Electrical Acceptance Testing

Rev 1 · Updated Jun 18, 2026 · View history

Build a datasheet from this standard Start a project with this standard already attached — one click, no setup.
Use in a project

1 Scope

NOTE This standard governs the field acceptance testing of new electrical power distribution equipment and systems performed by an independent testing organization prior to initial energization and final project acceptance. (1.1)
NOTE Acceptance testing exists to answer one question before a system is energized: was the equipment installed correctly, and is it electrically sound? Factory and routine production tests prove the equipment left the factory in good order; they say nothing about transit damage, field assembly errors, contamination during construction, mis-torqued connections, or settings that do not match the approved studies. Acceptance testing closes that gap. It is the last independent check between a finished installation and the moment it is placed in service, and once a system is energized many of these tests become impractical or unsafe to perform. (1.2)

1.3 Applicable equipment and voltage range

NOTE This standard applies to electrical power distribution equipment rated 600 V and below (low voltage) through 38 kV (medium voltage) wherever acceptance testing is specified by the Owner, the authority having jurisdiction, or the Engineer of Record. (1.3.1)
NOTE Equipment within scope includes: power transformers (liquid-filled and dry-type); metal-enclosed and metal-clad switchgear; low-voltage switchgear and switchboards; panelboards and motor control centers; molded-case, insulated-case, and power circuit breakers; protective relays (electromechanical, solid-state, and microprocessor); shielded and unshielded power cables; grounding and bonding systems; current and potential (instrument) transformers; automatic transfer switches; variable frequency drives; battery, UPS, and energy storage systems; and solar photovoltaic system power equipment. (1.3.2)

1.4 Boundaries with adjacent standards

NOTE Acceptance testing verifies that installed protective settings match the approved studies; it does not perform those studies. Short-circuit, load-flow, coordination, and arc-flash analysis are governed by Short Circuit Study, Protective Coordination Study, and Arc Flash Study. (1.4.1)
NOTE This standard covers the field test program applied after switchgear is installed. Procurement, ratings, construction, and factory testing of that equipment are governed by Low Voltage Switchgear and Medium Voltage Switchgear. (1.4.2)
NOTE Electrical acceptance testing is a discrete prerequisite input to total building commissioning, not a substitute for it. Commissioning process management, functional performance testing, and systems integration testing are governed by Commissioning. The interface between the two is defined in the Quality Assurance section. (1.4.3)
NOTE Factory acceptance testing and routine production tests conducted by equipment manufacturers at their own facilities are governed by the applicable UL, IEEE, and IEC product standards and are outside this scope. They are factory tests, not field tests. (1.4.4)
NOTE Structured cabling (Category 5e/6/8 and fiber certification), process control loop checks and field instrument calibration, and ongoing maintenance testing performed after project acceptance are outside this scope. Maintenance testing is governed by ANSI/NETA MTS, not by the acceptance testing specifications referenced here. (1.4.5)

2 Referenced Standards

2.1Equipment, materials, and field testing shall comply with the latest adopted edition of each of the following unless a specific edition is cited.
2.2Where referenced standards conflict, the more stringent requirement shall govern unless the Engineer of Record directs otherwise in writing.
Standard Title
ANSI/NETA ATS-2025 Acceptance Testing Specifications for Electrical Power Equipment and Systems
ANSI/NETA ETT-2022 Standard for Certification of Electrical Testing Technicians
NFPA 70 National Electrical Code (Article 110, General Requirements for Electrical Installations)
NFPA 70B-2023 Recommended Practice for Electrical Equipment Maintenance
NFPA 70E-2024 Standard for Electrical Safety in the Workplace
IEEE 400-2012 Guide for Field Testing and Evaluation of the Insulation of Shielded Power Cable Systems Rated 5 kV and Above
IEEE 400.2-2013 Guide for Field Testing of Shielded Power Cable Systems Using Very Low Frequency (VLF) (less than 1 Hz)
IEEE C57.12.90-2015 Standard Test Code for Liquid-Immersed Distribution, Power, and Regulating Transformers
IEEE C57.12.91-2011 Standard Test Code for Dry-Type Distribution and Power Transformers
IEEE C37.09-2018 Standard Test Procedure for AC High-Voltage Circuit Breakers Rated on a Symmetrical Current Basis
IEEE 81-2012 Guide for Measuring Earth Resistivity, Ground Impedance, and Earth Surface Potentials of a Grounding System
NEMA MG 1-2021 Motors and Generators

2.3 Edition selection

NOTE The current edition of the governing acceptance testing specification is ANSI/NETA ATS-2025, which supersedes the 2021 edition. The 2025 edition added field test procedures for battery energy storage systems and solar photovoltaic systems and expanded the medium-voltage cable acceptance test value tables. (2.3.1)
2.3.2The testing specification edition shall be selected to match the edition adopted by the project at the time of the construction contract.
Governing acceptance testing specification editionradio
ANSI/NETA ATS-2025
ANSI/NETA ATS-2021

3 Submittals

3.1 Action submittals

3.1.1The testing organization shall submit the following for review and approval before any field testing begins:
  • Testing organization accreditation certificate (NETA Accredited Company documentation)
  • Certifications and assigned competency level for each technician on the crew
  • Detailed test plan listing every device to be tested and the procedure for each
  • Sample test report forms for each equipment type
  • Current calibration certificates for all test instruments, traceable to NIST
  • Project-specific electrical safety plan referencing the current arc-flash study
Action submittals required before field testingcheckbox
Testing organization accreditation certificate
Technician certifications and competency levels
Detailed device-by-device test plan
Sample test report forms by equipment type
Instrument calibration certificates (NIST-traceable)
Project-specific electrical safety plan
3.1.2The testing organization shall receive the approved short-circuit, coordination, and arc-flash studies as reference documents before testing begins, so that installed relay settings and trip device settings can be verified against the engineered values.

3.2 Informational submittals

3.2.1The testing organization shall submit the following reference and qualification documents for the record:
  • Resume or equivalent qualification record for the designated crew lead
  • List of test instruments by manufacturer, model, serial number, and calibration date
  • Manufacturer published tolerance data for equipment being tested, where acceptance criteria reference manufacturer values
Informational submittalscheckbox
Crew lead qualification record
Test instrument inventory with calibration dates
Manufacturer published tolerance data

3.3 Closeout submittals

3.3.1Upon completion of testing, the testing organization shall submit the following as project closeout deliverables:
  • Final compiled test report covering every device tested, with as-found and as-left values
  • Summary of all out-of-tolerance findings and the corrective action taken for each
  • Index of devices tested cross-referenced to the approved test plan
  • Copies of all instrument calibration certificates valid for the test period
Closeout submittalscheckbox
Final compiled test report (all devices)
Out-of-tolerance findings and corrective actions
Device index cross-referenced to test plan
Instrument calibration certificates for test period
3.3.2The final test report shall be delivered to the Owner, the Engineer of Record, and the authority having jurisdiction in the format and quantity specified below.
Final test report delivery formatcheckbox
Electronic PDF (searchable)
Stamped and signed hard copies
Native test-set data files (COMTRADE, instrument exports)
Test report recipientscheckbox
Owner / facility records
Engineer of Record
Authority having jurisdiction
Commissioning agent
Test report retention periodradio
Life of the equipment
10 years
5 years

4 Quality Assurance

4.1 Independence of the testing organization

NOTE NETA requires that field acceptance testing be performed by an organization with no financial interest in the outcome of the work it tests. An installing contractor who tests its own installation has every incentive to pass marginal results and no independent check on whether the work was done correctly. Independence is the entire value of the program; without it the test report is self-certification. (4.1.1)
4.1.2Acceptance testing shall be performed by an independent testing organization that is not the installing electrical contractor and has no financial interest in the installation under test.
4.1.3The testing organization shall be a NETA Accredited Company (NAC), or an owner-furnished in-house testing group meeting the same accreditation, instrument calibration, and technician certification requirements.
NOTE A specification that requires only a "NETA-compliant" testing firm allows non-accredited contractors to claim compliance. Accreditation shall be stated explicitly as a NETA Accredited Company, not as general compliance. (4.1.4)
Testing organization qualificationradio
NETA Accredited Company (NAC), independent third party
Owner-furnished in-house group meeting NAC standards
OEM field service paired with independent NETA testing

4.2 Technician qualification

NOTE Technician competency is defined by ANSI/NETA ETT, which establishes four certification levels. Level 3 is the practical minimum for a crew lead on a distribution project: a Level 3 technician can independently perform and evaluate the full range of acceptance tests and direct lower-level technicians. Specifying a higher level than the work warrants raises cost without improving outcomes; specifying too low a level puts inexperienced technicians in charge of go/no-go decisions. (4.2.1)
4.2.2Each test crew shall be led by a technician certified to the specified ANSI/NETA ETT level minimum.
Crew lead minimum ETT certification levelradio
ETT Level 2
ETT Level 3
ETT Level 4
4.2.3Personnel performing energized work shall be qualified under NFPA 70E-2024 and shall use the arc-flash personal protective equipment determined by the project arc-flash study.

4.3 Test instrument calibration

NOTE A test instrument that is out of calibration produces numbers that look authoritative and may be wrong. Acceptance decisions rest on absolute measurements compared against tight tolerances, so the instruments must be traceable to a national standard and recently verified. (4.3.1)
4.3.2All test instruments shall have current calibration traceable to NIST, performed within the 12 months preceding the test.
4.3.3Calibration stickers showing the instrument serial number and calibration date shall be documented in the test report for each instrument used.

4.4 Coordination with commissioning

NOTE Acceptance testing verifies equipment integrity (insulation, timing, contact resistance, settings) before energization. Commissioning functional testing verifies that energized systems perform their intended function. The two are sequential and complementary; treating them as one scope causes scheduling disputes with the commissioning agent. The boundary shall be documented so neither program assumes the other will perform a given test. (4.4.1)
4.4.2Acceptance testing shall be completed and the results accepted before the affected equipment is released to the commissioning agent for functional performance testing under Commissioning.

4.5 Hold points and scheduling

NOTE Without a contractual hold point requiring acceptance test sign-off before energization, systems are routinely energized before testing is complete, after which many de-energized tests become impractical or unsafe. The hold point is what makes the program enforceable. (4.5.1)
4.5.2A formal hold point shall be established at which acceptance test results for each system are reviewed and signed off by the Engineer of Record before that system is energized.
4.5.3Equipment installed in concealed spaces shall be acceptance-tested before architectural closure (ceilings, walls, flooring) renders it inaccessible.
4.5.4The final compiled test report shall be reviewed and accepted by the Engineer of Record before the certificate of substantial completion is issued.
Testing milestone relative to project scheduleradio
Before energization, per-system hold point
Before substantial completion
Before final payment
Testing sequencingradio
Single mobilization, all equipment at once
Phased / sequential energization of feeders with defined hold points

5 Scope of Equipment Tested

NOTE A specification that omits an explicit equipment inclusion list invites scope disputes: the testing organization tests the obvious major equipment, and panelboards, transfer switches, or drives are quietly energized without testing. The equipment list is the single most important thing the specifier controls, because everything not listed tends not to get tested. (5.1)
NOTE The default acceptance test scope is 100% of installed distribution equipment. Selective sampling shall be used only where the Engineer of Record has specifically authorized it and shall be defined by an explicit inclusion and exclusion list by equipment type and voltage class. (5.2)
5.3Equipment to be acceptance-tested shall be selected from the list below; any equipment present on the project and not selected shall be explicitly identified as excluded with the reason recorded.
Equipment included in acceptance test scopecheckbox
Power transformers (liquid-filled)
Power transformers (dry-type)
Metal-clad / metal-enclosed switchgear
Low-voltage switchgear and switchboards
Panelboards
Motor control centers
Molded-case and insulated-case circuit breakers
Power (drawout) circuit breakers
Protective relays
Medium-voltage power cables
Low-voltage power cables
Grounding and bonding system
Instrument transformers (CT / PT)
Automatic transfer switches
Variable frequency drives
Battery / UPS systems
Acceptance test coverageradio
100% of installed distribution equipment
Selective sampling per authorized inclusion/exclusion list

6 Acceptance Criteria

NOTE Where both a manufacturer published tolerance and a NETA table value exist for the same test, the specification must state which governs and which takes precedence on conflict; otherwise the testing organization decides case by case and results are inconsistent across the project. (6.1)
6.2The source of acceptance criteria shall be stated below. Where the selected source is silent on a given test, the other source shall apply.
Primary source of acceptance criteriaradio
Manufacturer published tolerances govern; NETA tables where manufacturer is silent
NETA ATS tolerance tables govern; manufacturer values where NETA is silent

6.3 Contact and milliohm resistance acceptance

NOTE Contact resistance is a sensitive indicator of connection quality: a loose bolt, a contaminated contact surface, or partial conductor seating all show up as elevated resistance long before they cause a visible failure. Measurement is taken with a high-current micro-ohmmeter, and the result is judged against either the manufacturer baseline or the NETA table value. (6.3.1)
6.3.2Bolted and contact connection resistance shall be measured and shall be rejectable when it exceeds 125% of the manufacturer published value, or the applicable NETA ATS table value where no manufacturer value is provided.
Contact / milliohm resistance acceptance thresholdradio
> 125% of manufacturer published value (or NETA table)
> 150% of manufacturer published value
Contact resistance test currentrange
A DC
10200
Default: 100 A DC

7 Insulation Resistance Testing

NOTE Insulation resistance testing applies a DC voltage across insulation and measures the resulting leakage current, expressed as resistance. It is the most widely applied acceptance test because it catches contamination, moisture, and physical damage to insulation across almost every class of equipment. The test voltage must be matched to the equipment rating: too low a voltage misses defects, too high a voltage can stress sound insulation unnecessarily. (7.1)

7.2 Test voltage selection

NOTE The DC test voltage shall be selected from NETA ATS Table 100.1 according to the rated voltage of the equipment under test. (7.2.1)
7.2.2Insulation resistance test voltage shall be selected per the following equipment voltage classes.
Insulation resistance test voltage by equipment classradio
500 V DC (120-240 V equipment)
1000 V DC (600 V equipment)
2500 V DC (2.5 kV equipment, up to 5 kV)
5000 V DC (5-15 kV equipment)

7.3 Acceptance values

7.3.1Insulation resistance on 600 V equipment shall be measured at 1000 V DC for a 1-minute reading, with a minimum acceptable value of 1 MΩ per kV of rated voltage.
NOTE New 600 V equipment in sound condition typically reads between 100 MΩ and 1000 MΩ; any reading below 1 MΩ is rejectable and shall be investigated before energization. (7.3.2)
Insulation resistance minimum acceptance (600 V class)range
1100
Default: 100 MΩ
7.3.3For rotating machines, transformers, and other windings where a polarization index is taken, the ratio of the 10-minute reading to the 1-minute reading shall be evaluated against the minimum below.
Polarization index (PI) minimum acceptance ratiorange
ratio
13
Default: 2 ratio

8 Medium-Voltage Cable Testing

NOTE Medium-voltage cable acceptance testing is where method selection matters most. DC high-potential (hipot) testing was the legacy field method, but DC voltage is now known to damage extruded dielectric (XLPE and EPR) insulation by injecting space charge that accelerates water-tree growth. Industry practice has moved to very low frequency (VLF) testing at 0.1 Hz, which stresses the insulation realistically without the DC damage mechanism. VLF can be run as a simple withstand test (pass/fail at voltage) or with tan-delta (dissipation factor) monitoring, which also grades the overall condition of the cable. (8.1)
8.2DC hipot shall not be specified for new extruded-dielectric (XLPE or EPR) medium-voltage cable.
8.3VLF withstand or VLF tan-delta per IEEE 400.2 shall be used for new extruded-dielectric cable work; DC hipot is retained only for testing legacy systems where it is already established.

8.4 Cable test method

8.4.1The medium-voltage cable acceptance test method shall be selected below.
Medium-voltage cable test methodradio
VLF withstand at 0.1 Hz
VLF tan-delta (dissipation factor) at 0.1 Hz
DC hipot (legacy systems only)

8.5 VLF withstand criteria

NOTE VLF withstand testing applies 0.1 Hz AC at twice the phase-to-ground voltage (2U0) for a sustained period; the cable passes if no dielectric breakdown occurs over the full duration. For 15 kV class cable, U0 is approximately 8.66 kV, so the test voltage is approximately 17.3 kV. (8.5.1)
8.5.2Each medium-voltage cable shall be VLF withstand tested at 0.1 Hz at the specified multiple of U0 for the specified duration with no dielectric breakdown.
VLF withstand test voltageradio
2U0 (twice phase-to-ground voltage)
1.5U0
3U0
VLF withstand test durationrange
min
1560
Default: 60 min

8.6 VLF tan-delta criteria

NOTE Tan-delta measures dielectric loss, which rises as insulation degrades. Two numbers matter: the absolute loss at operating voltage, and how much the loss changes as voltage is raised (tip-up). Both are evaluated against the limits below per IEEE 400.2. (8.6.1)
8.6.2Where tan-delta is specified, the dissipation factor measured at 1U0 shall not exceed the limit below for XLPE and EPR insulation.
Tan-delta (dissipation factor) limit at 1U0, XLPE/EPRrange
%
0.050.2
Default: 0.1 %
8.6.3The change in tan-delta (tip-up) between 0.5U0 and 2U0 for XLPE cable shall not exceed the limit below.
Tan-delta tip-up limit (0.5U0 to 2U0), XLPErange
%
0.020.1
Default: 0.06 %

8.7 Cable insulation resistance

8.7.1Medium-voltage cable insulation resistance shall be measured at 2500 V to 5000 V DC per NETA ATS Table 100.1 before the VLF test is applied, to confirm the cable is fit to receive the higher test voltage.

9 Transformer Testing

NOTE Transformer acceptance testing confirms three things: that the windings are electrically continuous and correctly connected (turns ratio, winding resistance), that the insulation is dry and clean (insulation resistance, power factor), and that the unit was not damaged in shipment or installation. The test methods follow IEEE C57.12.90 for liquid-filled units and C57.12.91 for dry-type units. (9.1)

9.2 Turns ratio

9.2.1Transformer turns ratio (TTR) shall be measured at every tap position and shall be within 0.5% of the nameplate ratio per NETA ATS Section 7.2.
Turns ratio (TTR) acceptance tolerancerange
%
0.251
Default: 0.5 %
Turns ratio test scoperadio
All tap positions
Nominal tap only

9.3 Insulation power factor

NOTE Insulation power factor (also called dissipation factor) grades the overall condition of the insulation system and oil. It is the most sensitive transformer insulation test and is measured with a high-voltage power factor (dissipation factor) test set. (9.3.1)
9.3.2Insulation power factor testing shall be performed on all liquid-filled transformers; dry-type transformers shall be power-factor tested where specified below.
9.3.3The corrected insulation power factor of liquid-filled transformers at 20°C shall not exceed the value below per NETA ATS Table 100.5; values above 1.0% at 20°C warrant investigation.
Liquid-filled transformer insulation power factor limit at 20°Crange
%
0.51
Default: 0.5 %
Dry-type transformer power factor testingradio
Required
Not required (insulation resistance only)

9.4 Winding insulation resistance

9.4.1Transformer winding insulation resistance shall be measured at the DC test voltage corresponding to the winding rated voltage, with a polarization index taken where specified.

10 Circuit Breaker Testing

NOTE Circuit breaker acceptance testing verifies that the breaker will both carry normal current with low losses and operate fast enough to clear a fault. Contact resistance addresses the first; timing and travel analysis address the second. For drawout and power circuit breakers, timing is measured with a travel analyzer that records when each pole opens and closes, per IEEE C37.09. (10.1)

10.2 Contact resistance

10.2.1The main-contact resistance of each circuit breaker pole shall be measured in microohms and shall be within the manufacturer tolerance, or the NETA ATS Table 100.12 value where no manufacturer value is provided.
NOTE Typical acceptable main-contact resistance ranges from 15 µΩ to 100 µΩ on a 1200 A frame and 5 µΩ to 50 µΩ on a 2000 A and larger frame; readings well above these ranges indicate a contact or connection problem. (10.2.2)

10.3 Timing and travel

10.3.1For medium-voltage power circuit breakers, opening and closing times shall be measured with a travel analyzer and shall be within the manufacturer published tolerance.
10.3.2Pole-to-pole timing spread (the difference between the first and last pole to operate) shall not exceed the value below.
Circuit breaker 3-pole timing spread limitrange
ms
15
Default: 2 ms
Circuit breaker timing tolerance vs. manufacturerrange
%
515
Default: 10 %

10.4 Molded-case breaker trip testing

10.4.1Molded-case and insulated-case breakers shall be primary-current injection tested to verify long-time and instantaneous trip operation against the published trip curve, on a sampling basis where specified.
Molded-case breaker trip test scoperadio
All breakers above a specified frame size
Sample of each frame size and type
All breakers

11 Protective Relay Testing

NOTE Protective relays are tested by injecting known currents and voltages with a relay test set and verifying that the relay picks up and times out exactly as its settings dictate. The critical discipline is that the field settings must match the approved coordination study; a relay that tests perfectly against the wrong settings is a coordination failure waiting to happen. The testing organization must therefore work from the stamped coordination study, not from settings transcribed in the field. (11.1)

11.2 Relay test scope

NOTE The protective relay test scope shall be selected below. A functional trip test confirms the relay trips its breaker; characteristic verification confirms the timing curve; injection testing with a calibrated relay test set is required to confirm settings match the study. (11.2.1)
Protective relay test scoperadio
Functional trip test only
Functional trip plus pickup/timing verification at set points
Full characteristic verification with relay test-set injection

11.3 Settings verification

11.3.1Installed relay settings shall be verified against the approved coordination study from Protective Coordination Study; any discrepancy shall be reported to the Engineer of Record before the relay is placed in service.
11.3.2Overcurrent relay operating time shall be verified by injecting test current at 2× and 5× pickup, and the measured operate time shall be within 5% of the published time-current curve at each multiple.
Overcurrent relay timing tolerancerange
%
310
Default: 5 %
11.3.3Overcurrent relay pickup current shall be within 5% of the set value.
Relay pickup tolerancerange
%
310
Default: 5 %

12 Grounding System Testing

NOTE Grounding acceptance testing measures the resistance of the grounding electrode system to remote earth, which determines how effectively fault current and surge energy are conducted to ground. The fall-of-potential method per IEEE 81 is the reference field method. The acceptance value depends on the facility: sensitive electronic and substation grounds require a low resistance, while general installations are held to a looser limit consistent with NEC 250.53. (12.1)
12.2The grounding electrode system resistance to ground shall be measured by the fall-of-potential method per IEEE 81 and shall not exceed the limit selected below.
Ground resistance acceptance limitradio
5 Ω (substations, sensitive electronic facilities)
25 Ω (general installations, NEC 250.53)
1 Ω (large substations, special requirements)
12.3Continuity of equipment grounding and bonding connections shall be verified per Grounding And Bonding for all equipment within the test scope.

13 Instrument Transformer and Auxiliary Equipment Testing

NOTE Current and potential transformers feed the relays and metering; if their ratio or polarity is wrong, every downstream measurement and protection function is wrong. Ratio, polarity, and insulation are verified at acceptance. Automatic transfer switches and drives have their own functional acceptance checks that confirm transfer timing and protective settings before the systems they serve are commissioned. (13.1)
13.2Current and potential transformer ratio and polarity shall be verified, and insulation resistance measured, before the associated metering and protection are placed in service.
13.3Automatic transfer switch acceptance testing shall verify transfer and re-transfer operation, timing, and any associated protective settings; coordination of the standby source is governed by Emergency And Standby Power.
13.4Variable frequency drive acceptance testing shall verify control power, insulation resistance of power circuits, and protective trip functions per the manufacturer field commissioning procedure; drive application requirements are governed by Low Voltage Variable Frequency Drives.

14 Test Reporting

NOTE The test report is the permanent record of the as-installed condition of the electrical system and the baseline against which all future maintenance testing is judged per NFPA 70B. Informal field notes do not satisfy AHJ record-keeping requirements and cannot serve as a maintenance baseline. The report must capture, for every device, what was found, what tolerance applied, and whether it passed, with the instruments and their calibration identified. (14.1)
14.2The test report shall include, for each device tested: device identification, the test performed, the as-found and as-left values, the applicable acceptance tolerance, the pass/fail determination, and the instruments used with their calibration dates.
14.3All out-of-tolerance findings shall be recorded together with the corrective action taken and the as-left retest result.
14.4The compiled report shall be indexed against the approved test plan so that any device omitted from testing is immediately apparent.
Out-of-tolerance dispositionradio
Repair and retest until within tolerance
Repair, retest, and engineer review before energization
Reject and replace

15 Field Quality Control

NOTE Visual and mechanical inspection precedes every electrical test: a technician confirms the equipment is correctly installed, anchored, labeled, and free of shipping braces and debris before any voltage is applied. Many defects are caught here, before an instrument is connected. (15.1)
15.2A visual and mechanical inspection shall be performed on each device before electrical testing, confirming correct installation, anchorage, labeling per Equipment Labeling, removal of shipping restraints, and torque verification of accessible bolted connections.
15.3Bolted electrical connections shall be torque-verified to the manufacturer published values, or calibrated to a low-resistance measurement where torque access is not practical.
15.4The testing organization shall coordinate any required partial or phased energization with the serving utility and shall observe the project hold points before each energization step.

16 Delivery, Storage, and Handling

16.1Test instruments and reference equipment shall be transported and stored so that their calibration is not disturbed, and any instrument subjected to physical shock shall be re-verified before use.
NOTE Equipment awaiting acceptance testing shall be protected from construction moisture and contamination; space heaters in switchgear and transformers shall be energized where provided, since damp insulation will fail insulation resistance and power factor tests that the equipment would otherwise pass. (16.2)

17 Warranty

17.1The testing organization shall warrant that all testing was performed in accordance with the specified acceptance testing specification and that the reported results accurately represent the as-found and as-left condition of the equipment.
NOTE Acceptance testing does not extend or alter the equipment manufacturer warranties; defects revealed by testing shall be corrected under the applicable equipment or installation warranty. (17.2)

Edit this page

SynC Standards are reference material provided for informational purposes only and as a guide. They are not engineering, architectural, or legal advice and are not a substitute for the judgment of a licensed design professional. It is the responsibility of the user to determine the applicability of any standard to a specific project and to verify all requirements against the governing codes, manufacturer data, and project conditions. SynC does not render professional services and forms no professional relationship by publishing this content. Provided "as is," without warranty of any kind, including fitness for a particular purpose. See our Terms of Use for the complete terms.

This standard is published by SynC and licensed under Creative Commons Attribution-ShareAlike 4.0. You may share and adapt it, including commercially, provided you give credit, link to the license, indicate any changes, and license your adaptations under the same terms. Keep the attribution and notice below with any copy — it includes the warranty disclaimer the license requires you to retain.

Attribution & reuse notice — keep this with any copy:
"Electrical Acceptance Testing." SynC Standards. Licensed under CC BY-SA 4.0 (https://creativecommons.org/licenses/by-sa/4.0/). Source: https://synergyinconstruction.com/wiki/sync/electrical-acceptance-testing — reference material only; not professional engineering advice and provided without warranty. Verify against governing codes and have a licensed professional review before use.