard: (1.7)
  • The permanent well pump, its motor, column, discharge head, cable, and field test under Vertical Turbine PumpsVertical Turbine PumpsResolves to the current adopted revision.sync/vertical-turbine-pumps
  • Groundwater monitoring wells and piezometers under ASTM D5092, the piezometer under Geotechnical Instrumentation And MonitoringGeotechnical Instrumentation and MonitoringResolves to the current adopted revision.sync/geotechnical-instrumentation-and-monitoring and the monitoring well drilled for environmental compliance not yet owned by a SynC standard, and geotechnical borings under Geotechnical Instrumentation And MonitoringGeotechnical Instrumentation and MonitoringResolves to the current adopted revision.sync/geotechnical-instrumentation-and-monitoring and the geotechnical report
  • Construction dewatering wells and well points, with routine sump pumping under EarthworkEarthworkResolves to the current adopted revision.sync/earthwork and designed wellpoint, deep well, and eductor systems under Excavation Support And DewateringExcavation Support and DewateringResolves to the current adopted revision.sync/excavation-support-and-dewatering
  • Injection, recharge, and aquifer storage and recovery wells, geothermal wells, and the rehabilitation of an existing well, none of which is yet owned by a SynC standard
  • Radial collector wells, horizontal wells, dug wells, and springs
  • The well house building and its mechanical and electrical work under the building standards, the raw water main from the wellhead under Water Distribution PipingSite Water Distribution PipingResolves to the current adopted revision.sync/water-distribution-piping and Site UtilitiesSite UtilitiesResolves to the current adopted revision.sync/site-utilities, excavation for the pad and the well house under EarthworkEarthworkResolves to the current adopted revision.sync/earthwork, and the pad concrete under Cast In Place ConcreteCast-in-Place ConcreteResolves to the current adopted revision.sync/cast-in-place-concrete
  • Disinfection of building plumbing under Disinfection Of Water SystemsDisinfection of Domestic Water SystemsResolves to the current adopted revision.sync/disinfection-of-water-systems, which references AWWA C654 for building-side practice only
1.8 The Contractor shall drill, case, seal, screen, develop, test, disinfect, and complete the well at the location shown on the well plan.
1.9 The Contractor shall coordinate the work under this standard with Vertical Turbine PumpsVertical Turbine PumpsResolves to the current adopted revision.sync/vertical-turbine-pumps for the casing diameter, the pump setting, and the pitless unit the pump is set through; with Water Distribution PipingSite Water Distribution PipingResolves to the current adopted revision.sync/water-distribution-piping and Site UtilitiesSite UtilitiesResolves to the current adopted revision.sync/site-utilities for the raw water main at the wellhead; with EarthworkEarthworkResolves to the current adopted revision.sync/earthwork for the excavation of the pad and the well house; with Erosion And Sediment ControlErosion and Sediment ControlResolves to the current adopted revision.sync/erosion-and-sediment-control for the discharge of drilling fluid, development water, and test pumping water; and with the building standards for the well house.

2 Referenced Standards

2.1 Materials, construction, testing, and disinfection shall comply with the latest adopted edition of each of the following unless a specific edition is cited.
2.2 Where referenced standards conflict, the more stringent requirement shall govern unless the Engineer of Record directs otherwise in writing.
Standard Title
AWWA A100 Water Wells
AWWA C654 Disinfection of Wells
AWWA M21 Groundwater (Manual of Water Supply Practices)
ANSI/NGWA-01 Water Well Construction Standard
ASTM A53/A53M Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
ASTM A589/A589M Seamless and Welded Carbon Steel Water-Well Pipe
ASTM A139/A139M Electric-Fusion (Arc)-Welded Steel Pipe (NPS 4 and Over)
ASTM A778/A778M Welded, Unannealed Austenitic Stainless Steel Tubular Products
ASTM A312/A312M Seamless, Welded, and Heavily Cold Worked Austenitic Stainless Steel Pipes
ASTM F480 Thermoplastic Well Casing Pipe and Couplings Made in Standard Dimension Ratios (SDR), SCH 40 and SCH 80
ASTM C150/C150M Portland Cement
ASTM C136/C136M Sieve Analysis of Fine and Coarse Aggregates
AWWA C206 Field Welding of Steel Water Pipe
NSF/ANSI/CAN 60 Drinking Water Treatment Chemicals, Health Effects
NSF/ANSI/CAN 61 Drinking Water System Components, Health Effects
40 CFR Part 141 National Primary Drinking Water Regulations
State well construction code The water well construction rules of the state in which the well is drilled, as adopted and enforced by the Authority Having Jurisdiction
NOTE The state well construction code is the governing document for the sealed depth, the annular width, the grout materials the state admits, the casing stickup, the sanitary setbacks, the driller's license, the well completion report, and the abandonment procedure; AWWA A100 is the construction standard the industry writes against, and where the two differ the code governs because it is the one with a permit behind it. (2.3)
2.4 The Contractor shall confirm the governing edition of the state well construction code and the primacy agency's requirements for a new source with the Authority Having Jurisdiction before the well construction permit application is filed.

3 Submittals

3.1 Action Submittals

3.1.1 The Contractor shall submit the following for review by the Engineer of Record and the hydrogeologist of record before the work they describe begins:
  • The well driller's state license and the licenses of the drilling crew the state requires, with the project references this standard requires
  • A copy of the well construction permit and of every other permit the drilling, the discharge, and the well require
  • Drilling plan describing the drilling method, the rig, the drilling fluid and its additives, the casing program with the diameter, wall thickness, and setting depth of each string, the sequence of pilot hole, logging, reaming, casing, sealing, screening, filter packing, and development, and the drilling fluid containment and disposal
  • Product data for the casing, identifying the material, the governing product standard, the grade, the wall thickness, and the joint
  • Product data for the screen, identifying the type, the material, the open area per foot for each slot size, the collapse strength, and the connection to the casing
  • Grout mix design for the annular seal, stating the material, the water-to-cement ratio or the solids content, the additives, and the placement method
  • Filter pack product data with a sieve analysis per ASTM C136/C136M and a certification of the silica content and the washing and disinfection of the material
  • Screen design submittal, after the pilot hole samples have been analyzed, stating the slot size, the screen length, the screen settings, the filter pack gradation, and the sieve analyses they were designed from
  • Development plan describing the methods, the equipment, the chemical aids and their certification, the sequence, and the disposal of development water
  • Test pumping plan describing the test pump and its power, the discharge measurement, the water level measurement in the pumped well and in observation wells, the measurement schedule, the discharge route, and the sand sampling
  • Disinfection plan under AWWA C654 describing the chlorine form, the dose, the method of application, the contact time, the flushing and dechlorination, and the bacteriological sampling
  • Product data for the well seal or the pitless unit, the vent, the sounding tube, and the cap
Action Submittals Requiredcheckbox
☑ Driller's license and project references
☑ Well construction permit and discharge permits
☑ Drilling plan with casing program and fluid disposal
☑ Casing product data
☑ Screen product data
☑ Grout mix design
☑ Filter pack product data and sieve analysis
☑ Screen design submittal from the pilot hole samples
☑ Development plan
☑ Test pumping plan
☑ Disinfection plan
☑ Wellhead completion product data
3.1.2 The screen shall not be ordered, and the filter pack shall not be delivered, until the screen design submittal has been approved in writing by the Engineer of Record on the hydrogeologist of record's recommendation.
3.1.3 Review of a submittal does not relieve the Contractor of responsibility for compliance with the Contract Documents or with the state well construction code.

3.2 Informational Submittals

3.2.1 The Contractor shall deliver the following as the work produces them, within two working days of the day each is produced, so the hydrogeologist of record is reading the well as it is drilled rather than after it is cased:
  • The daily driller's log for every day the rig is on the well
  • The formation samples, labeled by depth, and the sieve analyses of the samples from the aquifer zones
  • The geophysical logs, in the field print and in digital form
  • The video survey recording for each survey stage
  • The plumbness and alignment test record
  • The development log, with the method, the duration, the discharge rate, the sand content, and the turbidity for each development period
  • The test pumping field data, with every discharge and water level reading and its time
  • The laboratory reports for the water quality samples and the bacteriological samples
  • The disinfection record, with the chlorine form and quantity, the measured residual, the contact time, and the flushing and dechlorination
Informational Submittals Requiredcheckbox
☑ Daily driller's log
☑ Formation samples and sieve analyses
☑ Geophysical logs in print and digital form
☑ Video survey recordings
☑ Plumbness and alignment test record
☑ Development log
☑ Test pumping field data
☑ Water quality and bacteriological laboratory reports
☑ Disinfection record

3.3 Closeout Submittals

3.3.1 The Contractor shall deliver the following before the well is turned over for the installation of the permanent pump, and shall deliver the compiled set before substantial completion:
  • The as-built well record stating the casing material, diameter, wall thickness, and setting depth of each string, the sealed interval and grout quantities, the screen type, material, slot size, and settings, the filter pack gradation, interval, and quantity, the total depth, the static water level, the pumping water level and the specific capacity at the test rate, the sand content, the plumbness and alignment result, and the recommended production rate and pump setting
  • The test pumping report
  • The state well completion report, as filed with the state and stamped or acknowledged by it
  • The compiled driller's logs, geophysical logs, video surveys, development log, and laboratory reports
  • The abandonment record for every test hole and every failed well on the site, as filed with the state
  • The primacy agency's new-source approval, where the well is a public water supply source
  • The warranty
Closeout Submittals Requiredcheckbox
☑ As-built well record
☑ Test pumping report
☑ State well completion report as filed
☑ Compiled logs, surveys, and laboratory reports
☑ Abandonment records for test holes and failed wells
☑ Primacy agency new-source approval
☑ Warranty
3.3.2 The as-built well record shall be measured from the well as built, not transcribed from the design, and every depth in it shall be referenced to the top of the casing and to the ground surface elevation at the well.

4 Quality Assurance

4.1 Well Driller Qualifications

4.1.1 The well shall be drilled by a well drilling contractor who holds the license the state requires for the construction of water wells of the class and use of this well, and the license shall be current on every day the rig is on the site.
4.1.2 The well driller shall have constructed not fewer than three wells of comparable diameter, depth, drilling method, and completion within the preceding five years, and shall submit those project references with the license.
4.1.3 The rig operator shall be the licensed driller or a person working under the driller's direct supervision as the state well construction code defines it.
NOTE Most states license well drillers separately from excavation, utility, and plumbing contractors, and most license the pump installer separately again; the state inspects the license before it accepts the well completion report, and a well drilled by an unlicensed crew is a well the state does not accept as a public water supply source whatever its construction. (4.1.4)

4.2 Hydrogeologist of Record

4.2.1 The Owner shall retain a hydrogeologist of record, licensed as a professional geologist or professional engineer where the state licenses the practice, to design the well, to interpret the formation samples and the logs, to design the screen and the filter pack, to direct the development and the test pumping, and to prepare or review the test pumping report.
4.2.2 The hydrogeologist of record shall observe the hold points listed in this standard and shall direct, in writing, the response to every condition in the borehole that differs from the well design memorandum.
4.2.3 The hydrogeologist of record shall accept or reject the formation samples, the screen design, the completion of development, and the completion of the test pumping on the basis of the criteria in this standard.
4.2.4 The hydrogeologist of record may stop drilling, development, or test pumping that does not conform to this standard or to the well design memorandum, and the Contractor shall comply with that direction.
NOTE The hydrogeologist's role is the one the geotechnical engineer plays on an earthwork site: the well design memorandum was written from regional data and a test hole or two, and the aquifer the bit actually reaches is confirmed or contradicted foot by foot as the samples come up, so the person who wrote the memorandum is the one positioned to revise it. (4.2.5)

4.3 Permits and Approvals

4.3.1 The Contractor shall obtain the well construction permit from the state well program or the Authority Having Jurisdiction before the rig is mobilized, and shall post it at the site as the code requires.
4.3.2 The Owner shall obtain the water right, the water use permit, or the registration the state requires for the withdrawal, where the state requires one, and the Contractor shall not conduct the test pumping until the permit the test discharge requires has been issued.
4.3.3 Where the well is a public water supply source, the primacy agency's review of the well site and the well design shall be complete before drilling begins, and the agency's new-source approval shall be obtained before the well is connected to the system.
4.3.4 The well shall be used as indicated in the datasheet, which sets the approvals and the water quality sampling that apply to it.
Well Useselect
Public water supply source
Treatment plant process, service, or utility water
Industrial process supply
Irrigation supply
Private domestic supply
NOTE A public water supply source brings the primacy agency into the design, the siting, the sampling, and the approval to operate, and brings the drinking water contact certifications with it; a plant service or process well and an industrial supply well are permitted by the state well program under the same construction rules and sampled for the parameters the use needs rather than the full new-source list; an irrigation well is held to the construction code and to the water right and little else; a private domestic well is permitted and inspected by the state or county well program and released on a bacteriological sample. The use changes who approves the well and what is sampled, not how it is built. (4.3.5)

4.4 Well Location and Sanitary Setbacks

4.4.1 The well shall be located at the point shown on the well plan and at not less than the sanitary setback the state well construction code requires from every sewer, septic system, sewage lagoon, fuel storage tank, chemical storage, stormwater infiltration facility, permeable pavement, animal enclosure, cemetery, and other contamination source the code names, whether that source exists or is shown on the drawings.
4.4.2 The Contractor shall verify the setbacks from the sources shown on the site utility plan and from every existing source within the setback distance before the permit application is filed, and shall report a setback that cannot be met to the Engineer of Record before drilling begins.
NOTE The setback runs both ways: the well constrains where Permeable PavingPermeable PavingResolves to the current adopted revision.sync/permeable-paving, Stormwater Management SystemsStormwater Management and Detention SystemsResolves to the current adopted revision.sync/stormwater-management-systems, Sanitary Sewer SystemsSanitary Sewer Systems (Site)Resolves to the current adopted revision.sync/sanitary-sewer-systems, and Fuel Dispensing And Storage TanksFuel Storage TanksResolves to the current adopted revision.sync/fuel-dispensing-and-storage-tanks place their facilities, and those standards carry the setback from the well as a requirement on their work; the well plan is the drawing on which the Engineer of Record reconciles the two. (4.4.3)
4.4.4 Where the well is a public water supply source, the wellhead protection area or the sanitary control zone the primacy agency requires shall be as shown on the well plan, and the Owner shall hold the control it requires over that area before the new-source approval is sought.

4.5 Pre-Drilling Conference

4.5.1 Before the rig is mobilized, the Contractor shall convene a conference attended by the well driller, the hydrogeologist of record, the Engineer of Record, the Owner's operations representative, and the state well inspector or the primacy agency's representative where the permit requires that attendance.
4.5.2 The conference shall review the well design memorandum, the drilling plan and the casing program, the sampling and logging program, the hold points and the notice each requires, the screen design procedure, the development and test pumping plans and the discharge route, the disinfection and sampling plan, the drilling fluid containment and disposal, the protection of the well during construction, and the procedure for abandoning a test hole or a failed well.

4.6 Hold Points

4.6.1 The Contractor shall give the hydrogeologist of record and the Engineer of Record not less than 24 hours notice before each hold point listed below, and shall not proceed past a hold point until the hydrogeologist of record has released it in writing:
  • Completion of the pilot hole and the geophysical logs, before reaming or casing
  • Approval of the screen design submittal, before the screen is ordered
  • Setting of the surface casing and of each production casing string, before the annular seal is placed
  • Placement of the annular seal, with the grout volume reconciled against the calculated annular volume
  • Setting of the screen and placement of the filter pack, with the filter pack volume reconciled
  • Completion of development, on the criteria in this standard
  • Installation of the test pump and the measurement equipment, before the step-drawdown test
  • Completion of the test pumping, before the test pump is removed
  • Disinfection and bacteriological clearance, before the well is released for the permanent pump
4.6.2 Where a hold point inspection is not performed within 24 hours of the scheduled time through no fault of the Contractor, the Contractor may proceed after notifying the Engineer of Record in writing, and the Owner shall bear the cost of standby time the delay causes.
NOTE A well is built in a hole no one can see into, and each hold point is the last moment at which a decision is still reversible: a screen set in the wrong interval, a seal placed over a cavity, and a filter pack that bridged halfway down are each found afterward only by pulling the well apart or abandoning it. (4.6.3)

5 Well Design Basis

5.1 Design Values Carried by the Hydrogeologist

5.1.1 The target aquifer and the formation the well is screened in shall be as described in the well design memorandum and shown on the well section.
5.1.2 The design depth of the well shall be as indicated in the datasheet.
Design Depthrange
ft
503000
Per drawings — the well plan and section and the well design memorandum (deferred by default)
5.1.3 The nominal diameter of the production casing shall be as indicated in the datasheet.
Production Casing Nominal Diameterrange
in
4568101214161820243036
Per drawings — the well plan and section and the well design memorandum (deferred by default)
5.1.4 The anticipated yield on which the well is designed shall be as indicated in the datasheet.
Anticipated Yieldrange
gpm
510000
Per drawings — the well design memorandum (deferred by default)
NOTE The depth, the diameter, and the yield are the hydrogeologist's reading of the aquifer and the pump the Owner intends to set in it, and no well standard has a norm for any of them; they defer to the memorandum because that is where the hydrogeologist recorded them, and the as-built well record is where the values the well actually delivered are written beside them. The casing diameter is also the first number the pump standard reads, because the bowl assembly and the submersible motor are chosen to fit inside it with the clearance the pump manufacturer requires. (5.1.5)
5.1.6 Where the formation encountered differs from the well design memorandum in a way that changes the design depth, the casing program, the screen interval, or the anticipated yield, the hydrogeologist of record shall direct the change in writing before the Contractor proceeds, and a change in depth or diameter directed for a condition the memorandum did not identify shall be paid as a change.
5.1.7 The Contractor shall not deepen, shorten, or change the diameter of the well on the Contractor's own judgment.

5.2 Drinking Water Contact

5.2.1 Where the well is a public water supply source, the casing, the screen, the filter pack, the grout, the sealants, and every other component that remains in contact with the water shall meet the drinking water contact provisions of Common Work Results ProcessCommon Work Results for Process EquipmentResolves to the current adopted revision.sync/common-work-results-process to the extent the state well construction code and the primacy agency require certification to NSF/ANSI/CAN 61 for well components.
5.2.2 Drilling fluid additives, development chemicals, and disinfectants introduced into any well shall be certified to NSF/ANSI/CAN 60.
NOTE The drilling fluid, the dispersant, and the chlorine are the chemicals that go down the hole on every well, and NSF/ANSI/CAN 60 certification is what lets the primacy agency accept that they left nothing behind; the casing and screen certification under NSF/ANSI/CAN 61 is required by some states and not by others, which is why the first clause reads from the code and the second does not. (5.2.3)

6 Drilling

6.1 Drilling Method

6.1.1 The well shall be drilled by the method indicated in the datasheet.
Drilling Methodselect
Cable tool
Direct mud rotary
Reverse-circulation rotary
Air rotary
Air rotary with casing hammer
Dual rotary
NOTE Cable tool drills by lifting and dropping a bit, drives the casing as it goes, uses no drilling fluid, and produces the cleanest formation samples and the most reliable water level observations of any method, at a rate of a few tens of feet per day; it is the method for a boulder or cobble formation, for a shallow unconsolidated aquifer where fluid loss or formation damage is the concern, and for a site where the rig the Contractor has is a cable tool rig. Direct mud rotary circulates a bentonite fluid down the drill pipe and up the annulus, holds the hole open with the fluid column, and drills unconsolidated and soft rock formations in days rather than weeks, at the cost of a filter cake on the aquifer face that development has to remove and samples that arrive mixed and delayed by the circulation time. Reverse-circulation rotary pulls the fluid up the drill pipe at a velocity that lifts coarse cuttings, runs on water with little or no additive, and drills the large-diameter hole in unconsolidated sand and gravel that a municipal filter-packed well needs, at the cost of a large water supply, a large pit, and a formation that stands open only where the water table is deep enough to hold a fluid head. Air rotary lifts the cuttings with compressed air, drills consolidated rock faster than any fluid method, shows the water as it is encountered, and leaves no cake, and it cannot hold an unconsolidated formation open. Air rotary with a casing hammer, and dual rotary which turns the casing and the drill string independently, advance the casing with the bit through overburden, boulders, and caving sand, so the hole is cased as it is drilled, at the cost of a rig that is not everywhere available. (6.1.2)
6.1.3 The drilling method shall be suited to the formation described in the well design memorandum, and a method that cannot hold the hole open, cannot reach the design depth, or cannot produce samples adequate for screen design shall not be used.
6.1.4 The drilling fluid containment shall be as indicated in the datasheet.
Drilling Fluid Containmentradio
○ Portable above-ground tanks
○ Lined earthen pit
○ Unlined earthen pit
6.1.5 An earthen pit shall not be used where its bottom lies below Seasonal High Groundwater ElevationSeasonal High Groundwater ElevationParameterEach project supplies its own value.seasonal-high-groundwater-elevation, within the sanitary setback of the well, or where the state well construction code prohibits it.
NOTE Above-ground tanks keep the fluid, the cuttings, and the additives off the ground and out of the water table and are what a public water supply site and a tight site call for, at the cost of tank rental and a pump to move the fluid; a lined pit holds a larger volume for a reverse-circulation rig and depends on a liner that survives the excavator; an unlined pit is the cheapest containment, is admitted by some codes on a rural site in tight soil, and puts the fluid into the ground within feet of the well that is supposed to be protected from it. (6.1.6)

6.2 Pilot Hole and Reaming

6.2.1 The borehole shall be advanced as indicated in the datasheet.
Borehole Advancementradio
○ Pilot hole to total depth, logged, then reamed to the design diameter
○ Drilled at the design diameter in a single pass
NOTE A pilot hole is drilled small and fast to the design depth, logged, and sampled, so the screen interval and the filter pack are designed against the formation that is actually there before the full-diameter hole is cut; the single pass saves the reaming on a cable tool well, on a hammer-cased well that cannot be reamed, and on a small well where the formation is known from a test hole beside it. (6.2.2)
6.2.3 Where a pilot hole is drilled, it shall be advanced to the design depth or to the depth the hydrogeologist of record directs on the basis of the samples, and it shall not be reamed until the geophysical logs have been run and the screen design submittal has been approved.
6.2.4 The reamed borehole shall be of a diameter not less than the outside diameter of the casing or screen plus twice the annular width this standard requires, through every interval that will be sealed or filter-packed.

6.3 Formation Sampling

6.3.1 Formation samples shall be collected at every change in formation and at intervals not exceeding the interval indicated in the datasheet.
Formation Sampling Intervalrange
ft
251020
Default: Not more than 5 ft
6.3.2 Each sample shall be representative of the interval it is labeled with, shall be of not less than one quart, shall be washed free of drilling fluid where a fluid method is used, and shall be placed in a labeled container showing the well, the date, and the depth interval.
6.3.3 On a direct mud rotary hole, the sample at the surface arrives after the cuttings have traveled the full annulus, and the driller shall correct the labeled depth for the circulation lag time measured at that depth.
6.3.4 The Contractor shall retain every sample at the site until the hydrogeologist of record releases it, and shall deliver the samples the hydrogeologist designates to the Owner with the well record.
6.3.5 Samples from each interval the hydrogeologist of record designates as a candidate screen interval shall be sieved per ASTM C136/C136M, and the sieve analysis shall be delivered to the hydrogeologist of record before the screen design submittal is prepared.
NOTE The sieve curve of the aquifer sand is the single input from which the slot size, the filter pack gradation, and the pack-to-formation ratio are designed, and a well with a sand problem for its whole life is usually a well whose samples were taken too far apart, mixed across a formation change, or sieved after the screen was ordered. (6.3.6)

6.4 Geophysical Logging

6.4.1 The geophysical logs indicated in the datasheet shall be run in the pilot hole or the open borehole over its full depth before the casing and screen are set, by a logging contractor who performs geophysical logging of water wells as a regular business.
Geophysical Logs Requiredcheckbox
☑ Electrical resistivity, single-point or multi-point
☑ Spontaneous potential
☑ Natural gamma
☑ Caliper
☐ Fluid temperature and conductivity
☐ Flowmeter (spinner) log
NOTE Resistivity and spontaneous potential together distinguish the permeable sand from the clay in an unconsolidated section and show where the formation water changes quality, natural gamma reads the clay content through casing and in a hole that has no fluid, and the caliper measures the hole diameter the annular grout and filter pack volumes are calculated from; those four are the suite a rotary pilot hole in an unconsolidated aquifer is logged with, and a cable tool well that was sampled every few feet and had its water level measured as it went is sometimes logged with gamma and caliper alone. The fluid log locates the zones that contribute flow and the interface between fresh and brackish water, and the spinner log measures how much of the yield each zone delivers, which matters where the screen is to be set in some zones and blanked across others. (6.4.2)
6.4.3 The logs shall be delivered in a field print and in a digital form the hydrogeologist of record accepts, with the depths referenced to the ground surface at the well.
6.4.4 The video survey of the well shall be made at the stages indicated in the datasheet, with a downhole color camera with side-view capability, and the recording shall show the depth continuously.
Video Survey Stagescheckbox
☐ Open borehole, before the casing and screen are set
☑ After development, before the test pump is set
☐ After test pumping and disinfection, before the well is released
NOTE The survey after development is the one that shows the screen slots clear, the casing joints sound, and the well bottom free of the sand the development pulled in, which is the condition the pump is set into; the open-hole survey shows the formation face in a rock well where the screen is to be set across fractures; the final survey records the well as it was released, which is the record an owner opens when the pump is pulled years later. (6.4.5)
6.4.6 A video survey shall be made only after the water in the well has cleared enough to see the casing wall, and the Contractor shall pump or bail the well to clear it before the survey where it has not.

7 Well Casing

7.1 Casing Material

7.1.1 The production casing shall be of the material indicated in the datasheet.
Production Casing Materialselect
Low-carbon steel
Stainless steel, Type 304L
Stainless steel, Type 316L
PVC per ASTM F480
NOTE Low-carbon steel is the casing of nearly every public supply well, welded in the field, driven or set to any depth, and left to a slow corrosion that a few decades of service in ordinary groundwater tolerate; stainless steel casing is set where the water is corrosive, where the Owner expects the well to outlast steel, or where iron pickup from the casing is a water quality objection, at several times the cost and with a joint that needs a qualified stainless welder; Type 316L adds resistance to chloride where the groundwater is brackish; PVC casing is light, immune to corrosion, admitted by most state codes for a well of moderate depth and diameter, and limited by its collapse strength under the grout and the formation, by the depth to which a plastic string can be set, and by a code that in some states does not admit it for a public supply well. (7.1.2)
7.1.3 Steel casing shall conform to ASTM A53/A53M Grade B, ASTM A589/A589M, or ASTM A139/A139M Grade B for the diameter furnished, shall be new, and shall bear the mill marking of the standard it was made to.
7.1.4 Stainless steel casing shall conform to ASTM A778/A778M or ASTM A312/A312M in the type indicated in the datasheet, and shall not be placed in contact with carbon steel casing without an insulating connection where the groundwater is corrosive.
7.1.5 PVC casing shall conform to ASTM F480 in the schedule or dimension ratio the collapse pressure at the setting depth requires, shall be used only where the state well construction code admits it for the use and depth of the well, and shall not be driven.
7.1.6 The casing wall thickness shall be as indicated in the datasheet.
Steel Casing Wall Thicknessrange
in
0.1880.250.31250.3750.50.6250.75
Derived — the casing diameter, the setting depth, and the drilling method, against the minimum wall thickness AWWA A100 tabulates for steel casing and the collapse and driving loads of the casing program (by default)
7.1.7 Where the casing is driven by a cable tool rig or a casing hammer, the wall thickness shall be not less than the thickness the drilling plan states for the driving loads, and the casing shall be furnished with a drive shoe.

7.2 Casing Joints

7.2.1 Steel casing joints shall be as indicated in the datasheet.
Steel Casing Jointradio
● Full-penetration butt weld
○ Threaded and coupled
NOTE A welded joint is as strong as the casing, adds nothing to the outside diameter, and is the joint of every casing larger than a hand can thread, at the cost of a welder on the rig floor for every joint and a weld that is made in the weather; a threaded and coupled joint is made up in minutes on a small-diameter casing, costs a coupling that enlarges the annulus the grout has to pass, and is the joint a driven casing on a cable tool rig is usually run with. (7.2.2)
7.2.3 Welded casing joints shall be made by a welder qualified under AWWA C206 or the equivalent procedure for the material, as full-penetration butt welds around the full circumference, with the sections aligned by a welding collar or alignment clamp so the string is straight.
7.2.4 Threaded casing joints shall be made up to the coupling manufacturer's torque, with the threads clean and the joint fully engaged.
7.2.5 PVC casing joints shall be of the type the casing manufacturer qualifies under ASTM F480 for the setting depth, and solvent-cemented joints shall not be used in a public water supply well unless the state well construction code admits them.

7.3 Surface and Conductor Casing

7.3.1 Surface casing shall be set where the state well construction code or the well design memorandum requires it, to the depth shown on the well section, and shall be sealed in the annulus between the surface casing and the borehole under the annular seal article of this standard.
7.3.2 Surface casing shall be of a diameter that admits the production casing and the annular width this standard requires between the two.
7.3.3 The disposition of the surface casing after the production casing is set shall be as indicated in the datasheet.
Surface Casing Dispositionradio
○ Left in place, with the annulus between the two casings grouted
○ Withdrawn as the annular seal is placed
NOTE A surface casing left in place is a second steel wall through the unconsolidated upper section and the one the code counts where it requires a cased and grouted interval to a stated depth, at the cost of a double annulus to grout; a withdrawn casing is pulled in stages as the grout rises behind it, so the seal is placed against the formation rather than against a pipe, and it is the position where the surface casing was temporary support for the drilling and the code does not require it to remain. (7.3.4)
7.3.5 A temporary conductor casing set to hold the collar of the hole during drilling shall be withdrawn before the annular seal is completed, or shall be grouted inside and outside as a permanent casing.

7.4 Casing Installation

7.4.1 Casing shall be set plumb and centered in the borehole with centralizers at intervals not exceeding the spacing indicated in the datasheet, with one centralizer within 10 ft of the bottom of each string.
Casing Centralizer Spacingrange
ft
2030406080
Default: Not more than 40 ft
NOTE A centralizer holds the casing off the borehole wall so the grout surrounds it, and a casing that lies against the wall has a seal on one side and a channel on the other; the spacing tightens where the hole is deviated or the casing is light, and it is not applied to a driven casing, which has no annulus to center in. (7.4.2)
7.4.3 The casing string shall be suspended from the rig and held in tension while the annular seal is placed and until the grout has set, and a string that is set on the bottom of the hole shall have the bottom of the hole cleaned to firm material first.
7.4.4 The casing shall extend above the finished grade at the wellhead by not less than the stickup indicated in the datasheet, and above the flood elevation shown on the well plan by the clearance the state well construction code requires.
Casing Stickup Above Finished Graderange
in
1218243648
NOTE Twelve inches is the floor most state codes set, 18 to 24 in. is what a public supply well with a surface discharge head is built to so the head stands clear of the pad, and a taller stickup is set where the well is in a floodplain, where snow lies against the casing, or where the well house floor is raised above the pad. (7.4.5)

8 Annular Seal

8.1 Grout Material

8.1.1 The annulus between the casing and the borehole, and between a surface casing and the production casing, shall be sealed with the grout indicated in the datasheet from the bottom of the sealed interval to the ground surface.
Annular Seal Groutselect
Neat cement grout
Cement-bentonite grout
High-solids bentonite grout
Bentonite chips or pellets
Sand-cement grout
NOTE Neat cement, portland cement per ASTM C150/C150M and water, sets hard, bonds to steel, and is the seal every state admits for every well, at the cost of shrinkage on setting that a bentonite addition is used to offset and of a heat of hydration that softens PVC casing in a deep sealed interval; cement-bentonite, with a few percent bentonite, shrinks less and pumps more easily; a high-solids bentonite grout stays plastic, follows the casing as it moves, does not heat, and is the seal many codes admit for a well outside a public supply and some admit for any well, and it cannot be placed where it will dry or where the formation water is saline enough to flocculate it; chips or pellets are poured dry and hydrate in place, which works in a shallow annulus above the water table and bridges in a deep or wet one; sand-cement grout carries more volume per sack for a large annulus and is admitted by some codes and not others. (8.1.2)
8.1.3 The grout shall be of a material the state well construction code admits for the well use and the sealed interval, and the mix shall be as stated in the approved grout mix design.
8.1.4 Grout placed around PVC casing shall be of a material and placed in a sequence that keeps the heat of hydration below the temperature the casing manufacturer permits for the casing at the setting depth.

8.2 Sealed Depth and Annular Width

8.2.1 The sealed interval shall extend from the ground surface to a depth not less than that indicated in the datasheet, and in no case less than the depth the state well construction code requires for the well use and the formation.
Sealed Depth Below Graderange
ft
201000
Per drawings — the well section (deferred by default)
8.2.2 Where the well is screened in a confined aquifer, the seal shall extend through the confining layer above the screen, and where the well is screened in more than one aquifer, the seal shall extend across every interval between them that the hydrogeologist of record designates, so the well does not connect them.
8.2.3 The annular width between the casing and the borehole wall, through every sealed interval, shall be not less than that indicated in the datasheet.
Annular Width for the Sealrange
in
1.5234
NOTE An inch and a half is the narrowest annulus a tremie pipe passes through and the floor most codes set, 2 in. is the common code figure and the width a coupling on a threaded casing needs, and 3 to 4 in. is set where a grout pipe is to be left in place beside the casing, where the formation caves, or where the code requires it for a public supply well. (8.2.4)

8.3 Grout Placement

8.3.1 The annular seal shall be placed in one continuous operation from the bottom of the sealed interval upward, by the method indicated in the datasheet, until grout of the mix placed returns at the surface.
Annular Seal Placement Methodselect
Tremie pipe in the annulus, withdrawn as the grout rises
Pressure grouting through a grout pipe to the casing shoe
Grouting through the casing with a drillable plug
NOTE A tremie pipe lowered to the bottom of the annulus and kept below the grout surface as it is withdrawn places the seal from the bottom up in any annulus wide enough to pass it, and it is the method on most wells; pressure grouting through a pipe set to the casing shoe pumps the grout up the annulus from the bottom without a pipe in the annulus, which suits a narrow annulus and a deep interval; grouting through the casing displaces the grout out the bottom of the casing and up the annulus, leaves a plug in the casing that is drilled out after the grout sets, and is the method on a deep well where neither pipe can be placed. Pouring grout from the surface is not among them, because grout poured down an annulus bridges, dilutes in the standing water, and leaves voids the surface never sees. (8.3.2)
8.3.3 Grout shall not be poured or dumped into the annulus from the surface, and chips or pellets, where the datasheet admits them, shall be placed in the lifts and at the rate the manufacturer states so they do not bridge.
8.3.4 The volume of grout placed shall be measured and reconciled against the annular volume calculated from the caliper log or the bit diameter, and where the volume placed is less than the calculated volume, the Contractor shall notify the hydrogeologist of record before proceeding.
8.3.5 Where the grout returns at the surface fall back as the grout sets, the annulus shall be topped off with the same grout until it stands at the surface.
8.3.6 Drilling, casing withdrawal, and any other work that disturbs the casing shall not resume until the grout has cured for not less than the period indicated in the datasheet.
Grout Cure Before Work Resumesrange
hours
12244872
NOTE Twenty-four hours is the common code minimum for a cement grout, 72 hours is set where the casing shoe is to be drilled out or the string will be loaded before the grout has full strength, and 12 hours is admitted by some codes where an accelerator is used; a bentonite grout has no set to wait for and is held for the period the code states for it. (8.3.7)
NOTE A grout seal is the one component of a well that cannot be inspected after it is placed and cannot be repaired without abandoning the well, and the volume reconciliation and the returns at the surface are the only two facts that show it reached the bottom of the interval and filled it. (8.3.8)

9 Well Screen

9.1 Screen Type and Material

9.1.1 The well screen shall be of the type indicated in the datasheet.
Well Screen Typeselect
Continuous-slot wire-wound
Louvered (shutter)
Bridge-slot
Machine-slotted pipe
Wire-wrapped on perforated pipe base
NOTE A continuous-slot screen is a wire wound on rods with a slot that is accurate to a thousandth of an inch and an open area that no other type matches, so it passes the most water per foot at the lowest entrance velocity and develops the most completely, at the highest cost per foot and a collapse strength that limits it in a deep or caving hole; a louvered screen is punched from heavy pipe, is strong enough to be driven or set in a deep hole, and is the screen of the filter-packed wells of the arid West, where its lower open area is made up by a long screen in a thick aquifer; a bridge-slot screen is punched and formed from sheet, costs less than wire-wound at an open area between the two, and is set in a filter-packed well of moderate depth; machine-slotted pipe is a casing with slots sawn in it, has the lowest open area, the least accurate slot, and the lowest cost, and is admitted on a low-yield well where the aquifer is coarse enough that the slot is not the limit; a pipe-base screen puts a wire wrap over a perforated pipe, which carries the collapse strength of the pipe with the slot accuracy of the wire, and it is the screen of a deep well in a weak formation. (9.1.2)
9.1.3 The well screen shall be of the material indicated in the datasheet.
Well Screen Materialselect
Stainless steel, Type 304
Stainless steel, Type 316
Low-carbon steel
Galvanized steel
PVC per ASTM F480
9.1.4 Where the groundwater has a chloride content, a dissolved carbon dioxide content, or a hydrogen sulfide content the hydrogeologist of record identifies as corrosive to Type 304 stainless steel, the screen shall be Type 316 stainless steel unless the datasheet indicates a material the hydrogeologist has accepted for the water.
NOTE Type 304 stainless is the screen material of nearly every public supply well, because the screen is the one component that corrodes from both sides and cannot be replaced, and its cost over steel is small against the cost of the well; Type 316 adds molybdenum for a brackish or sulfide water; low-carbon and galvanized steel screens are set in a short-lived or low-value well where the water is not aggressive and the cost of the screen is the deciding number, and they bring the incrustation and the slot enlargement that a steel screen suffers in iron-bearing water; PVC screen is immune to corrosion and is set in a shallow well of small diameter, and it cannot be developed as hard or set as deep as a metal screen. (9.1.5)
9.1.6 A screen of a different material from the casing shall be connected to it through an insulating connection where the groundwater is corrosive, so the two metals do not form a couple in the water.

9.2 Screen Design and Setting

9.2.1 The screen slot size shall be as indicated in the datasheet.
Screen Slot Sizerange
in
0.0060.25
Derived — the sieve analyses of the formation samples from the screened interval and, in a filter-packed well, the filter pack gradation, as stated in the approved screen design submittal (by default)
9.2.2 The screen length, the slot size or sizes by interval, the blank sections, and the setting depth of the screen shall be as stated in the screen design submittal the Engineer of Record has approved, and a screen shall not be ordered against the design values on the drawings.
NOTE The screen design is made after the samples are sieved because the drawings were drawn before the hole was drilled: the slot is chosen to retain the filter pack or, in a naturally developed well, to pass the fine fraction of the aquifer and retain the coarse, and the setting is chosen against the logs so the screen sits in the sand and not in the clay above or below it. A slot chosen from the drawings passes sand for the life of the well or chokes it, and both are repaired only by a new well. (9.2.3)
9.2.4 The screen shall be sized so that the entrance velocity at the design yield, taken as the yield divided by the open area of the screen after allowance for the blockage of the filter pack or the formation, does not exceed the velocity indicated in the datasheet.
Screen Entrance Velocityrange
ft/s
0.050.5
Default: Not more than 0.1 ft/s
NOTE An entrance velocity at or below a tenth of a foot per second keeps the flow through the slot laminar, so the pack and the formation stay where development left them and the incrustation that a turbulent slot accelerates is held back, and it is the figure the well design texts and AWWA M21 are written around; a higher velocity shortens the screen in a thin aquifer at the cost of sand movement and faster plugging, and a lower figure buys a longer screen in a well the Owner expects to run for decades. (9.2.5)
9.2.6 The screen shall be furnished with a closed bottom and a sump below the lowest screen section of not less than the length indicated in the datasheet, closed with a welded plate or a threaded bail plug.
Screen Bottom Sump Lengthrange
ft
5102040
NOTE The sump is where the sand that passes the screen settles instead of accumulating in the screen, and it is also the length the well can be cleaned to before the screen is reached; 5 to 10 ft is the usual allowance on a municipal well, a longer sump is set where the formation is fine and some sand production is expected, and zero is the position where the code sets the total depth or the aquifer bottom is at the screen. (9.2.7)
9.2.8 The screen shall be connected to the production casing as indicated in the datasheet.
Screen Connection to Casingradio
○ Welded or threaded directly to the production casing, pipe-size screen
○ Telescoped through the casing and sealed with a packer
NOTE A pipe-size screen is set as part of the casing string and seals to it at the joint, which is the arrangement of a well drilled to full diameter with the screen in the string; a telescoped screen is lowered through the casing after the casing is set and sealed to it with a lead or neoprene packer at the overlap, which is the arrangement of a cable tool well, of a well whose screen interval was not known until the casing was down, and of a screen that can later be pulled and replaced. (9.2.9)
9.2.10 A telescoped screen shall overlap the casing by not less than the length the screen manufacturer requires for the packer, and the packer shall be expanded and tested for seal before the filter pack is placed.

10 Filter Pack

10.1 Well Completion Type

10.1.1 The well shall be completed as indicated in the datasheet.
Well Completionradio
○ Filter-packed, with a designed gravel pack placed in the annulus around the screen
○ Naturally developed, with the screen set against the formation
NOTE A filter-packed well puts a designed sand or gravel envelope between the screen and the aquifer, so the slot is chosen to hold the pack and the pack is chosen to hold the formation, and it is the completion of a fine, uniform, or layered aquifer and of nearly every large municipal well in unconsolidated sand; a naturally developed well sets the screen against the formation and develops the formation itself into a graded envelope by pulling the fines through the slot, which costs nothing in pack and depends on an aquifer that is coarse and well graded enough to build its own filter. (10.1.2)
10.1.3 Requirements in the articles below apply where a filter-packed completion is selected in the datasheet.

10.2 Filter Pack Material and Gradation

10.2.1 The filter pack shall be clean, washed, well-rounded, siliceous sand or gravel, free of clay, organic matter, limestone, shale, and other soft or soluble grains, and shall be disinfected before placement as AWWA C654 directs.
Filter Pack-to-Formation Ratiorange
ratio of median grain sizes
310
Derived — the sieve analyses of the formation samples in the screened interval and the uniformity of the formation, as stated in the approved screen design submittal (by default)
10.2.3 The uniformity coefficient of the filter pack shall not exceed the value indicated in the datasheet.
Filter Pack Uniformity Coefficientrange
13
Default: Not more than 2.5
NOTE A pack whose median grain is four to six times the formation's holds the formation back while passing the water, a ratio above that lets the formation migrate into the pack and the pack into the screen, and a ratio below it chokes the well; the ratio is pushed to the upper end in a uniform formation and held low in a layered one, and a uniformity coefficient near 2.5 or below keeps the pack from segregating as it is placed and from building a layered envelope of its own. (10.2.4)
10.2.5 The filter pack shall extend from the bottom of the screen to not less than the height above the top of the screen indicated in the datasheet, and a fine sand seal or a bentonite seal shall be placed above it before the annular grout is placed.
Filter Pack Height Above the Screenrange
ft
10203050100
NOTE The pack settles as the well is developed and pumped, and the height above the screen is the reserve that keeps the top of the screen in pack rather than in grout or formation as it does; 20 ft is the usual allowance on a shallow well, 50 ft or more on a deep well where the pack is placed through a long tremie and settles further, and the fill pipe below is what replenishes it. (10.2.6)

10.3 Filter Pack Placement

10.3.1 The filter pack shall be placed as indicated in the datasheet.
Filter Pack Placement Methodradio
● Tremie pipe to the bottom of the annulus, with the fluid circulating
○ Poured from the surface with the fluid circulating
NOTE A tremie places the pack from the bottom up at a rate the operator controls and is the method on a deep well, a narrow annulus, and any well where bridging would leave the screen in open hole; pouring from the surface is admitted by some codes on a shallow well with a wide annulus and a thin fluid, where the grains fall fast enough not to bridge, and it is the method a crew without a tremie reaches for on every well. (10.3.2)
10.3.3 The pack shall be placed at a steady rate that does not bridge in the annulus, with the drilling fluid thinned and circulating so the pack settles through it, and the depth to the top of the pack shall be sounded as it is placed.
10.3.4 The volume of pack placed shall be measured and reconciled against the annular volume calculated from the caliper log or the bit diameter, and where the volume placed differs from the calculated volume by more than the amount the hydrogeologist of record accepts, the Contractor shall notify the hydrogeologist before the fine sand seal is placed.
10.3.5 A filter pack fill pipe shall be furnished as indicated in the datasheet, extending from the top of the pack to the wellhead, capped at the surface, so the pack can be replenished after development and during the life of the well.
Filter Pack Fill Piperadio
○ Furnished
○ Not furnished
NOTE A fill pipe is the only way to add pack after the seal is placed, and a well whose pack has settled below the top of the screen without one admits formation sand at the top of the screen for the rest of its life; it is omitted where the pack reserve above the screen is generous, where the annulus is too narrow for the pipe beside the casing, and where the code requires a grouted annulus that the pipe would penetrate. (10.3.6)
10.3.7 Where the pack settles during development, the Contractor shall add pack through the fill pipe until the top of the pack stands at the height this standard requires above the screen, and shall record the quantity added.

11 Plumbness and Alignment

11.1 Plumbness and alignment shall be tested after the casing and screen are set and the annular seal has cured, and again after development where the hydrogeologist of record directs, by the method indicated in the datasheet, over the depth indicated in the datasheet, before the test pump is installed.
Plumbness and Alignment Test Methodcheckbox
Any of:
☑ Dummy cylinder and plumb line per AWWA A100
☐ Downhole deviation survey, gyroscopic or inclinometer
NOTE The dummy cylinder is a rigid section of pipe a little smaller than the casing, lowered on a line through the full test depth, and the plumb line is read at the surface against a template as it goes; it proves the one thing the pump installer needs, that a rigid body of the pump's diameter passes, and it is the method AWWA A100 describes. A deviation survey measures the inclination and direction of the hole continuously and plots the well in three dimensions, which is the record a deep well with a long line-shaft pump wants, and it does not by itself prove that a dummy passes. (11.2)
11.3 The plumbness and alignment test depth shall be as indicated in the datasheet.
Plumbness and Alignment Test Depthradio
○ To the maximum anticipated pump setting depth plus a margin
○ To the bottom of the production casing
○ To the total depth of the well, including the screen
NOTE The pump is what the test protects, so testing to the setting depth with a margin is enough on a well whose pump will never go deeper; testing to the casing bottom records the full cased section for a pump that is lowered as the water level declines over the years; testing through the screen is set where the screen is pipe-size and a pump or a tool will pass into it. (11.4)
11.5 The well shall be within the plumbness and alignment limits AWWA A100 sets for the casing diameter over the test depth, and the dummy cylinder shall pass freely through the test depth without binding.
11.6 A well that fails the plumbness or alignment test shall be corrected by the Contractor at the Contractor's expense, or shall be abandoned and replaced under this standard at the Contractor's expense, unless the Engineer of Record accepts the well on the hydrogeologist of record's recommendation after the Contractor demonstrates that a dummy of the diameter and length of the permanent pump assembly passes to the setting depth.
NOTE The pump the well is built for is a rigid column several hundred feet long hung from the surface, and a casing that drifts or doglegs binds the column, wears the bearings on one side, and in a submersible well pump holds the motor against the casing where it cannot cool; the test is made before the pump is bought because the alternative is a pump that will not go down. (11.7)

12 Well Development

12.1 Development Methods

12.1.1 After the screen and the filter pack are in place and the annular seal has cured, the Contractor shall develop the well by the mechanical methods permitted in the datasheet, in the sequence the approved development plan states, until the completion criteria of this standard are met.
Mechanical Development Methods Permittedcheckbox
Any of:
☑ Mechanical surging with a surge block
☑ Air-lift pumping and surging
☑ High-velocity horizontal jetting
☑ Overpumping and backwashing
☑ Isolation tool with dual swabs and pumping between them
NOTE A surge block moved up and down in the casing drives water in and out through the screen and is the oldest and the most forceful method, effective in a naturally developed well and capable of locking a filter pack if it is used before the pack has settled; air-lift pumping lifts the water with compressed air and surges it by cutting the air, which develops and cleans the well at the same time and needs a compressor matched to the depth; jetting directs a horizontal water jet through the slots from inside the screen while the well is pumped, and it is the method that reaches the pack and the wall cake behind a continuous-slot screen most completely; overpumping at a rate above the design rate and backwashing by stopping the pump and letting the column fall is the gentlest method and the one every well finishes with; a dual-swab isolation tool pumps one section of screen at a time at a velocity no whole-screen method reaches, which is the method of a long screen whose lower sections never see flow otherwise. The plan sequences the gentle methods first and the forceful ones after the pack has settled. (12.1.2)
12.1.3 Development shall not begin until the annular seal has cured for the period this standard requires, and a surge block shall not be used on a filter-packed well until the pack has been settled by pumping or air-lift and replenished.
12.1.4 The chemical development aids permitted in the datasheet shall be used only where the approved development plan states the chemical, the dose, the contact time, the method of agitation, and the neutralization and disposal of the spent solution, and only after the hydrogeologist of record has released that step.
Chemical Development Aids Permittedcheckbox
Any of:
☐ Polyphosphate or organic dispersant
☐ Acid, muriatic or sulfamic, with inhibitor
☐ Chlorine, as a biocide and dispersant
☐ None
NOTE A dispersant breaks up the clay and the drilling fluid cake left on the formation face and is the chemical nearly every rotary-drilled well is developed with; acid dissolves the carbonate cement and the incrustation in a limestone or an iron-bearing formation and brings the handling, the neutralization, and the state's rules on acid in a well with it; chlorine at a development dose kills the bacteria the drilling introduced and breaks down an organic polymer fluid, and it is counted again at the disinfection, which it does not replace. Selecting none is the position on a cable tool well with no fluid to remove and on a site whose permit admits no chemical in the well. (12.1.5)
12.1.6 Chemical aids shall be certified to NSF/ANSI/CAN 60, and an organic polymer drilling fluid shall be broken down with the breaker the fluid manufacturer specifies before chemical development is counted complete.
12.1.7 Development water shall be discharged through the sediment and erosion controls required by Erosion And Sediment ControlErosion and Sediment ControlResolves to the current adopted revision.sync/erosion-and-sediment-control to the destination indicated in the datasheet for the test pumping discharge, and a chemically treated development water shall be neutralized to the pH range the discharge permit sets before it is discharged.

12.2 Development Completion Criteria

12.2.1 Development shall continue until the sand content of the discharge, measured with a centrifugal sand sampler after not less than 15 minutes of pumping at the design yield, does not exceed the content indicated in the datasheet.
Sand Content at Completion of Developmentrange
ppm by volume
125101520
Default: Not more than 5 ppm by volume
12.2.2 Development shall continue until the turbidity of the discharge, measured at the same time, does not exceed the value indicated in the datasheet.
Turbidity at Completion of Developmentrange
NTU
1251025
12.2.3 Development shall continue until the specific capacity measured at the design yield changes by not more than the percentage indicated in the datasheet between two consecutive development periods of equal duration.
Specific Capacity Stabilization Between Development Periodsrange
%
12510
12.2.4 Development shall continue for not less than the duration indicated in the datasheet, whatever the criteria above show earlier.
Development Durationrange
hours
4816244872120
NOTE Five parts per million of sand at the design rate is the figure the well standards and the pump standards agree on, because it is the content the bronze bearings and the wear rings of a well pump tolerate for decades, and the pump standard reads it from the well record; a lower figure is set where the well feeds a membrane or a meter that sand damages, and a higher one is accepted on an irrigation well with a pump built for it. Turbidity catches the clay and the drilling fluid that a sand sampler does not, specific capacity stabilization is the sign that development has stopped improving the well, and the minimum duration is the floor that keeps a crew from stopping at the first clean sample on a well whose pack has not yet settled; the duration is set by the hydrogeologist against the method and the depth, with 24 to 48 hours the usual figure on a municipal well. (12.2.5)
12.2.6 The hydrogeologist of record shall release the completion of development in writing on the development log, and the Contractor shall not install the test pump until that release is given.
12.2.7 Where the sand content or the turbidity cannot be brought within the criteria, the hydrogeologist of record shall determine whether the cause is the screen, the pack, or the formation, and a well whose sand production results from a slot, a pack, or a placement that departs from the approved screen design submittal shall be corrected or replaced at the Contractor's expense.

13 Test Pumping

13.1 Test Pump and Discharge

13.1.1 The Contractor shall furnish, install, operate, and remove a temporary test pump with its power supply, discharge piping, and controls, capable of pumping continuously at not less than the percentage of the anticipated yield indicated in the datasheet against the pumping water level the hydrogeologist of record projects, with the discharge throttled by a valve at the surface.
Test Pump Capacity Relative to the Anticipated Yieldrange
% of anticipated yield
100125150200
Default: Not less than 150 % of anticipated yield
13.1.3 The test pump shall be set at the depth the hydrogeologist of record directs, below the pumping water level projected at the maximum test rate by a submergence the pump manufacturer requires, and shall be installed with a sounding tube or an open annulus through which the water level can be measured.
13.1.4 The test pump shall not be the permanent pump, and the permanent pump furnished under Vertical Turbine PumpsVertical Turbine PumpsResolves to the current adopted revision.sync/vertical-turbine-pumps shall not be installed until the test pumping is complete and the well record has been issued.
13.1.5 The test discharge shall be conveyed through the sediment and erosion controls required by Erosion And Sediment ControlErosion and Sediment ControlResolves to the current adopted revision.sync/erosion-and-sediment-control to the destination indicated in the datasheet, far enough from the well that the discharge does not recharge the aquifer the well draws from during the test.
Test Pumping Discharge Destinationselect
Storm drainage system through a sediment control device
Land application on the site
Surface water under a discharge permit
Sanitary sewer with the utility owner's written approval
Existing raw water system of the plant
Per drawings — the well plan (deferred by default)
NOTE A storm drain takes the flow where one is within reach and the sediment control is sized for the pump rate; land application needs ground that will take a day or three of the test rate without eroding or ponding back to the well; a surface water discharge needs its own permit, and on a public supply test the chlorinated development water before it needs dechlorination; a sanitary sewer takes a chemically treated discharge the storm system cannot, where the utility agrees to the volume; a plant raw water system takes the water where the well is at the plant and the plant can accept an untreated source during the test. (13.1.6)

13.2 Discharge and Water Level Measurement

13.2.1 The discharge rate shall be measured by the method indicated in the datasheet, read and recorded at every water level reading, and held within the tolerance this standard sets.
Test Discharge Measurement Methodselect
Circular orifice weir
Calibrated flow meter, propeller or magnetic
V-notch weir
Volumetric, by timed filling of a container
NOTE The orifice weir, a plate on the end of a horizontal discharge pipe read with a manometer tube, is the instrument of the well test as it has been run for a century, accurate to a few percent, and cheap, and it needs a full pipe and a level run; a calibrated meter reads directly, totalizes, and logs, and it is the instrument on a test whose data goes to a primacy agency that asks for a calibration certificate; a V-notch weir in an open channel serves a small well and a discharge that runs across the ground; timed filling of a container serves the smallest wells and the field check of any of the others. (13.2.2)
13.2.3 Water levels in the pumped well shall be measured by the methods indicated in the datasheet, referenced to a marked measuring point on the casing whose elevation is surveyed and recorded.
Water Level Measurement in the Pumped Wellcheckbox
☑ Electric water level sounder
☑ Pressure transducer with a data logger
☐ Air line and pressure gauge
☐ Steel tape, chalked
NOTE A transducer in the well logs the level every few seconds through the test and through recovery, which is the data a type-curve analysis of the aquifer wants, and it drifts, so the sounder reads the level by hand on the schedule and checks it; the air line is the instrument of a well whose pump column fills the casing, and the chalked tape is the reference every other method is checked against at the static level. Furnishing both the sounder and the transducer is what a test for a public supply well is run with. (13.2.4)
13.2.5 Water levels shall also be measured, by the same methods and on the same schedule, in the observation wells shown on the well plan, and in every existing well within the distance the hydrogeologist of record designates whose owner permits it.
13.2.6 Water levels and discharge shall be read on a schedule that begins at intervals of one minute or less at the start of each pumping step and of recovery and lengthens logarithmically to intervals not exceeding one hour, as stated in the approved test pumping plan.
13.2.7 The discharge rate during each constant-rate step shall be held within the tolerance of the target rate indicated in the datasheet.
Discharge Rate Tolerance During a Test Steprange
% of the target rate
2510
Default: Not more than 5 % of the target rate
13.2.8 Where the discharge rate leaves the tolerance, or the pump stops, for longer than the period the hydrogeologist of record accepts, the step shall be restarted after the water level has recovered to static, at the Contractor's expense where the interruption was the Contractor's.

13.3 Step-Drawdown Test

13.3.1 Before the constant-rate test, the well shall be pumped in a step-drawdown test of not fewer than the number of steps indicated in the datasheet, each at a constant rate held for not less than the duration indicated in the datasheet, with the rates stepped upward from a fraction of the anticipated yield to a rate above it.
Step-Drawdown Test Stepsrange
36
13.3.2 The duration of each step shall be as indicated in the datasheet.
Step-Drawdown Step Durationrange
hours
1234
NOTE The step test separates the drawdown that belongs to the aquifer from the drawdown that belongs to the well, so the hydrogeologist can set the production rate where the well loss is still small; three steps are the fewest that define the curve, four or five give the fit a check, and the step is run long enough for the level to stabilize at each rate, which is an hour in a transmissive aquifer and longer in a tight one. (13.3.3)
13.3.4 The step rates shall be as stated in the approved test pumping plan, and the final step shall be at or above the rate the constant-rate test is to be run at.
13.3.5 The water level shall be allowed to recover to within the margin of static the hydrogeologist of record accepts between the step-drawdown test and the constant-rate test.

13.4 Constant-Rate Test

13.4.1 The well shall be pumped at the constant rate indicated in the datasheet for not less than the duration indicated in the datasheet, without interruption.
Constant-Rate Test Raterange
gpm
510000
Per drawings — the well design memorandum (deferred by default)
13.4.2 The duration of the constant-rate test shall be as indicated in the datasheet.
Constant-Rate Test Durationrange
hours
81224487296168
Per drawings — the well design memorandum (deferred by default)
NOTE The rate and the duration are the hydrogeologist's: the rate is set against the anticipated yield and the step test, and the duration against the aquifer, the boundaries the hydrogeologist wants the drawdown curve to reach, and the floor the primacy agency sets for a new source, which is a day on most public supply wells and three days where the agency wants to see the well through a boundary or the Owner wants a yield it can rely on in a drought. Neither has a norm a standard can assert. (13.4.3)
13.4.4 The constant-rate test shall not begin until the water level has recovered from the step-drawdown test, and a constant-rate test interrupted for longer than the period the hydrogeologist of record accepts shall be restarted from static.
13.4.5 Where the primacy agency requires the test to be witnessed, the Contractor shall schedule the test so the agency's representative can attend the start and the sampling.

13.5 Recovery Measurement

13.5.1 When the pump is stopped at the end of the constant-rate test, water levels shall be measured on the same logarithmic schedule until the level has recovered to within 5 percent of the measured drawdown, or for not less than the duration indicated in the datasheet, whichever comes first.
Recovery Measurement Durationrange
hours
248122448
NOTE Recovery is the second half of the test and the half that costs nothing to run, because the aquifer recovers on its own schedule and the transmissivity read from the recovery curve checks the one read from the drawdown; a short recovery is set where the aquifer is transmissive and recovers in hours, and a day or two where it is tight and the hydrogeologist wants the full curve. (13.5.2)

13.6 Sand and Water Quality Sampling During the Test

13.6.1 The sand content of the discharge shall be measured with a centrifugal sand sampler at the start of each step, at the start of the constant-rate test, and at intervals not exceeding four hours through the constant-rate test, and shall be recorded with the discharge rate and the water level at each measurement.
13.6.2 Where the sand content during the constant-rate test exceeds the content this standard sets for the completion of development, the hydrogeologist of record shall determine whether the test continues, and the well shall be redeveloped under this standard and retested at the Contractor's expense where the sand results from the screen, the pack, or the development.
13.6.3 Water quality samples shall be collected from the discharge during the final hours of the constant-rate test, by the hydrogeologist of record or by a sampler the laboratory certifies, under chain of custody, and analyzed by a laboratory certified by the state for drinking water analysis for the parameters the primacy agency requires of a new source and for every additional parameter the well design memorandum names.
13.6.4 The water quality results shall be delivered to the hydrogeologist of record and the Engineer of Record before the test pumping report is issued, and a well whose water does not meet the primacy agency's requirements for the use shall be reported to the Owner and the Engineer of Record for a decision on treatment, on an alternative screened interval, or on abandonment.
NOTE The sample is taken at the end of the test because the water that arrives first is the water that sat in the well and the pack, and only after a day of pumping is the discharge the aquifer's own; the list is the agency's because it is the agency that decides whether the well is a source, and the memorandum adds the parameters the plant's treatment is designed around. (13.6.5)

13.7 Test Pumping Report and the Well Record

Test Pumping Report Prepared Byradio
○ The hydrogeologist of record, from the Contractor's field data
○ The Contractor's well driller, reviewed by the hydrogeologist of record
13.7.3 The Contractor shall deliver the as-built well record, with the content the closeout submittals article of this standard lists and the values from the test pumping report, before the well is released for the permanent pump.
13.7.4 The Engineer of Record shall incorporate the well record on the well plan and section, so that the permanent pump furnished under Vertical Turbine PumpsVertical Turbine PumpsResolves to the current adopted revision.sync/vertical-turbine-pumps is selected against the casing inside diameter, set against the pumping water level, and specified against the sand content the well actually produced.
NOTE The well record is the handoff between two trades that never meet on the site: the driller is gone when the pump installer arrives, and the casing diameter, the pumping level, the sand content, and the plumbness result on that one sheet are everything the pump installer knows about the hole the pump is going into. (13.7.5)

14 Disinfection

14.1 Disinfection Procedure

14.1.1 After the test pumping is complete and the test pump has been removed, and again after the permanent pump furnished under Vertical Turbine PumpsVertical Turbine PumpsResolves to the current adopted revision.sync/vertical-turbine-pumps has been set, the well shall be disinfected in accordance with AWWA C654 and the state well construction code, by the Contractor on the first occasion and by the pump installation contractor under this article on the second.
14.1.2 The chlorine for disinfection shall be of the form indicated in the datasheet, certified to NSF/ANSI/CAN 60.
Disinfectant Formradio
○ Calcium hypochlorite, granular or tablet
○ Sodium hypochlorite solution
NOTE Calcium hypochlorite is carried as a dry solid, dissolves in the well as it is placed, and is the form a driller stocks; sodium hypochlorite is a liquid that is mixed at the surface and poured or pumped in a known concentration, which is easier to dose accurately in a large well and degrades in storage, so its strength is checked before it is used. Both forms are what C654 is written for. (14.1.3)
14.1.4 The chlorine shall be introduced so that it reaches every part of the casing, the screen, the filter pack, and the sump, and the well shall be agitated by surging, by recirculating through the pump, or by the method the disinfection plan states, so the solution is distributed through the full water column.
14.1.5 The chlorine dose shall produce a free chlorine residual throughout the water column of not less than the concentration indicated in the datasheet, verified by a field test of the water at the top and the bottom of the column after the solution has been distributed.
Free Chlorine Residual Throughout the Wellrange
mg/L
50100200500
14.1.6 The solution shall remain in the well for not less than the contact time indicated in the datasheet, and not less than the time AWWA C654 and the state well construction code require, with the well capped and the pump, where set, left idle.
Disinfection Contact Timerange
hours
48122448
NOTE Fifty milligrams per liter is the floor C654 sets, 100 to 200 is what most state codes and hydrogeologists specify for a new well, whose pack and formation face consume chlorine that a clean distribution main does not, and a higher dose is set where the development used an organic polymer or the bacteriological samples have failed once; the contact time trades against the dose, with a day the usual figure and a shorter contact admitted at a higher concentration where the code allows it. (14.1.7)
14.1.8 After the contact time, the well shall be pumped to waste until the free chlorine residual of the discharge is at or below the residual the discharge permit and the receiving water allow, and the discharge shall be dechlorinated before it reaches any surface water or storm drain.
14.1.9 Disinfection shall not be counted complete, and bacteriological samples shall not be taken, until the chlorine residual of the discharge has fallen to the background residual of the aquifer, so that the samples are of the water and not of the chlorine.

14.2 Bacteriological Clearance

14.2.1 After the final disinfection and flushing, the number of consecutive bacteriological samples indicated in the datasheet shall be collected from the well discharge at the interval the primacy agency or the state well construction code requires, by a sampler the laboratory certifies, and analyzed by a laboratory certified by the state for total coliform.
Consecutive Bacteriological Samples for Clearancerange
13
NOTE One sample is the release a private well program accepts, two consecutive samples a day apart are what most primacy agencies require of a new public supply source, and three are set where the agency or the Owner wants a clearance that a single borderline result cannot pass. (14.2.2)
14.2.3 Where any sample is positive for coliform, the Contractor shall repeat the disinfection and the sampling at the Contractor's expense until the required consecutive samples are negative, and where the samples remain positive after two repeat disinfections, the hydrogeologist of record shall investigate the cause before a further disinfection is made.
14.2.4 The well shall not be connected to a public water supply system, and a plant well shall not be placed in service, until the bacteriological clearance has been obtained and, for a public supply source, the primacy agency's approval to operate has been issued.

15 Wellhead Completion

15.1 Discharge Arrangement at the Wellhead

15.1.1 The wellhead shall be completed with the discharge arrangement indicated in the datasheet.
Wellhead Discharge Arrangementradio
○ Above-ground discharge through a discharge head or sanitary well seal on the casing top
○ Below-ground discharge through a pitless adapter or pitless unit
NOTE An above-ground discharge puts the discharge head, the sanitary seal, and the first valve on top of the casing inside a well house, where they can be seen and serviced, and it is the arrangement of a line-shaft turbine well and of any well in a building; a pitless adapter or unit carries the discharge out through the casing wall below frost, with the casing sealed to the unit and the cap above grade, and it is the arrangement of a submersible well with no building over it. (15.1.2)
15.1.3 Where a pitless unit or a discharge tee is used, it shall be furnished by the party indicated in the datasheet, shall be rated for the discharge pressure, and shall seal the casing against the entry of surface water and shall be listed or certified for the use where the state well construction code requires it.
Pitless Unit or Discharge Tee Furnished Byradio
○ The well driller, under this standard
○ The pump manufacturer, with the well pump
NOTE The driller installs the pitless unit as part of the wellhead when it is a weld-on unit set into the casing before the pad is poured, which is the usual sequence where the casing is steel and the driller is on the site; the pump manufacturer furnishes it when it is matched to the pump column and the discharge head, which is the position Vertical Turbine PumpsVertical Turbine PumpsResolves to the current adopted revision.sync/vertical-turbine-pumps takes where the drawings assign it there. The field settles which, so the two standards do not both furnish it. (15.1.4)
15.1.5 The pitless adapter or unit shall be set with its discharge connection below Frost DepthFrost DepthParameterEach project supplies its own value.frost-depth, and the excavation for it shall be backfilled under EarthworkEarthworkResolves to the current adopted revision.sync/earthwork after the connection to the raw water main has been made and tested under Water Distribution PipingSite Water Distribution PipingResolves to the current adopted revision.sync/water-distribution-piping.

15.2 Casing Top, Vent, and Sounding Tube

15.2.1 The top of the casing shall be fitted with a watertight, vermin-proof cap or well seal that excludes surface water and insects, and that is secured so it cannot be removed without a tool.
15.2.2 The well shall be vented to the atmosphere through a screened vent on the cap or the discharge head, turned downward, screened with corrosion-resistant 24-mesh screen, with its opening not less than 12 in. above the pad and above the flood elevation the casing stickup is set to.
15.2.3 A sounding tube shall be furnished from the cap or the discharge head to below the lowest anticipated pumping water level, of not less than the nominal size indicated in the datasheet, open at the bottom, capped at the top, and secured to the pump column by the pump installation contractor under Vertical Turbine PumpsVertical Turbine PumpsResolves to the current adopted revision.sync/vertical-turbine-pumps when the pump is set.
Sounding Tube Nominal Sizerange
in
0.7511.251.52
NOTE A three-quarter-inch tube passes an electric sounder probe, a one-inch tube passes most transducers, and a larger tube passes a transducer with its cable and leaves room for a second instrument, at the cost of annulus between the pump column and the casing that a tight well does not have; the tube is the only route to the water level once the pump is in, and the level in the well is the number that tells the Owner the aquifer is declining. (15.2.4)
15.2.5 The wellhead shall be fitted with a gauge port and a sample tap on the discharge, a port for the filter pack fill pipe where one is furnished, and a conduit entry for the pump cable and the level instrument cable, each sealed against surface water.

15.3 Well Pad and Site Finish

15.3.1 A concrete pad shall be placed around the casing at the finished grade, extending from the casing not less than the distance indicated in the datasheet in every direction, not less than 4 in. thick, sloped to drain away from the casing, and cast under Cast In Place ConcreteCast-in-Place ConcreteResolves to the current adopted revision.sync/cast-in-place-concrete.
Well Pad Extent From the Casingrange
ft
23456810
NOTE Two feet is the pad a state code requires around a private well, a 3 to 4 ft pad is the usual finish at a public supply wellhead outside a building, and a larger pad is the floor of a well house or the apron a crane sets up on to pull the pump. (15.3.2)
15.3.3 The pad shall be cast against the casing with the annular seal brought to the underside of the pad, and the joint between the pad and the casing shall be sealed so surface water does not pass it.
15.3.4 The ground surface within the sanitary setback of the well shall be graded to drain away from the well in every direction under EarthworkEarthworkResolves to the current adopted revision.sync/earthwork, and no depression that holds water shall remain within it.
15.3.5 Where the wellhead stands outside a building in an area trafficked by vehicles, it shall be protected by bollards or a barrier shown on the well plan.
15.3.6 A permanent identification plate shall be fixed to the casing or the discharge head stating the well name, the state well identification number, the total depth, the casing diameter, the screen interval, and the date of completion.

16 Protection of the Well During Construction

16.1 The Contractor shall keep the well capped with a watertight cover at all times when work is not in progress in it, from the day the surface casing is set until the permanent pump is installed.
16.2 No fuel, lubricant, drilling fluid additive, chemical, or waste shall be stored within the sanitary setback of the well, and the rig and the support equipment shall be fueled and serviced so that a spill cannot reach the well or the pit.
16.3 Drilling fluid, cuttings, development water, and chemically treated water shall be contained, treated, and disposed of as the drilling plan and the discharge permit state, and shall not be discharged to the ground within the sanitary setback, to a surface water without a permit, or to a storm drain without the sediment control Erosion And Sediment ControlErosion and Sediment ControlResolves to the current adopted revision.sync/erosion-and-sediment-control requires.
16.4 The Contractor shall not introduce into the well any water other than water from a source the hydrogeologist of record has accepted, and water used in drilling, development, or disinfection shall be from a potable supply or be chlorinated before it enters the well.
16.5 Where a spill of fuel or chemical reaches the borehole, the annulus, or the pit, the Contractor shall notify the hydrogeologist of record and the Engineer of Record within one working day, and the well shall not be released until the hydrogeologist of record has determined that the spill has not affected the water.
NOTE A well is a direct path from the surface to the aquifer with no soil between to filter what goes down it, and a well that is contaminated during construction is contaminated for the life of the aquifer it penetrates; a cap, a setback, and a pit that is where the plan says it is are the whole of the protection. (16.6)

17 Abandonment of Test Holes and Failed Wells

17.1 A test hole, a pilot hole not completed as the well, and a well that is not accepted under this standard shall be abandoned by the Contractor in accordance with the state well construction code, by filling the borehole from the bottom up with a grout the code admits for abandonment, with the casing withdrawn or perforated as the code requires so the grout seals against the formation.
17.2 The Contractor shall file the abandonment report the state requires for every hole abandoned and shall deliver a copy with the closeout submittals.
17.3 A test hole shown on the drawings, and a well abandoned because the aquifer at the design depth does not produce the anticipated yield or the water quality the use requires, shall be paid for as drilled and abandoned, and the cost of a replacement well at another location or depth the hydrogeologist of record directs shall be paid as a change.
17.4 A well abandoned because it fails the plumbness or alignment test, because the casing, the seal, the screen, or the filter pack was not constructed as this standard and the approved submittals require, because it produces sand from a departure from the approved screen design, or because the Contractor's construction contaminated it, shall be abandoned and replaced at the Contractor's expense.
17.5 Where the parties disagree whether a well failed because of the aquifer or because of its construction, the Engineer of Record shall make the initial determination on the hydrogeologist of record's recommendation.
NOTE A hole left open after it has failed is the conduit between aquifers and the surface that every other clause in this standard exists to prevent, and the code requires its abandonment for that reason rather than as housekeeping. (17.6)

18 Records

18.1 The driller shall keep a daily log for every day the rig is on the well, recording the depth at the start and end of the day, the formation and the drilling rate by interval, the drilling fluid properties and additions, the water levels observed and the depths at which water was first encountered, the casing set, the grout and pack quantities placed, the samples taken, the equipment downtime and its cause, and the names of the driller and the crew.
18.2 The Contractor shall file the state well completion report within the period the state well construction code sets after the well is completed, and shall deliver the filed copy with the closeout submittals.
18.3 Every depth in the driller's log, the geophysical logs, the video survey, the well record, and the test pumping report shall be referenced to the same measuring point on the casing, whose elevation and height above the ground surface shall be stated on each record.
18.4 The geophysical logs shall be delivered in a digital log format the hydrogeologist of record accepts, and the video surveys in a digital video format, each labeled with the well name, the state well identification number, and the date.
NOTE The state well completion report is the public record of the well, and it is the document the next hydrogeologist on the aquifer, the next driller on the site, and the state well program read when the well is deepened, rehabilitated, or abandoned decades after everyone who built it is gone. (18.5)

19 Delivery, Storage, and Handling

19.1 Casing and screen shall be delivered with the ends capped, stored off the ground on supports that do not bend the sections, and kept free of soil, grease, and debris until they are lowered into the well.
19.2 Screen shall be handled with slings and lifting devices that do not deform the slots or the wire, and a screen section with a damaged slot, a broken weld, or a dented end shall be rejected and not installed.
19.3 Stainless steel casing and screen shall be stored and handled so they do not contact carbon steel, and shall be cleaned of any iron contamination before installation.
19.4 Filter pack shall be delivered in bags or in a clean container, stored where it cannot be contaminated by soil or runoff, and disinfected before placement.

20 Warranty

Well Construction Warranty Periodrange
years
1235
Default: Not less than 1 years
NOTE A one-year period matches the general warranty of the construction contract and covers the first year of pumping, in which a pack that was going to settle has settled and a seal that was going to leak has leaked; a longer period is set where the Owner has had a well fail on earlier work, where the well is deep, or where the Owner wants the sand warranty to run past the first drought summer. (20.2)
20.3 The warranty does not extend to the yield of the aquifer, to a decline in the static or pumping water level, to a change in water quality from a cause outside the well, or to the permanent pump, which is warranted under Vertical Turbine PumpsVertical Turbine PumpsResolves to the current adopted revision.sync/vertical-turbine-pumps.
20.4 Warranty correction shall include the redevelopment, the repair, or the replacement of the well, the removal and reinstallation of the pump where the correction requires it, and the disinfection and bacteriological clearance after the correction, at the Contractor's expense.
20.5 Where the parties disagree whether a sand production or a seal failure is attributable to the well construction or to the aquifer, the hydrogeologist of record shall make the initial determination.

Edit this page

SynC Standards are reference material provided for informational purposes only and as a guide. They are not engineering, architectural, or legal advice and are not a substitute for the judgment of a licensed design professional. It is the responsibility of the user to determine the applicability of any standard to a specific project and to verify all requirements against the governing codes, manufacturer data, and project conditions. SynC does not render professional services and forms no professional relationship by publishing this content. Provided "as is," without warranty of any kind, including fitness for a particular purpose. See our Terms of Use for the complete terms. Moderation log.

This standard is published by SynC and licensed under Creative Commons Attribution-ShareAlike 4.0. You may share and adapt it, including commercially, provided you give credit, link to the license, indicate any changes, and license your adaptations under the same terms. Keep the attribution and notice below with any copy — it includes the warranty disclaimer the license requires you to retain.

Attribution & reuse notice — keep this with any copy:
"Water Supply Wells." SynC Standards. Licensed under CC BY-SA 4.0 (https://creativecommons.org/licenses/by-sa/4.0/). Source: https://synergyinconstruction.com/wiki/sync/water-wells — reference material only; not professional engineering advice and provided without warranty. Verify against governing codes and have a licensed professional review before use.