SynC · SynC Standards

Protective Device Coordination Study

Rev3
IssuedJun 8, 2026

Revision history

Build a datasheet from this standard Start a project with this standard already attached — one click, no setup.
Use in a project

1 Scope

NOTE This specification covers the preparation, documentation, and acceptance of a protective device coordination study for the project's electrical distribution system. (1.1)
1.2 The study shall demonstrate, by time-current curve analysis, that the overcurrent protective devices installed in the system operate selectively over the full range of available fault currents and overload conditions.
1.3 Selective operation means the device immediately upstream of a fault opens first and the remainder of the system stays energized.
NOTE A coordination study is the middle study in a three-study sequence: the short-circuit study establishes available fault current at every bus, the coordination study uses those values to set protective devices selectively, and the arc-flash study then calculates incident energy at those settings. (1.4)
1.5 The Contractor shall not begin the coordination study until the short-circuit study is complete and accepted. See Short Circuit Study.
1.6 The Contractor shall not begin the arc-flash study until the coordination study is complete and accepted. See Arc Flash Study.
1.7 This standard shall apply from the project's point of common coupling with the serving utility through every downstream overcurrent protective device on the project, including service equipment, distribution switchgear and switchboards, panelboards, motor control centers, dry-type and pad-mount transformers serving the project, on-site generators and uninterruptible power supplies, and the protective devices ahead of utilization equipment where required for selective coordination.
1.8 Coordination with the utility's protective devices shall be included only to the extent that the utility's settings are available and that coordination at the service entrance is required by the project documents or by the utility.
NOTE This standard does not cover the design of the protective relaying scheme; the selection of relay functions, the choice of CT ratios, and the architecture of differential and pilot schemes are engineered upstream of the study by the Engineer of Record. (1.9)
1.10 The study shall use the as-designed protective relaying scheme and produce settings for it.

2 Referenced Standards

2.1 Equipment, calculations, and study methodology shall comply with the latest adopted edition of the following standards and codes.
2.2 Where the contract documents, the adopted building code, or a referenced standard conflict, the more stringent requirement shall govern unless the Engineer of Record directs otherwise in writing.

2.3 Applicable Standards and Codes

Standard Title
NFPA 70 National Electrical Code (Articles 240, 430, 450, 517, 695, 700, 701, 702, 708)
NFPA 70E Standard for Electrical Safety in the Workplace
NFPA 110 Standard for Emergency and Standby Power Systems
IEEE 242 Recommended Practice for Protection and Coordination of Industrial and Commercial Power Systems (Buff Book)
IEEE 399 Recommended Practice for Industrial and Commercial Power Systems Analysis (Brown Book)
IEEE 551 Recommended Practice for Calculating Short-Circuit Currents in Industrial and Commercial Power Systems (Violet Book)
IEEE 1015 Recommended Practice for Applying Low-Voltage Circuit Breakers Used in Industrial and Commercial Power Systems (Blue Book)
IEEE C37.13 Low-Voltage AC Power Circuit Breakers Used in Enclosures
IEEE C37.90 Relays and Relay Systems Associated with Electric Power Apparatus
IEEE C37.91 Guide for Protecting Power Transformers
IEEE C37.96 Guide for AC Motor Protection
IEEE C57.12.00 General Requirements for Liquid-Immersed Distribution, Power, and Regulating Transformers
IEEE C57.109 Guide for Liquid-Immersed Transformers Through-Fault-Current Duration
IEEE C57.12.59 Guide for Dry-Type Transformer Through-Fault Current Duration
ICEA P-32-382 Short-Circuit Characteristics of Insulated Cable
ICEA P-45-482 Short-Circuit Performance of Metallic Shields and Sheaths on Insulated Cable
ANSI/NETA ATS Acceptance Testing Specifications for Electrical Power Equipment and Systems
ANSI/NETA ETT Standard for Certification of Electrical Testing Technicians
UL 489 Molded-Case Circuit Breakers, Molded-Case Switches, and Circuit-Breaker Enclosures
UL 1066 Low-Voltage AC and DC Power Circuit Breakers Used in Enclosures

3 Submittals

3.1 Action Submittals

3.1.1 Contractor shall submit the following for the Engineer's review and acceptance:
  • Study report, sealed by a Professional Engineer licensed in the project jurisdiction, organized as described in Deliverables below
  • Software model file used to produce the study, in the native format of the software identified in the study, available to the Engineer of Record on request
  • Time-current curve (TCC) plots covering every coordination pair in the system, in PDF and in the source format of the study software
  • A consolidated settings table listing every adjustable device, every adjustment, the recommended setting, and any field-set or factory-set status
  • A list of any coordination compromises required by the system and the basis for accepting each compromise
  • A list of any equipment changes (frame size changes, fuse class changes, trip-unit replacements) required to achieve coordination, with cost and schedule impact identified
Action Submittals Requiredcheckbox
PE-sealed study report
Software model file (native format)
TCC plots (PDF + source)
Consolidated device settings table
List of coordination compromises with justifications
List of required equipment changes
Settings sheets formatted for relay technicians
3.1.2 Field commissioning of relay and breaker settings shall not proceed until the coordination study is accepted in writing.

3.2 Closeout Submittals

3.2.1 Contractor shall provide the following at substantial completion, after field commissioning of the protective devices:
  • As-set settings table, recording the actual setting applied to each device in the field, signed by the commissioning technician
  • Settings verification test reports per Electrical Acceptance Testing showing that each adjustable device trips at its recommended pickup and within the recommended time delay
  • An updated TCC plot package reflecting any settings deviations made during commissioning, with each deviation justified
  • A written re-study trigger list (see Re-Study Triggers below) issued to the Owner for inclusion in the facility's electrical operating procedures
Closeout Submittals Requiredcheckbox
As-set settings table signed by commissioning technician
Settings verification test reports
Updated TCC plot package with justified deviations
Written re-study trigger list issued to Owner

4 Quality Assurance

4.1 Engineer of Record for the Study

4.1.1 The coordination study shall be performed by, or under the direct supervision of, a Professional Engineer licensed in the project jurisdiction and experienced in the protection and coordination of power systems of the type, voltage, and size of the project's system.
4.1.2 The study report shall bear the seal and original signature of that engineer.

4.1.3 Study Engineer Qualification

Study Engineer Qualificationselect
PE licensed in project jurisdiction, electrical discipline
PE plus NETA Level III or IV technician oversight
PE plus NICET Level III or IV electrical power testing certification

4.2 Study Software

4.2.1 The study shall be performed in commercial power-systems analysis software that maintains a current library of low-voltage breaker trip curves, fuse curves, relay characteristics, and motor data, and that produces TCC plots on logarithmic axes.
4.2.2 Hand-drawn or general-purpose-plotting-software TCC curves shall not be acceptable for the action submittal because they cannot be verified against published device characteristics.
4.2.3 The software's device library shall be at a release current within twelve months of the study date.
4.2.4 The study report shall identify the software name, version, and device-library revision so that the model can be reopened and re-evaluated during the system's life.

4.2.5 Study Software Selection

Study Softwareselect
Commercial power-systems analysis software with maintained device library
Owner-specified software (project-specific)

4.3 Independence

4.3.1 Where the contract documents specify an independent coordination study, the study engineer shall not be employed by, contracted to, or financially associated with the manufacturer of the protective devices being studied.

4.3.3 Study Independence Selection

Study Independenceradio
Independent — engineer not affiliated with equipment manufacturer
Manufacturer-performed — included with equipment supply

5 Coordination Criteria

NOTE The coordination criteria are the rules the study uses to decide whether two devices in series coordinate. (5.1)
5.2 These criteria shall be stated in the study report so that the basis for every conclusion is auditable.

5.3 Coordination Time Interval

NOTE Selective coordination is demonstrated by maintaining a minimum time interval between the operating curve of any downstream device and the operating curve of any upstream device, over the range of fault currents at which both devices respond. (5.3.1)
5.3.2 The minimum coordination time interval (CTI) shall account for the upstream device's breaker interrupting time, the downstream device's overshoot or memory error, and a safety margin.

5.3.3 CTI Setpoints

Minimum CTI — Electromechanical Relays Upstreamrange
seconds
0.250.5
0.30.350.40.5
Default: 0.4 seconds
Minimum CTI — Microprocessor (Static) Relays Upstreamrange
seconds
0.150.4
0.20.250.30.4
Default: 0.3 seconds
Minimum CTI — Low-Voltage Breaker to Low-Voltage Breakerrange
seconds
0.060.3
0.10.150.20.3
Default: 0.1 seconds
NOTE The IEEE 242 guidance is that electromechanical relays require approximately 0.3 to 0.4 seconds between curves, and microprocessor relays require approximately 0.2 to 0.3 seconds; low-voltage power circuit breakers with short-time delay coordinate on a tighter interval because their internal clocks are deterministic. (5.3.4)
5.3.5 The CTI shall be measured at the minimum point of separation between curves, not over the full curve length.
5.3.6 Brief intersections at currents that are not credible at the bus in question shall not be treated as coordination failures, but shall be identified in the study report as discussed in [Coordination Compromises](#coordination-compromises) below.

5.4 Selectivity Type

Selectivity Requirement — General Distributionradio
Full selective coordination at all fault currents up to the available short-circuit current
Partial selectivity — selective up to the published manufacturer let-through value
Time-based selectivity only — selective above the instantaneous knee
NOTE Full selective coordination ensures that the downstream device clears every fault, including bolted faults, before the upstream device unlatches. (5.4.1)
5.4.2 Partial selectivity shall be acceptable for general distribution only where the Engineer documents the consequence of a non-selective trip at the bus in question.
5.4.3 Time-based selectivity, in which devices coordinate only above the upstream device's instantaneous pickup, shall be acceptable only where the downstream device's instantaneous region does not overlap any current the downstream device will see in service.
5.4.4 For the emergency and legally required standby branches addressed in [Selective Coordination for Life Safety](#selective-coordination-for-life-safety) below, full selective coordination is required by code and shall not be reduced.

5.5 Instantaneous Override and Energy Reduction

5.5.1 The selective-coordination requirement shall not exempt a breaker from the arc energy reduction requirements of NEC 240.87 (for circuit breakers rated or adjustable to 1200 A or higher) or 240.67 (for fuses of equivalent rating).
5.5.2 Where an energy-reducing method is employed, the study shall demonstrate that the method does not compromise selective coordination outside of its activation window.
NOTE For an energy-reducing maintenance switch, the activation window is the period during which the switch is in the maintenance position. (5.5.3)

5.5.4 Arc Energy Reduction Approach

Arc Energy Reduction Coordination Approachselect
Zone-selective interlocking (ZSI) — no degradation to coordination
Energy-reducing maintenance switch (ARMS) — coordination evaluated in normal mode only
Differential relaying — coordination preserved by selectivity of the differential zone
Instantaneous trip set below available arcing current — coordination evaluated as set
Energy-reducing active arc-flash mitigation — coordination evaluated in normal mode only
NOTE Zone-selective interlocking is the preferred method on systems where selective coordination is required because it reduces upstream clearing time only when no downstream device sees the fault, so coordination is preserved by the interlock signal itself. (5.5.5)
5.5.6 Where energy-reducing maintenance switches are used, the study shall evaluate coordination in the normal (non-maintenance) state.
NOTE The ARMS-active state intentionally sacrifices coordination to limit incident energy and is acceptable for that purpose. (5.5.7)
5.5.8 Temporary adjustment of the instantaneous trip setting to achieve arc energy reduction is not permitted by NEC 240.87(B), and the study shall not recommend it.

6 Input Data Requirements

NOTE The coordination study cannot proceed without complete and verified input data. (6.1)
6.2 The Contractor shall not submit a coordination study until every input listed below is in hand.
6.3 Assumed or placeholder values shall be flagged in the report and corrected before acceptance.

6.4 Short-Circuit Study Results

6.4.1 The accepted short-circuit study per Short Circuit Study shall be used as the source of the available short-circuit current at every bus in the system.
6.4.2 The coordination study shall use the same software model — or a model verified against the same one-line, equipment data, and impedance values — as the short-circuit study so that the two analyses produce consistent fault currents.

6.4.3 Short-Circuit Study Status

Short-Circuit Study Statusradio
Accepted by Engineer of Record — used as input to this study
Submitted but not yet accepted — coordination study held pending acceptance
Not yet performed — coordination study not started

6.5 Utility Source Data

6.5.1 The serving utility's available short-circuit contribution, X/R ratio at the point of common coupling, and the time-current characteristics of the utility's protective device(s) immediately upstream of the project shall be obtained in writing from the utility.
6.5.2 Where the utility declines to provide its protective device curves, the study shall document the request and the response, and coordination at the service entrance shall be limited to the available information.

6.6 Equipment Nameplate and Curve Data

NOTE The required equipment data includes the following: (6.6.1)
  • Transformer kVA, primary and secondary voltages, percent impedance, X/R, vector group, and category for through-fault analysis per IEEE C57.109 or C57.12.59
  • Motor nameplate horsepower, full-load amps, locked-rotor amps, locked-rotor time, code letter, and starting method for every motor 50 hp and larger; smaller motors shall be modeled in aggregate at each bus
  • Cable type, conductor material, insulation type, size, and length for every feeder, for conductor damage curve plotting per ICEA P-32-382
  • Generator nameplate kW/kVA, subtransient and transient reactances, decrement curve, and the operating characteristics of the generator overcurrent device
  • Relay model and firmware, CT ratios, and CT accuracy class
  • Breaker frame size, trip unit model and rating plug, and adjustable function range
Equipment Data Sourceradio
As-built nameplate data verified at equipment
Manufacturer-confirmed shop submittal data
Specification or schedule data (verify before commissioning)
6.6.2 The study shall use the actual nameplate and curve data of the equipment installed on the project, not generic or assumed values.
6.6.3 Coordination based on specification data shall be acceptable for the action submittal so that ordering and installation are not delayed.
6.6.4 The study shall be updated against as-built nameplate data before commissioning.
NOTE A coordination study performed on imagined or rounded equipment data is not a coordination study. (6.6.5)

6.7 One-Line Diagram

6.7.1 A single-line diagram showing the complete system from the utility source through every overcurrent device covered by the study shall be provided in the report.
6.7.2 The one-line shall identify each device by its project tag, frame size, trip rating, and the bus to which it is connected, and shall show available short-circuit current at every bus.

7 Coordination Analysis

NOTE The coordination analysis is the work of selecting a setting for every adjustable device such that the criteria in [Coordination Criteria](#coordination-criteria) are met. (7.1)
7.2 The study shall analyze, at minimum, the coordination pairs listed in [Coordination Pairs Analyzed](#coordination-pairs-analyzed) below.

7.3 Coordination Pairs Analyzed

Coordination Pairs Included in Studycheckbox
Utility protective device to project main
Project main to each feeder
Each feeder to its downstream distribution device
Distribution device to each branch device
Branch device to motor starter (where applicable)
Branch device to fuse / fused disconnect (where applicable)
Generator overcurrent device to downstream distribution
UPS bypass overcurrent device to downstream distribution
Transfer switch upstream and downstream devices (emergency / standby)
7.3.1 Each pair shall be plotted on a single TCC sheet showing both devices' curves, the relevant damage curves and equipment envelopes, the available short-circuit current at the downstream device's load terminals, and the available short-circuit current at the upstream device's load terminals where different.

7.4 Transformer Damage Curves

7.4.1 For every transformer in the system, the through-fault damage curve per IEEE C57.109 (liquid-filled) or C57.12.59 (dry-type) shall be plotted on the TCC sheet showing the transformer's primary and secondary overcurrent devices.
7.4.2 The primary protective device shall clear a secondary-side bolted fault before the through-fault curve is reached.
NOTE The through-fault clearing requirement is a coordination requirement with equipment, not a coordination requirement between two devices, but it shall be demonstrated on the same plot. (7.4.3)

7.4.4 Transformer Category for Through-Fault Curve

Transformer Category for Through-Fault Curveselect
Auto-select per kVA and IEEE C57.109
Category I (5–500 kVA single-phase / 15–500 kVA three-phase)
Category II (501–1667 kVA single-phase / 501–5000 kVA three-phase)
Category III (1668–10000 kVA single-phase / 5001–25000 kVA three-phase)
Category IV (above Category III limits)
7.4.5 Transformer inrush (commonly modeled at 8 to 12 times full-load current for 0.1 seconds, with manufacturer data preferred where available) shall be plotted as a point or short curve on the primary side so that the primary protective device's curve is shown not to operate on inrush.
7.4.6 The IEEE C37.91 guidance on transformer overcurrent protection shall be applied to verify that fuse and relay selections sit below the damage curve and above the inrush point.

7.5 Motor Starting and Inrush

7.5.1 For every motor 50 hp and larger, the motor starting envelope (locked-rotor current for locked-rotor time, plus any reduced-voltage or soft-start profile if applicable) shall be plotted on the TCC sheet showing the motor branch overcurrent device.
7.5.2 The branch device's long-time pickup and curve shall be clear of the starting envelope.
7.5.3 The instantaneous shall be set above the locked-rotor current with margin sufficient to avoid nuisance trips on starting transients.
7.5.4 Motor overload elements (thermal or electronic) shall be plotted to demonstrate that the overload protects the motor's thermal damage curve.

7.5.5 Motor Starting Method Modeled

Motor Starting Method Modeledselect
Across-the-line (full-voltage start)
Reduced-voltage soft start (RVSS)
Variable-frequency drive (VFD)
Wye-delta or autotransformer
7.5.6 Motors below 50 hp shall be modeled in aggregate at their bus to capture their contribution to short-circuit current.
NOTE Individual coordination of small-motor branch circuits is generally not required unless specifically called for. (7.5.7)

7.6 Conductor Damage Curves

7.6.1 Cable damage curves per ICEA P-32-382 shall be plotted for every feeder where the cable's short-circuit withstand is a binding constraint on the upstream device's setting — typically every feeder of 1/0 AWG and larger and every conductor in series with an upstream device set to delay tripping.
7.6.2 The upstream device's curve shall clear the fault before the cable damage curve is reached, so that a fault at the far end of the feeder does not damage the cable insulation before the breaker interrupts.

7.6.3 Conductor Damage Curve Scope

Conductor Damage Curves Plotted Forselect
All feeders 1/0 AWG and larger
All feeders to switchboards, MCCs, and large panelboards
Only where required by Engineer of Record (per-feeder direction)
NOTE ICEA cable damage curves became part of mainstream coordination practice with the 2008 NEC revisions. (7.6.4)
7.6.5 ICEA cable damage curves shall be used in preference to manufacturer-specific curves except where the cable manufacturer publishes a more restrictive curve.

7.7 Ground-Fault Coordination

7.7.1 Where ground-fault protection is provided on multiple devices in series — most commonly on a service main of 1000 A or larger per NEC 230.95 and on downstream feeders — the ground-fault protective devices shall be coordinated independently of the phase coordination.
7.7.2 Ground-fault pickup and time delay shall be plotted on separate TCC sheets from the phase coordination, because the available ground-fault current and the relevant device curves differ from the phase case.

7.7.3 Ground-Fault Coordination Applicability

Ground-Fault Coordination Requiredradio
Yes — ground-fault protection present on two or more series devices
No — ground-fault protection on service main only
Not applicable — no ground-fault protection on the system
NOTE NEC 230.95(A) limits the maximum setting of the service-equipment ground-fault protective device to 1200 A pickup and 1 second time delay at 3000 A. (7.7.4)
7.7.5 Coordination of downstream ground-fault devices with the service main shall respect the NEC 230.95(A) ceiling.

8 Settings Recommendations

8.2 Recommendations of the form "set per manufacturer" or "factory defaults" shall not be acceptable for adjustable devices.

8.3 Low-Voltage Breaker Trip Unit Settings

8.3.1 For every low-voltage breaker with an electronic trip unit, the study shall recommend the following:
  • Long-time pickup (LTPU) — typically expressed as a multiple of the rating plug
  • Long-time delay (LTD) — at a specified reference current per the trip unit's curve family
  • Short-time pickup (STPU) — typically expressed as a multiple of the LTPU
  • Short-time delay (STD) — including I²t in/out selection where the trip unit supports it
  • Instantaneous pickup (INST) — or "off" / "maintenance" for selectively coordinated systems with separate arc energy reduction
  • Ground-fault pickup and delay (LSIG units), with I²t in/out where adjustable
  • Zone-selective interlocking (ZSI) participation — short-time, ground-fault, or both
Trip Unit Setting Format in Reportradio
Per-device settings sheet (one page per breaker)
Consolidated table (all breakers, one document)
Both per-device sheet and consolidated table

8.4 Protective Relay Settings

8.4.1 For every microprocessor or electromechanical relay, the study shall recommend the setting for each enabled element.
8.4.3 For directional and differential elements the study shall recommend the relevant slope, pickup, and characteristic-angle settings.
8.4.4 Relay function numbers per IEEE C37.2 shall be used to identify each element.
8.4.5 Settings shall be presented in a format that can be entered directly into the relay's commissioning software without translation.

8.5 Fuse Selection

8.5.1 Where fuses are used, the study shall recommend the fuse class, ampere rating, and where applicable the interrupting rating necessary for the available fault current at the fuse location.
8.5.2 Where coordination requires a specific fuse manufacturer's curve family — for example, where a Class L time-delay fuse coordinates with a downstream Class J in a way that a fast-acting Class L would not — the study shall note that the curve family, not a specific manufacturer's catalog number, is the basis for coordination.

8.6 Motor Overload Elements

8.6.1 For thermal or electronic motor overload elements, the study shall recommend the trip class (NEMA Class 10, 20, or 30) and the pickup current setting.
8.6.2 Trip class shall be selected to protect the motor without nuisance-tripping on the motor's acceleration time.

8.6.3 Motor Overload Trip Class

Motor Overload Trip Class Defaultselect
Class 10 (standard, acceleration time below 10 s)
Class 20 (long acceleration, high-inertia loads)
Class 30 (very long acceleration, mining/grinding-type loads)

8.7 Coordination Compromises

NOTE A real system frequently contains a coordination pair that does not coordinate at every credible fault current. (8.7.1)
8.7.2 The study shall not pretend otherwise.
NOTE Common compromises include the following: (8.7.3)
  • An upstream main with an instantaneous element that overlaps the downstream feeder above a certain fault current, accepted because the available fault current at the feeder is below the overlap.
  • A series-rated combination of an upstream breaker and a downstream breaker that is listed by the manufacturer but is not selectively coordinated; the listing is a fault-withstand listing, not a selectivity listing.
  • A current-limiting fuse and an upstream breaker whose let-through coordinate above the fuse's current-limiting threshold but not below; selectivity is achieved on bolted faults but not on lower-current faults.
8.7.4 Each compromise shall be identified, the fault-current range over which the compromise occurs shall be stated, the consequence of a non-selective trip shall be described, and the Engineer of Record's acceptance of the compromise shall be obtained in writing.
8.7.5 Compromises shall not be applied to circuits required by code to be selectively coordinated (see [Selective Coordination for Life Safety](#selective-coordination-for-life-safety)) without a code variance from the Authority Having Jurisdiction.

9 Selective Coordination for Life Safety

9.1 NEC 700.27 — Emergency Systems

9.1.1 Overcurrent devices in the emergency system distribution shall be selectively coordinated with all supply-side overcurrent protective devices per NEC 700.27.
NOTE Selective coordination means that the device immediately upstream of a fault opens before any further upstream device, at all available fault currents and at all overload currents, including at the instantaneous region of the curves. (9.1.2)
9.1.3 Partial coordination, time-based coordination above a current threshold, and series-rated combinations that do not maintain selectivity shall not be acceptable for the emergency branch.

9.1.4 Emergency System Present

Emergency System Present on Projectradio
Yes — Article 700 emergency system included
No
9.1.5 Where an emergency system is present, the study shall include a dedicated section that demonstrates selective coordination from the emergency source (generator, central inverter, or other) through every device on the emergency branch.
9.1.6 The 2023 NEC clarified, in 700.32, that selective coordination shall be examined both upstream and downstream of any device that is replaced or modified during the life of the system; this re-evaluation obligation shall be communicated to the Owner in the re-study trigger list.

9.2 NEC 701.27 — Legally Required Standby Systems

9.2.1 Overcurrent devices for the legally required standby system shall be selectively coordinated with all supply-side overcurrent protective devices per NEC 701.27.
9.2.2 The selective-coordination requirement, including the upstream-and-downstream re-evaluation obligation added to 701.32 in the 2023 NEC, shall apply to the legally required standby branch in the same manner as to the emergency branch.

9.2.3 Legally Required Standby System Present

Legally Required Standby System Present on Projectradio
Yes — Article 701 legally required standby system included
No

9.3 NEC 708 — Critical Operations Power Systems

9.3.1 Where the project includes a Critical Operations Power System (COPS) per NEC Article 708, the dedicated selective coordination requirements of 708.54 shall apply.
NOTE COPS is most commonly identified for designated critical-operations data centers, water and wastewater facilities, and certain government facilities. (9.3.2)

9.3.3 Critical Operations Power System Present

Critical Operations Power System (NEC 708) Presentradio
Yes
No

9.4 Healthcare Essential Electrical Systems

NOTE For healthcare facilities the essential electrical system per NFPA 99 and NEC Article 517 imposes additional reliability and selective-coordination considerations. (9.4.1)
9.4.2 Where the project includes a healthcare essential electrical system, coordination shall additionally satisfy NFPA 99 and the requirements of Healthcare Essential Electrical Systems.

9.4.3 Healthcare Essential Electrical System Present

Healthcare Essential Electrical System Presentradio
Yes — coordinate with healthcare standard
No

9.5 Fire Pump Circuits

9.5.1 Fire pump circuits per NEC Article 695 shall be served such that the fire pump runs without interruption short of mechanical failure of the pump itself.
9.5.2 The fire pump's individual overcurrent device shall be sized to carry locked-rotor current indefinitely per 695.4(B)(2)(a), which produces a curve that intentionally does not coordinate with anything downstream and is not expected to.
9.5.3 The study shall plot the fire pump device's curve and shall demonstrate that the upstream service device coordinates with the fire pump device for non-fire-pump faults.

10 Deliverables

10.1 The study report shall be organized so that the Engineer of Record, the commissioning technician, and the Owner's maintenance staff can each find what they need without reading the entire report.

10.2 Report Organization

Study Report Sections (Minimum)checkbox
Executive summary and conclusions
Study methodology and software identification
System one-line diagram with device tags and fault currents
Input data summary (equipment, cable, motor, source)
Coordination criteria stated explicitly
TCC plots for every coordination pair
Consolidated settings table
Per-device settings sheets for field use
Coordination compromises with justifications and EOR acceptance
Selective coordination demonstration for emergency / standby branches
Re-study trigger list
PE seal and signature

10.3 TCC Plots

10.3.1 TCC plots shall be on logarithmic axes with current on the horizontal axis and time on the vertical axis, scaled so that the relevant portions of every curve on the sheet are visible.
10.3.2 Each plot shall show the following:
  • All devices in the coordination pair, drawn in distinct line styles or colors
  • Damage curves and operating envelopes relevant to the pair (transformer through-fault, conductor damage, motor starting and overload)
  • Vertical lines at the available short-circuit currents at the relevant buses, labeled
  • A title block identifying the bus, the devices, the current and voltage base, and the source data
  • A legend identifying every curve and envelope on the sheet

10.4 Consolidated Settings Table

NOTE The consolidated settings table is the master reference for commissioning and for future re-studies; if a setting is not in the table, the study has not made a recommendation about it. (10.4.2)

10.5 Per-Device Settings Sheets

10.5.1 For field use during commissioning, the report shall include a one-page settings sheet per device.
10.5.3 The settings sheet is what the technician carries to the breaker and shall not require cross-reference to other parts of the report.

11 Re-Study Triggers

NOTE The protective device coordination study reflects the system as designed and as commissioned. (11.1)
11.2 Subsequent changes to the system can invalidate the coordination demonstrated by the study, and the Owner shall have an explicit list of events that trigger a re-study.
11.3 The study shall include a re-study trigger list, written for the Owner's operations staff in non-engineering language.
11.4 At a minimum, the re-study trigger list shall include the events enumerated below.

11.5 Re-Study Trigger Events

Re-Study Triggers Communicated to Ownercheckbox
Addition or removal of any generator, UPS, or other on-site source
Change in utility service capacity or available fault current
Replacement of a protective device with a different frame or trip type
Field change to any recommended setting
Firmware update to a microprocessor relay or trip unit
Major load addition (typically 25% of bus capacity or more)
Equipment replacement following a fault event
Change to the emergency or legally required standby branch (NEC 700.32 / 701.32)
Change to the project's healthcare essential electrical system (NFPA 99)
11.5.1 The 2023 NEC change to 700.32 and 701.32 made the re-evaluation obligation explicit for the emergency and legally required standby branches: when an overcurrent device on those branches is replaced or modified, selective coordination shall be re-verified upstream and downstream.
11.5.2 The Owner's operations procedures shall reflect the 700.32 / 701.32 re-evaluation obligation, and the re-study trigger list is the bridge between the original study and the procedures.
11.5.3 Where any trigger event occurs, the Owner shall obtain an updated coordination study, an updated arc-flash study per Arc Flash Study, and updated arc-flash labels before the affected portion of the system is returned to normal operation.

12 Coordination with Adjacent Scopes

NOTE Coordination study work intersects with several other electrical and project scopes. (12.1)

12.3 Adjacent Scope Matrix

Adjacent scope Coordination point
Short Circuit Study Provides input fault currents; study cannot start without it
Arc Flash Study Consumes coordination settings; runs after coordination
Low Voltage Switchgear Supplies trip unit data and accepts settings
Low Voltage Switchboards Supplies trip unit data and accepts settings
Medium Voltage Switchgear Supplies relay and CT data and accepts settings
Motor Control Centers Supplies starter overload data and accepts settings
Emergency And Standby Power Establishes emergency / standby branches and generator data
Healthcare Essential Electrical Systems Imposes additional coordination requirements where present
Electrical Acceptance Testing Verifies as-set values match the study

Edit this page

SynC Standards are reference material provided for informational purposes only and as a guide. They are not engineering, architectural, or legal advice and are not a substitute for the judgment of a licensed design professional. It is the responsibility of the user to determine the applicability of any standard to a specific project and to verify all requirements against the governing codes, manufacturer data, and project conditions. SynC does not render professional services and forms no professional relationship by publishing this content. Provided "as is," without warranty of any kind, including fitness for a particular purpose. See our Terms of Use for the complete terms.

This standard is published by SynC and licensed under Creative Commons Attribution-ShareAlike 4.0. You may share and adapt it, including commercially, provided you give credit, link to the license, indicate any changes, and license your adaptations under the same terms. Keep the attribution and notice below with any copy — it includes the warranty disclaimer the license requires you to retain.

Attribution & reuse notice — keep this with any copy:
"Protective Device Coordination Study." SynC Standards. Licensed under CC BY-SA 4.0 (https://creativecommons.org/licenses/by-sa/4.0/). Source: https://synergyinconstruction.com/wiki/sync/protective-coordination-study — reference material only; not professional engineering advice and provided without warranty. Verify against governing codes and have a licensed professional review before use.