SynC · SynC Standards

Arc-Flash Hazard Analysis

Rev4
IssuedJun 12, 2026

Revision history

Build a datasheet from this standard Start a project with this standard already attached — one click, no setup.
Use in a project

1 Scope

1.1 This specification covers the engineering analysis required to determine the incident energy exposure and arc-flash boundary at each location in an electrical power system where a worker may interact with energized equipment, and to produce the equipment labels and the supporting documentation required by NFPA 70E and NFPA 70 (NEC).
1.2 The analysis shall be performed using the calculation methodology of IEEE 1584, current edition, supplemented for conditions outside the IEEE 1584 model range by methods identified in NFPA 70E Annex D.
NOTE An arc-flash hazard analysis is not a stand-alone study because incident energy at any bus depends on both the arcing current at that bus (a short-circuit problem) and on the clearing time of the protective device upstream (a coordination problem). (1.3)
1.4 The arc-flash study shall be performed only after the short-circuit study per Short Circuit Study and the protective device coordination study per Protective Coordination Study are complete and the protective device settings are finalized.
1.5 The arc-flash calculation shall not be re-run with assumed device settings and reconciled later, because an arc-flash label is only valid when the device that clears the arc has been set to the values used in the calculation.
NOTE The study deliverable is twofold: a calculation report documenting the system model, input data, methodology, and bus-by-bus results, and a set of physical labels installed on the equipment. (1.6)
1.7 The study shall produce a calculation report that documents the system model, the input data, the methodology, and the results bus-by-bus.
1.8 The study shall produce a set of physical labels installed on the equipment so that a worker about to open a door or remove a cover can read, in front of the equipment, the incident energy at the working distance, the arc-flash boundary, the nominal voltage, and the PPE required to perform the intended task.
1.9 Both the calculation report and the physical labels are required; neither substitutes for the other.
NOTE This standard does not establish the site's electrical safety program; it produces the technical inputs that the safety program relies on. (1.10)
1.11 The Owner remains responsible for adopting NFPA 70E (or an equivalent standard), training qualified workers, establishing energized-work permitting, providing and maintaining PPE, and reviewing the analysis on the schedule required by NFPA 70E.
1.12 Work practices and training shall be coordinated with Electrical Safety Program.
1.14 The arc-flash study shall include every piece of equipment specified by the coordinated equipment standards that is within the analysis voltage threshold.

2 Referenced Standards

2.1 Analysis, labeling, and documentation shall comply with the latest adopted edition of the following standards and codes.
Standard Title
IEEE 1584 Guide for Performing Arc-Flash Hazard Calculations
IEEE 1584.1 Guide for the Specification of Scope and Deliverable Requirements for an Arc-Flash Hazard Calculation Study in Accordance with IEEE Std 1584
NFPA 70 National Electrical Code (Articles 110.16, 130.5, 240.87)
NFPA 70E Standard for Electrical Safety in the Workplace
OSHA 29 CFR 1910.269 Electric Power Generation, Transmission, and Distribution
OSHA 29 CFR 1910.333 Selection and Use of Work Practices
OSHA 29 CFR 1910.335 Safeguards for Personnel Protection
IEEE 551 Recommended Practice for Calculating AC Short-Circuit Currents in Industrial and Commercial Power Systems (Violet Book)
ANSI/IEEE C37.010 Application Guide for AC High-Voltage Circuit Breakers Rated on a Symmetrical Current Basis
ANSI/IEEE C37.13 Low-Voltage AC Power Circuit Breakers Used in Enclosures
IEEE 242 Recommended Practice for Protection and Coordination of Industrial and Commercial Power Systems (Buff Book)
ANSI Z535.4 Product Safety Signs and Labels
UL 969 Marking and Labeling Systems
2.2 Where the contract documents, the adopted edition of NFPA 70, or a referenced standard conflict, the more stringent requirement shall govern unless the Engineer of Record directs otherwise in writing.
NOTE NFPA 70E is the dominant authority for the worker-facing portion of the analysis (PPE, boundaries, labels, work practices), IEEE 1584 is the dominant authority for the calculation methodology, and OSHA 29 CFR Subpart S references both and is the enforceable federal requirement in the United States. (2.3)

3 Submittals

3.1 Action Submittals

3.1.1 Contractor or the Engineer of Record shall submit the following for review prior to performing the analysis, so that disagreements over scope do not surface only after the report is delivered:
  • Qualifications of the analyst, including degree, professional engineering registration, and a record of comparable completed studies
  • Identification of the calculation software, version, and the IEEE 1584 model edition the software implements
  • A scope statement listing every bus, switchboard, panelboard, motor control center, switchgear lineup, transformer, and other equipment to be included, and explicit identification of any equipment excluded from the study with justification
  • A list of source data the analyst will rely on, including utility short-circuit data, equipment nameplates, conductor sizes and lengths, and protective device settings
  • A field-survey plan for any data that must be collected on site
  • A draft single-line diagram showing the level of detail to be modeled, including where the model terminates at downstream branches
  • A proposed label format compliant with NFPA 70E 130.5(H) and any Owner-specific label requirements
  • A schedule milestone for delivery of the calculation report, draft labels, and final labels
Action Submittals Requiredcheckbox
Analyst qualifications and PE registration
Calculation software identification and version
Study scope statement (included / excluded equipment)
Source data list and field-survey plan
Draft single-line diagram for modeling
Proposed label format and content
Delivery schedule

3.2 Closeout Submittals

3.2.1 Contractor shall provide the following at substantial completion, delivered in a form that can be re-opened and edited when the study is updated:
  • Final arc-flash calculation report, sealed by a registered professional engineer
  • Native calculation-software project file (not only a PDF export) so that future updates can be performed without rebuilding the model
  • Final single-line diagram with bus identifiers matching the report and the labels
  • Bus-by-bus results table including bolted-fault current, arcing current, arc duration, working distance, incident energy at the working distance, arc-flash boundary, and the required PPE category or arc-rating
  • A copy of each installed label with its corresponding bus identifier
  • Photographs of installed labels on each piece of equipment
  • A statement of the date of the study, the protective device settings the calculation assumed, and the utility fault current the calculation assumed
Closeout Submittals Requiredcheckbox
Final sealed arc-flash calculation report
Native calculation-software project file
Final single-line diagram with matching bus identifiers
Bus-by-bus results table
Copy of each installed label with bus identifier
Photographs of installed labels
Statement of study date and assumed settings / fault current

4 Quality Assurance

4.1 Analyst Qualifications

Analyst Relationship to Design Teamradio
Engineer of Record performs the study
Independent third-party engineer performs the study
Manufacturer-provided study (subject to independent review)
4.1.1 The arc-flash analysis shall be performed under the responsible charge of a registered professional engineer with documented experience performing arc-flash studies to IEEE 1584.
4.1.2 The analyst shall have completed a minimum of five comparable studies for facilities of similar size and voltage class.
4.1.3 The analyst shall be familiar with both the calculation methodology and the practical realities of field data collection.
NOTE The analyst is not required to be the same engineer who designed the electrical system; an independent analyst brings fresh eyes while the designer of record has the most complete knowledge of the system, and either is acceptable provided the qualifications are met. (4.1.4)
4.1.5 A manufacturer-provided study is acceptable only where the manufacturer also models the upstream utility source and the downstream branches that affect arcing current.
4.1.6 A study limited to the manufacturer's own equipment lineup is not a complete facility study.

4.2 Calculation Software

IEEE 1584 Calculation Editionradio
IEEE 1584-2018 (current edition)
IEEE 1584-2002 with 2004a amendment (legacy)
4.2.1 The analysis shall be performed in a software package that implements the IEEE 1584 calculation method to the edition specified in this standard.
4.2.2 Hand calculations and spreadsheet implementations are not acceptable for a facility study.
NOTE The IEEE 1584-2018 model has more than thirty equations selected and weighted by voltage range and electrode configuration, and propagating an error through a spreadsheet is too easy. (4.2.3)
4.2.4 The 2018 edition shall be used for new studies.
4.2.5 Where an existing site has a 2002-edition study on file, the next periodic review shall convert the study to the 2018 model rather than continuing to update under the superseded edition.
NOTE The 2002 edition's two-equation model has been replaced by a substantially different model that incorporates electrode configuration, enclosure size, and a broader empirical test database, and is identified here only so that a legacy study can be recognized on inspection. (4.2.6)
4.2.7 The 2002 model shall not be the basis of a new analysis.

5 Methodology

5.1 IEEE 1584-2018 Model

NOTE The IEEE 1584-2018 model calculates the arcing current, the arc duration, the incident energy at a working distance, and the arc-flash boundary as a function of bolted-fault current, system voltage, electrode configuration, enclosure dimensions, electrode gap, and working distance. (5.1.1)
NOTE The model is empirical and is valid only within the range of conditions from which it was derived. (5.1.2)
5.1.3 For conditions outside the model range — for example, voltages below 208V, single-phase systems, DC systems, or open-air arcs in configurations not tested — alternative methods from NFPA 70E Annex D shall be applied and identified in the report.
NOTE The voltage range of the 2018 model is 208V to 15kV. (5.1.4)
NOTE The bolted-fault-current range is 500A to 106kA for low-voltage equipment and 200A to 65kA for medium-voltage equipment. (5.1.5)
NOTE The electrode gap range is 6mm to 76mm (0.25 in. to 3 in.) for low voltage and 19mm to 254mm (0.75 in. to 10 in.) for medium voltage. (5.1.6)
5.1.7 The analyst shall confirm that every bus modeled lies within the model's voltage, bolted-fault-current, and electrode-gap ranges.
5.1.8 The analyst shall document the alternative method used for any bus that does not lie within the model's ranges.

5.2 Electrode Configuration

NOTE IEEE 1584-2018 introduced explicit electrode configuration as an input to the calculation. (5.2.1)
NOTE The five configurations and their typical application are: (5.2.2)
Configuration Description Typical Application
VCB Vertical electrodes inside a metal box enclosure Most LV switchgear and switchboards
VCBB Vertical electrodes terminated in an insulating barrier inside a metal box LV equipment with barrier between bus and cable compartment
HCB Horizontal electrodes inside a metal box enclosure Some LV switchgear designs; many MV configurations
VOA Vertical electrodes in open air Open-frame substations, exposed bus, cable terminations in open air
HOA Horizontal electrodes in open air Open-frame substations with horizontal bus
Electrode Configuration Selection Basisradio
Per equipment construction (specific configuration for each bus)
Conservative default (VCBB for all LV, HCB for all MV)
NOTE For identical electrical conditions, electrode configuration alone can change the calculated incident energy by a factor of four or more, and selecting VCBB for every bus inflates incident energy uniformly, masks the equipment where mitigation would pay off, and drives unnecessary PPE category increases. (5.2.3)
5.2.4 The analyst shall select the electrode configuration that matches the actual equipment construction, not the most conservative configuration as a default.
5.2.5 The electrode configuration shall be documented in the bus-by-bus results table.

5.3 Maximum and Minimum Arcing Current

5.3.1 The analysis shall be performed at both the maximum and the minimum arcing current at each bus.
NOTE Maximum arcing current produces the worst-case incident energy when the upstream device trips on its instantaneous element, while minimum arcing current — a 0.85 multiplier for low voltage and 0.96 for medium voltage — is the lower-bound case in which the upstream device may clear on a longer time-delay band and the arc burns longer. (5.3.2)
5.3.3 The reported value at each bus shall be the higher of the maximum-arcing-current and minimum-arcing-current results.
5.3.4 A 2018-edition study that does not show both the maximum and minimum arcing-current values in the bus-by-bus results has not been performed correctly.
NOTE The dual maximum/minimum calculation is a frequent point of error in legacy 2002-edition studies, which used a single arcing-current value. (5.3.5)

5.4 Arc Duration

NOTE Arc duration is the time from arc initiation to the moment the upstream device interrupts the current. (5.4.1)
NOTE It is the dominant variable in incident energy: doubling the duration doubles the incident energy. (5.4.2)
2-Second Maximum Arc Duration Capradio
Apply per IEEE 1584 / NFPA 70E (worker can move away)
Do not apply (use actual device clearing time)
5.4.3 Arc duration shall be determined from the protective device's time-current characteristic at the calculated arcing current, plus the device's interrupting time.
5.4.4 For an instantaneous trip, duration is the relay or trip-unit operate time plus the breaker interrupting time, typically 3 to 5 cycles total for low-voltage power circuit breakers and 5 to 8 cycles for medium-voltage breakers.
5.4.5 For a time-delayed trip, duration is the time read off the upstream device's time-current curve at the arcing current.
5.4.6 Where the upstream device does not clear within 2 seconds, NFPA 70E permits the analysis to assume a 2-second maximum on the basis that a worker can typically move out of the arc-flash zone in 2 seconds.
5.4.7 The analyst shall document any bus where the 2-second cap is applied and shall flag those locations because the cap is a worker-movement assumption, not a device characteristic.
NOTE The 2-second cap is defensible for accessible above-ground equipment in a normal working position, but not for a worker in a pit, in a confined space, on a ladder, or in any other location from which escape in 2 seconds is unlikely. (5.4.8)
5.4.9 The Engineer shall identify any location from which escape in 2 seconds is unlikely during the study and shall override the 2-second cap for those buses.

5.5 Working Distance

NOTE Working distance is the distance from the arc source to the worker's face and chest. (5.5.1)
5.5.2 Incident energy at the working distance is what the label reports and what the PPE shall protect against.
NOTE IEEE 1584 provides typical working distances by equipment class. (5.5.3)
Equipment Class Typical Working Distance
Low-voltage MCC and panelboards 18 in. (455 mm)
Low-voltage switchgear and switchboards 24 in. (610 mm)
Medium-voltage switchgear 36 in. (910 mm)
Cable 18 in. (455 mm)
Working Distance Basisradio
IEEE 1584 typical values by equipment class
Task-specific working distance (justified per task)
5.5.4 A task-specific working distance shorter than the typical value shall be used where the task being performed places the worker closer to the arc source than the typical value assumes.
5.5.5 The label shall report the incident energy at the working distance assumed in the calculation, and that distance shall be stated on the label.

5.6 Modeling Boundary

Downstream Modeling Limitselect
Every branch-circuit panelboard
Every MCC bucket and motor disconnect
Every distribution panelboard 100A and above
Every piece of equipment 240V and above
Project-specific (see scope statement)
5.6.1 The model shall extend from the utility source down to the lowest level of distribution at which workers will perform energized tasks.
5.6.2 Equipment below the modeling boundary may be analyzed by inference from its upstream device, provided the inference is documented and the worker-facing label is conservative.
5.6.3 The Engineer shall set the downstream limit consistent with the work that will actually be performed energized.
5.6.4 Where a class of equipment will never be opened energized, that equipment shall instead be labeled with a generic warning and an instruction to de-energize before opening.

5.7 Equipment Below 240V

5.7.1 The analyst shall model buses below 240V by the 2018 method, because the 2018 edition deprecated the 2002 edition's exemption for equipment below 240V served by transformers smaller than 125kVA and recognizes that arcs can sustain at 208V given sufficient available current.
5.7.2 Where the calculated incident energy is low enough that the equipment does not need a hazard label, the equipment shall still be modeled in the report and the low-energy result documented.
5.7.3 The report shall not assert that equipment below 240V is exempt.

6 Input Data Requirements

6.1 Upstream of the Service

Utility Source Fault Current Dataselect
Utility-provided three-phase and single-line-to-ground available fault current at the service
Utility-provided infinite-bus equivalent (with documented system X/R)
Assumed value pending utility confirmation
6.1.1 Utility fault current shall be obtained in writing from the serving utility.
6.1.2 An assumed value is acceptable for a preliminary study only and shall be reconciled before the labels are produced.
6.1.3 The utility data shall include both the maximum available fault current and, where the utility can provide it, a minimum available fault current corresponding to a single-source contingency on the utility side, which drives the minimum-arcing-current case.

6.2 Equipment Data

6.2.1 The analyst shall collect, for every piece of modeled equipment, the data required by the IEEE 1584 model:
  • Nominal voltage and configuration (3-phase 3-wire, 3-phase 4-wire)
  • Frame size and short-circuit current rating
  • Enclosure dimensions (height, width, depth) where the equipment is enclosed
  • Bus gap (electrode spacing) per the manufacturer's published data
  • Electrode configuration (per the table above)
  • Conductor size, type, and length from the upstream source
  • Transformer kVA, impedance, and connection where transformers are within the model
Equipment Data Collection Methodradio
Field survey by the analyst
Owner-provided equipment list (verified by spot-check field survey)
Manufacturer shop drawings (new construction)
6.2.2 Enclosure dimensions and bus gap, new requirements introduced by the 2018 edition, shall be obtained from the equipment manufacturer's published data or, where the equipment is in service and not documented, from physical measurement of representative units.
NOTE For new construction, manufacturer shop drawings are the authoritative source. (6.2.3)
NOTE For an existing facility, a field survey by the analyst is the safest approach because nameplate ratings and as-installed configurations frequently diverge from the original record drawings. (6.2.4)

6.3 Protective Device Settings

Protective Device Setting Verificationradio
Field-verified settings (every device in the model)
Coordination-study settings (assumed installed correctly)
6.3.1 Protective device settings shall be the as-set values from the coordination study, confirmed by field verification.
6.3.2 The arc-flash analyst shall not assume settings or take settings from a design submittal that has not been confirmed in the field.
6.3.3 Where the field verification finds a device set differently than the coordination study assumed, the discrepancy shall be resolved — either by adjusting the device to the studied setting or by re-running the arc-flash calculation with the as-found setting — before labels are produced.

7 Maintenance Mode Analysis

7.1 Energy Reduction Methods

NOTE NFPA 70 Article 240.87 requires that any circuit breaker rated 1200A or more, or any breaker with a continuous current setting of 1200A or more, employ one of the following methods to reduce arcing duration: (7.1.1)
  • Zone-selective interlocking (ZSI)
  • Differential relaying
  • Energy-reducing maintenance switching (ERMS, also called arc-reduction maintenance switch or ARMS) with a local status indicator
  • Energy-reducing active arc-flash mitigation system
  • An instantaneous trip setting less than the available arcing current
  • An instantaneous override setting less than the available arcing current
  • An approved equivalent means
Arc Energy Reduction Method Applied to 1200A+ Breakersselect
Zone-selective interlocking (ZSI)
Differential relaying (87)
Energy-reducing maintenance switching (ERMS)
Energy-reducing active arc-flash mitigation system
Instantaneous trip setting below available arcing current
Approved equivalent
ERMS Reporting on Labelradio
Show both normal and maintenance-mode incident energy
Show maintenance-mode value only (ERMS required to interact)
Show normal-mode value only (ERMS not provided)
7.1.2 Where ERMS is employed, the device has two distinct states with different incident energy, and the analysis shall calculate and report the incident energy in both the normal-operation and maintenance-mode states.
7.1.3 The label shall show the incident energy in both states or, where the equipment is wired to require ERMS engagement before doors can be opened, shall show only the maintenance-mode value with a notation that the equipment requires ERMS engagement prior to interaction.
NOTE ZSI operates continuously and does not have a worker-engaged state in the same way ERMS does, but a ZSI scheme that has been disabled or whose interlock signal has been disconnected provides no benefit. (7.1.4)
7.1.5 The analysis shall confirm that ZSI is in fact active in the as-installed wiring.
7.1.6 The arc-flash report shall identify ZSI buses and recommend periodic functional verification of the interlock.

7.2 Other Operating States

7.2.1 The analysis shall consider operating states that affect available fault current and clearing time:
  • Alternate-source operation (generator running, normal source unavailable)
  • Tie-breaker closed on multi-source systems
  • Bypass operation of a UPS or static switch
  • Maintenance bypass of a paralleling switchgear
Alternate Operating States Analyzedcheckbox
Normal utility source
Standby generator (utility unavailable)
Multi-source with tie closed
UPS bypass
Maintenance bypass / paralleling switchgear
7.2.2 The reported incident energy at each bus shall be the worst-case value across all credible operating states.
7.2.3 Where a state produces a higher incident energy only briefly during a transfer, the analyst shall document the state and may exclude it if it is not a state in which workers will perform energized tasks.

8 Equipment Labeling Requirements

8.1 Required Label Content

Label Methodradio
Incident energy analysis method (engineered values)
PPE category method (NFPA 70E task tables)
Minimum Label Contentcheckbox
Nominal system voltage
Arc-flash boundary (distance)
Available incident energy (cal/cm²)
Working distance for the reported incident energy
Minimum arc rating of required PPE (cal/cm²)
Site-specific PPE description
Equipment identifier matching the single-line diagram
Date of the study
Engineer's seal or study report reference
8.1.1 Per NFPA 70E 130.5(H), each piece of equipment within the scope of the study shall be field-marked with a label containing, at a minimum, the nominal system voltage, the arc-flash boundary, and at least one of the following: available incident energy and corresponding working distance, minimum arc rating of clothing, site-specific level of PPE, or hazard/risk category from the NFPA 70E task tables.
NOTE This standard requires the incident-energy method for all labels, because a site that has performed the engineering study should report its actual results rather than the PPE-category tabular shortcut. (8.1.2)
8.1.3 The label shall use one selection method consistently, because the 2024 edition of NFPA 70E explicitly prohibits showing both an incident-energy value and a PPE category from the task tables on the same label.

8.2 Label Format and Hazard Word

8.2.1 The hazard signal word on the label shall be selected per ANSI Z535.4 and NFPA 70E based on the incident energy:
Incident Energy Signal Word
Up to 1.2 cal/cm² CAUTION (no PPE required for typical tasks; verify the no-hazard task assumption)
1.2 to 40 cal/cm² WARNING
Greater than 40 cal/cm² DANGER — no safe PPE available; equipment shall not be worked energized
Label Signal Word Applicationradio
Per ANSI Z535.4 / incident-energy thresholds above
Uniform WARNING on all labels (legacy practice)
8.2.2 Buses with incident energy above 40 cal/cm² shall be labeled DANGER with a notation that no commercially available PPE provides reliable protection at that energy level.
8.2.3 The Owner shall identify the buses with incident energy above 40 cal/cm² in the electrical safety program and shall require de-energization before any work is performed.

8.3 Label Construction

Label Materialselect
Polyester with adhesive backing (indoor, conditioned space)
Vinyl with UV-resistant overlaminate (indoor industrial / unconditioned)
Engraved phenolic plate, mechanically fastened (outdoor / harsh environment)
Stainless steel with engraved or etched lettering (outdoor / corrosive)
Label Mounting Methodradio
Adhesive on cleaned, dry equipment surface
Mechanical fasteners (screws or rivets)
Magnetic mount (movable equipment only)
8.3.1 A label in a humid mechanical room, an outdoor switchyard, a chemical-process area, or a high-temperature switchgear room shall be of sufficient durability for that environment per the 2024 edition of NFPA 70E, and shall not fade, peel, or become unreadable within the periodic review interval.
NOTE Adhesive-backed labels in unconditioned spaces commonly fail within five years from heat cycling and ultraviolet exposure. (8.3.2)
8.3.3 For outdoor switchyards, generator yards, and rooftop equipment, an engraved phenolic plate or stainless-steel label mechanically fastened to the equipment shall be specified.

8.4 Label Location

Label Granularityselect
Per equipment lineup only
Per section (vertical section of switchgear, column of MCC)
Per individual device (each breaker, each bucket)
8.4.1 Labels shall be installed on each piece of equipment in a location where they are visible to a worker before that worker opens, racks, or otherwise interacts with the equipment energized.
8.4.2 For lineup equipment such as switchgear and motor control centers, a label shall be applied to each section, each individually drawable breaker, and each MCC bucket — not only to the equipment as a whole.
NOTE Per-section labeling is the practical compromise for most installations and is the basis for the cost and label-count estimates in the study. (8.4.3)
8.4.4 Per-device labeling shall be specified at the start of the project where it is required by the Owner's safety program, because retrofitting per-device labels after a per-section study approximately doubles the label count.
8.4.5 The label location on each piece of equipment shall be repeatable and shall not be obscured by handles, hinges, latches, or routine maintenance hardware.
8.4.6 Where the equipment door swings outward, the label shall be on the door at the worker's eye level; where the worker approaches the equipment from the side, the label shall be on the side panel.
8.4.7 Label placement details shall be provided on representative equipment types — switchgear section, MCC column, panelboard cover, transformer enclosure. Label placement details on representative equipment types — switchgear section, MCC column, panelboard cover, transformer enclosure

9 Deliverables

9.1 The deliverable set for the arc-flash study comprises three artifacts that shall be consistent with each other in every value.

9.2 Calculation Report

9.2.1 The report shall include, at minimum:
  • Executive summary identifying the highest-incident-energy buses and the buses where incident energy exceeds 40 cal/cm²
  • System description with single-line diagram, bus identifiers, and the modeling boundary
  • Utility data source and date
  • Equipment data sources (field survey, manufacturer data, shop drawings)
  • Protective device settings table with the source of each setting (coordination study, field-verified, etc.)
  • Methodology statement identifying the IEEE 1584 edition, electrode configurations applied, working distances used, and any departures from the standard methodology
  • Bus-by-bus results table with bolted-fault current, arcing current (both max and min cases), arc duration, working distance, incident energy at the working distance, arc-flash boundary, label signal word, and required PPE
  • Mitigation recommendations for any bus where reasonable design changes could lower the incident energy meaningfully
  • Statement of assumptions and the conditions under which the study shall be reviewed or re-run
  • Engineer's seal and signature

9.3 Labels

9.3.1 The physical labels shall match the report values exactly.
9.3.2 A discrepancy between the report and a label is a finding against the study and shall be corrected before closeout.

9.4 Single-Line Diagram

9.4.1 The single-line diagram delivered with the study shall identify every modeled bus by the same identifier used on the labels and in the report.
9.4.2 The single-line diagram shall be maintained as a controlled document for the life of the facility and shall be updated whenever the study is updated.

10 Worker Training Coordination

Owner Training Coordinationcheckbox
Worker training on label interpretation
Energized-work permitting procedure references study
PPE inventory matched to study results
Periodic-review schedule established
NOTE The arc-flash study is an input to the Owner's electrical safety program, not a substitute for it. (10.1)
10.2 NFPA 70E requires that workers who perform tasks on or near energized equipment be trained as qualified persons, that they be familiar with the labels installed on equipment they will interact with, and that they be retrained at intervals not exceeding three years.
10.3 The Contractor's responsibility under this standard ends at the delivery of the labels and the report.
10.4 The Owner is responsible for incorporating the study results into worker training, energized-work permitting, PPE selection, and the periodic-review schedule.
10.5 The study shall identify, in its mitigation recommendations, any task-specific PPE that requires specification of a particular arc-rating beyond commodity electrical PPE.
10.6 The Owner shall procure any task-specific PPE identified by the study before workers are permitted to perform the affected tasks.

11 Re-Study Triggers

NOTE NFPA 70E 130.5(G) requires that the arc-flash risk assessment be reviewed periodically at intervals not exceeding five years, and reviewed whenever changes occur that could affect the analysis. (11.1)
Conditions Triggering Re-Study Before the Five-Year Intervalcheckbox
Utility available fault current change (notified by utility)
Service or main equipment replacement or upgrade
Protective device settings change (any device in the model)
Protective device replacement (new make or model)
Addition of significant new load (motors, transformers, generation)
Addition or removal of on-site generation
Configuration change (tie operation, bypass routing)
Discovery of a field condition inconsistent with the modeled assumptions
Periodic Review Intervalselect
5 years (NFPA 70E maximum)
3 years (conservative)
Annual (high-change facilities)
11.2 The Owner shall maintain a record of the study date on every label and shall track the next review date in the facility records.
11.3 A review at the five-year interval is not necessarily a full recalculation; the reviewer shall confirm that none of the re-study trigger conditions has changed since the prior study.
11.4 Where any re-study trigger condition has changed, the affected portion of the study shall be re-run and new labels produced for the affected buses.
11.5 As part of the five-year review, the Owner shall request updated available fault current data from the serving utility and compare it to the value used in the study.
11.6 Any material increase in utility available fault current requires re-running the study.
NOTE Utility fault current change is the trigger most commonly missed, because utilities increase available fault current as they reinforce their distribution system and the increase is not always communicated to the customer. (11.7)
11.8 The Owner's maintenance procedures shall include notification of the responsible engineer when a protective device in the arc-flash model is replaced.
NOTE A protective device replacement is the second commonly missed trigger, because a breaker replaced with one of different manufacture or trip-unit family may have substantially different clearing characteristics. (11.9)
NOTE A 5-year interval is the NFPA 70E maximum and is appropriate for stable facilities with documented change-management procedures, while a shorter interval is appropriate where the facility undergoes frequent reconfiguration or change-management procedures do not reliably capture electrical-system modifications. (11.10)

12 Mitigation Hierarchy

12.1 The study report shall identify mitigation options for buses with incident energy that would require Category 3 (25 cal/cm²) or higher PPE, or that exceed 40 cal/cm².
12.2 Mitigation shall be evaluated in the following order, which corresponds to the hierarchy of controls in NFPA 70E and reflects effectiveness from most to least:
  1. Eliminate the need to work on the equipment energized (de-energize, lock out, verify)
  2. Substitute the equipment for a design with lower arcing characteristics (arc-resistant switchgear, current-limiting fuses upstream)
  3. Engineer the protective system for faster clearing (faster instantaneous, ZSI, ERMS, differential)
  4. Administrative controls (restrict tasks, increase working distance, require remote operation)
  5. PPE (last line of defense)
Mitigation Recommendations Provided In Reportradio
For every bus exceeding 8 cal/cm²
For every bus exceeding 25 cal/cm²
For every bus exceeding 40 cal/cm² only
12.3 The report shall present mitigation as engineering recommendations, not as design changes.
12.4 The Owner and Engineer of Record shall decide which recommendations to implement; the analyst's role is to identify the options and the order-of-magnitude reduction each would achieve.
12.5 Where a mitigation recommendation is adopted, the affected portion of the study shall be re-run with the changed conditions and new labels produced.

13 Field Verification

13.1 Before the labels are released for installation, the Contractor shall verify that the field conditions match the study assumptions.
13.2 The verification shall include, at minimum:
  • Protective device settings read at each device in the model and compared to the report's setting table
  • Available fault current at the service compared to the utility data used in the study
  • Equipment identifiers on the equipment match the identifiers used in the report
  • Any ERMS or similar maintenance-mode switches are functional and wired as the report assumes
  • Any ZSI interlock signals are continuous through every device in the scheme
Pre-Installation Verificationcheckbox
Protective device settings verified at every device
Utility fault current re-confirmed at study delivery
Equipment identifier reconciliation
ERMS functional verification
ZSI continuity verification
13.3 Any discrepancy found during verification shall be resolved before labels are installed.
NOTE Installing a label that does not match the as-installed condition is worse than no label at all, because it creates a false sense of protection. (13.4)

14 Delivery, Storage, and Handling

14.1 The calculation report, the native software project file, and the photographic record of installed labels shall be delivered to the Owner in both printed and electronic form.
14.2 The electronic form shall be on durable media or in a managed document repository that the Owner controls.
14.3 Reliance on a contractor's cloud storage account for the only copy of the study is not acceptable; the Owner shall be able to retrieve and edit the study without contacting the original analyst.
14.4 Spare labels — at least one duplicate of each installed label — shall be delivered to the Owner for replacement of labels damaged in service.
14.5 Spare labels shall be stored in the main electrical room or in another location identified in the closeout documentation.

15 Warranty

Analyst Warranty Periodselect
1 year from report issue
Through the project warranty period
Through the first periodic review
15.1 The analyst shall warrant the analysis for accuracy at the time of issue, against the input data provided and the standards in force.
15.2 The analyst is not responsible for changes in field conditions, utility fault current, or protective device settings that occur after the study is issued; those are the Owner's responsibility under the periodic-review program.
15.3 The Contractor shall warrant the physical installation of the labels — adhesion, location, and correspondence between label content and the report — for the project warranty period.
15.4 Labels that detach, fade, or are found to disagree with the report during the warranty period shall be replaced at no cost to the Owner.

Edit this page

SynC Standards are reference material provided for informational purposes only and as a guide. They are not engineering, architectural, or legal advice and are not a substitute for the judgment of a licensed design professional. It is the responsibility of the user to determine the applicability of any standard to a specific project and to verify all requirements against the governing codes, manufacturer data, and project conditions. SynC does not render professional services and forms no professional relationship by publishing this content. Provided "as is," without warranty of any kind, including fitness for a particular purpose. See our Terms of Use for the complete terms.

This standard is published by SynC and licensed under Creative Commons Attribution-ShareAlike 4.0. You may share and adapt it, including commercially, provided you give credit, link to the license, indicate any changes, and license your adaptations under the same terms. Keep the attribution and notice below with any copy — it includes the warranty disclaimer the license requires you to retain.

Attribution & reuse notice — keep this with any copy:
"Arc-Flash Hazard Analysis." SynC Standards. Licensed under CC BY-SA 4.0 (https://creativecommons.org/licenses/by-sa/4.0/). Source: https://synergyinconstruction.com/wiki/sync/arc-flash-study — reference material only; not professional engineering advice and provided without warranty. Verify against governing codes and have a licensed professional review before use.